ESBD_358125_1714683788600_381859-25-24-05-plans.pdf

PDF 3 MB Posted

Attached to
RFC 381859-25-24-05 Fire Repairs, Childress DHQ
Solicitation number
381859-25-24-05
Issued by
Cherokee County, Texas

About this file

This document contains construction plans and specifications for a repair project at the Childress District Headquarters (DHQ) facility in Childress County, Texas. The project scope includes restoration of a pre-engineered metal building to its pre-fire condition, including replacement of metal siding, overhead doors, electrical conduit and wiring, lights, and other damaged appurtenances. The work must comply with applicable building codes, including the International Building Code, Texas Accessibility Standards, and National Electric Code. The project has a contract number of 38-1859-25-24-05 and the lead agency is the Texas Department of Transportation.

The repair plans provide detailed information on the required work, including keyed notes describing specific items to be removed and replaced. The electrical plans identify locations where light fixtures, wiring, and circuits need to be removed and replaced. The project also includes minor concrete and masonry repairs. No specific quantities or pricing terms are included in the documents provided. The project timeline or procurement schedule is not stated.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL NOTES

1. WORK SHALL CONFORM TO THE CONSTRUCTION DOCUMENTS &

APPLICABLE BUILDING CODES (INCLUDING FEDERAL & STATE CODES,

ORDINANCES, REGULATIONS, ETC.) CONSTRUCTION DOCUMENTS

INCLUDE DRAWINGS & SPECIFICATIONS PLUS ANY ADDENDA TO THE

AFOREMENTIONED.

2. CONSTRUCTION DOCUMENTS ARE INTENDED TO INCLUDE ITEMS

NECESSARY TO CONVEY DESIGN INTENT OF THE WORK.

MANUFACTURERS' INSTRUCTIONS SHALL BE CONSIDERED AS PART OF

THE SPECIFICATIONS WHETHER INCLUDED OR NOT IN THE

SPECIFICATION MANUAL.

3. PERIODIC SITE VISITS BY OWNER'S REPRESENTATIVE SHALL NOT BE

CONSTRUED AS SUPERVISION OF MEANS, METHODS, TECHNIQUES,

SEQUENCES OR PROCEDURES FOR CONSTRUCTION, NOR IMPLY

RESPONSIBILITY FOR PROVIDING A SAFE PLACE FOR PERFORMANCE

OF WORK BY CONTRACTOR OR CONTRACTOR'S EMPLOYEES, OR

EMPLOYEES OF SUPPLIERS, OR FOR ACCESS, VISITS, USE, WORK,

TRAVEL, OR OCCUPANCY BY ANY PERSON.

4. CONTRACTOR IS RESPONSIBLE FOR CONTINUOUS SECURITY AT

AFFECTED OPENINGS FOR THE DURATION OF THE COSNTRUCTION

CONTRACT. COORDINATE SECURITY STATUS CHANGES W/ DISTRICT

REPRESENTATIVE PRIOR TO IMPLEMENTING CHANGES.

5. CONTRACTOR SHALL:

- VERIFY DIMENSIONS & FIELD CONDITIONS BEFORE PROCEEDING.

- NOTIFY ARCHITECT OF FIELD CONDITIONS REQUIRING DEVIATIONS

FROM CONSTRUCTION DOCUMENTS BEFORE THE CONSTRUCTION

OF ANY MODIFICATION.

- PROVIDE ADEQUATE BRACING & SHORING AS NECESSARY UNTIL

PERMANENT SUPPORTS & STIFFENERS ARE INSTALLED.

- IMMEDIATELY REPAIR OR REPLACE DAMAGED OR DEFECTIVE

WORK TO THE APPROVAL OF (AND AT NO ADDITIONAL COST TO)

THE OWNER

- NOTIFY ARCHITECT & APPROPRIATE INSPECTORS AT CRITICAL

CONSTRUCTION MILESTONES IN ORDER TO OBTAIN NECESSARY

APPROVALS & INSPECTIONS PRIOR TO COMMENCEMENT OF

SUBSEQUENT WORK.

- TAKE REASONABLE PRECAUTIONS FOR THE SAFETY OF, AND

PROVIDE REASONABLE PROTECTION TO PREVENT DAMAGE,

INJURY OR LOSS TO:

a) EMPLOYEES & ALL OTHER AFFECTED PERSONS

b) ALL WORK, MATERIALS & EQUIPMENT

c) OTHER PROPERTY AT SITE OR ADJACENT THERETO.

- UPON COMPLETION OF THE WORK, REMOVE MATERIALS, TOOLS &

EQUIPMENT AND LEAVE SITE IN A CONDITION ACCEPTABLE TO

OWNER.

PROJECT

LOCATION

NORTH

THIS PROJECT INCLUDES RESTORATION OF A PRE-ENGINEEERED METAL BUILDING TO PRE-FIRE CONDITION. SCOPE INCLUDES REPLACEMENT OF METAL SIDING, OVERHEAD DOORS, ELECTRICAL CONDUIT AND WIRING, LIGHTS AND OTHER DAMAGED APPURTENANCES. SCOPE INCLUDES

CLEANING OF FIRE STAINING. SCOPE INCLUDES MINOR REPAIRS TO CONCRETE AND CMU.

COVERED ENTRY PORCH: ### SQFT.

OFFICE: #,### SQFT.

SHOP / STORAGE: #,### SQFT.

TRUCK WASH / EQUIP. ROOM: #,### SQFT.

MATERIAL SHED: #,### SQFT.

TOTAL SCOPE: NOT APPLICABLE.

TOTAL STAFF: ## FTEs

SCOPE OF WORK:

BUILDING SUMMARY: TDLR REGISTRATION:

EABPRJ NOT APPLICABLE TO REPAIR

BUILDING CODES:

INTERNATIONAL BUILDING CODE IBC - 2021

AMERICANS W/ DISABILITIES ACT ADAAG - 2010

TEXAS ACCESSIBILITY STANDARDS TAS - 2012

INTERNATIONAL ENERGY CODE IECC - 2018

INTERNATIONAL MECHANICAL CODE IMC - 2021

ASHRAE 62.1 - 2016

INTERNATIONAL PLUMBING CODE IPC - 2021

INTERNATIONAL FUEL AND GAS CODE IFGC- 2021

NATIONAL ELECTRIC CODE NEC - 2023

NATIONAL FIRE CODE NFPA 1 - 2021

NATIONAL LIFE SAFETY CODE NFPA 101 - 2021

TxDOT STANDARD SPECS FOR ... STREETS - 2014

WICHITA

FALLS

BEAUMONT

PARIS

ATLANTA

BRYAN

BROWNWOOD

AMARILLO

ABILENE

CHILDRESS

FORT

WORTH

CORPUS

CHRISTI

DALLAS

EL PASO

HOUSTON

LAREDO

LUBBOCK

LUFKIN

ODESSA

SAN

ANGELO

SAN

ANTONIO

YOAKUM

WACO

TYLER

PHARR

CHILDRESS COUNTY, TX

CHILDRESS DISTRICT (25)

Support Services Division / Facilities Planning & Management

COPYRIGHT 2022 TEXAS DEPTARTMENT OF TRANSPORTATION

6230 E. Stassney LN Austin, Texas 78744-3147 c

VICINITY MAP

INDEX OF DRAWINGS

PROJECT:

Project Manager:

STRUCTURE:

G E

N E

R A

T E

D O

N

NOT FOR REGULATORY

APPROVAL, PERMITTING,

OR CONSTRUCTION

SUBMITTAL

/2

/2

:5 :1

A

M C

U s e rs

\A S

T O

N E

\D o w n lo a d s \c h ild re s s C

H S

\C H

S D

H Q f ir e r e p a ir .r v t

C H

IL

D

R E

S S

D H

Q

F

IR

E R

E P

A

IR

P R

O J E

C T

N U

M B

E R

-1

-2

-2

-0

PROJECT NUMBER: 38-1859-25-24-05

SITE # 259036

BUILDING # 258063

CHRISTOPHER BECK

806-224-6737

CHRISTOPHER.BECK@TXDOT.GOV

CHILDRESS DHQ - FIRE REPAIR

NAME

Phone: (###) ###-#### E-mail: EMAIL@TXDOT.GOV

7599 US 287, CHILDRESS, TEXAS, 79201

_GENERAL

G2.01 REPAIR FLOOR PLAN

G3.01 LIGHTING REPAIR PLAN

G4.01 POWER REPAIR PLAN

G5.01 BUILDING REPAIR ELEVATIONS

_EXISTING CONSTRUCTION

D-N/a SELECTED EXISTING

CONSTRUCTION SHEETS

04/29/2024

REPAIR KEYED NOTES

1. REMOVE, AND REPLACE WITH NEW, EXTERIOR METAL WALL PANELS

FROM END OF BUILDING TO RIGHT HAND SIDE OF SECOND DOOR.

REPLACE FROM TOP OF CMU WALL TO EAVE. MATCH EXISTING IN KIND.

2. REMOVE, AND REPLACE WITH NEW, SPLIT FACE CMU FROM RIGHT

HAND EDGE OF FIRST DOOR TO 7 BLOCKS TO THE RIGHT. REPLACE WITH

FACTORY EDGE PIECES AND COMPLETE BLOCK ONLY. MATCH EXISTING.

3. REMOVE, AND REPLACE WITH NEW, EXHAUST FANS IN KIND.

4. REMOVE, AND REPLACE WITH NEW, LOUVERS, FRAMING AND ALL

ACCESSORIES ASSOCIATED WITH EXHAUST FANS IN KIND.

5. REMOVE, AND REPLACE WITH NEW, FLASHING ABOVE CANOPY FROM

END OF BUILDING TO RIGHT HAND SIDE OF SECOND DOOR. MATCH OR

EXCEED EXISTING.

6. REMOVE, AND REPLACE WITH NEW, INTERIOR METAL PANELS FROM

END OF BUILDING TO CMU WALL LABELED 6A.. SEE FLOOR PLAN.

7. REMOVE, AND REPLACE WITH NEW, WARPED GIRTS FROM EDGE OF

FIRST DOOR TO PEMB FRAMELINE. SEE FLOOR PLAN. .

8. CLEAN AND REPAINT BOLLARD TO MATCH EXISTING.

9. CLEAN AND REPAINT PILASTER TO MATCH EXISTING.

10. REMOVE, AND REPLACE WITH NEW, OVERHEAD COILING DOOR,

OPENING MECHANISM, WIRING, FRAMING AND ALL ACCESSORIES

ASSOCIATED WITH OVERHEAD DOOR. MATCH OR EXCEED EXISTING.

11. REMOVE, AND REPLACE WITH NEW, OVERHEAD DOOR, OPENING

MECHANISM WIRING AND CIRCUT, AND OTHER ACCESSORIES. MATCH OR

EXCEED EXISTING.

12 REMOVE SPALLED CONCRETE AND PATCH WITH PORTLAND CEMENT

BASED PATCHING MATERIAL SUCH AS SIKASET MORTAR OR OTHER

APPROVED MATERIAL.

13. CLEAN REMAINDER OF UNDERSIDE OF SOFFIT TO CORNER OF

BUILDING

14.CLEAN REMAINDER OF FACE OF CANOPY, AND CLEARANCE SIGNS TO

CORNER OF BUILDING.

15. REMOVE, AND REPLACE WITH NEW, SOFFIT METAL PANELS AND FACE

OF CANOPY FOR THREE BAYS. MATCH EXISTING.

ELECTRICAL KEYED NOTES

A. REMOVE, AND REPLACE WITH NEW, LIGHT FIXTURES, WIRING,

CONDUIT AND CIRCUIT UNDER FIRST THREE BAYS OF CANOPY. SEE

INFORMATIONAL SPECIFICATIONS.

B. REMOVE, AND REPLACE WITH NEW, FIRST THREE EXTERIOR WALL

PACK LIGHTS, WIRING, CONDUIT AND CIRCUIT. SEE INFORMATIONAL

SPECIFICATIONS.

C. REMOVE, AND REPLACE WITH NEW, ELECTRICAL CIRCUIT, WIRING AND

CONDUITS FOR EXHAUST FANS.

D. REMOVE, AND REPLACE WITH NEW, ELECTRICAL CIRCUIT, WIRING AND

CONDUITS FOR FIRST TWO OVERHEAD DOORS.

E. REMOVE, AND REPLACE WITH NEW, DAMAGED ELECTRICAL CIRCUIT,

WIRING AND CONDUITS FOR OVERHEAD SHOP CRANE.

F. CLEAN REMAINDER OF WALL PACK LIGHTS TO CORNER OF BUILDING.

G. REPLACE WIRING AND LIGHT FIXTURES UNDER CANOPY, FIVE BAYS.

F

6A

G

THIS DRAWING CREATED FOR PRODUCTION ON 22"x34" SHEET SIZE. DO NOT SCALE PRINTS.

G E

N E

R A

T E

D O

N

REVISIONS:

COPYRIGHT 2021c

Texas of Transportation Department

R

NOT FOR REGULATORY

APPROVAL, PERMITTING,

OR CONSTRUCTION

SUBMITTAL

/2

/2

:1 :4

P

M C

U s e rs

\A S

T O

N E

\D o w n lo a d s \c h ild re s s C

H S

\C H

S D

H Q f ir e r e p a ir .r v t

G2.01

C H

IL

D

R E

S S

D H

Q

F

IR

E R

E P

A

IR

U S

C H

IL

D

R E

S S

T

E X

A S

P R

O J E

C T

N O

-1

-2

-2

-0

DRAWN BY: Author

ISSUED: 11/22/2019

C H

IL

D

R E

S S

C H

IL

D

R E

S S

C O

U N

T Y

REPAIR FLOOR PLAN

CHECKED BY: Checker

FLOOR PLAN NOTES

1. CONTRACTOR IS RESPONSIBLE FOR CONTINUOUS SECURITY AT

AFFECTED OPENINGS FOR THE DURATION OF THE COSNTRUCTION

CONTRACT. COORDINATE SECURITY STATUS CHANGES W/ DISTRICT

REPRESENTATIVE PRIOR TO IMPLEMENTING CHANGES.

2. INFORMATION CONCERNING EXISTING CONDITIONS IS SUITABLE FOR

PREPARATION OF THE DRAWINGS & GIVEN FOR THE CONTRACTOR'S

CONVENIENCE.

3. ENGINEER DOES NOT GUARANTEE ACCURACY OF SUCH

INFORMATION. IT IS CONTRACTOR'S RESPONSIBILITY TO INFORM

HIMSELF & NECESSARY OFFICIALS AS TO THE CONDITIONS AFFECTING

THE WORK.

4. WHERE CONSTRUCTION FEATURES EXIST, VERIFY DIMENSIONS WITH

FIELD CONDITIONS

5. COORDINATE ALL TRADES TO ENSURE COMPLETE & WORKING

INSTALLATIONS.

6. NOTIFY ENGINEER OF ANY DISCREPANCIES.

AIR QUALITY / ENERGY NOTES

1. LIMIT AIR INFILTRATION INTO CONDITIONED AND/OR OCCUPIED SPACES

BY SEALING, CAULKING, GASKETING, AND/OR WEATHER-STRIPPING

THE FOLLOWING:

- EXTERIOR JOINTS AROUND WINDOWS & DOOR FRAMES

- OPENINGS BETWEEN EXTERIOR WALLS & FOUNDATIONS

- OPENINGS BETWEEN EXTERIOR WALLS & ROOF

- OPENINGS AT PENETRATIONS OF UTILITIES THROUGH EXTERIOR

FLOORS, WALLS AND/OR ROOFS

- ALL OTHER SUCH OPENINGS IN THE BUILDING ENVELOPE.

2. PROVIDE IC-RATED RECESSED LIGHTING FIXTURES WHERE ADJACENT

TO INSULATION OTHER THAN CLOSED-CELL SPRAY FOAM.

G5.01

B

A

G

ELECTRICAL KEYED NOTES

A. REMOVE, AND REPLACE WITH NEW, LIGHT FIXTURES, WIRING,

CONDUIT AND CIRCUIT UNDER FIRST THREE BAYS OF CANOPY. SEE

INFORMATIONAL SPECIFICATIONS.

B. REMOVE, AND REPLACE WITH NEW, FIRST THREE EXTERIOR WALL

PACK LIGHTS, WIRING, CONDUIT AND CIRCUIT. SEE INFORMATIONAL

SPECIFICATIONS.

C. REMOVE, AND REPLACE WITH NEW, ELECTRICAL CIRCUIT, WIRING AND

CONDUITS FOR EXHAUST FANS.

D. REMOVE, AND REPLACE WITH NEW, ELECTRICAL CIRCUIT, WIRING AND

CONDUITS FOR FIRST TWO OVERHEAD DOORS.

E. REMOVE, AND REPLACE WITH NEW, DAMAGED ELECTRICAL CIRCUIT,

WIRING AND CONDUITS FOR OVERHEAD SHOP CRANE.

F. CLEAN REMAINDER OF WALL PACK LIGHTS TO CORNER OF BUILDING.

G. REPLACE WIRING AND LIGHT FIXTURES UNDER CANOPY, FIVE BAYS.

REPAIR KEYED NOTES

1. REMOVE, AND REPLACE WITH NEW, EXTERIOR METAL WALL PANELS

FROM END OF BUILDING TO RIGHT HAND SIDE OF SECOND DOOR.

REPLACE FROM TOP OF CMU WALL TO EAVE. MATCH EXISTING IN KIND.

2. REMOVE, AND REPLACE WITH NEW, SPLIT FACE CMU FROM RIGHT

HAND EDGE OF FIRST DOOR TO 7 BLOCKS TO THE RIGHT. REPLACE WITH

FACTORY EDGE PIECES AND COMPLETE BLOCK ONLY. MATCH EXISTING.

3. REMOVE, AND REPLACE WITH NEW, EXHAUST FANS IN KIND.

4. REMOVE, AND REPLACE WITH NEW, LOUVERS, FRAMING AND ALL

ACCESSORIES ASSOCIATED WITH EXHAUST FANS IN KIND.

5. REMOVE, AND REPLACE WITH NEW, FLASHING ABOVE CANOPY FROM

END OF BUILDING TO RIGHT HAND SIDE OF SECOND DOOR. MATCH OR

EXCEED EXISTING.

6. REMOVE, AND REPLACE WITH NEW, INTERIOR METAL PANELS FROM

END OF BUILDING TO CMU WALL LABELED 6A.. SEE FLOOR PLAN.

7. REMOVE, AND REPLACE WITH NEW, WARPED GIRTS FROM EDGE OF

FIRST DOOR TO PEMB FRAMELINE. SEE FLOOR PLAN. .

8. CLEAN AND REPAINT BOLLARD TO MATCH EXISTING.

9. CLEAN AND REPAINT PILASTER TO MATCH EXISTING.

10. REMOVE, AND REPLACE WITH NEW, OVERHEAD COILING DOOR,

OPENING MECHANISM, WIRING, FRAMING AND ALL ACCESSORIES

ASSOCIATED WITH OVERHEAD DOOR. MATCH OR EXCEED EXISTING.

11. REMOVE, AND REPLACE WITH NEW, OVERHEAD DOOR, OPENING

MECHANISM WIRING AND CIRCUT, AND OTHER ACCESSORIES. MATCH OR

EXCEED EXISTING.

12 REMOVE SPALLED CONCRETE AND PATCH WITH PORTLAND CEMENT

BASED PATCHING MATERIAL SUCH AS SIKASET MORTAR OR OTHER

APPROVED MATERIAL.

13. CLEAN REMAINDER OF UNDERSIDE OF SOFFIT TO CORNER OF

BUILDING

14.CLEAN REMAINDER OF FACE OF CANOPY, AND CLEARANCE SIGNS TO

CORNER OF BUILDING.

15. REMOVE, AND REPLACE WITH NEW, SOFFIT METAL PANELS AND FACE

OF CANOPY FOR THREE BAYS. MATCH EXISTING.

THIS DRAWING CREATED FOR PRODUCTION ON 22"x34" SHEET SIZE. DO NOT SCALE PRINTS.

G E

N E

R A

T E

D O

N

REVISIONS:

COPYRIGHT 2021c

Texas of Transportation Department

R

NOT FOR REGULATORY

APPROVAL, PERMITTING,

OR CONSTRUCTION

SUBMITTAL

/2

/2

:1 :4

P

M C

U s e rs

\A S

T O

N E

\D o w n lo a d s \c h ild re s s C

H S

\C H

S D

H Q f ir e r e p a ir .r v t

G3.01

C H

IL

D

R E

S S

D H

Q

F

IR

E R

E P

A

IR

U S

C H

IL

D

R E

S S

T

E X

A S

P R

O J E

C T

N

-1

-2

-2

-0

DRAWN BY: DRAFTER

ISSUED: 11/22/2019

C H

IL

D

R E

S S

C H

IL

D

R E

S S

C O

U N

T Y

LIGHTING REPAIR PLAN

CHECKED BY: Checker

1/4" = 1'-0"

LIGHTING PLAN

D

C

C

D

E

ELECTRICAL KEYED NOTES

A. REMOVE, AND REPLACE WITH NEW, LIGHT FIXTURES, WIRING,

CONDUIT AND CIRCUIT UNDER FIRST THREE BAYS OF CANOPY. SEE

INFORMATIONAL SPECIFICATIONS.

B. REMOVE, AND REPLACE WITH NEW, FIRST THREE EXTERIOR WALL

PACK LIGHTS, WIRING, CONDUIT AND CIRCUIT. SEE INFORMATIONAL

SPECIFICATIONS.

C. REMOVE, AND REPLACE WITH NEW, ELECTRICAL CIRCUIT, WIRING AND

CONDUITS FOR EXHAUST FANS.

D. REMOVE, AND REPLACE WITH NEW, ELECTRICAL CIRCUIT, WIRING AND

CONDUITS FOR FIRST TWO OVERHEAD DOORS.

E. REMOVE, AND REPLACE WITH NEW, DAMAGED ELECTRICAL CIRCUIT,

WIRING AND CONDUITS FOR OVERHEAD SHOP CRANE.

F. CLEAN REMAINDER OF WALL PACK LIGHTS TO CORNER OF BUILDING.

G. REPLACE WIRING AND LIGHT FIXTURES UNDER CANOPY, FIVE BAYS.

THIS DRAWING CREATED FOR PRODUCTION ON 22"x34" SHEET SIZE. DO NOT SCALE PRINTS.

G E

N E

R A

T E

D O

N

REVISIONS:

COPYRIGHT 2021c

Texas of Transportation Department

R

NOT FOR REGULATORY

APPROVAL, PERMITTING,

OR CONSTRUCTION

SUBMITTAL

/2

/2

:1 :4

P

M C

U s e rs

\A S

T O

N E

\D o w n lo a d s \c h ild re s s C

H S

\C H

S D

H Q f ir e r e p a ir .r v t

G4.01

C H

IL

D

R E

S S

D H

Q

F

IR

E R

E P

A

IR

U S

C H

IL

D

R E

S S

T

E X

A S

P R

O J E

C T

N

-1

-2

-2

-0

DRAWN BY: Author

ISSUED: 11/22/2019

C H

IL

D

R E

S S

C H

IL

D

R E

S S

C O

U N

T Y

POWER REPAIR PLAN

CHECKED BY: Checker

EXTERIOR ELEVATION NOTES

1. DIMENSIONS GIVEN ARE TO FACE OF FRAMING, UNLESS INDICATED

OTHERWISE.

2. WHERE CONSTRUCTION FEATURES EXIST, VERIFY DIMENSIONS WITH

FIELD CONDITIONS & NOTIFY ARCHITECT OF DISCREPANCIES.

3. INFORMATION CONCERNING EXISTING CONDITIONS IS SUITABLE FOR

THE PREPARATION OF THE DRAWINGS & GIVEN FOR THE

CONTRACTOR'S CONVENIENCE. ARCHITECT DOES NOT GUARANTEE

ACCURACY OF SUCH INFORMATION. IT IS THE CONTRACTOR'S

RESPONSIBILITY TO INFORM HIMSELF & NECESSARY OFFICIALS AS TO

THE CONDITIONS AFFECTING THE WORK.

10 2

3 34 4

REPAIR KEYED NOTES

1. REMOVE, AND REPLACE WITH NEW, EXTERIOR METAL WALL PANELS

FROM END OF BUILDING TO RIGHT HAND SIDE OF SECOND DOOR.

REPLACE FROM TOP OF CMU WALL TO EAVE. MATCH EXISTING IN KIND.

2. REMOVE, AND REPLACE WITH NEW, SPLIT FACE CMU FROM RIGHT

HAND EDGE OF FIRST DOOR TO 7 BLOCKS TO THE RIGHT. REPLACE WITH

FACTORY EDGE PIECES AND COMPLETE BLOCK ONLY. MATCH EXISTING.

3. REMOVE, AND REPLACE WITH NEW, EXHAUST FANS IN KIND.

4. REMOVE, AND REPLACE WITH NEW, LOUVERS, FRAMING AND ALL

ACCESSORIES ASSOCIATED WITH EXHAUST FANS IN KIND.

5. REMOVE, AND REPLACE WITH NEW, FLASHING ABOVE CANOPY FROM

END OF BUILDING TO RIGHT HAND SIDE OF SECOND DOOR. MATCH OR

EXCEED EXISTING.

6. REMOVE, AND REPLACE WITH NEW, INTERIOR METAL PANELS FROM

END OF BUILDING TO CMU WALL LABELED 6A.. SEE FLOOR PLAN.

7. REMOVE, AND REPLACE WITH NEW, WARPED GIRTS FROM EDGE OF

FIRST DOOR TO PEMB FRAMELINE. SEE FLOOR PLAN. .

8. CLEAN AND REPAINT BOLLARD TO MATCH EXISTING.

9. CLEAN AND REPAINT PILASTER TO MATCH EXISTING.

10. REMOVE, AND REPLACE WITH NEW, OVERHEAD COILING DOOR,

OPENING MECHANISM, WIRING, FRAMING AND ALL ACCESSORIES

ASSOCIATED WITH OVERHEAD DOOR. MATCH OR EXCEED EXISTING.

11. REMOVE, AND REPLACE WITH NEW, OVERHEAD DOOR, OPENING

MECHANISM WIRING AND CIRCUT, AND OTHER ACCESSORIES. MATCH OR

EXCEED EXISTING.

12 REMOVE SPALLED CONCRETE AND PATCH WITH PORTLAND CEMENT

BASED PATCHING MATERIAL SUCH AS SIKASET MORTAR OR OTHER

APPROVED MATERIAL.

13. CLEAN REMAINDER OF UNDERSIDE OF SOFFIT TO CORNER OF

BUILDING

14.CLEAN REMAINDER OF FACE OF CANOPY, AND CLEARANCE SIGNS TO

CORNER OF BUILDING.

15. REMOVE, AND REPLACE WITH NEW, SOFFIT METAL PANELS AND FACE

OF CANOPY FOR THREE BAYS. MATCH EXISTING.

AIR QUALITY / ENERGY NOTES

1. LIMIT AIR INFILTRATION INTO CONDITIONED AND/OR OCCUPIED SPACES

BY SEALING, CAULKING, GASKETING, AND/OR WEATHER-STRIPPING

THE FOLLOWING:

- EXTERIOR JOINTS AROUND WINDOWS & DOOR FRAMES

- OPENINGS BETWEEN EXTERIOR WALLS & FOUNDATIONS

- OPENINGS BETWEEN EXTERIOR WALLS & ROOF

- OPENINGS AT PENETRATIONS OF UTILITIES THROUGH EXTERIOR

FLOORS, WALLS AND/OR ROOFS

- ALL OTHER SUCH OPENINGS IN THE BUILDING ENVELOPE.

2. PROVIDE IC-RATED RECESSED LIGHTING FIXTURES WHERE ADJACENT

TO INSULATION OTHER THAN CLOSED-CELL SPRAY FOAM.

THIS DRAWING CREATED FOR PRODUCTION ON 22"x34" SHEET SIZE. DO NOT SCALE PRINTS.

G E

N E

R A

T E

D O

N

REVISIONS:

COPYRIGHT 2021c

Texas of Transportation Department

R

NOT FOR REGULATORY

APPROVAL, PERMITTING,

OR CONSTRUCTION

SUBMITTAL

/2

/2

:1 :4

P

M

1 Date 1 Initials1

C U s e rs

\A S

T O

N E

\D o w n lo a d s \c h ild re s s C

H S

\C H

S D

H Q f ir e r e p a ir .r v t

G5.01

C H

IL

D

R E

S S

D H

Q

F

IR

E R

E P

A

IR

U S

C H

IL

D

R E

S S

T

E X

A S

P R

O J E

C T

N

-1

-2

-2

-0

DRAWN BY: Author

ISSUED: 11/22/2019

C H

IL

D

R E

S S

C H

IL

D

R E

S S

C O

U N

T Y

BUILDING REPAIR ELEVATIONS

CHECKED BY: Checker

For information only

Amy Stone Checker Line

Amy Stone Checker Line

Sheets
G0.0 - COVER SHEET

File details come from the government source that posted it. Updated .