This document is a Bid Proposal for the American Plaza to Exchange Parkway Water Transmission Line Improvements, Phase II project, issued by the City of Waco, Texas. The project generally consists of the installation of approximately 6,800 linear feet of 30-inch C-900 PVC DR 18 water line, 745 linear feet of 42-inch steel pipe bore and encase construction for TxDOT and Union Pacific Railroad crossings, and associated pipe and miscellaneous work. A non-mandatory pre-bid meeting will be held on July 10, 2024. The bid proposal includes a detailed pricing sheet with 82 line items for various water infrastructure components, general conditions, and miscellaneous improvements. Contractors must identify any subcontractors they will use for the work. Pricing information notes that quantities may be reduced or increased during the contract period, and the contractor is responsible for all calculations. There is no mention of any funding sources, set-asides, or incumbent contractors for this project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEM NO. DESCRIPTION QTY UNIT UNIT PRICE SUB-TOTAL
GENERAL CONDITIONS
1 Mobilization, Permits and Project Incidentals (10% Maximum of Total Bid) 1 LS $ -
2 Bonding & Insurance (2.5% Maximum of Total Bid) 1 LS $ -
3 Stormwater Pollution & Prevention Plan 1 LS $ -
4 Stormwater Pollution & Prevention Plan Implementation 1 LS $ -
Testing of Improvements, including but not limited to all testing required for acceptance of the water improvements, and all material, labor, equipment and incidentals, complete and in place.
1 LS $ -
6 Coordination of Utility Installation with Private Utility Companies 1 LS $ -
7 Trench Safety Plan 1 LS $ -
8 Confined Space Plan & Implementation 1 LS $ -
9 Traffic Control Plan 1 LS $ -
10 Traffic Control Implementation 1 LS $ -
UPRR Coordination including by not limited to Safety Training, Flagging, Observation, Track Monitoring, Liability Insurance, as required within the UPRR Pipeline Agreement
1 LS $ -
Building Waco Signage, including all signage, anchorage, installation, removal, and all material, labor, equipment, and incidentals, complete and in place
3 EA $ -
SUBTOTAL - GENERAL CONDITIONS $ -
WATER IMPROVEMENTS
Existing 6" Water Line (All Types) to be abandoned in place, including installation of plugs in pipe, grout installation, and all material, labor, equipment and incidentals, complete and in place
78 LF $ -
Existing 8" Water Line (All Types) to be abandoned in place, including installation of plugs in pipe, grout installation, and all material, labor, equipment and incidentals, complete and in place
332 LF $ -
Existing 12" Water Line (All Types) to be abandoned in place, including installation of plugs in pipe, grout installation, and all material, labor, equipment and incidentals, complete and in place
635 LF $ -
PRICING INFORMATION
NOTE: Depending on unit prices, requirements and approved budgeted funds, quantities may be reduced or increased during the contract period.
THE CONTRACTOR IS RESPONSIBLE FOR ALL MATH, CALCULATIONS, AND FORMULAS
American Plaza to Exchange Parkway Water Transmission Line Improvements, Phase II
BID PROPOSAL
RFB 2024-055 Page 15
Existing 16" Water Line (All Types) to be abandoned in place, including installation of plugs in pipe, grout installation, and all material, labor, equipment and incidentals, complete and in place
3250 LF $ -
Existing Gate Valve to be closed, remove valve lid and fill valve stem with 2,000 PSI concrete, and all material, labor, equipment and incidentals, complete and in place
4 EA $ -
Existing Gate Valve (All Sizes) to be Removed and Delivered to the City of Waco, including necessary excavation, dewatering, transportation and delivery to City Facilities, installation of backfill, installation of solid block sod, and all material, labor, equipment, and incidentals complete and in place
11 EA $ -
Existing Fire Hydrant to be Removed and Delivered to the City of Waco, including necessary excavation, dewatering, transportation and delivery to City Facilities, installation of backfill, installation of solid block sod, and all material, labor, equipment, and incidentals complete and in place
3 EA $ -
Installation of 16" Concrete Plug, including all necessary excavation, cutting of pipe, installation of plug, trench backfill, surface replacement, and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
Connection to existing 8" water line, including necessary pothole investigation, special fittings, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
6 EA $ -
Connection to existing 12" water line, including necessary pothole investigation, special fittings, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
Connection to existing 16" water line, including necessary pothole investigation, special fittings, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
3 EA $ -
Connection to existing 30" water line, including necessary pothole investigation, special fittings, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
Connection to existing 42" water line, including necessary pothole investigation, special fittings, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
2 EA $ -
American Plaza to Exchange Parkway Water Transmission Line Improvements, Phase II
BID PROPOSAL
RFB 2024-055 Page 16
8" C-900 DR18 PVC Restrained Joint Water Line (All Depths) (Street Trench) including necessary excavation, embedment, tracer wire, marking tape, installation of utility, and trench backfill and all material, labor, equipment, and incidentals complete and in place
289 LF $ -
12 C-900 DR18 PVC Restrained Joint Water Line (All Depths) (Off Street Trench) including necessary excavation, embedment, tracer wire, marking tape, installation of utility, trench backfill and all material, labor, equipment, and incidentals complete and in place
55 LF $ -
16" C-900 DR18 PVC Restrained Joint Water Line (All Depths) (Street Trench) including necessary excavation, embedment, tracer wire, marking tape, installation of utility, and trench backfill and all material, labor, equipment, and incidentals complete and in place
129 LF $ -
30" C-900 DR 18 PVC Water Line (All Depths) (Street Trench) including necessary excavation, embedment, tracer wire, marking tape, installation of utility, trench backfill and all material, labor, equipment, and incidentals complete and in place
1182 LF $ -
30" C-900 DR 18 PVC Water Line (All Depths) (Off Street Trench) including necessary excavation, embedment, tracer wire, marking tape, installation of utility, trench backfill and all material, labor, equipment, and incidentals complete and in place
733 LF $ -
30" C-900 DR 18 PVC Restrained Joint Water Line (All Depths) (Street Trench) including necessary excavation, embedment, tracer wire, marking tape, installation of utility, trench backfill and all material, labor, equipment, and incidentals complete and in place
3254 LF $ -
30" C-900 DR 18 PVC Restrained Joint Water Line (All Depths) (Off Street Trench) including necessary excavation, embedment, tracer wire, marking tape, installation of utility, trench backfill and all material, labor, equipment, and incidentals complete and in place
740 LF $ -
30" C-900 DR 18 PVC Water Line installed in 42" Steel Encasement Pipe (All Depths) including tracer wire, installation of utility and all material, labor, equipment, and incidentals complete and in place
20 LF $ -
30" C-900 DR 18 Restained Joint PVC Water Line installed in 42" Steel Encasement Pipe (All Depths) including tracer wire, installation of utility and all material, labor, equipment, and incidentals complete and in place
858 LF $ -
American Plaza to Exchange Parkway Water Transmission Line Improvements, Phase II
BID PROPOSAL
RFB 2024-055 Page 17
42" Steel Encasement Pipe installed by Open Cut (All Depths) including necessary excavation, embedment, tracer wire, marking tape, installation of utility, trench backfill and all material, labor, equipment, and incidentals complete and in place
133 LF $ -
42" Steel Encasement Pipe installed by Dry Bore (All Depths) including necessary excavation, construction of bore pits, jacking of encasement pipe, and all material, labor, equipment, and incidentals complete and in place
745 LF $ -
37 42" X 30" DIP Tee, including necessary excavation, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
38 30" X 30" DIP Tee, including necessary excavation, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
3 EA $ -
39 30" X 16" DIP Tee, including necessary excavation, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
40 30" X 12" DIP Tee, including necessary excavation, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
41 30" X 8" DIP Tee, including necessary excavation, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
3 EA $ -
42 30" X 6" DIP Tee, including necessary excavation, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
43 16" X 16" DIP Tee, including necessary excavation, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
44 8" X 8" DIP Tee, including necessary excavation, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
45 8" X 6" DIP Tee, including necessary excavation, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
2 EA $ -
30" X 16" DIP Reducer, including necessary excavation, connection to water line, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
3 EA $ -
47 16" DIP Plug, including necessary excavation, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
American Plaza to Exchange Parkway Water Transmission Line Improvements, Phase II
BID PROPOSAL
RFB 2024-055 Page 18
6" - 45° DIP Bend, including necessary excavation, connection to water line, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
2 EA $ -
8" - 45° DIP Bend, including necessary excavation, connection to water line, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
12 EA $ -
8" - 22 1/2° DIP Bend, including necessary excavation, connection to water line, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
8" - 11 1/4° DIP Bend, including necessary excavation, connection to water line, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
5 EA $ -
12" - 45° DIP Bend, including necessary excavation, connection to water line, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
4 EA $ -
16" - 45° DIP Bend, including necessary excavation, connection to water line, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
10 EA $ -
30" - 45° DIP Bend, including necessary excavation, connection to water line, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
49 EA $ -
30" - 22 1/2° DIP Bend, including necessary excavation, connection to water line, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
9 EA $ -
30" - 11 1/4° DIP Bend, including necessary excavation, connection to water line, spool pieces, thrust blocking, trench backfill and all material, labor, equipment, and incidentals complete and in place
12 EA $ -
42" Resilient Seat Gate Valve, including necessary excavation, connection to water line, thrust blocking, tracer wire, thrust blocking, valve box and lid, and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
30" Resilient Seat Gate Valve, including necessary excavation, connection to water line, thrust blocking, tracer wire, thrust blocking, valve box and lid, and all material, labor, equipment, and incidentals complete and in place
13 EA $ -
American Plaza to Exchange Parkway Water Transmission Line Improvements, Phase II
BID PROPOSAL
RFB 2024-055 Page 19
16" Resilient Seat Gate Valve, including necessary excavation, connection to water line, thrust blocking, tracer wire, thrust blocking, valve box and lid, and all material, labor, equipment, and incidentals complete and in place
2 EA $ -
16" Resilient Seat Gate Valve "Cut-In" to Existing Pipe, including necessary excavation, connection to water line, thrust blocking, tracer wire, thrust blocking, valve box and lid, and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
12" Resilient Seat Gate Valve, including necessary excavation, connection to water line, thrust blocking, tracer wire, thrust blocking, valve box and lid, and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
8" Resilient Seat Gate Valve, including necessary excavation, connection to water line, thrust blocking, tracer wire, thrust blocking, valve box and lid, and all material, labor, equipment, and incidentals complete and in place
6 EA $ -
4" Air Release & Vacuum Valve (In Street), including service tap, service, line, valve vault, appurtenances, vent, vent enclosure, and all material, labor, equipment, and incidentals complete and in place
14 EA $ -
4" Air Release & Vacuum Valve (Off Street), including service tap, service, line, valve vault, appurtenances, vent, vent enclosure, and all material, labor, equipment, and incidentals complete and in place
1 EA $ -
Fire Hydrant Assembly, including necessary excavation, embedment, 6" DIP Fire Line, 6" Resilient Seat Gate Valve, valve box and lid, Gradlock, trench backfill, and all material labor, equipment, and incidentals complete and in place
3 EA $ -
2" Service Tap and 2" Ball Corporation Stop, including necessary excavation, tap of pipe, installation, and all material, labor, equipment, and incidentals complete and in place.
1 EA $ -
Type K Copper Tubing, including necessary excavation, embedment, tracer wire, marley tape, installation of utility, embedment, backfill, and all material, labor, equipment, and incidentals, complete and in place.
56 LF $ -
2" Commercial Service (Street Trench) including connection to water main, necessary excavation, embedment, installation of service, backfill, connection to existing bullhead meter, and all material, labor, equipment, and incidentals, complete and in place.
1 EA $ -
Trench Safety Implementation, including all necessary material, labor, equipment, training and incidentals complete and in place
6647 LF $ -
SUBTOTAL - WATER IMPROVEMENTS $ -
American Plaza to Exchange Parkway Water Transmission Line Improvements, Phase II
BID PROPOSAL
RFB 2024-055 Page 20
MISCELLANEOUS IMPROVEMENTS
Existing Concrete Curb and Gutter to Be Removed and Replaced, including necessary saw cutting, removal transportation and disposal, forming, reinforcement, dowels, placement of concrete, curing, and all material, labor, equipment and incidentals complete and in place
270 LF $ -
Class 'A' Surface Replacement, including all necessary preparation, sawcutting of existing pavement, subgrade compaction, installation of concrete base, bonding course, placement of HMAC (Type D), cleanup and all material, labor, equipment and incidentals complete and in place
4732 LF $ -
Class 'D' Surface Replacement, including all necessary preparation, sawcutting of existing pavement, subgrade compaction, reinforcement, forming, installation of asphalt, connection to existing concrete pavement, cleanup and all material, labor, equipment and incidentals complete and in place
110 LF $ -
Class 'F' Surface Replacement Solid Block Sod, including all necessary preparation, installation of salvaged topsoil, watering, and all material, labor, equipment and incidentals complete and in place
1184 SY $ -
Class 'F' Surface Replacement Hydromulch Seeding, including all necessary preparation, installation of salvaged topsoil, watering, and all material, labor, equipment and incidentals complete and in place
2282 SY $ -
Temporary Street Replacement, including installation of prime coat on gravel trench backfill, installation of 2" HMAC Type"C", installation of temporary striping as required, saw cutting and removal of material upon acceptance of utility, disposal of removed material, and all material, labor, equipment and incidentals complete and in place
4575 LF $ -
Installation of Reflective Pavement Markings and Markers(All Types), including all necessary surface preparation, removal of temporary striping, and all material, labor, equipment, and incidentals, complete and in place
1 LS $ -
Removal & Replacement of Existing Fence (all Types), including removal and disposal of existing wire, posts, foundations, installation of new posts, foundations, necessary bracing, wire and all material, labor, equipment and incidentals complete and in place
40 LF $ -
8" Diameter Steel Bollards, including excavation, placement, any necessary surface repair, and all material, labor, equipment and incidentals complete and in place
24 EA $ -
American Plaza to Exchange Parkway Water Transmission Line Improvements, Phase II
BID PROPOSAL
RFB 2024-055 Page 21
Removal and Replacement of Reinforced Concrete Channel, including sawcutting, subgrade preparation, forming, dowels, reinforcement, placement of concrete, and all material, labor, equipment, and incidentals complete and in place.
525 SF $ -
Removal and Replacement of Existing Concrete Drive Approach, including sawcutting, subgrade preparation, forming, dowels, reinforcement, placement of concrete, and all material, labor, equipment, and incidentals complete and in place.
210 SF $ -
81 Furnish and Install Galvanized Steel Delineator Post and Signage (All Types), including all material, labor, equipment, and incidentals, complete and in place
1 EA $ -
Tapco Round Dometop Utility Water Marker, including all material, labor, equipment, and incidentals, complete and in place
4 EA $ -
SUBTOTAL - MISCELLANEOUS IMPROVEMENTS $ -
TOTAL BASE BID AMOUNT -$
American Plaza to Exchange Parkway Water Transmission Line Improvements, Phase II
BID PROPOSAL
RFB 2024-055 Page 22
BID PROPOSAL
THIS COMPLETE FORM MUST BE SUBMITTED WITH BID
SIGNATURE PAGE
SUBCONTRACTOR TYPE OF WORK
FIRM NAME:
BY:
TITLE:
ADDRESS:
Contractor acknowledges and agrees that the official TOTAL AMOUNT OF BID is determined by multiplying the unit bid prices by the respective estimated quantities shown in this bid proposal and then totaling all of the extended amounts.
Extended amounts SHOULD NOT be rounded up or down. All dollar amounts should be either written legibly or typed.
Any mistakes should be rewritten and initialed by the Contractor.
The General Contractor must self perform a minimum of 51% of the work in the awarded contract.
I WILL USE THE FOLLOWING SUBCONTRACTORS FOR THIS WORK:
American Plaza to Exchange Parkway Water Transmission Line Improvements, Phase II
BID PROPOSAL
RFB 2024-055 Page 23
File details come from the government source that posted it. Updated .