Equipment List
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF_30_Quote_Due_Date.pdf | ||
| Qs_and_As_for_EA-133M-16-RQ-0376.pdf | ||
| SF_30_Amendment_Questions_and_Answers_HVAC_OMAO-A.pdf | ||
| LIST_OF_HVAC_EQUIPMENT_SvsContr_MOC-A_2016-05-13.xls | XLS spreadsheet | |
| www.wdol.gov_wdol_scafiles_std_15-4341.pdf | ||
| Site_Investigation_Report_No_Pricing.pdf | ||
| HVAC_SOW_MOC-A__2016-03-31.pdf | ||
| RFQ_Combined_Synopsis_Solicitation_-_HVAC_Services.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
s = semi-annual - a = annual Designation Location Sub-L. Sub-L. Required Service
AHU-2-Bldg1 Bldg 1 Roof NW Wing Quarterly and Annually RTU-2b-Bldg1 Bldg 1 Roof N Center Quarterly and Annually
AHU-1-CU Bldg 1 Roof Above
Passageway Quarterly and Annually
Packaged RTU Bldg 1 Roof Center WH Quarterly and Annually Packaged RTU #2 Bldg 1 Roof Above Trng Rm Quarterly and Annually Exist Pkd RTU Bldg 1 Roof South WH Quarterly and Annually Exist Boiler Bldg1 Bldg 1 Mech Rm SEE SOW AHU Stricker Bldg 1 Mech Rm Quarterly and Annually AHU-3-Bldg1 Bldg 1 Mech Rm Quarterly and Annually Chiller Bldg1 Bldg 1 Mech Rm Quarterly and Annually Chiller Cntrls Bldg 1 - - Quarterly and Annually CW/HW Pumps Bldg 1 Mech Rm Annually Marley SPX CT Bldg 1 Outside By Mech Rm Quarterly, SA, and Annually
Pkgd DX RTU Bldg 2 Roof Center Quarterly and Annually Comp Rm Spl Sys Bldg 2 Roof Center Quarterly and Annually Exist Boiler Bldg2 Bldg 2 2nd Fl W See SOW
AHU-3 Bldg 2 1st Fl Mech Rm
Quarterly and Annually
AHU-4 Bldg 2 1st Fl Mech Rm
Quarterly and Annually
AHU-5 Bldg 2 1st Fl Mech Rm
Quarterly and Annually
AHU-6 Bldg 2 1st Fl Mech Rm
Quarterly and Annually
CU-3 Bldg 2 Outside Mech Rm
Quarterly and Annually
CU-4 Bldg 2 Outside Mech Rm
Semi-Annually
CU-5 Bldg 2 Outside Mech Rm
Semi Annually
CU-6 Bldg 2 Outside Mech Rm
Semi Annually
All air filter changes will be documented on each filter, date replaced AHU-3, AHU-4, AHU-5, AHU-6 are in tight space Mech Room Bldg 2, caution advised CWPs Annaul Maintenance: Check operability, lubricate motors
Note
Coil Unit
Coil Unit
Coil Unit
Air Handler Unit
Air Handler Unit
Air Handler Unit
Coil Unit
Building 2 HVAC Equip Packaged Roof Top Unit Computer Room Split System Boiler
Air Handler Unit
Air Handler Unit Chiller Chiller Controls Chilled/Hot Water Pumps (3 ea) Cooling Tower
Packaged Roof Top Unit Boiler Air Handler Unit
Packaged Roof Top Unit Packaged Roof Top Unit
Air Handler Unit
Packaged Roof Top Unit Packaged Roof Top Unit
SERVICE CONTRACT MAINTENANCE PLAN
k) - m = monthly - q = quarterly -
Equip
Building 1 HVAC Equip
Table 1