s = semi-annual - a = annual Designation Location Sub-L. Sub-L. Required Service

AHU-2-Bldg1 Bldg 1 Roof NW Wing Quarterly and Annually RTU-2b-Bldg1 Bldg 1 Roof N Center Quarterly and Annually

AHU-1-CU Bldg 1 Roof Above

Passageway Quarterly and Annually

Packaged RTU Bldg 1 Roof Center WH Quarterly and Annually Packaged RTU #2 Bldg 1 Roof Above Trng Rm Quarterly and Annually Exist Pkd RTU Bldg 1 Roof South WH Quarterly and Annually Exist Boiler Bldg1 Bldg 1 Mech Rm SEE SOW AHU Stricker Bldg 1 Mech Rm Quarterly and Annually AHU-3-Bldg1 Bldg 1 Mech Rm Quarterly and Annually Chiller Bldg1 Bldg 1 Mech Rm Quarterly and Annually Chiller Cntrls Bldg 1 - - Quarterly and Annually CW/HW Pumps Bldg 1 Mech Rm Annually Marley SPX CT Bldg 1 Outside By Mech Rm Quarterly, SA, and Annually

Pkgd DX RTU Bldg 2 Roof Center Quarterly and Annually Comp Rm Spl Sys Bldg 2 Roof Center Quarterly and Annually Exist Boiler Bldg2 Bldg 2 2nd Fl W See SOW

AHU-3 Bldg 2 1st Fl Mech Rm

Quarterly and Annually

AHU-4 Bldg 2 1st Fl Mech Rm

Quarterly and Annually

AHU-5 Bldg 2 1st Fl Mech Rm

Quarterly and Annually

AHU-6 Bldg 2 1st Fl Mech Rm

Quarterly and Annually

CU-3 Bldg 2 Outside Mech Rm

Quarterly and Annually

CU-4 Bldg 2 Outside Mech Rm

Semi-Annually

CU-5 Bldg 2 Outside Mech Rm

Semi Annually

CU-6 Bldg 2 Outside Mech Rm

Semi Annually

All air filter changes will be documented on each filter, date replaced AHU-3, AHU-4, AHU-5, AHU-6 are in tight space Mech Room Bldg 2, caution advised CWPs Annaul Maintenance: Check operability, lubricate motors

Note

Coil Unit

Coil Unit

Coil Unit

Air Handler Unit

Air Handler Unit

Air Handler Unit

Coil Unit

Building 2 HVAC Equip Packaged Roof Top Unit Computer Room Split System Boiler

Air Handler Unit

Air Handler Unit Chiller Chiller Controls Chilled/Hot Water Pumps (3 ea) Cooling Tower

Packaged Roof Top Unit Boiler Air Handler Unit

Packaged Roof Top Unit Packaged Roof Top Unit

Air Handler Unit

Packaged Roof Top Unit Packaged Roof Top Unit

SERVICE CONTRACT MAINTENANCE PLAN

k) - m = monthly - q = quarterly -

Equip

Building 1 HVAC Equip

Table 1