Summary of Statement of Work: Repair Fire Protection Systems - Hangar 6
This Statement of Work (SOW) is a turnkey procurement for the United States Air Force Reserve Command (AFRC) to repair and restore fire protection deluge and pre-action sprinkler systems at Hangar 6, Grissom Air Reserve Base, Indiana, scheduled for August 2026. The project encompasses two primary task areas: (1) Compressed Air System Repairs involving demolition of existing fouled air lines, installation of a new C-Aire fire-protection rated air compressor, new air maintenance devices (AMDs), and new air lines across all four pre-action systems; and (2) Linear Heat Detection System (Protectowire) Repairs requiring installation of new Protectowire linear heat detection cable and two new Protectowire CTM 250 interface modules for Zones 1 and 2 pre-action sprinkler systems, with comprehensive system functionality testing. The contractor must provide all labor, management, supervision, tools, materials, equipment, transportation, and engineering/design services in strict compliance with UFC 3-600-01, UFGS 21 13 18 and UFGS 28 31 00, NFPA 13, NFPA 72, NFPA 409, and AFMAN 32-1067.
Work must be performed during normal base hours (Monday-Friday, 7:00 AM to 3:30 PM), with the contractor supplying all specialized equipment including two 60-foot aerial boom lifts, safety equipment, and certified electrical subcontractor services (ERMCO or equivalent). Key deliverables include a Safety Plan (10 days post-award), manufacturer datasheets (15 days), System Impairment Schedule (5 days prior to work), electrician certifications (prior to mobilization), final testing reports (5 days post-testing), and as-built diagrams (10 days post-completion). Final acceptance requires error-free standby operation for 48 continuous hours with joint inspection by the contractor, Contracting Officer Representative, and Grissom ARB Fire Inspector. Excluded from scope are general interior painting, structural ceiling/wall modifications unless required for routing, relocation of major existing wet-pipe piping, and external post-completion monitoring services.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
PROJECT TITLE: Repair Fire Protection Systems - Hangar 6 (Air Line & Protectowire Replacement)
LOCATION: Hangar 6, Grissom Air Reserve Base (ARB), Indiana 46971
DATE: August 2026
PREPARED FOR: United States Air Force Reserve Command (AFRC)
1.0 DESCRIPTION OF WORK
The Contractor shall provide all labor, management, supervision, tools, materials, equipment, transportation, and engineering/design services necessary to repair and restore to full operational status the fire protection deluge and pre-action systems in Hangar 6 at Grissom Air Reserve Base, Indiana.
The project consists of two primary task areas:
1. Compressed Air System Repairs: Demolition of existing fouled air lines, installation of a new air compressor, new air maintenance devices, and new air lines across all four (4) pre-action systems.
2. Linear Heat Detection System (Protectowire) Repairs: Installation of new linear heat detection wire (Protectowire) and associated interface modules for Zones 1 and 2 pre-action sprinkler systems, and system functionality testing.
This project is a turnkey procurement. All work shall be performed in strict accordance with this Statement of Work, the contract drawings, applicable Unified Facilities Criteria (UFC), Unified Facilities Guide Specifications (UFGS), National Fire Protection Association (NFPA) standards, and base safety/security regulations.
2.0 BACKGROUND & SITE DESCRIPTION
Hangar 6 at Grissom ARB is an active, mission-critical aircraft maintenance hangar.
The hangar is protected by double-interlock pre-action and deluge sprinkler systems designed to protect high-value military assets.
Currently, the fire protection systems are experiencing significant operational issues:
• Pre-Action Air Supply Clogging: The deluge and pre-action systems are tripping. Investigation revealed that the air lines supplying supervisory air to the systems are severely clogged with debris and moisture, restricting air flow, causing pressure drops, and resulting in system trips.
• Linear Heat Detection Faults: The linear heat detection system (Protectowire) in Zones 1 and 2 is failing, causing continuous fault alarms and accidental trips of the pre-action sprinkler systems.
Immediate repairs are required to restore fire protection capabilities, protect personnel and aircraft, and ensure base operational readiness.
3.0 APPLICABLE CODES, STANDARDS, AND
SPECIFICATIONS
The Contractor shall ensure that all designs, materials, installations, and testing comply with the latest editions of the following federal, military, and national codes and standards:
3.1 Unified Facilities Criteria (UFC)
• UFC 3-600-01: Fire Protection Engineering for Facilities (specifically Section 4-1 for Aircraft Hangars and Section 4-1.2 for Deluge/Pre-action Systems)
• UFC 3-501-01: Electrical Engineering
• UFC 1-200-01: General Building Requirements
3.2 Unified Facilities Guide Specifications (UFGS)
• UFGS 21 13 18: Pre-Action and Deluge Sprinkler Systems
• UFGS 28 31 00: Fire Detection and Alarm Systems, Addressable
• UFGS 22 15 00: General Service Compressed-Air Systems, Low-Pressure
• UFGS 26 05 00: Common Work Results for Electrical
3.3 National Fire Protection Association (NFPA) Codes
• NFPA 13: Standard for the Installation of Sprinkler Systems
• NFPA 70: National Electrical Code (NEC)
• NFPA 72: National Fire Alarm and Signaling Code
• NFPA 409: Standard on Aircraft Hangars
3.4 Air Force & Local Regulations
• AFMAN 32-1067: Water and Fuel Systems
• Grissom ARB Local Fire Department Impairment and Reporting Procedures.
4.0 SCOPE OF WORK
4.1 Task 1: Air Line Replacement & Air Compressor
Installation The Contractor shall perform the following work to repair and upgrade the supervisory air supply lines and compression equipment for all four (4) pre-action sprinkler systems in Hangar 6:
3. Demolition:
• Safe-off, isolate, and depressurize the pre-action systems in coordination with the Grissom ARB Fire Department.
• Completely demolish, remove, and legally dispose of all existing, clogged air lines, fittings, and associated old air maintenance devices servicing the four
(4) systems.
4. Equipment Installation:
• Provide and install one (1) new C-Aire fire-protection rated air compressor.
• Ensure structural mounting, vibration isolation, and alignment of the new compressor are executed in accordance with manufacturer specifications and
UFGS 22 15 00.
• Coordinate and utilize a certified electrical subcontractor (ERMCO or approved equivalent) to perform all necessary electrical hookups, line runs, circuit breakers, and power connections to the new compressor unit in compliance with NFPA 70.
5. Piping and Air Maintenance:
• Provide and install new air maintenance devices (AMDs) on all four (4) systems. AMDs must meet the requirements of NFPA 13 and UFGS 21 13 18.
• Provide and install completely new air lines, fittings, and check valves to reconnect the new C-Aire compressor through the AMDs to all four (4) pre-action systems. All piping must be corrosion-resistant and sized properly to maintain required supervisory air pressure.
6. System Testing:
• Conduct a comprehensive pneumatic pressure test on the newly installed air lines to verify zero-leakage.
• Perform functional testing on all four (4) pre-action systems to verify proper air-fill rates, pressure-switch operations, and system-trip prevention.
4.2 Task 2: Zones 1 & 2 Protectowire Replacement
The Contractor shall perform the following work to restore the linear heat detection system in Hangar 6 to full compliance:
7. System Preparation:
• Coordinate with the base Fire Alarm Monitoring station to put the Hangar 6 alarm panels into test mode and bypass local release circuits to prevent accidental suppression discharge.
• Existing Protectowire for Zone 1 and Zone 2 shall be abandoned and left in place to avoid ceiling/wall structural compromises, as permitted by local fire regulations and UFC criteria.
8. Protectowire Installation:
• Furnish and install completely new Protectowire linear heat detection cable across Zone 1 and Zone 2.
• The new Protectowire shall be installed utilizing proper support hardware, messenger wire (if required for long spans), and in exact alignment with the detection paths of the protected zones.
• Installation must strictly adhere to the manufacturer's instructions, NFPA 72, and UFGS 28 31 00.
9. Control Module Upgrades:
• Furnish and install two (2) new Protectowire CTM 250 interface modules (one module dedicated to Zone 1, and one module dedicated to Zone 2).
• Integrate the new interface modules with the existing Fire Alarm Control Panel (FACP) in Hangar 6.
• Program, wire, and calibrate the CTM 250 modules to properly report zone status (Normal, Fault, Alarm) and localize exact detection coordinates/distances back to the primary FACP.
10. Integration & Commissioning:
• Perform comprehensive loop resistance and insulation testing on the new Protectowire runs.
• Conduct full functional testing of the dual-zone detection loops to verify that thermal criteria correctly actuate the pre-action system valves without causing false fault alarms.
5.0 GENERAL CONDITIONS AND EXCLUSIONS
5.1 Hours of Work
All on-site operations shall be conducted during normal base working hours:
Monday through Friday, 7:00 AM to 3:30 PM. Any work required outside of these hours must be requested in writing at least 72 hours in advance and approved by the Contracting Officer (CO).
5.2 Contractor-Furnished Equipment (CFE)
The Contractor is solely responsible for supplying all specialized tools and access equipment required for high-elevation work in Hangar 6. The Contractor must supply:
• Two (2) 60-foot aerial boom lifts in fully operational, inspected condition.
• All safety harnesses, lanyards, and Personal Protective Equipment (PPE) required for fall protection in compliance with OSHA and EM 385-1-1 (USACE Safety Manual).
• Fuel, maintenance, and secure storage for all on-site lifts.
5.3 Work Exclusions & Boundaries
The following scope items are specifically excluded from this contract. Any requirement for these items discovered during execution must be negotiated via a formal contract modification with the CO:
• General interior painting or aesthetic coating of Hangar 6 walls or ceilings.
• Cutting, removal, or replacement of structural ceiling tiles, drywall, or architectural features (unless explicitly required to route new Protectowire/air lines).
• Relocation of major existing wet-pipe sprinkler or deluge main piping (except for the direct air line hookups noted in Section 4.1).
• External fire system monitoring services post-completion.
6.0 COORDINATION, SAFETY, AND
ENVIRONMENTAL
6.1 Base Access and Security
• All personnel must obtain proper security clearance and base passes prior to entering Grissom ARB. The Contractor shall submit all required National Agency Check (NACI) or background information for personnel at least 14 days prior to the start of work.
• Vehicles, equipment, and trailers are subject to search at the base entry gates.
6.2 System Impairments and Coordination
Hangar 6 must remain operational to the maximum extent possible.
• The Contractor shall coordinate all system outages, alarm bypasses, or line de-pressurizations with the Grissom ARB Fire Department and PMI/RPM project managers.
• A written Fire Protection System Impairment Request must be submitted and approved at least five (5) working days prior to disabling any portion of the fire suppression or detection systems.
• The Contractor shall ensure that alternative fire watch measures are established if required by the Grissom ARB Fire Chief.
6.3 Cleanup and Waste Disposal
• The Contractor shall maintain a clean and orderly work area. At the end of each shift, the Contractor shall clean up and dispose of all debris, wire scraps, packaging, and discarded materials.
• All demolished components (old air lines, devices, defunct modules) shall be legally disposed of off-base in accordance with state and federal environmental regulations.
7.0 QUALITY ASSURANCE AND DELIVERABLES
7.1 Deliverables
The Contractor shall submit the following documentation to the Contracting Officer Representative (COR) for review and approval:
Deliverable ID Description Timeline
DEL-01 Safety Plan & Accident Prevention Plan (APP)
10 Days Post-Award
DEL-02 Manufacturer Datasheets (Compressor, AMDs, 15 Days Post-Award
Protectowire, CTM 250)
DEL-03 System Impairment & Outage Schedule
5 Days Prior to On-site Work
DEL-04 Electrician Certification (ERMCO) & Lift Inspection Logs
Prior to On-site Mobilization
DEL-05 Final Testing Reports (Pneumatic & Alarm Functionality)
5 Days Post-Testing
DEL-06 Closeout Redlines / As- Built Diagrams & Operation Manuals
10 Days Post-Completion
7.2 Final Inspection and Acceptance
• Upon completion of all installations, a joint final inspection and functional demonstration shall be conducted with the Contractor, the COR, and the Grissom ARB Fire Inspector.
• The fire protection system must demonstrate error-free standby operation (no faults, leaks, or pressure drops) for a continuous period of 48 hours prior to final government acceptance.
| STATEMENT OF WORK (SOW) |
| 1.0 DESCRIPTION OF WORK |
| 2.0 BACKGROUND & SITE DESCRIPTION |
| 3.0 APPLICABLE CODES, STANDARDS, AND SPECIFICATIONS |
| 3.1 Unified Facilities Criteria (UFC) |
| 3.2 Unified Facilities Guide Specifications (UFGS) |
| 3.3 National Fire Protection Association (NFPA) Codes |
| 3.4 Air Force & Local Regulations |
| 4.0 SCOPE OF WORK |
| 4.1 Task 1: Air Line Replacement & Air Compressor Installation |
| 4.2 Task 2: Zones 1 & 2 Protectowire Replacement |
| 5.0 GENERAL CONDITIONS AND EXCLUSIONS |
| 5.1 Hours of Work |
| 5.2 Contractor-Furnished Equipment (CFE) |
| 5.3 Work Exclusions & Boundaries |
| 6.0 COORDINATION, SAFETY, AND ENVIRONMENTAL |
| 6.1 Base Access and Security |
| 6.2 System Impairments and Coordination |
| 6.3 Cleanup and Waste Disposal |
| 7.0 QUALITY ASSURANCE AND DELIVERABLES |
| 7.1 Deliverables |
| 7.2 Final Inspection and Acceptance |