573-2.pdf

PDF 20 KB Posted

Attached to
Dockside Repairs to NOAA Ship GORDON GUNTER
Solicitation number
EA133M-11-RP-0150
Issued by

About this file

STD SPEC 573-2

View the file

Other files

File Type Posted
Gordon Gunter EA133M-11-RP-0150 Amend 0003.pdf PDF
Gordon Gunter EA133M-11-RP-0150 Amend 0002.pdf PDF
Gordon Gunter EA133M-11-RP-0150 Amend 0001.PDF PDF
625-6233589.pdf PDF
512-6233797.pdf PDF
573-1C.pdf PDF
GU-512-003 Revision B.pdf PDF
ATT J.2 SF24.pdf PDF
GU-512-002 Revision B.pdf PDF
512-6233792.pdf PDF
NAVSEA Manual S9073-A2-HBK-010.pdf PDF
ASHRAE Standard 151 - HVAC Balancing Testing.pdf PDF
s2906.pdf PDF
ATT J.5 OF 17 Offer Label.pdf PDF
GU-506-001 Revision A.pdf PDF
512-6233799.pdf PDF
Information Data Sheet for type 5B5000H Machinery Mount.pdf PDF
GU-520-001 Revision A.pdf PDF
631-2D.pdf PDF
000-1G.pdf PDF
GU - FY12 Dockside Repair Spec Package9-27-11.pdf PDF
ATT J.3 SF1416 Payment Bond.pdf PDF
American Industrial Heat Transfer AA-STA Series Brochure.pdf PDF
GU-801-001 Revision A.pdf PDF
Quincy QR-25 Model 340 Air Compressor.pdf PDF
s0100.pdf PDF
ATT J.4 SF1418 Performance Bond.pdf PDF
Okeanos Explorer Aft Peak Oil Line Cofferdam.pdf PDF
183-6233564.pdf PDF
512-6233802.pdf PDF
RFP EA133M11RP0150 Gordon GunterSol.pdf PDF
GU-830-002.pdf PDF
Amercoat 182 Spec Sheet.pdf PDF
512-6233801.pdf PDF
Marco WT202 Trawl Winch.pdf PDF
s1600.pdf PDF
512-6233800.pdf PDF
GU-512-004 Revision A.pdf PDF
GU - FY12 Dockside Repair Spec Package 27 Sep 11.pdf PDF
GU - FY12 Dockside Repair Spec Package.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOC-573-2

September 2000

National Oceanic and Atmospheric Administration Marine Operation Center

Standard Specification MOC-573-2

OVERHAUL/REPAIR OF HYDRAULIC CYLINDERS

1. SCOPE: This specification provides the minimum requirements for the overhaul and/or repair of hydraulic cylinders.

2. REFERENCES

None

3. REQUIREMENTS

3.1 Tag out system controllers and actuators to preclude

inadvertent operation and secure the movable member to prevent movement while cylinder is removed.

3.1.1 Disconnect and cap hydraulic lines from the cylinder.

Ensure containment is provided to prevent spillage of oil.

Hydraulic lines and inlet/outlet ports shall be capped or plugged with threaded fittings to prevent leakage or contamination of the system.

3.1.2 Remove the cylinder from the ship and transport to

repair facility.

3.2 Perform the following work on the removed cylinder:

3.2.1 Completely disassemble the cylinder and clean all

parts.

3.2.2 Prepare and preserve the external painted surfaces in

accordance with the identified painting specification or as original.

3.2.3 Reassemble the cylinder under clean conditions using

new "O" rings, seals, gaskets, packing, and piston rings.

Materials used shall meet or exceed original manufacturers specifications. During reassembly lubricate the above with a product equal to Hilton's Hyper-Lube, that is compatible with the system fluid.

3.2.4 Provide and install new nuts, washers, bolts, studs and inlet and outlet fittings.

3.3 Reinstall the cylinder in its original location.

MOC-573-2

September 2000

3.4 Top off hydraulic reservoir to full mark and purge all air from the system taking care to contain any fluid bled off.

3.5 Remove tag outs.

4. QUALITY ASSURANCE

4.1 After disassembly, inspect all components for trueness of bore and rod, wear, damage, corrosion or pitting. Provide a Condition Report detailing the inspection results, contractor's corrective action recommendations, and list of additional parts, material and labor not covered by this specification, required to restore the cylinder to the manufacturers specifications.

4.2 After reassembly, bench test the assembly at system working pressure to prove smoothness of operation and tightness of sealing surfaces.

4.3 Cycle the cylinder through a minimum of four evolutions to demonstrate operation and tightness of all disturbed fittings and connections. Upon satisfactory demonstration of operation and tightness apply "Denso tape" to all connections.

END OF SPECIFICATION

Page 1