Electrical Equipment Pre-Purchase SOW 9-03-24.docx.docx
DOCX document 25 KB Posted
- Attached to
- Building 420 Sector 36 Solid State Amplifiers
- Solicitation number
- 4-B176-Q-00735-00
- Issued by
-
Department of Energy Office of Science
About this file
This document is a Statement of Work (SOW) for the pre-purchase of electrical equipment (transformer, switchboards, and panelboards) required for the Building 420 Sector 36 Solid State Amplifiers project at Argonne National Laboratory. The SOW provides the specifications and requirements for the equipment, including the required tasks and delivery schedule. The equipment is being pre-purchased to benefit the project schedule, with the installation and commissioning to be performed by an electrical contractor under a separate construction contract. Manufacturers are required to submit a schedule listing the lead time and proposed equipment, along with shop drawings, within specified timeframes. The procurement is being conducted through a Request for Quote (RFQ) issued by the Department of Energy Office of Science, with a response due date of September 18th. The award will be made on a lowest price technically acceptable basis.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 26 2416-Panelboards REV 2.pdf | ||
| Addendum and Acknowledgement Doc.doc | DOC document | |
| Reps and Certs ANL-70B.doc | DOC document | |
| 2024.09.03_ANL_SSA_Prepurchase_SPECS.pdf.pdf | ||
| 2024.09.03_ANL_SSA_Prepurchase_DWGS_R3.pdf.pdf | ||
| Property Requirements-31-AUG-2023.PDF | ||
| Appendix A-71COM-13-FEB-2023.PDF | ||
| LPTA Form.docx.docx | DOCX document | |
| ANL-70 Request for Quotation.doc | DOC document | |
| Enclosure No.1 Instructions to Offerors_4-B176-Q-00735-00.doc | DOC document | |
| Appendix D8C-12-DEC-2023.PDF | ||
| Property Questionnaire-08-SEP-2023.PDF | ||
| Special Cl-Progress Pmts-02-SEP-2015.PDF |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Building 420 Sector 36 Solid State Amplifiers
Electrical Equipment Pre-purchase
Statement of Work (SOW) 09/03/2024
Background
UChicago Argonne, LLC is seeking proposals for the procurement of electrical equipment (transformer, switchboards, and panelboards) as part of the proposed Building 420 Sector 36 Solid State Amplifiers project. New electrical infrastructure to power the amplifiers will be required, and in order to benefit the project schedule, ANL wishes to purchase the electrical equipment ahead of a construction contract being awarded. The equipment will be ordered as part of this scope but it will be received, installed, started, and commissioned under an electrical contractor. This Statement of Work (SOW) describes the specifications and other requirements that the manufacturers will be required to meet.
Scope
The Supplier shall provide quotes for manufacturers as specified in the following Bid Documents attached to this SOW:
· 2024.09.03_ANL_SSA_Prepurchase_SPECS
· 2024.09.03_ANL_SSA_Prepurchase_DWGS_R3
Tasks & Delivery
The supplier shall submit a schedule listing the lead time and proposed manufacturer for each of the pieces of equipment they are proposing. The schedule shall include the activities listed below for each of the proposed manufacturers within the bid.
The manufacturer shall include shipping and any other associated costs to deliver the equipment to Building 420 located at 9700 South Cass Avenue located in Lemont, IL. The General/Electrical Contractor for the construction will receive and install the equipment.
| Item |
| Description |
| Complete by |
| Notes |
| 1 |
| Manufacturer submits shop drawings |
| 10/18/2024 |
Within 10 working days after Contract Award
| 2 |
| A/E Review, manufacturer resubmittal with A/E comments as required, A/E approval |
| 11/08/2024 |
| Within 15 working days |
| 3 |
| Manufacturer releases equipment for production |
Include duration
Period of Performance October 7, 2024 – September 30, 2025