573-2, Overhaul-Repair of Hydraulic Cylinders.pdf

PDF 22 KB Posted

Attached to
FY2018 DOCKSIDE REPAIRS TO NOAA SHIP GORDON GUNTER
Solicitation number
EA133M18RP0026
Issued by

About this file

REFERENCE DOCUMENT 19 of 29

View the file

Other files

File Type Posted
528-6233903_Plumbing_Drains_Main_Deck_&_Below_(1).pdf PDF
Amendment_0004.pdf PDF
0000214_E_Plumbing_Draing_&_Sewage_Sys_Dia_T-AGOS_1_Class.pdf PDF
528-6233893_Plumbing_Drains_Above_Main_Deck.pdf PDF
CHwiring.pdf PDF
T9593-A6-MMO-010_0_A_Sewage_Lift_Station_Onmipure.pdf PDF
Rixson_Model_0600K_Pull_Side_Mounting_Instruction.pdf PDF
528-6233824_Plumbing_Drains_&_Sewage_System_Diagram.pdf PDF
Amendment_0003,_SF30_1.pdf PDF
Amendment_P002.pdf PDF
Amendment_0001,_SF30.pdf PDF
GU-555-001--.pdf PDF
512-6233797.pdf PDF
GU-436-6233675.pdf PDF
NOAA_Weight_Reporting_Spreadsheet.xlsx XLSX spreadsheet
GU-512-002.pdf PDF
NOAA Ship Gordon Gunter Drawing Index List.xlsx XLSX spreadsheet
573-1C Weight Handling Gear Testing.pdf PDF
ATTACHMENT_J.4_Past_Performance_Questionnaire.doc DOC document
ATTACHMENT_J.5_U_S_DOL_POSTER.pdf PDF
512-6233792.pdf PDF
085-6233560 General Arrangement Main Deck and Below.pdf PDF
634-1B_DECK COVERINGS.pdf PDF
SeaClear - Typical Window Seal.pdf PDF
085-6233567 General Arrangement Fcsle Dk _ Above.pdf PDF
ASHRAE Standard 151 - HVAC Balancing _ Testing.pdf PDF
ATTACHMENT_J.2__Optional_Form_(OF)_17-BidProposal_Envelope_Label.pdf PDF
RFP.pdf PDF
ATTACHMENT_J.1_GU_FY18_DS_Spec.pdf PDF
MOC-631-2D, Coating Systems for Steel Surfaces.pdf PDF
MSD Model 12 M1-1.pdf PDF
s2906 Arc Welding on Waterborne Vessels.pdf PDF
AMC-583-1B General Requirements for Liferaft Inspections.pdf PDF
555-6233815.pdf PDF
ATTACHMENT_J.3_Past_Performance_Information_Form.docx DOCX document
512-6233800.pdf PDF
GU-512-004 Revision A.pdf PDF
GU-512-6233799 Revision B.pdf PDF
GU-512-6233801.pdf PDF
MOC-000-1G General Requirements for Ship Repair Work on NOAA Ships.pdf PDF
GU-085-6233567.pdf PDF
MOC-510-1B,_HVAC_Cleaning_(3_sheets)_(1).pdf PDF
GU-512-003 Revision B.pdf PDF
s1600 Structural Access Cuts.pdf PDF
GU-512-6233802.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOC-573-2

September 2000

National Oceanic and Atmospheric Administration Marine Operation Center

Standard Specification MOC-573-2

OVERHAUL/REPAIR OF HYDRAULIC CYLINDERS

1. SCOPE: This specification provides the minimum requirements for the overhaul and/or repair of hydraulic cylinders.

2. REFERENCES

None

3. REQUIREMENTS

3.1 Tag out system controllers and actuators to preclude

inadvertent operation and secure the movable member to prevent movement while cylinder is removed.

3.1.1 Disconnect and cap hydraulic lines from the cylinder.

Ensure containment is provided to prevent spillage of oil.

Hydraulic lines and inlet/outlet ports shall be capped or plugged with threaded fittings to prevent leakage or contamination of the system.

3.1.2 Remove the cylinder from the ship and transport to

repair facility.

3.2 Perform the following work on the removed cylinder:

3.2.1 Completely disassemble the cylinder and clean all

parts.

3.2.2 Prepare and preserve the external painted surfaces in

accordance with the identified painting specification or as original.

3.2.3 Reassemble the cylinder under clean conditions using

new "O" rings, seals, gaskets, packing, and piston rings.

Materials used shall meet or exceed original manufacturers specifications. During reassembly lubricate the above with a product equal to Hilton's Hyper-Lube, that is compatible with the system fluid.

3.2.4 Provide and install new nuts, washers, bolts, studs and inlet and outlet fittings.

3.3 Reinstall the cylinder in its original location.

MOC-573-2

September 2000

3.4 Top off hydraulic reservoir to full mark and purge all air from the system taking care to contain any fluid bled off.

3.5 Remove tag outs.

4. QUALITY ASSURANCE

4.1 After disassembly, inspect all components for trueness of bore and rod, wear, damage, corrosion or pitting. Provide a Condition Report detailing the inspection results, contractor's corrective action recommendations, and list of additional parts, material and labor not covered by this specification, required to restore the cylinder to the manufacturers specifications.

4.2 After reassembly, bench test the assembly at system working pressure to prove smoothness of operation and tightness of sealing surfaces.

4.3 Cycle the cylinder through a minimum of four evolutions to demonstrate operation and tightness of all disturbed fittings and connections. Upon satisfactory demonstration of operation and tightness apply "Denso tape" to all connections.

END OF SPECIFICATION