HVAC_SOW_MOC-A__2016-03-31.pdf

PDF 182 KB Posted

Attached to
NOAA OMAO MOC HVAC Preventative Maintenance Federal contract opportunity
Solicitation number
EA-133M-16-RQ-0376
Issued by
Department of Commerce National Oceanic and Atmospheric Administration

About this file

Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to NOAA OMAO MOC HVAC Preventative Maintenance, newest first.
File Type Posted
SF_30_Quote_Due_Date.pdf PDF
Qs_and_As_for_EA-133M-16-RQ-0376.pdf PDF
SF_30_Amendment_Questions_and_Answers_HVAC_OMAO-A.pdf PDF
LIST_OF_HVAC_EQUIPMENT_SvsContr_MOC-A_2016-05-13.xls XLS spreadsheet
Equipment_List.pdf PDF
Site_Investigation_Report_No_Pricing.pdf PDF
RFQ_Combined_Synopsis_Solicitation_-_HVAC_Services.pdf PDF
www.wdol.gov_wdol_scafiles_std_15-4341.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOA HVAC PM STATEMENT OF WORK

Annual Service for Maintenance of Heating, Ventilation and Air Conditioning (HVAC) and Energy Management Systems at the National Oceanic and Atmospheric Administration (NOAA) Marine Operations Center-Atlantic (MOC-A)

The NOAA MOC-A (Building 1) is located at 435 West York Street Norfolk, VA 23510 and is the operational support facility for nine (9) ships based on the Atlantic seaboard and the Gulf of Mexico. In addition, NOAA’s Office of Coast Survey’s Atlantic Hydrographic Branch is co-located at the MOC-A facility in adjacent Building Two. The buildings were constructed in the early 1920’s (Building 1) and 1960’s (Building 2). The HVAC system is aging and frequent repairs and services are required. NOAA intends to contract services for repair, maintenance, and troubleshooting of the 2 ea. HVAC systems outlined in this statement of work for a total of one year with options to renew for an additional year.

I. STATEMENT OF WORK

The Contractor shall furnish all labor, material, equipment, and incidentals to provide a Preventive Maintenance and Service for the HVAC equipment listed in Appendix A. Service intervals and list of services to be provided are as per this Statement of Work, Appendix A is a summary and intended to be a checklist for the Contractor.

II. EQUIPMENT AND DETAILED DESCRIPTION OF WORK

Boilers

• Conduct combustion analysis on all boilers annually, adjust and trim as needed. Check boiler for overall condition and serviceability. If major maintenance is required, report to MOC-A Facilities Maintenance Lead, Prepare a quote for MOC-A approval and processing. If approved, perform service and send an invoice after servicing is completed, using the same numbering system as the related quote.

Rooftop Units

• Service all rooftop units (3 ea. in Building 1 and 2 ea. in Building 2) and exhaust fans. Verify operability, replace air filters, service belts/sheaves as needed and in accordance with Appendix A.

Cooling Tower

• Check cooling tower for overall serviceability. Clean strainer in accordance with the attached

Schedule. Lubricate motor, check tension on belt. Check tank heater for operability.

Air Handler Units (AHUs)

• Service AHU’s listed and in accordance with Appendix A. Replace air filters at the frequency listed in Appendix A, documenting replacement date on the air filter on the side visible for verification. Check all belts and sheaves on air handlers and exhaust fans. Tighten sheaves or replace belt as needed. Lubricate motors annually.

Coil Units

• Check coil units for overall serviceability. Clean and check Freon charge in accordance with

Appendix A schedule.

• Change air filters quarterly. Service belts as needed; belt tension adjusted and belts changed as needed based on wear.

Chillers - one chiller for building #1.

Conduct the following services to the Trane packaged chiller:

• Perform overall inspection of Bldg1 chiller.

• Verify refrigerant pressures and temperatures

• Calculate lift and calculate optimum setpoint

• Verify oil levels and conduct oil changes

• Check electrical connections, tighten if needed.

• If major maintenance is required, report to MOC-A Facilities Maintenance Lead, and prepare a quote for MOC-A approval and processing. If approved, perform service and send an invoice after servicing is completed, using the same numbering system as the related quote.

Pumps (6 in Building 1 and 2 in Building 2):

• Verify operation of pumps for HVAC hot water and chilled water

• HVAC pumps lubricated as required

HVAC Controls

• Some HVAC controls are currently not working and will be renovated in the near future. Check with Royal Evans on specific HVAC controls to see if NOAA desires a quote on HVAC control repairs.

Miscellaneous

• If any major issues are discovered requiring work beyond the scope of this contract, notify MOC-

A Facilities to see if MOC-A wants repairs. If authorized by MOC-A chain of command, prepare a quote detailing the work needed, and the technician’s evaluation of the condition of the equipment serviced. If approved, perform service and send an invoice after servicing is completed, using the same numbering system as the related quote.

III. ADDITIONAL REQUIREMENTS

VENDOR SIGN-IN

All vendors must sign in/sign out at the Guard Shack when arriving/leaving.

MAINTENANCE RECORDS

1. The contractor shall supply and maintain written records of maintenance and repairs before leaving MOC-A.

2. Note and report any mechanical, electrical or control system discrepancies that would affect equipment operations.

3. Document all work performed, including all pertinent pressures, temperatures, voltages, fluid levels and test results.

4. The report shall contain any uncorrected deficiencies noted at inspection.

MATERIALS

All materials and preventive maintenance parts shall be new, of good quality and warrantied according to the manufacturer. Materials requiring a Material Safety Data Sheet, (MSDS) shall be reviewed by the Contractor prior to usage.

UNSCHEDULED MAINTENANCE AND EMERGENCY REPAIRS

1. Upon request by authorized MOC-A representatives (the XO and Royal Evans), the Contractor shall perform authorized repairs.

2. Authorized repairs shall be made during normal working hours of 8:00am to 5:00pm Monday thru Friday. Emergency work on Federal Holidays must be approved.

3. All emergency repairs must be approved by the Executive Officer of MOA.

HEALTH AND SAFETY REGULATIONS

I. It is the responsibility of the Contractor to comply with all Federal laws governing the Health and Safety of its employees including all regulations promulgated under the Occupational Safety and Health Act (OSHA.)

2. Such compliance shall include but not be limited to ensuring that all employees are properly trained for the work to be performed and have been supplied with all necessary protective and safety equipment.

SAFETY- LOCK OUT/TAG OUT

1. Advise MOC-A Point of Contact prior to starting maintenance or repair procedures.

2. Disconnect power supply; Tag unit as "Out of Service" as per OSHA requirements.

CODES AND STANDARDS:

Latest effective publication or applicable codes of the following standards, codes, etc., as they apply.

American Society of Heating, Refrigeration, and Air Conditioning Engineers, (ASHREA)

National Building Code, (BOCA)

Factory Mutual Engineering Association, (FM) Underwriters' Laboratories, Inc. (UL)

National Electrical Code (NFPA 70-99), National Electrical Safety Code

(ANSI C2) and the NECA Standard of Installation or Local standards, whichever is more stringent. The NEC (2002) will be followed, as applicable.

American Society of Mechanical Engineers, (ASME) Air Conditioning and Refrigeration Institute, (ARI) Air Movement and Control Association, (AMCA) Ameri an Gas Association, (A9A)

American National Standards Institute, (ANSI) American Society for Testing and Materials, (ASTM) Electrical Testing Laboratories, (ETL)

International Mechanical Code, 1996

OSHA General Industry Safety and Health Standards (29 CFR 1910); OSHA Construction Industry Standards (29 CFR 1926) Single copies of these regulations are available from the local OSHA Area Offices. These documents are also for sale by the Superintendent of Documents, US. Government Printing Office, Washington, DC 20402

Environmental Protection Agency (EPA) Final Rule (40 CFR, Part 761)

IV. GOVERNMENT FURNISHED INFORMATION

1. Any service manuals, Operation and Maintenance manuals that MOC-A have available.

(NOTE: Some of the HVAC equipment at MOC-A have no service or O&M manuals.

2. March 2016 Site Investigation Report for HVAC and Mechanical Equipment, by Associated Design Group.

V. MINIMAL TECHNICAL REQUIREMENTS:

• Vendor must have expertise and show proof of past experience servicing similar HVAC and Energy Management systems listed above

• Vendor must show proof of liability insurance

• Vendor must show proof of registration in the government System for Award

Management (SAM) database system

• Vendor must be available for emergency call out services 24/7 including weekends, holidays and after normal business hours. The response time will vary based on the severity of the malfunctioning system. Due to the sensitive nature of computer networks and servers, response within 4 hours is required for all air conditioning and heating emergencies. All other repair response times are variable.

• Vendors must be located within the Hampton Roads area in order to respond to emergency services within the time required

• Vendors key personnel must show proof of HVAC certification and any other applicable certifications including electrician

VI. NONCOMPLIANCE STATEMENT

1. MOC-A may cancel this contract with a thirty (30) day written notice of cancellation for noncompliance of all or part of this agreement.

2. The contractor will have five (5) working days to correct any/all deficiencies or the agreement is cancelled.

VII. SITE EXAMINATION

Interested vendors must perform a site visit and walk through of both buildings at MOC-A Norfolk prior to providing response and bid. The date and time of this meeting shall be announced in the Solicitation. Point of contact for this site visit is:

Royal Evans, Lead Maintenance Mechanic NOAA OMAO Marine Operations Center - Atlantic 439 West York Street Norfolk, VA 23510-1114

(757) 441-6797

END OF STATEMENT OF WORK

s = semi-annual - a = annual Designation Location Sub-L. Sub-L. Required Service

AHU-2-Bldg1 Bldg 1 Roof NW Wing Quarterly and Annually RTU-2b-Bldg1 Bldg 1 Roof N Center Quarterly and Annually

AHU-1-CU Bldg 1 Roof Above

Passageway Quarterly and Annually

Packaged RTU Bldg 1 Roof Center WH Quarterly and Annually Packaged RTU #2 Bldg 1 Roof Above Trng Rm Quarterly and Annually Exist Pkd RTU Bldg 1 Roof South WH Quarterly and Annually Exist Boiler Bldg1 Bldg 1 Mech Rm SEE SOW AHU Stricker Bldg 1 Mech Rm Quarterly and Annually AHU-3-Bldg1 Bldg 1 Mech Rm Quarterly and Annually Chiller Bldg1 Bldg 1 Mech Rm Quarterly and Annually Chiller Cntrls Bldg 1 - - Quarterly and Annually CW/HW Pumps Bldg 1 Mech Rm Annually Marley SPX CT Bldg 1 Outside By Mech Rm Quarterly, SA, and Annually

Pkgd DX RTU Bldg 2 Roof Center Quarterly and Annually Comp Rm Spl Sys Bldg 2 Roof Center Quarterly and Annually Exist Boiler Bldg2 Bldg 2 2nd Fl W See SOW

AHU-3 Bldg 2 1st Fl Mech Rm

Quarterly and Annually

AHU-4 Bldg 2 1st Fl Mech Rm

Quarterly and Annually

AHU-5 Bldg 2 1st Fl Mech Rm

Quarterly and Annually

AHU-6 Bldg 2 1st Fl Mech Rm

Quarterly and Annually

CU-3 Bldg 2 Outside Mech Rm

Quarterly and Annually

CU-4 Bldg 2 Outside Mech Rm

Semi-Annually

CU-5 Bldg 2 Outside Mech Rm

Semi Annually

CU-6 Bldg 2 Outside Mech Rm

Semi Annually

All air filter changes will be documented on each filter, date replaced AHU-3, AHU-4, AHU-5, AHU-6 are in tight space Mech Room Bldg 2, caution advised CWPs Annaul Maintenance: Check operability, lubricate motors

Note

Coil Unit

Coil Unit

Coil Unit

Air Handler Unit

Air Handler Unit

Air Handler Unit

Coil Unit

Building 2 HVAC Equip Packaged Roof Top Unit Computer Room Split System Boiler

Air Handler Unit

Air Handler Unit Chiller Chiller Controls Chilled/Hot Water Pumps (3 ea) Cooling Tower

Packaged Roof Top Unit Boiler Air Handler Unit

Packaged Roof Top Unit Packaged Roof Top Unit

Air Handler Unit

Packaged Roof Top Unit Packaged Roof Top Unit

SERVICE CONTRACT MAINTENANCE PLAN

k) - m = monthly - q = quarterly -

Equip

Building 1 HVAC Equip

Equipment List.pdf