ES7034 (Attachment 5).pdf
PDF 184 KB Posted
- Attached to
- F-15 SMDC Federal contract opportunity
- Solicitation number
- FA8213-20-R-3010
About this file
This document provides guidance on rework and repair of nonconforming materials for a federal contractor. It defines rework as reprocessing material to fully conform to requirements, while repair reduces but does not eliminate nonconformance. For rework, the contractor must document procedures and inspection methods for government review and approval before use. For repair, the contractor must submit procedures on a Request for Deviation/Waiver form to the contracting officer for written approval. With any submission, the contractor must describe the nonconformance cause and corrective actions. Reworked or repaired items must pass reinspection according to a procedure ensuring government assurance of meeting standards, which takes precedence over technical data package requirements. These requirements flow down to all subcontractors, suppliers and vendors.
The related federal contract opportunity is solicitation number FA8213-20-R-3010 for F-15 SMDC services through the Air Force Materiel Command Lifecycle Management Center at Hill Air Force Base.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| F01-333-9317 SPI.pdf | ||
| F010174540 SPI2.pdf | ||
| QALI F-15 SMDC.pdf | ||
| FD2020-20-50006 (USAF)_50007 (FMS)_CDRLS_updated.pdf | ||
| REPSHIP 11 Mar 14.pdf | ||
| EDL_010697777.pdf | ||
| FA821320R3010.pdf | ||
| Bid Sets 20-50007.pdf | ||
| ADC SOW Jan 2018.pdf | ||
| PHST-SOW w_Packaging.pdf | ||
| F01-069-7776 SPI.pdf | ||
| 20-50006 Bid Sets.pdf | ||
| TransInstruction15.pdf | ||
| F01-069-7777 SPI.pdf | ||
| EDL_013339317.pdf | ||
| EDL_010697776.pdf | ||
| AIR SPEC updated.pdf | ||
| CADPAD Item Marking Instruction - Ver 1.5 - 20190501.pdf | ||
| F010142406 SPI1.pdf |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5
(ES7034)
REWORK AND REPAIR OF NONCONFORMING MATERIAL
Jan 2012 (version)
(a) Rework and Repair are defined as follows:
(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
(c) Repair procedures shall be documented by the Contractor and submitted on a Request for
Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the
Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.
(End of clause)