This is a Firm Fixed Price contract between Brookhaven Science Associates, LLC (BSA) and an unnamed contractor for the design and delivery of a robotic system for autonomous preparation and characterization of solution-deposited thin films on rigid substrate samples. Contract Number 479928 is valued at TBD, with Crystal Lopez serving as BSA's Contractual Representative (631.344.6121, clopez1@bnl.gov).
The contractor must deliver the following milestones: equipment footprint and laboratory requirements within 4 weeks of contract award; Installation Work Plan and Job Hazard Analysis within 8 weeks; delivery of the instrument within 18 weeks; and Site Acceptance Test and Commissioning Report within 22 weeks. Payment will be made upon receipt and approval of properly certified invoices according to a four-milestone payment schedule covering delivery to BNL, commissioning, training, and delivery of end-item documentation. Payment terms are Net 30 for large businesses and Net 10 for small businesses. Freight is FOB BSA National Laboratory at 98 Rochester Street, Upton, New York, either Freight Prepaid or Delivered at Place (DAP). All shipments must comply with detailed labeling, packing, and notification requirements, including special handling for items exceeding 3,000 lbs. or 8 feet in any direction, which require three days' advance notice to BNL's Receiving Department. The contract incorporates Brookhaven Science Associates' General Terms and Conditions for Commercial Items and Services (Rev 24.0, April 2026) and Supplemental Terms and Conditions for Work by Contractors Onsite at Brookhaven National Laboratory (Rev 24.0, April 2026), including a requirement for the contractor to provide a Phase Hazard Analysis (PHA). The contract period of performance extends through TBD. Additional attachments include a Statement of Work (dated March 26, 2026), Technical Specifications, and BNL Supplier Quality Assurance Requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
April 9, 2025 1 Rev. 10
BSA’s Contractual Representative
Overall Value Amount
Contract Type Contract Number
Crystal Lopez TBD Firm Fixed Price 479928
BROOKHAVEN NATIONAL LABORATORY
Brookhaven Science Associates
P.O. Box 5000
UPTON, L.I., N.Y. 11973-5000
Name and Address of Contractor
CONTRACT
This Contract (the “Contract”) is between the party named above (the “Contractor”), and Brookhaven Science Associates, LLC (“BSA”), the latter acting under a Prime Contract with the United States of America (the “Government”) represented by the United States Department of Energy (“DOE”).
I. SCOPE OF WORK
The Contractor shall provide a robotic system integrating multiple instruments, designed to autonomously prepare and characterize libraries of solution-deposited thin films (10- 100000 nm thick) on rigid substrate coupon samples with systematically varied discrete material and process parameters. All work shall be conducted in strict accordance with the attached BSA Statement of Work, dated March 26, 2026, and Technical Specifications incorporated herein.
A. Reports/Deliverables: The Contractor shall provide the following deliverable(s) to BSA’s Technical Representative (Tech Rep):
(Service or Item) and Description Due Date
Equipment footprint and laboratory requirements 4 weeks after contract award
Installation Work Plan/ Job Hazard Analysis 8 weeks after contract award
Delivery of the Instrument 18 weeks after contract award
Site Acceptance Test and Commissioning Report
22 weeks after contract award
April 9, 2025 2 Rev. 10
II. PERIOD OF PERFORMANCE
This Contract shall be effective as of the date executed by both parties. It shall remain in effect through TBD.
III. FIRM FIXED PRICE AND PAYMENT
A. Firm Fixed Price: In full consideration of the Contractor's performance hereunder, BSA shall pay the Contractor the firm fixed price of TBD U.S. Dollars ($0.00). The said sum shall constitute full compensation for all services and materials furnished hereunder.
B. Payment: Payment will be made upon receipt and approval of properly certified invoices. Payment will be in accordance with the following milestone payment schedule:
Milestone Amount
1. Delivery to BNL TBD
2. Commissioning of Instrument TBD
3. Training on equipment TBD
4. Delivery of End Item Documentation Package TBD
Payment terms are Net XX (large businesses 30, small businesses 10).
Invoices shall be directed to BSA’s Accounts Payable Department via electronic or regular mail.
Electronic invoice submittal is preferred by BSA. The Contractor shall make every effort to have systems in place that allow for electronic invoice transmittal.
Invoices shall be submitted in PDF format, via email, to apinvoices@bnl.gov.
Hard copy invoices, if applicable, shall be directed to BSA's Accounts Payable Department, Contracts Division, Bldg. No. 400D.
The Contractor shall indicate the final invoice by clearly marking such invoice as “FINAL.” A copy of the final invoice must be submitted to BSA’s Contractual Representative.
C. Freight: Freight terms shall be FOB BSA National Laboratory, 98 Rochester
Street, Upton, Long Island, New York, Freight Prepaid.
- or -
“DAP” Delivered At Place, BSA National Laboratory, 98 Rochester Street, Upton, Long Island, New York.
D. Labelling, Packing, and Notification Requirements:
More detailed instructions are available at https://www.bnl.gov/shipping/ or by emailing WarehouseOperations@bnl.gov.
mailto:apinvoices@bnl.gov https://www.bnl.gov/shipping/ mailto:WarehouseOperations@bnl.gov
April 9, 2025 3 Rev. 10
Labeling Requirements
All shipments must comply with the following labelling requirements. Failure to do so may result in delayed payments. Labels must be placed on the upper left portion of the container when possible and contain:
Brookhaven National Laboratory Brookhaven’s Contract Number 98 Rochester St.
Upton, NY 11973 Box Number / Number of Boxes
Packing List Requirements
Every shipping container must include a packing list. The packing list must be clearly identified and affixed to a side of the shipping container. At a minimum, the packing list should contain the following information:
• Ship from company name and address
• Supplier contact name
• Supplier telephone number
• Ship to address as instructed by Buyer/Contracts Specialist
• Brookhaven’s Contract number
• Part number, description, quantity, unit of measure, and corresponding BNL
Contract line number
Special Notification of Delivery
If a shipment is heavier than 3,000 lbs., longer than 8 feet in any direction, or has a high center of gravity, it will require rigging upon receipt and the shipper shall provide a minimum of 3 days’ advance notice of delivery to BNL’s Receiving Department via email to WarehouseOperations@bnl.gov. The shipper must obtain acknowledgement from BNL that delivery notification was received. Failure to contact BNL will result in delays during delivery and any resulting demurrage will be at the shipper’s expense.
Marking of Outer Package
Each shipping container (transport package) with a gross weight equal to or greater than 400 lbs. (180 kilograms) must be marked with the center of gravity location and gross weight on at least one side or end panel. It must also meet the requirements of the latest revision of ASTM Standard D 3951, Standard Practice for Commercial Packaging. This applies to any item shipped (originally packaged or repackaged) to BNL or other locations cited in the Contract.
Protection of Material and Equipment
The Contractor shall employ procedures which ensure adequate protection of https://www.astm.org/Standards/D3951.htm
April 9, 2025 4 Rev. 10 material and equipment during shipment and while in storage. Such protection shall include special environmental packaging as necessary. All items shipped (originally packaged or repackaged) to BNL or other locations cited in the PO or Contract shall comply with the requirements for preservation, packaging, and marking as stated in the latest revision of ASTM Standard D 3951-10, Standard Practice for Commercial Packaging.
Unacceptable Packing Material
Do not use vermiculite as a packaging material inside any shipments to BNL unless required by shipping regulation. “Vermiculite” as defined in this specification means the hydrous, silicate mineral classified as a phyllosilicate that has been expanded by heating. Vermiculite used as a packaging material in shipments must be determined to be free of asbestos (<1% chrysolite, amosite, crocidolite, tremolite, anthophyllite, and actinolite). All shipments containing vermiculite must be accompanied by documentation stating that the vermiculite used is certified asbestos-free. This documentation must be affixed to the outside of the package.
Radioactive Shipments
Shipments to Brookhaven National Laboratory (BNL) containing radioactive material require pre-authorization prior to shipment. Contact the following staff in the Packaging & Transportation Group for instructions:
• Brett Fagan, Ext. 5645, bfagan@bnl.gov
• Kenneth Hansen, khansen2@bnl.gov
• Steven Woodburn, Ext. 3271, woodburn@bnl.gov
Ocean Shipments
Foreign shipments transported via ocean freight must use the 10+2 REQUIREMENTS Form (PDF). The form must be completed by the Contractor 72 hours before departure of the vessel. Send form to the following:
Interfreight Harmonized Logistics, Inc.
Fax: 516-371-6880 bnl@interfreight.net
Brookhaven National Laboratory WarehouseOperations@bnl.gov
Once the form is submitted to customs, an acceptance number will be provided.
Freight will not be loaded onto a vessel without an acceptance number. Failure to submit the 10+2 form may result in fines. It is the Contractor's responsibility to make sure the 10+2 form is submitted 72 hours prior to the vessel sailing. BSA https://www.astm.org/Standards/D3951.htm mailto:bfagan@bnl.gov mailto:khansen2@bnl.gov mailto:woodburn@bnl.gov https://www.bnl.gov/shipping/files/pdf/10-2-security-filing-bnl-interfreight.pdf https://www.bnl.gov/shipping/files/pdf/10-2-security-filing-bnl-interfreight.pdf mailto:bnl@interfreight.net
April 9, 2025 5 Rev. 10 shall withhold payment from the Contractor's final invoice for any penalties incurred by BSA due to late or incorrect ISF filing by the Contractor.
IV. AUTHORIZED REPRESENTATIVES
A. BSA’s Technical Representative: TBD, telephone no. TBD, TBD (email), is BSA's Technical Representative, and shall act as liaison between BSA and the Contractor in technical matters only.
B. BSA’s Contractual Representative: Crystal Lopez, telephone no.
631.344.6121, clopez1@bnl.gov (email), is BSA's Contractual Representative.
Any change or modification in the terms and conditions of this Contract shall require the written approval of BSA's Contractual Representative or designee.
C. Contractor’s Technical Representative: TBD, telephone no. TBD, TBD
(email), is the Contractor’s authorized Technical Representative, and shall act as point of contact between BSA and the Contractor in technical matters only.
D. Contractor’s Contractual Representative: TBD, telephone no. TBD, TBD
(email), is the Contractor’s authorized Contractual Representative and shall act as liaison between BSA and the Contractor.
V. PATENT CERTIFICATION - RESERVED
VI. GOVERNMENT PROPERTY- RESERVED
VII. ADDITIONAL TERMS
The provisions of Brookhaven Science Associates, LLC, General Terms and Conditions for Commercial Items and Services, Rev 24.0 (April 2026) are incorporated herein and made a part hereof.
The provisions of Brookhaven Science Associates, LLC, Supplemental Terms and
Conditions for Work by Contractors Onsite at Brookhaven National Laboratory, Rev 24.0 (April 2026) are incorporated herein and made a part hereof.
As noted in this Contract, Supplemental Terms and Conditions for Work by Contractors Onsite at Brookhaven National Laboratory are incorporated herein. In accordance with Article 8 of these Supplemental Terms and Conditions, the Contractor is required to provide a Phase Hazard Analysis (PHA).
This Contract is issued pursuant to Brookhaven Science Associates General and/or Supplemental Terms and Conditions listed above, which are incorporated herein by reference. The complete text of these terms and conditions can be viewed at PPM | Terms and Conditions. Should the Contractor have any questions and/or not have access to these terms and conditions, contact the Buyer or Contracts Specialist immediately.
https://www.bnl.gov/ppm/terms-and-conditions.php https://www.bnl.gov/ppm/terms-and-conditions.php
April 9, 2025 6 Rev. 10
The following documents attached hereto and made a part hereof, contain additional provisions of this Contract:
Attachment A Statement of Work, dated March 26, 2026 Attachment B Technical Specifications Attachment C BNL Supplier Quality Assurance Requirements
This Contract does not bind nor purport to bind the Government of the United States.
ACCEPTED:
CONTRACTOR BROOKHAVENSCIENCE
ASSOCIATES, LLC.
By: By:
Name: Name:
Title: Title:
Date: Date:
The Contractor shall sign and return one (1) copy of this contract via email to the attention of Crystal Lopez, Procurement and Property Management Division at clopez1@bnl.gov.
| Invoices shall be directed to BSA’s Accounts Payable Department via electronic or regular mail. |
| Electronic invoice submittal is preferred by BSA. The Contractor shall make every effort to have systems in place that allow for electronic invoice transmittal. Invoices shall be submitted in PDF format, via email, to apinvoices@bnl.gov. |
| Hard copy invoices, if applicable, shall be directed to BSA's Accounts Payable Department, Contracts Division, Bldg. No. 400D. |