Enclosure 4 - CPCS Gantt Chart (Rev 2023-05-24).pdf
PDF 105 KB Posted
- Attached to
- Catfish Point Control Structure Federal contract opportunity
- Solicitation number
- W912P823R0053
About this file
This Gantt chart outlines the schedule for rehabilitation work on the Catfish Point Control Structure gate bays. The project involves removing and replacing the two sector gate leaves and associated machinery and electrical systems. The contractor will have 75 days to complete the work after receiving a notice to proceed, with tasks including procuring materials, removing existing structures, installing new gate leaves and anchoring systems, performing field machining, and conducting electrical, hydraulic, and cathodic protection work. Concurrent with the contractor work, the USACE will require 45 days onsite to oversee the project. Key milestones include submittal approval within 7 days, procurement within 20 days of notice to proceed, and completion of all contractor work within the 75-day performance period.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912P823R0053 AM0003.pdf | ||
| W912P823R00530003 FINAL SF30 Catfish Point.pdf | ||
| W912P823R00530002 FINAL SF30 8-28.pdf | ||
| W912P823R00530001 FINAL SPS Catfish Point CS.pdf | ||
| W912P823R0053 FINAL SPS Solicitation CPCS 7-31.pdf | ||
| Enclosure 2 - CPCS Technical Specifications.pdf | ||
| Enclosure 1 - CPCS SS Ref Docs for GF Sector Gates.pdf | ||
| Enclosure 5 - CPCS Machinery Pit and Anchorage Details.pdf | ||
| Enclosure 1 - CPCS SS Ref Docs for GFE (Hagglunds-Instructions).pdf | ||
| Enclosure 1 - CPCS SS Ref Docs for GFE (Hagglunds-Manual).pdf | ||
| Enclosure 3 - CPCS Plans.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
NTP Issued 1 1
Contractor to gather Submittal Data 7 1 2 3 4 5 6 7
Submittal Approval Process 14 1 2 3 4 5 6 7
Procurment Period 20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Install needles & dewatering structure 5 1 2 3 4 5
Remove west sector gate leaf 5 1 2 3 4 5
Remove west leaf machinery & anchorage 3 1 2 3
Install GF west sector gate leaf 14 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Install west leaf new machinery anchorage 7 1 2
Field machine west leaf steel band at rack locaiton 2 1 2
Install west leaf GF machinery & install rack 5 1 2 3 4 5
Perform electrical work on west gate leaf 21 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Perform cathodic protectoin work on west gate leaf 10 1 2 3 4 5 6 7 8 9 10 11 12
Remove east sector gate leaf 5 1 2 3 4 5
Remove east leaf machinery & anchorage 3 1 2 3
Install GF east sector gate leaf 14 1 2 3 4 5 6 7 8 9
Install east leaf new machinery anchorage 7 1 2
Field machine east leaf steel band at rack locaiton 2
Install east leaf GF machinery & install rack 5
Perform electrical work on east gate leaf 21
Perform cathodic protectoin work on east gate leaf 10
Perform hydraulic work on west gate leaf 5
Perform hydraulic work on east gate leaf 5
Rewater structure & pull needles 3
USACE‐ODY TIMELINE 45 1
CONTRACTOR TIMELINE 75 1 41
CPCS Schedule for Gate Bay 1 ‐ USACE‐ODY and Contractor Effort
Key
Description of Task Duration (days)
Days
ODY
KTR
ONSITE
OFFSITE
5/24/2023
56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75
NTP Issued
Contractor to gather Submittal Data
Submittal Approval Process
Procurment Period
Install needles & dewatering structure
Remove west sector gate leaf
Remove west leaf machinery & anchorage
Install GF west sector gate leaf
Install west leaf new machinery anchorage
Field machine west leaf steel band at rack locaiton
Install west leaf GF machinery & install rack
15 16 17 18 19 20 21 Perform electrical work on west gate leaf
Perform cathodic protectoin work on west gate leaf
Remove east sector gate leaf
Remove east leaf machinery & anchorage
10 11 12 13 14 Install GF east sector gate leaf
Install east leaf new machinery anchorage
1 2 Field machine east leaf steel band at rack locaiton
1 2 3 4 5 Install east leaf GF machinery & install rack
1 2 3 4 5 6 7 8 9 10 11 12 13 14 Perform electrical work on east gate leaf
1 2 3 4 5 6 7 8 9 10 Perform cathodic protectoin work on east gate leaf
1 2 3 4 5 Perform hydraulic work on west gate leaf
1 2 3 4 5 Perform hydraulic work on east gate leaf
1 2 3 Rewater structure & pull needles
45 USACE‐ODY TIMELINE
35 CONTRACTOR TIMELINE
Description of Task
ONSITE