This document is an Engineer's Estimate for two stream restoration and riparian reclamation projects funded by the South Carolina Office of Resilience (SCOR) through an ARPA-funded Stormwater Infrastructure Program (ASIP) grant for Greenville County. The project consists of two separate locations: Little Creek and North Chastain, totaling approximately 12 acres of restoration work. The projects involve stream restoration, reforestation, and riparian area reclamation along previously acquired floodplain buyout properties in the Reedy River watershed. The restoration work includes bank grading, soil lifts, coir and turf reinforcement matting, boulder walls, bank toe treatments, and installation of instream features like cross vanes, boulder riffles, and single arm vanes.

The total estimated project cost is $1,391,916.13, with the North Chastain project estimated at $591,483.83 and the Little Creek project estimated at $800,432.29. Key line items include mobilization, erosion and sediment control, clearing and grubbing, excavation, various stream restoration features, vegetation establishment, and plantings. All spoil material will be taken to Blackberry Valley Residential Waste and Recycling Center at no tipping fee, and boulders are available at no cost from Twin Chimneys Landfill. The project's Notice to Proceed is contingent on pending permit approvals, with the estimated timeline set for November 2024.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM # DESCRIPTION QTY UNIT UNIT PRICE TOTAL PRICE

1 MOBILIZATION - LS - 53,771.26$

2 AS-BUILTS - LS - 5,600.00$

3 EROSION AND SEDIMENT CONTROL - LS 7,825.93$ 49,303.33$

4 CLEARING AND GRUBBING 1.9 AC 7,903.09$ 15,015.87$

EXCAVATION, FILLING, AND GRADING

(CUT=2250CY, FILL=420CY, NET=1830CY)

1,830 CY 61.50$ 112,539.96$

6 CROSS VANE 1 EA 9,800.00$ 9,800.00$

7 SINGLE ARM VANE 2 EA 4,900.00$ 9,800.00$

8 BOULDER WALL 1 EA 9,744.00$ 9,745.00$

9 BOULDER RIFFLE 4 EA 3,900.00$ 15,600.00$

10 BOULDER TOE 510 LF 131.25$ 66,937.50$

11 TOE ROCK 980 LF 61.25$ 60,025.00$

COIR TURF REINFORCEMENT MATTING

(700G)

4,440 SY 17.39$ 77,211.60$

COIR TURF REINFORCEMENT MATTING

(320G)

1,160 SY 5.82$ 6,751.20$

14 PERMANENT TRM 150 SY 39.25$ 5,887.50$

TURF ERADICATION AND SEEDBED

PREPARATION

4.4 AC 2,250.00$ 9,900.00$

SEEDING, MULCHING AND VEGETATION

ESTABLISHMENT

6.3 AC 3,750.00$ 23,625.00$

17 LIVE STAKES 100 BN 100.00$ 10,000.00$

18 BALLED BURLAPPED TREE/SHRUB 7 EA 550.00$ 3,850.00$

19 7-GALLON TREE/SHRUB 7 EA 144.00$ 1,008.00$

20 3-GALLON TREE/SHRUB 504 EA 49.00$ 24,696.00$

21 PLUGS/BARE ROOT STEMS 2,256 EA 6.50$ 14,664.00$

22 HEADWALL 1 EA 5,000.00$ 5,752.61$

591,483.83$

NORTH CHASTAIN STREAM RESTORATION AND RIPRARIAN RECLAMATION:

ENGINEER'S ESTIMATE

NOV 2024

TOTAL

*NOTE: ALL SPOIL MATERIAL IS TO BE TAKEN TO BLACKBERRY VALLEY RESIDENTIAL WASTE AND RECYCLING

CENTER AT 409 BLACKBERRY VALLEY ROAD, GREENVILLE SC 29617. THERE WILL BE NO TIPPING FEE.

ITEM # DESCRIPTION QTY UNIT UNIT PRICE TOTAL PRICE

1 MOBILIZATION - LS - 70,380.21$

2 AS-BUILTS - LS - 6,200.00$

3 EROSION AND SEDIMENT CONTROL - LS 10,846.19$ 75,923.33$

4 CLEARING AND GRUBBING 2 AC 6,293.18$ 10,698.41$

EXCAVATION, FILLING, AND GRADING

(CUT=2950CY, FILL=530CY, NET=2420CY)

2,950 CY 49.83 146,994.64$

6 CROSS VANE 1 EA 9,800.00$ 9,800.00$

7 SINGLE ARM VANE 2.0 EA 4,900.00$ 9,800.00$

8 BOULDER TOE 840 LF 262.50$ 110,250.00$

9 TOE ROCK 1,350 LF 61.25$ 82,687.50$

COIR TURF REINFORCEMENT MATTING

(700G)

3,000 SY 17.39$ 52,170.00$

COIR TURF REINFORCEMENT MATTING

(320G)

1,600 SY 5.82$ 9,021.00$

12 PERMANENT TRM 1,600 SY 47.94$ 75,745.20$

13 VEGETATED CONCRETE BLOCK MATTING 200 SY 220.00$ 44,000.00$

TURF ERADICATION AND SEEDBED

PREPARATION

5 AC 2,250.00$ 11,925.00$

SEEDING, MULCHING AND VEGETATION

ESTABLISHMENT

7.0 AC 3,750.00$ 26,250.00$

16 LIVE STAKES 100 BN 100.00$ 10,000.00$

17 BALLED BURLAPPED TREE/SHRUB 7 EA 550.00$ 3,850.00$

18 7-GALLON TREE/SHRUB 7 EA 144.00$ 1,008.00$

19 3-GALLON TREE/SHRUB 560 EA 49.00$ 27,440.00$

20 PLUGS/BARE ROOT STEMS 2,506 EA 6.50$ 16,289.00$

800,432.29$

1,391,916.13$

LITTLE CREEK STREAM RESTORATION AND RIPRARIAN RECLAMATION:

ENGINEER'S ESTIMATE

NOV 2024

PROJECT TOTAL

TOTAL

*NOTE: ALL SPOIL MATERIAL IS TO BE TAKEN TO BLACKBERRY VALLEY RESIDENTIAL WASTE AND RECYCLING CENTER AT 409 BLACKBERRY VALLEY ROAD, GREENVILLE SC 29617. THERE WILL BE NO TIPPING FEE.