This is an Engineering Data List (EDL) for a Circuit Card Assembly (NSN: 5998016295711WF) for the F-16 aircraft, issued by the 429 SCMS/GUMACA organization at Ogden Air Logistics Center.
The EDL, dated October 4, 2022 (Revision 3), lists four key engineering documents: 1) Hill AFB Form 462 containing engineering data requirements (marked as supplied but not in JEDMICS), 2) Document 201126351 for the printed circuit board assembly, 3) Document 20156881 for acceptance test procedure, and 4) Document 20156882 for select-at-test component procedure. The latter three documents are marked to be furnished with solicitation and have a distribution code "D". The document includes a foreign disclosure notice requiring approval for release to foreign-owned, controlled, or influenced companies. The CAGE code for this item is 98747.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ENGINEERING DATA LIST
DATE:
04 OCT 2022
REVISION: 3 *HISTORY*
CAGE:
98747
PAGE:
NSN:
5998016295711WF
DATA TECH:
Lawson, Brian D
END ITEM:
F-16
ORGANIZATION/OFFICE SYMBOL:
429 SCMS GUMACA/
MANUFACTURER NAME:
OGDEN AIR LOGISTICS CENTER
REFERENCE NUMBER:
201126351-30
NOUN:
CIRCUIT CARD ASSEMB
LINE/
SUB CAGE
ENG DRAWING NUM/ ACCOMP
DOC NUM REV
NR
SHEETS
FURN
CODE
DIST
CODE NOUN REMARKS
L 98747 HILL AFB FORM 462 X ENGINEERING DATA
REQUIREMENTS.
(ATTACHMENT-A)
L 98747 201126351 S D ASSEMBLY, PRINTED CIRCUIT
BOARD
L 98747 20156881 S D ACCEPTANCE TEST
PROCEDURE
L 98747 20156882 S D SELECT-AT-TEST COMPONENT
PROCEDURE
STANDARD ENGINEERING TEXT
Lawson, Brian D 04 OCT 2022
RELEASE OF THIS DATA TO A FOREIGN OWNED, CONTROLLED OR INFLUENCED COMPANY IS DEPENDENT UPON THE APPROVAL OF THE FOREIGN DISCLOSURE OFFICE.
NAME: DATE:
C - CLASSIFIED DOCUMENT.
S - FURNISHED WITH SOLICITATION.
M - STABLE BASE DRAWING REQUIRED; FURNISHED WITH
CONTRACT AWARD.
X - DATA SUPPLIED (NOT IN JEDMICS).
R - FURNISHED BY PCO UPON REQUEST.
P - PARTIAL DOCUMENT FURNISHED.
V - VENDOR DRAWING; (NOT PROVIDED).
G - GOV'T DOCUMENT.
O - OTHERS, CONTRACTOR MUST ACQUIRE.
A- DATA NOT AVAILABLE.
FURNISHED METHOD CODE LEGEND:
Page 1 of 1EDL Version 3Generated by PRPS using Jasper Reports on 03 Jan 2025