This document appears to be a draft contract between Brookhaven Science Associates, LLC (BSA) and a contractor for the design, manufacture, inspection, testing, and delivery of fifteen (15) skid-mounted secondary unit substations for the Electron-Ion Collider (EIC) at Brookhaven National Laboratory.
The key details include:
- The contractor shall provide various deliverables including a program plan, shop drawings, progress reporting, acceptance test procedures, factory witness testing, installation instructions, and end item documentation.
- The delivery date for the final product is no later than May 21, 2027.
- The contract is a firm fixed price contract, with specific milestones and payment terms outlined.
- Freight terms are FOB Brookhaven National Laboratory for North American shipments and DAP (Delivered At Place) for foreign shipments.
- The procurement has been set aside for Minority and Women-Owned Business Enterprises (MWBE).
- The contract is issued pursuant to BSA's General and Supplemental Terms and Conditions.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Specialist Amount Contract Number
Kevin Kirkendall TBD 438602
BROOKHAVEN NATIONAL LABORATORY
Brookhaven Science Associates
P.O. Box 5000
UPTON, L.I., N.Y. 11973-5000
Name and Address of Contractor
CONTRACT
This Contract (the "Contract") is between the party named above (the "Contractor"), and
Brookhaven Science Associates, LLC. ("BSA"), the latter acting under a Prime Contract with the
United States of America (the "Government") represented by the United States Department of
Energy ("DOE”).
I. SCOPE OF WORK
The Contractor shall design, manufacture, inspect, test and deliver fifteen (15) Unit Sub-
Stations in accordance with Attachment (C) Statement of Work entitled “Statement of
Work for the Secondary Unit Substations for EIC” Doc. No. EIC-IFD-SOW-016, Rev 05, Dated May 22, 2024 and Attachment (D, Da) Specifications D Dated May 21, 2024 and
Da Dated December 14, 2023.
A. Reports/Deliverables: The Contractor shall provide the following deliverable(s) to and as directed by BSA’s Technical Representative:
Item Deliverable Due BSA Approval
1 Program Plan At award of contract Yes
Initial Shop Drawings for review
8 weeks after award of contract, or as determined at contract award
No
3 Final Shop
Drawings for review and approval
As set forth in contract Yes
4 Progress Reporting 2 weeks after the planned start of fabrication/ monthly thereafter
No
5 Acceptance Test
Procedure (ATP), for review and approval
8 weeks prior to start of factory testing
Yes
6 Factory Witness Testing Notify BSA 4 weeks in advance No
Acceptance Test Procedure
(ATP) Factory Witness
Testing Documentation, for review and approval
Delivery at conclusion of Factory
Witness Testing for each unit prior to shipment
Yes; BSA Approval following each inspection including testing reports
8 Installation Instructions 4 weeks prior to first delivery No
9 Delivery of equipment As set forth in the schedule Yes
10 End Item Documentation Within 1 week following final delivery or earlier
Yes
II. DELIVERY DATE:
The delivery date of a final product (Item 10 above) shall be no later than May 21, 2027.
III. FIRM FIXED PRICE AND PAYMENT
A. Firm Fixed Price: In full consideration of the Contractor's performance hereunder
BSA shall pay the Contractor the firm fixed price of TBD. The said sum shall constitute full compensation for all services and materials furnished hereunder.
B. Availability of Funds: Funds are not presently available for this Contract. BSA’s obligation under this Contract is contingent upon the availability of appropriated funds from which payment for contractual purposes can be made.
No legal liability on the part of BSA for any payment may arise until funds are made available for this Contract and until the Contractor receives notice of such availability to be confirmed in writing.
C. Payment: Payment will be made upon receipt and approval of properly certified invoices. Payment will be in accordance with the Milestone Payment Schedule.
D. Milestones Payment Schedule: BSA will pay the Contractor upon receipt and approval of invoices that list the work completed and the Contract number.
Payment will be made in accordance with the below Milestones Payment
Schedule. All payments require prior receipt and acceptance of the milestones listed by the BSA Technical Representative.
Milestones Payment Amount
Final Shop Drawings
Acceptance Test Procedure (ATP)
Factory Witness Testing Documentation
Delivery of Group 1
Delivery of Group 2
Delivery of Group 3
Delivery of Group 4
Maintenance Manuals, As-Built Drawings
Total
Payment terms are TBD.
Invoices shall be directed to BSA’s Accounts Payable Section via electronic or regular mail.
Electronic invoice submittal is preferred by BSA. The Contractor shall make every effort to have systems in place that allow for electronic invoice transmittal. Invoices shall be submitted in PDF format, via e-mail, to apinvoices@bnl.gov.
Hard copy invoices, in duplicate, shall be directed to BSA's Accounts Payable
Section, Contracts Division, Bldg. No. 400D.
The Contractor shall indicate the final invoice by clearly marking such invoice as
"FINAL". A copy of the final invoice must be submitted to BSA’s Contractual
Representative.
E. Freight: Freight terms shall be (for North American shipments insert:) FOB
Brookhaven National Laboratory, 98 Rochester Street, Upton, Long Island, New
York. Freight Prepaid, (for foreign shipments insert:) “DAP” Delivered At Place, Brookhaven National Laboratory, 98 Rochester Street, Upton, Long Island, New
York.
E. Shipping and Labeling: Unless otherwise specified, standard Shipping
Instructions apply. Standard Shipping Instructions are provided at https://www.bnl.gov/shipping/.
Two (2) weeks prior to delivery of all items the contractor shall contact BSA as to the type of freight carrier that will be used.
Delivery Hours:
All deliveries must arrive at BNL, at the above address, Building 98 between the hours of 8:00 am to 11:45 am or from 12:30 pm to 4:00 pm EST, Monday through
Friday. Any delivery outside normal delivery hours will NOT be accepted unless advanced notification was provided, and arrangements were made through
Receiving (631-344-2310, 631-344-4336, or 631-344-2300 or via email warehouseoperations@bnl.gov).
Special Notification of Delivery:
Advanced Notice, within 72 hours of expected delivery to BNL, shall be provided by the supplier or shipper to BNL’s Receiving department either by telephone at:
631-344-2310, 631-344-4336, or 631-344-2300, OR via email at:
warehouseoperations@bnl.gov due to weight, size, and/or volume parameters of the end item(s) requiring special material handling/rigging by BSA personnel.
Failure to contact BSA will result in delays during delivery and demurrage will be at the supplier’s/shipper’s expense.
Package Labeling Requirements:
All packages delivered to BNL must be labeled with the complete Purchase
Order/Contract Number as a minimum. Each shipping container (transport package) with a gross weight equal to or greater than 400 pounds (180 kilograms) must be marked with the center of gravity and gross weight on at least one side, or end panel in addition to meeting the requirements of the latest revision of ASTM
Standard D 3951-98, Standard Practice for Commercial Packaging. This applies to any item shipped (originally packaged or repackaged) to BNL or other locations cited in the purchase order or contract.
Ocean Shipments:
For foreign shipments that will be transported via ocean freight the 10-2
REQUIREMENTS Form located at https://www.bnl.gov/shipping/files/pdf/10-2-https://www.bnl.gov/shipping/ mailto:warehouseoperations@bnl.gov mailto:warehouseoperations@bnl.gov https://www.bnl.gov/shipping/files/pdf/10-2-security-filing-bnl-interfreight.pdf security-filing-bnl-interfreight.pdf must be completed by the supplier 72 hours before departure of the vessel. The form can either be faxed to Interfreight
Harmonized Logistics, Inc. at 516-371-6880 or emailed to BNL@interfreight.net.
A copy should also be emailed to warehouseoperations@bnl.gov. Once the form is submitted to customs an acceptance number will be given. No freight will be loaded on a vessel without this acceptance number.
Special notice regarding 10-2 Form: On July 9, 2013 US Customs and Border
Protection began full enforcement of Importer Security Filing (ISF) and will assess liquidated damages for violations. Failure to submit the 10-2 Form may result in fines from $5,000 up to $15,000. It is the Contractor’s responsibility to make sure
Form 10-2 is submitted 72 hours prior to the vessel sailing. BSA shall withhold payment from the Contractor’s final invoice for any penalties incurred by BSA due to late or incorrect ISF filing by the Contractor. For more information go to https://www.cbp.gov/border-security/ports-entry/cargo-security/importer-security-filing-102
All Ocean Bill of Ladings and Airway Bills must be addressed to:
Brookhaven National Laboratory
Bldg 98
Upton, New York 11973
In addition, the Contractor must notify:
Interfreight Harmonized Logistics Inc.
221 Sheridan Blvd.
Inwood, NY 11096 / USA
Phone 1-516-371-0775
The Contractor must fax or e-mail immediately to Interfreight copies of:
Ocean Bill of lading or Airway Bill
Commercial Invoice
Packing List
Fax 1-516-371-6880 e-mail BNL@interfreight.net
IV. AUTHORIZED REPRESENTATIVES
A. BSA’s Technical Representative: XXXX is BSA's Technical Representative, hereunder. He shall act as liaison between BSA and the Contractor in technical matters only and can be reached at XXXX@bnl.gov or at (631)344-XXXX.
B. BSA’s Contractual Representative: Kevin Kirkendall, located in Building
1005S, telephone no. (631)344-4605, kkirkenda@bnl.gov, is BSA's Contractual
Representative. Any change or modification in the terms and conditions of this contract shall require the written approval of BSA's Procurement and Property
Management Division’s Manager, or his designee.
C. Contractor’s Technical Representative: ______________________ is the
Contractor’s authorized Technical Representative, hereunder and shall act as point https://www.bnl.gov/shipping/files/pdf/10-2-security-filing-bnl-interfreight.pdf mailto:warehouseoperations@bnl.gov https://www.cbp.gov/border-security/ports-entry/cargo-security/importer-security-filing-102 https://www.cbp.gov/border-security/ports-entry/cargo-security/importer-security-filing-102 mailto:BNL@interfreight.net mailto:XXXX@bnl.gov mailto:kkirkenda@bnl.gov of contact between BSA and the Contractor in technical matters only. They can be reached at ____________________________________________________.
F. Contractor’s Contractual Representative: ____________________________is the Contractor’s authorized Contractual Representative, hereunder and shall act as liaison between BSA and the Contractor. They can be reached at ____________
V. ADDITIONAL TERMS
The provisions of Brookhaven Science Associates, LLC General Terms and Conditions for
Commercial Items and Services, Rev 22.0 Sept 2022, are incorporated herein and made a part hereof.
This Contract is issued pursuant to Brookhaven Science Associates General and/or
Supplemental terms and conditions listed above which are incorporated herein by reference. The complete text of these terms and conditions can be viewed via the internet at: PPM | Terms and Conditions (bnl.gov). Should the Contractor have any questions and/or not have access to these terms and conditions, contact the buyer or contracts specialist immediately.
The following documents attached hereto and made a part hereof, contain additional provisions of this contract:
Attachment (A): BSA General Terms and Conditions for Commercial Items and Services, Rev
22.0 Sept 2022
Attachment (B): BSA Supplemental Terms and Conditions for Work by Contractors on Site at
BNL – Rev 22.0; Sept 22
Attachment (C): Statement of Work Dated May 22, 2024
Attachment (D, Da): Specifications: D – Electrical Long Lead Package (LLP) and Da - BNL
Onelines
Attachment (E): BNL-QA-101 https://www.bnl.gov/ppm/terms-and-conditions.php
This Contract does not bind nor purport to bind the Government of the United States.
ACCEPTED:
CONTRACTOR BROOKHAVENSCIENCE
ASSOCIATES, LLC.
By: By:
Name: Name:
Title: Title:
Date: Date:
Should you accept this Contract without exception or alteration, one copy of the Contract executed by both parties shall be returned to BSA's Contractual Representative. Should you take any exceptions or attempt to alter the Contract in any manner, BSA's execution thereof shall be null and void. Should you wish to take exception(s)/alteration(s), you shall notify BSA's Contractual Representative. BSA will consider the requested exception(s)/alteration(s) and notify you accordingly. No Contract shall exist unless and until such differences are resolved.