encl a SOW.pdf

PDF 306 KB Posted

Attached to
Water Main Repair Wyman Ave
Solicitation number
N4008520B2559
Issued by

About this file

This scope of work document outlines the requirements for a water main repair project at Portsmouth Naval Shipyard in Maine. The base seeks to replace an existing 8-inch water distribution main in Wyman Avenue with new 16-inch piping, and to line an 8-inch main in Crane Street using cured-in-place pipe. Additional options include replacing a post indicator valve, filling the existing 8-inch main from B43 to Constitution Square with flowable fill, and lining the main in Dennett Street. The base specifies a 240-day period of performance for the base bid work and additional time periods ranging from 10 to 90 days should the optional items be exercised. Interested contractors must hold a pre-construction meeting no later than 30 days after receiving notice to proceed and submit various plans and qualifications in advance of the kickoff. Safety, quality control, and environmental protection requirements are also outlined.

View the file

Other files

File Type Posted
Attach 2_PNSYDIV1 Specs 152020.pdf PDF
Attach 5_Drawings.pdf PDF
Attach 3_Technical Specs.pdf PDF
Attach 7_PWD ME Water and Sewer Standards.pdf PDF
Attach 4_Submittal Register.xlsx XLSX spreadsheet
Attach 1_Bid Form.pdf PDF
Attach 6_MASTER eOMSI WORKBOOK REV 6.xlsx XLSX spreadsheet
N4008520B2559.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Public Works Department, Maine

Rev 21

From: PM & E

To: Acquisition

Date: 8/6/2020

Subject: MM UEM St Repair (FY 21) Water Main Wyman Ave eProjects #: 1617119

Point of Contact: Rick Dolce x4391

Attachments:

(1) Bid Form

(2) Div 1 Specs

(3) Technical Specifications

(4) Submittal Register

(5) Drawings

(6) Draft eOMSI Workbook

(7) PWD ME Water & Sewer Standards

1 SCOPE OF WORK:

The purpose of this project is to replace water distribution system lines in Facilities

Engineering & Maintenance Service Areas and connect this new water service to the B163 supply line. Work includes replacement of the existing 8" water distribution main in the

Wyman Avenue areas with new 16" piping; and Cured In Place Pipe (CIPP) lining to repair the 8" water main in Crane Street. This includes all fire and domestic water service piping and connections, and associated valves, restraints, couplers, thrust blocks, etc. to complete the project. Additionally, provide and install flow fill in the decommissioned 8” line.

Base Bid

Provide and install 16” DI Water Main to replace the existing 8” piping in Wyman Ave, and all associated fire and domestic water services. The new piping shall connect to the recently installed 16” water main in Wyman Ave, and run up to and connect to the main supply line coming from B163. Additionally, include installation of Cured-in-Place Pipe Lining

(CIPPL) down Crane Street, along with associated fire and water services, and various fire hydrants. This includes all valves, fittings, couplers, restraints, anchoring, etc. as necessary to create a complete and useable system, and as depicted on the contract drawings.

Includes 150CY of rock ledge removal, primarily anticipated to be encountered in Wyman

Avenue. Ledge is anticipated to be shallow, in the areas of new pipe installation.

Bid Option #1

Provide and install 6” fire service PIV and piping, to replace the existing PIV at the west side of B43. Connect from the existing 6” DI piping in Storer Street. This includes all

Subj: MM UEM St Repair Water Main Wyman Ave

Page: 2 of 17

Rev 21a fittings, couplers, anchoring, etc. as to create a complete and useable system, and as depicted on the contract drawings.

Bid Option #2

Provide and install flowable fill (pump-able, fly ash mix) in the existing 8” water main from the southwest corner of B43 to Constitution Square. Remove existing valves at the southwest corner of B43, associated with the 8” main to be commissioned. All inline valves to be in the ‘open’ position to facilitate installation of flow fill. Provide excavation for fill pits associated with work. Coordinate with construction project P-293 (Paint Rubber &

Blast Bldg.), especially the gas line replacement component of that project.

Bid Option #3

Provide and install Cured-in-Place Pipe Lining (CIPPL) down Dennett Street, along with associated domestic water services to Quarters C, D, E, and F. This includes all valves, fittings, couplers, restraints, anchoring, etc. as necessary to create a complete and useable system, and as depicted on the contract drawings.

Bid Option #4

Provide and install two (2) water main gate valves, of 16” diameter or smaller in size, associated with this project. Valve locations and size shall be identified by the Government, as to facilitate phasing of the project, or to provide improved system isolation as necessary.

This includes all excavation to perform the work, and all fittings, couplers, restraints, anchoring, etc. as necessary to create a complete and useable system. Provide backfill and asphalt required to complete the installation.

2 BASIS OF BID:

2.1 The contractor shall provide a firm fixed price for each work item and reflect the value of the material, labor and equipment with a line item total by completing the attached proposal form.

3 GENERAL REQUIREMENTS:

3.1 All work performed by the Contractor shall be in accordance with the requirements specified in herein and the project specifications and all local, State and Federal

Codes.

3.2 The means and methods of work associated with this project shall be in accordance with the tasks specified on the enclosed contract documents and the following general requirements:

3.3 Division 01 - General Requirements Specification

3.3.1 All requirements of Division 01 apply to this project unless otherwise noted herein or other contract documents or if means and methods do not invoke the requirement (i.e.: no confined space, no hazardous waste, etc.). Refer to the

Page: 3 of 17

Attachment 4 Submittal Register for additional items that do not apply which are not otherwise explicitly identified as such herein.

3.3.2 The Contractor shall coordinate all work to permit Navy/Facility Operations to be performed during the course of work. It is anticipated that the Contractor may need to work outside normal work hours and /or weekends to ensure

Shipyard/Facility operations are not impacted by work performed by

Contractor. Additionally, some delays due to periodic work stoppages or changes in work sequence necessitated by the Shipyard/Facility operations should be anticipated and taken into account by the Contractor. The performance period and contract completion date specified by the Contract includes adequate float to cover any such delays that may result.

Consequently, any delay claimed by the Contractor will not be entertained if they are related to such schedule impacts due to Shipyard/Facility operations.

3.3.3 All work shall be fully coordinated with the Contracting Officer’s

Representative and PWD-ME and shall comply with all Work Restrictions specified in Specification Section 01 14 00.00 22.

3.3.4 Contractor shall provide all supervision, labor, materials, tools, equipment, and transportation necessary to perform tasks within this project.

3.3.5 Not Applicable

3.3.6 Not Applicable

3.4 Contractor Security Responsibilities (PNSY)

3.4.1 Contractor employees shall not transport, drink, or have in their possession any alcoholic beverages. Possession of any controlled substances without a physician's prescription is also prohibited. Any Contractor employee appearing to be under the influence of intoxicating liquor or narcotics will be apprehended by Shipyard Police, escorted off of the Portsmouth Naval

Shipyard, and turned over to the local Police Department.

3.4.1.1 Any vehicle found to contain controlled substances, including usable residue, may be seized and impounded. Within 24 hours of the work day following any vehicle seizure, the Portsmouth Naval Shipyard

Police will have determined whether forfeiture of the vehicle is required. If not, the vehicle will be returned to the owner or authorized agent. If the vehicle is determined to be appropriate for forfeiture, the Portsmouth Naval Shipyard's Legal Officer will notify the Drug Enforcement Administration of such seizure and impoundment, for initiation of forfeiture proceedings pursuant to

Title 2l, U.S. Code, Section 88l. Such actions may be taken regardless of whether the owner/operator of the vehicle had knowledge of the presence of drugs in the vehicle. The Government

Page: 4 of 17 may pursue criminal or other disciplinary actions pursuant to Title l8, U.S. Code, Section l382.

3.4.2 Possession of firearms, ammunition and/or explosives is prohibited. In the event explosives are required for construction work, specific handling requirements and approvals shall be obtained from the Security Officer via the

Contracting Officer.

3.4.3 Cameras, video equipment, or similar photographic equipment shall not be introduced into nor removed from the Portsmouth Naval Shipyard. In the event such equipment is required for performance of contract work, approvals shall be obtained from the Security Officer via the Contracting Officer.

3.4.4 Weapons (firearms, personal knives with blades 2-1/2 inch long or greater, Mace, Pepper Spray etc.) are not permitted aboard the Shipyard.

3.4.5 Cell phones equipped with cameras are permitted aboard the Portsmouth

Naval Shipyard only outside NAVSEA controlled spaces, but taking pictures is prohibited. Cell Phones equipped with cameras are not allowed in the

Controlled Industrial Area (CIA), or any NAVSEA controlled space.

3.4.5.1 The following are the penalties for any Contractor personnel or

Subcontractor Personnel that are found to be in possession of a camera or cell phone equipped with a camera taking pictures outside

NAVSEA spaces:

3.4.5.1.1 1st offense with pictures: Full investigation with security forces and NCIS, camera or cell phone confiscation, and depending on results of investigation 30 days restriction.

3.4.5.1.2 2nd Offense with pictures: The offender will be permanently barred from access to NAVSEA spaces.

3.4.6 Cameras, or cell phones equipped with cameras, are not allowed in any

NAVSEA space such as the CIA, NWA, CNIA or Security Island.

3.4.6.1 If a Contractor is found with a camera equipped cell phone in a

NAVSEA space, the Standard Access Control Badge (SACB) and

Defense Biometric Identification System card (DBIDS) will be confiscated. Access to the installation will be denied and a Security

Deficiency Log (SDL) will be issued.

3.4.6.2 Cell phones with no pictures of NAVSEA spaces:

3.4.6.2.1 1st Offense: There is a 10 day deadline for completion of the SDL. Credentials will be reissued to the offender once the SDL response is received from the contracting company, reviewed and accepted by the Security office.

Page: 5 of 17

3.4.6.2.2 2nd Offense: The offender will be permanently barred from access to NAVSEA spaces.

3.4.6.3 Cell phones with pictures of NAVSEA spaces:

3.4.6.3.1 1st offense: The offender will be permanently barred from access to NAVSEA spaces.

3.4.6.3.2 At a minimum, all Superintendents & SSHO (and anyone acting in this capacity) shall have a CIA compliant mobile phone on their persons any time while work is occurring at the contract jobsite(s). The phone number(s) associated with these phones shall be provided during the pre-con meeting and work will not be allowed to proceed without one.

3.4.7 Laptops and any other computer, regardless of form factor, shall not be introduced nor removed from Portsmouth Naval Shipyard without authorization. Only business use computers are allowed. Contractors are not authorized to bring personally owned computers on-yard. If a computer is required to perform work on-yard, a Visitors Portable Computer Equipment

Registration form must be completed and submitted for approval. These forms can be obtained and completed at the pass office upon entrance to the shipyard or your shipyard POC.

3.4.8 Any computing devices that also have or had an installed camera, must follow the same requirements as cell phones. If the computing device is visiting a

NAVSEA space, it cannot have a camera. If the device has a camera, the only acceptable remediation is that the camera be professionally removed or drilled out and the resulting void must be filled with an opaque epoxy.

3.4.9 In the event that a camera is required for the performance of the contracted work, approval must be obtained from the C1120 security office. In the event of any deviation from the requirement to remove and epoxy the camera, authorization must be sought from C1120. All requests for camera use and deviations should come to C1120 through your COR or Shipyard POC.

Authorizations and approved computer registrations must remain with the devices and be presentable upon request. Devices without a documented approval or observed being used in a manner that violates the terms of the

Visitor Portable Computer Equipment Registration agreement are subject to search and seizure.

3.4.10 Use of wireless networking and communication on-yard by a contractor requires prior authorization. Communication devices such as cellular hotspots and wireless routers must also be registered using the same Visitors Portable

Computer Equipment Registration. This does not include air-cards and straight cellular data. It does include any device that transmits or broadcasts

Wi-Fi, including cellular phones with the personal hot-spot feature enabled.

Page: 6 of 17

3.4.11 Broadband internet connections must be authorized prior to use on-yard. All requests for physical cable service from an internet service provider (ISP) must be authorized and coordinated through C109. Contractors must work through their COR to request broadband access.

3.4.12 Driver use of a hand-held cellular phone in a moving vehicle on the

Portsmouth Naval Shipyard is prohibited. This prohibition does not include hands-free cellular phone devices. Hands-free devices include console/dash-mounted or otherwise secured cellular phones with integrated features such as voice-activation, speed dial, speakerphone or other similar technology for sending and receiving calls.

3.4.12.1 Driver use of any portable, personal listening device worn inside the aural canal, around or covering the driver's ear while operating a motor vehicle, is prohibited. Listening devices include wired or wireless earphones and headphones (including blue tooth or similar technology), and do not include hearing aids or devices designed and required for hearing protection.

3.4.13 The use of radar or laser detection devices to indicate the presence of speed recording instruments or to transmit simulated erroneous speeds is prohibited in accordance with OPNAVINST 5100.2H.

3.4.14 The Contractor shall indoctrinate personnel on access limitations to ensure security control is maintained as an integral part of their work pattern and habit.

3.4.15 Contractor is advised that any unescorted personnel found in security areas requiring a higher level clearance than the level represented by the badge displayed will be removed from the area with possible confiscation of security badges and vehicle passes.

3.5 Utility Locating Requirements:

3.5.1 The Contractor shall locate all utilities within the limits of ground penetrating work as specified in Specification Section 01 35 26.00 22 (PNSY).

3.5.2 The contractor shall provide the services of a qualified independent utility locating company/person(s) (Cannot be the Government’s Utility Locating

Firm). The utility locating company shall indicate the utility type, size, and depth of all utilities within the proposed area of excavation including, but not limited to, voice/data, electrical, gas, water, sanitary sewer, and storm drainage.

3.5.3 The Contractor shall be responsible for any damage to underground utilities which occur during excavation or ground penetrating work.

3.5.4 The contractor/excavator shall notify Dig Safe (1-888-344-7233) within 14 calendar days, but no more than 30 calendar days, prior to the start of

Page: 7 of 17 excavation or ground penetrating activity. The contractor/excavator shall comply with the State of Maine “Dig Safe” law (Title 23, MSRA 3360-A). If there are any questions regarding the Dig Safe process or underground utilities, contact the Contracting Officer Representative.

3.5.5 Not Applicable

3.5.6 Not Applicable

3.6 Utilities Within and Under Concrete Slabs, Bituminous Asphalt and Other

Impervious Surfaces:

3.6.1 Utilities located within and under concrete slabs or pier structures, bridges, parking areas, and the like, are extremely difficult to identify. Whenever contract work involves chipping, saw cutting, or core drilling through concrete, bituminous asphalt or other impervious surfaces, the Contractor shall provide the services of a third party, independent, private locating company to locate any utilities within the limits of work. The third party, independent, private locating company shall locate utility depth by use of

Ground Penetrating Radar (GPR), X-ray, bore scope, or ultrasound prior to the start of demolition and construction. Outages to isolate utility systems must be used in circumstances where utilities are unable to be positively identified.

The use of historical drawings does not alleviate the contractor from meeting this requirement.

3.6.2 The Contractor shall ensure work is conducted and completed in such a manner to allow access for emergency response vehicles throughout the construction period.

3.7 Contractor Laydown Space:

3.7.1 Contractor lay down space is to consist of an area as shown on the contract documents. Any additional space required to complete this work must first be approved by the Contracting Officer.

3.8 Construction Site Plan

3.8.1 The Contractor shall submit a site construction plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), access and haul routes, avenues of ingress/egress to the fenced area and details of the temporary construction safety fencing/barriers systems that complies with EM385-1-1 Sections 4 & 8.

3.8.2 Identify any areas where vehicle track pads will be installed to prevent the tracking of mud onto the pavement outside the project site limits. Indicate if the use of a supplemental or other staging area is desired.

3.8.3 Show locations & types of safety and construction fences/barrier systems, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, Page: 8 of 17 dewatering system storage tanks and infiltration pits. See EM385-1-1 Section

4.

3.9 Temporary Project Safety Fencing

3.9.1 Prior to the start of Construction, the Contractor shall furnish and erect temporary project safety fencing at the work site in accordance with the plans

& following requirements:

3.9.1.1 Temporary project fencing (or a substitute acceptable to the

Contracting Officer (GDA) and delineated in the APP) shall be provided on all projects. See also EM385-1-1 Sections 4 & 8.

3.9.1.2 Fencing shall extend from grade to a minimum of 4 ft above grade and shall have a maximum mesh size of 2 in. Fencing shall remain rigid/taut with a minimum of 200 lbs of force exerted on it from any direction with less than 4 in of deflection.

3.9.1.3 Signs warning of the presence of construction hazards and requiring unauthorized persons to keep out of the construction area shall be posted on the fencing. At minimum, signs shall be posted every 150

ft. Fenced sides of projects that are less than 150 ft shall, at minimum, have at least one warning sign.

3.9.1.4 Depending upon the nature and location of the project site, The

Contractor may request to modify the type of barrier or not install temporary fencing in some sections of the project site. The

Contractor’s SSHO shall submit a risk analysis (AHA) to the

Contracting Officer for review. This shall be based on a risk analysis of public exposure and other project specific considerations, and shall be included in the applicable AHA.

3.9.2 If the Contracting Officer approves the request and has determined fencing is not required, the Contractor shall install signs, other acceptable barriers systems, warning of construction hazards, shall be conspicuously posted.

3.9.3 If at any time it is determined the risk to the public changes based on the

Contractor’s work, the Contractor shall take immediate action to address any risk to the public.

3.9.4 The Contractor shall dispose of all removed materials in accordance with the

Shipyard/Facility, local, State and Federal regulations.

3.10 Concrete Work

3.10.1 Concrete material should be prevented from entering any drainage structure.

3.11 Not Applicable

3.12 Not Applicable

Page: 9 of 17

3.13 Not Applicable

3.13.1 Not Applicable

3.13.2 Personnel that complete 6010 training can serve as an escort for up to 5 additional contractor personnel or subcontractors. The escort must be within

10 feet or audio range, whichever is closer, and is responsible for the safety of the personnel they are escorting in an emergency.

3.14 Site Work Requirements:

3.14.1 For any Site work projects in the State of Maine:

3.14.1.1 Site work in the State of Maine Shoreland Zone, including any filling, excavation, landscaping, and/or other earthwork in excess of one cubic yard of disturbance, shall comply with State of Maine requirements for certification in erosion and sediment control practices. A certified individual shall be responsible for management of erosion and sediment control practices at the site each day earth moving activities occur. A certified individual is required to visit the site every day to ensure proper erosion and sediment control practices are followed. As an alternative, the Contractor may choose to contract with a certified individual to supervise the Contractor's work in Shoreland areas. Under the State of Maine's Shoreland

Zoning Statutes, the Portsmouth Naval Shipyard, Cutler Naval

Support Activity & Prospect Harbor Facilities are located within the state's Shoreland zone.

3.14.1.2 Erosion and sediment control measures shall be installed and maintained in accordance with Maine Erosion and Sediment Control

Law and Maine Erosion and Sediment Control Practices Field Guide for Contractors, latest edition. Erosion control inspections are required both before and after a precipitation event that has the potential to create runoff and at least weekly at a minimum.

Contractor shall provide inspection reports to CM electronically weekly.

3.14.2 The Contractor shall restore disturbed areas surrounding limits of work to original conditions. Reuse the existing soil material, if considered suitable, to the greatest extent possible, and compact in accordance with technical specifications. Suitable backfill material shall be fine readily compressible soil or granular material, at or near optimum moisture content, and shall not contain stones larger than 3 inches, frozen lumps, chunks of clay, mineral matter, or any other objectionable material.

3.14.3 Any pavement and pavement markings removed or disturbed by the construction shall be replaced in-kind.

Page: 10 of 17

3.14.4 During construction, the Contractor shall provide sediment erosion controls and dewatering controls to ensure that excavation material (i.e., debris, dust, silted or contaminated water, storm water) does not enter any drainage system.

Erosion and sediment controls shall be installed and maintained in accordance with applicable state Best Management Practices appropriate for the site conditions.

3.14.5 Construction dewatering shall comply with Section 31 23 00.00 22 and State of Maine erosion and sediment control requirements and State water quality standards. Dewatering discharges shall be re-infiltrated within the project limits unless written permission is granted by the Government for an alternative method. Dewatering discharges shall not be released to the storm drain system.

3.15 Soil Management & Disposal Requirements

3.15.1 For this Project, the excavation work is located outside an IR Site.

3.15.2 Any excess soils shall be sampled & tested by the Contractor. Once the sampling has been reviewed by Code 106.3, the Contractor shall transport the soils to a licensed disposal facility

3.15.3 The Contractor shall comply with the requirements specified in Section 31 23

00.00 22 for Soil Management and Disposal requirements. All soil sampling shall be coordinated with Code 106.3. Code 106.3 shall be notified at a minimum of seven (7) working days in advance of desired soil sampling event to allow Code 106.3 to be present during the sampling. No Soils shall be removed from PNSY without approval from Code 106.3.

3.16 Access to Unclassified Information

3.16.1 Access to U.S. Navy technical information manuals, documents, drawings, plans, specifications, and other information (e.g., photos, presentations, renderings, papers, etc.) is government propriety and restricted to an official need-to-know basis. Handle, control, and safeguard to prevent oral, visual, and documentary disclosure to the public, to foreign sources, and to personnel not having an official need-to-know.

3.17 Not Applicable

4 PERIOD OF PERFORMANCE:

4.1 BASE BID PERIOD OF PERFORMANCE 240 Calendar Days

4.2 ESTIMATED ON SITE TIME: 210 Calendar Days

4.3 OPTION 1 PERIOD OF PERFORMANCE: 10 Additional Calendar Days

4.3.1 May be exercised within 120 days of award

Page: 11 of 17

4.4 OPTION 2 PERIOD OF PERFORMANCE: 30 Additional Calendar Days

4.4.1 May be exercised within 120 days of award

4.5 OPTION 3 PERIOD OF PERFORMANCE: 90 Additional Calendar Days

4.5.1 May be exercised within 120 days of award

4.6 OPTION 4 PERIOD OF PERFORMANCE: 0 Additional Calendar Days

4.6.1 May be exercised within 210 days of award

4.7 The Contractor shall mobilize and commence work as soon as reasonably feasible from date of contract award but no later than 3-4 weeks after award.

Complete Installation of new 16” Water Main, with Final Flushing and Testing, Connection, and Full Restoration to Service to B163 Water Pipe/System Prior to September 1st; so it is not performed during Freeze Protection. – within 210 Calendar Days (from award)

5 NOTIFICATION OF COMMENCEMENT:

5.1 In accordance with the contract award notification & contract requirements, the

Contractor shall provide payment and performance bonds for 100% of the contract/task order value, as well as a Certificate of Insurance to the Contracting

Officer within ten (10) calendar days of the award notification. Once bonds have been authenticated, the Contractor will be issue a Notice to Proceed.

5.2 The Contractor shall notify the Construction Manager assigned to this project to arrange and hold a pre-construction conference with all interested parties prior to start of work. The Pre-Construction Conference shall be held no later than 30

Calendar days from receiving the Notice to Proceed from the Contracting

Officer.

5.3 The following Preconstruction submittals shall be submitted to the Contracting

Officer fifteen (15) calendar days prior to the pre-construction conference:

Specification Section

SD

# SD Description Item Submitted Paragraph

01 32 16.00 20 01 Preconstruction Submittals Construction Schedule 1.2

01 32 16.00 20 01 Preconstruction Submittals Construction Schedule (3 Week) 1.6

01 32 16.00 20 01 Preconstruction Submittals Construction Schedule (Outages) 1.8

01 35 26.00 22 01 Preconstruction Submittals Accident Prevention Plan (APP) 1.7

01 45 00.10 22 01 Preconstruction Submittals QC Plan 1.6

5.4 The following Pre-construction submittals shall be submitted to the Contracting

Officer at the pre-construction conference:

Page: 12 of 17

Specification Section

SD

# SD Description Item Submitted Paragraph

01 14 00.00 22 01 Preconstruction Submittals List of Contact Personnel 1.2.1

01 20 00.00 22 01 Preconstruction Submittals Schedule of Prices 1.3

01 30 00.00 22 01 Preconstruction Submittals NAVFAC Red Zone Checklist 1.6.1

01 30 00.00 22 01 Preconstruction Submittals NAVFAC PWD ME Follow-on Services List

1.6.4

01 31 23.13 20 01 Preconstruction Submittals List of Contractor's Personnel (eCMS)

1.4.2

01 33 00 01 Preconstruction Submittals Submittal Register 1.7

01 33 10.05 20 01 Preconstruction Submittals Consolidated RFP Documents 2.1

01 33 10.05 20 01 Preconstruction Submittals Submittal Register (DB) 1.5.5

01 50 00.00 22 01 Preconstruction Submittals Construction site plan 1.4

5.5 The following Pre-construction submittals shall be submitted to the Contracting

Officer prior to the start of construction:

Specification Section

SD

# SD Description Item Submitted Paragraph

01 50 00.00 22 01 Preconstruction Submittals Traffic control plan 3.3.1

01 57 19.00 22 01 Preconstruction Submittals Preconstruction Survey 1.5.1

01 57 19.00 22 01 Preconstruction Submittals Solid Waste Management Plan 3.4

01 57 19.00 22 01 Preconstruction Submittals Regulatory Notifications 1.5.2

01 57 19.00 22 01 Preconstruction Submittals Environmental Management Plan

(EMP)

3.1

01 57 19.00 22 01 Preconstruction Submittals Dirt and Dust Control Plan 3.14.1

01 57 19.00 22 01 Preconstruction Submittals Contractor Hazardous Material Inventory Log

3.6

01 57 19.00 22 01 Preconstruction Submittals Storm Water Management/Erosion and Sedimentation Control Plan

3.2.1

01 74 19.00 22 01 Preconstruction Submittals Waste Management Plan 1.3

6 DESIGN:

6.1 N/A

7 WINTER CONSTRUCTION CONDITIONS:

7.1 This Task Order will require construction operations during winter weather. The

Contractor shall include all materials, labor, equipment, and supervision required to perform the above work in cold weather conditions.

Page: 13 of 17

8 HAZARDOUS MATERIALS:

8.1 Unforeseen Hazardous Material

8.1.1 No known asbestos concerns are associated with excavation/repair of the water line. If suspect ACM piping or other suspect materials are discovered during excavation, stop that portion of work and notify the Contracting

Officer immediately.

9 CODE/REGULATORY REQUIREMENTS:

9.1 All work performed by the Contractor shall be in accordance with the requirements specified in the Project Specifications and all local, State and Federal Codes.

10 ENVIRONMENTAL PROTECTION REQUIREMENTS:

10.1 The Contractor shall prepare and submit an Environmental Protection Plan in accordance with the requirements specified in Specification Section 01 57 19.00 22.

10.2 The Contractor shall implement erosion and sediment control measures as needed.

10.3 This task order does not have a separate State or Federal permit.

11 CULTURAL AND NATURAL RESOURCE REQUIREMENTS:

11.1 The Contractor shall include the following in their means, methods, and scheduling of work:

11.1.1 In the event that archaeological resources are identified during construction, work shall stop immediately and notify the Contracting Officer and PWD-ME

ENV (Kerry Vautrot, 207-438-4488/Peter Michaud 207-438-4095) for further direction. Work shall not resume until directed by the Contracting Officer to proceed.

11.1.2 The proposed project is located within areas of archaeological sensitivity and archaeological monitoring by an archaeologist meeting the Secretary of the

Interior’s Professional Qualifications and on the Maine approved list is required to be onsite during all ground disturbing activities within this area.

The Contractor shall ensure compliance with the requirements related to

Specification Section 01 44 00.22 (Archaeological Monitoring PWD ME).

11.2 Any modifications to the proposed action must be reviewed and approved by PWD-

ME ENV prior to implementation.

12 SITE SUPERVISION:

12.1 The Project Site Superintendent for this project shall meet the qualifications specified in Specification Section 01 30 00.00 22.

12.2 The Project Superintendent shall be on site during working hours. The Superintendent cannot the Site Safety and Health Officer (SSHO).

Page: 14 of 17

12.3 The Site Superintendent can be the Quality Control Manager.

12.4 Approval of the on-site Project Superintendent by the Contracting Officer is required prior to start of construction. Provide resumes for the proposed on-site Project

Superintendent describing their experience with references and qualifications to the

Contracting Officer for approval. The Contracting Officer reserves the right to interview the proposed on-site Project Superintendent at any time in order to verify the submitted qualifications.

12.5 The Site Superintendent is subject to dismissal if the above duties are not being effectively carried out. If the Site Superintendent is dismissed, project work will be stopped and will not be allowed to resume until a suitable replacement is approved and the above duties are again being effectively carried out.

12.6 Site Superintendent Qualifications

12.6.1 The project site superintendent must have a minimum of five (5) years' experience in construction with at least three (3) of those years as a superintendent on projects similar in size and complexity. See Div 1 Section

01 30 00.00 22 ADMINISTRATIVE REQUIREMENTS (PWD ME) for additional requirements.

13 SITE SAFETY:

13.1 The Contractor shall provide a competent Site Safety and Health Officer (SSHO) in accordance with the requirements specified in Specification Section 01 35 26.00 22.

13.2 The SSHO cannot perform the duties of the Site Superintendent. The SSHO cannot perform the duties of the QC Manager.

13.3 The Contractor shall be responsible for maintaining a work site compliant with EM

385-1-1 Safety and Health Requirements Manual (Latest Edition), including latest errata and changes) and all other OSHA regulations associated with the completion of the work.

13.4 Approval of the SSHO by the Contracting Officer is required prior to start of construction. Provide resumes for the proposed SSHO describing their experience with references and qualifications to the Contracting Officer for approval. The

Contracting Officer reserves the right to interview the proposed SSHO at any time in order to verify the submitted qualifications.

13.5 The SSHO is subject to dismissal if the above duties are not being effectively carried out. If the SSHO is dismissed, project work will be stopped and will not be allowed to resume until a suitable replacement is approved and the above duties are again being effectively carried out.

14 QUALITY CONTROL:

Page: 15 of 17

14.1 The Contractor shall implement a Quality Control Program in accordance with the requirements specified in Specification Section 01 45 00.10 22. Provide a Site QC

Manager in accordance with Section 01 45 00.10 22 to manage to implement and manage the QC Program.

14.2 The QC Manager cannot perform the duties of the SSHO.

14.3 The QC Manager or can perform the duties of the Site Superintendent.

14.4 Approval of the QC Manager by the Contracting Officer is required prior to start of construction. Provide resumes for the proposed QC Manager describing their experience with references and qualifications to the Contracting Officer for approval.

The Contracting Officer reserves the right to interview the proposed QC Manager at any time in order to verify the submitted qualifications.

14.5 The QC Manager is subject to dismissal if the above duties are not being effectively carried out. If the QC Manager is dismissed, project work will be stopped and will not be allowed to resume until a suitable replacement is approved and the above duties are again being effectively carried out

15 MEASUREMENTS:

15.1 Contractor shall verify all measurements in the field prior to starting work.

Coordinate with the Contracting Officer Representative when scheduling visits to the site prior to construction activities.

16 CLEANUP:

16.1 Contractor shall clean up the job site daily, and shall use his or her own equipment to clean the work area to the satisfaction of the Contracting Officer Representative.

Upon completion of project work, contractor shall clean the work area free of equipment, tools, materials, trash, debris and dust. Upon site stabilization as defined by State and Federal erosion and sediment control laws, all temporary erosion and sediment controls shall be removed and disposed of in accordance with State and

Federal disposal regulations.

17 SUBMITTALS

17.1 Provide submittals as defined herein and in the contract documents including, but not limited to, the following in accordance with Specification Section 01 33 00 Submittal

Procedures:

17.2 For any projects that are awarded with a contract value of greater than $250,000, the

Contractor shall utilize NAVFAC’s Electronic Construction & Facility Support

Contract Management System (eCMS).

17.3 See Section 01 31 23.13 22 for eCMS requirements. The eCMS can be accessed at http://wl001.uat.navfac.us/cmicuat/SdMenu/. The administrator will provide a user name and password to log in.

Page: 16 of 17

17.4 The eCMS Processes & Procedures can be found at

https://www.navfac.navy.mil/content/dam/navfac/Capital%20Improvements/PDFs/ci

_ecms_processes_contractors.pdf.

18 AVAILABILITY AND USE OF UTILITY SERVICES

18.1 The following utilities will be made available to the Contractor without charge:

18.1.1 Electricity

18.1.2 Potable Water

18.2 See Specification Section 01 50 00 for additional requirements.

19 POST AWARD KICKOFF MEETING

19.1 N/A

20 ORDER OF PRECEDENCE:

20.1 In the event of conflict or inconsistency between any of the requirements included in the scope of work outlined herein conflict with the attached Div 1 Specs or the Div 1

Specs included in the original IDIQ Contract, the requirements outlined in this scope of work document will take precedence.

21 FACILITY TURNOVER PLANNING MEETINGS (NAVFAC Red Zone - NRZ)

21.1 The Contractor shall meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client in accordance with

Specification Section 01 30 00.00 22. Start the turnover process at the Pre

Construction Conference meeting and convene at the Facility Turnover Meetings once the project has reached approximately 75 percent completion or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.

21.2 See Appendix A of Section 01 30 00.00 22 for an example of the Facility Turnover

Planning Meeting Agenda, NRZ Checklist & POAM.

22 OPERATION & MAINTENANCE MANUALS

22.1 For this Project the following Data Packages are required for the following equipment:

22.1.1 16” Gate Valve Data Package No.1

22.1.2 Post Indicator Valve Data Package No.1

23 eOMSI

23.1 An initial, pre-edited draft of the Model & Facility Data Matrix tab within the eOMSI

Facility Data Workbook is attached (Attachment 6).

Page: 17 of 17

23.2 The Government will provide this eOMSI Facility Data Workbook electronically to the Contractor upon award. The Contractor shall add, delete, and update Master systems, Systems, and Subsystems that may have changed during construction, or any items that may have been omitted or missed during design, at no additional cost to the

Government. Complete the KTR Facility Data File tab based on the selection of

Master systems, Systems, and Subsystems installed.

24 INTERNAL SERVICE REQUIREMENTS LIST

24.1 Not Applicable

25 WARRANTY MANAGEMENT PLAN

25.1 The Contractor shall submit a warranty management plan in accordance with

Specification Section 01 78 00.00 22 at least 30 days before the planned pre-warranty conference, submit the warranty management plan for Government approval.

26 AS-BUILTS/ RECORD DRAWINGS

26.1 The Contractor shall provide Record Drawings in accordance with Specification

Section 01 01 78 00.00 22.

27 DD FORM 1354 - REAL PROPERTY RECORD CARD

27.1 N/A

28 TRAINING

28.1 N/A

29 ADDITIONAL INFORMATION

29.1 N/A

END