SOW_Pipe_and_Steel-Engine.pdf
PDF 1 MB Posted
- Attached to
- TS GOLDEN BEAR Piping and Steel Work
- Solicitation number
- DTMA9417Q00001
About this file
Revised Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_3_SF30.pdf | ||
| Revised_Pipe_and_Steel_Engine_Ship_Check_Notes.pdf | ||
| Pipe_and_Steel_Engine_Ship_Check_Notes.pdf | ||
| Amendment_2_SF30.pdf | ||
| Pipe_and_Steel-_Engine_T C.pdf | ||
| SF1449.pdf | ||
| wage_determination_Solono_Co_2005_rev_17.pdf | ||
| ATTCH_CLAUSES.pdf | ||
| Pipe_and_Steel_-_Engine_-Quote_Sheet.xlsx | XLSX spreadsheet | |
| amendment_1.pdf | ||
| SOW_Pipe_and_Steel.pdf | ||
| Pipe_and_Steel_T C.pdf | ||
| wage_determination_Solono_Co_2005_rev_17.pdf | ||
| ATTCH_CLAUSES.pdf | ||
| SF1449.pdf | ||
| Pipe_and_Steel_Quote_Sheet.xlsx | XLSX spreadsheet |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pipe and Steel -Engine 2017
PIPE AND STEEL –Engine - 2017
Item No 1 – SR No 5186732 – Fwd House Deep Sink Gray Water Drain
SR No 5186732 FWD HOUSE DEEP SINK GRAY WATER DRAINAGE
ABSTRACT
Forward House Deep Sink Gray Water drain pipe is wasted and needs to be renewed
Contractor to supply all necessary labor, material, rigging and transportation to remove old pipe and supply and install new pipe with proper supports
LOCATION AND DESCRIPTION
Location: Forward House Deep sink Gray water drainage
Description: Remove old pipe and interference as needed and supply and install new 2 inch Sch 80 pipe
STATEMENT OF WORK
Contractor to provide all necessary labor, material, rigging and transportation to remove old piping and install new piping with supports and necessary cleanouts
When job is completed, prime and paint the piping with one coat of primer and two coats of top coat with appropriate color per Chief Mate
Existing run of Sink drainage is severely corroded inside. Piping cannot be cleared using any conventional methods.
Approximately 6 feet of 2" schedule 80 seamless steel piping and 4-6 welded couplings and elbows are included in this run of pipping.
Crop out and remove existing section extending from sink P trap and penetration section of pipe that runs down into 2nd deck space.
Fabricate new section of drain pipe utilizing long radius ells instead of the existing 90 short elbows.
New pipe used shall be 2" Schedule 80 seamless steel. All fittings and couplings shall be sweep butt-weld type type. All joints shall use "wedding bands" or flanged joints if possible
Test to 1.5 times normal working pressure (estimated to be 50 psi maximum)
Item No 2 – SR No 5186717 – Seawater Flushing Isolation Valves
SR No 5186717 Saltwater Flushing Isolation Valves (Phase 1 of 3)
ABSTRACT
Contractor to supply all labor, material and transportation necessary to install new isolation shutoff valves in the ship’s saltwater flushing system in designated areas.
REFERENCES
Blue prints for ship’s saltwater flushing system in ship’s library
LOCATION / DESCRIPTION
Location:
Throughout the vessel
Description:
Miscellaneous valves sizes and types of valves in various locations to be renewed to replace those in service that no longer reliably secure a section of the flushing system
GOVERNMENT FURNISHED EQUIPMENT / MATERIAL / SERVICES
None
STATEMENT OF WORK
Justification: Cruise FY14 presented multiple sewage system problems that were complicated due the fact that individual areas of the ship could not be isolated which required a complete system shutdown to accomplish the work. Ship's aging saltwater piping requires continued maintenance and repair work. There is presently no means to isolate smaller zones of the living spaces rather than using existing valves that isolate an entire house.
In addition, one section of piping shall be removed from the overhead of an 02 port side fwd house state room living space and re-routed through the overhead of the adjacent passageway.
A hydrodynamic tank shall be installed on the end run of piping that serves the 03 deck forward house. This tank shall serve as a cushion to dynamic shock that salt water flushing pipework in the forward house presently endures.
The following areas are targeted as best places in the saltwater flushing pipework to install new “Ball Type” isolating valves.
01-151-02 ( passageway overhead ) - 1 1/4" 150# flanged brass ball valve
1-122-02 ( passageway overhead ) - 2" 150# flanged brass ball valve
1-137-01 (passageway overhead ) - 2" 150# flanged brass ball valve
1-121-01 ( stbd passageway overhead) - 1" brass ball valve brazed union connection
01-136-01 (cleaning gear locker overhead) - Crop out existing 1 1/4 gate type valve ....install new 1 1/4 brass ball valves brazed union connection
01-66-00 (Linen Locker overhead) - 2" 150# flanged brass ball valve
01-72-02 (passageway overhead ) - 2" 150# flanged brass ball valve
01-57-02 (passageway overhead ) - 2" 150# flanged brass ball valve
02-137 -01 (cleaing gear locker) - crop out existing 1 1/4" gate valves ....install new 1 1/4 brass ball valves brazed union connections.
02-110-01 (passageway) - 1 1/2 " ball valve brazed union connection
02-77-02 (passageway) - crop out existing gate valve and replace with new 1 1/2" brass ball valve brazed union connection.
03-119-02 ( passageway overhead ) - 1 1/2" brass ball valve brazed union connection
03-119-01 ( passageway overhead ) - 1- 1/4" brass ball valve brazed union connection
03-53-02 proposed space to install hydro tank on piping run
TBD – 4 Each Master shutoff valves (2 each in forward house and 2 each in after house) These are to supplement the individual area shutoff valves but are to be placed in the main supply lines feeding the forward and after houses
DELIVERABLES
Manufacturers bulletins for valves supplied by the contactor with supplier and spare parts information
ADDITIONAL WORK AND SUPPLEMENTARY
Contractor to submit a written Condition Found report (CFR) to the COTR for any additional work outside the contract. Approval for additional work must be approved by either the COTR ($5000 or less) or the Contracting Officer (over $5000)
Contractor to provide cost breakdowns as they relate to labor, material, subcontractors and travel costs, if applicable. Supplementary costs must be approved by COTR by written CFR, RFQ, Quotation and Delivery Order process.
Item No 3 – SR No 5189812 – Forward MSD Vent Reroute
SR No 5189812 Forward MSD Vent
ABSTRACT
Contractor to furnish all labor, materials, transportation and rigging to modify the Forward Sewage Device (MSD) 8 inch Vent to the that MSD. This modification is necessary to prevent accumulation of condensate and liquids that cause the vent to block flow of the gases from the MSD.
REFERENCE
Blueprints in the Ship’s Library
LOCATION AND DESCRIPTION
Location:
Gymnasium Room – Forward MSD Room Stbd outboard side – Fr 75
Description:
Modify the 8 inch MSD vent to the Fwd MSD to prevent the accumulation of condensation at ell
STATEMENT OF WORK
Contractor is responsible for all labor, material, transportation and rigging to modify the 8 inch MSD vent located on the starboard side of the gymnasium to the MSD.
Contractor to install approximately 50 feet of 8 inch Sch80 pipe with flanged connections from the vertical run of the 8 inch vent for the MSD. All piping to be routed as must as possible in the drop ceiling and to be fittted thru any interferences as necessary to route the piping with at least 2 foot drop between the vertical run and the connection to the MSD drop line penetration. Vent is to not have any long runs of horizontal piping without some amount of pitch
Contractor is responsible for doing a ship check to determine exact measurements as this statement of work is only an estimate of dimensions or interferences.
Contractor is responsible for removing and reinstallation of all interferences necessary to fit the 8 inch vent to the drop line to the MSD. Any sheetmetal will be refitted to shape around the pipe using the same materials.
Contractor is responsible for repainting all disturbed interferences and also the piping itself to match the color of the surrounding area. Painting shall include at a minimum one coat of primer and two coats of top coat using Chief Mates color and paint scheme.
Contractor is responsible for getting a hotwork permit from the Chief Mate and to make sure that the fire alarm system is turned off during all times that there is hotwork being done.
Contractor to provide the services of an ABS approved welder and those certificates must be available during solicitation and any time during the course of the job when they are requested by COR, Chief Engineer or ABS or other regulatory personnel.
Contractor to fit up the pipe penetrations in the 8 inch vent line and the MSD drop line so that the pipe is flush with the ID of the pipe and does not protrude beyond the inside wall of the vent pipe or MSD drop line.
Contractor to fit all flange connections with both an inside and outside pass using good engineering practice and ABS guidelines for the applicable piping installation.
DELIVERABLES
Supply Chief Engineer with receipts of the pipe and fittings for use to prove to ABS that the piping and fittings meet their requirements.
Item No 4 – SR No 5186731 – Boiler Room Gray Water Piping
SR No 5186731 Boiler Room Graywater piping
ABSTRACT
Contractor to supply all labor, material, transportation, rigging and staging to change the graywater piping for the Boiler Water Test Station and Deck Drains
REFERENCE
Blueprints in the Ship’s Library
LOCATION AND DESCRIPTION
Location:
02 and 03 Levels on After house. Frames 129 to 133
Description:
Existing pipe work for drains connect to boiler water test station and deck drains have severe interior corrosion. Drain piping is located in the overhead ceiling space located near and at 03-133-01.
• Approximately 25 feet of seamless schedule 80 2"steel pipe must be cropped out and renewed.
• Contractor shall identify correct run with help of ship’s crew.
• Contractor shall remove all interferences, paneling and wiring.
• Contractor is responsible for all protection of living quarters and state room furniture and fixtures.
• Crop out and remove section of pipe from deck drain penetration to section of same pipe run going down to 02 level. (03-133-01 to 03-129-01)
• Crop out and remove section of pipe from sink drain penetration to run of pipe also being removed. (03-130-01)
• Crop out and remove section of pipe from deck drain penetration to run of pipe going down to 02 deck (03-129-01)
• Contractor shall fabricate new sections of pipework similar to piping removed 2" schedule 80 seamless steel pipe . All fittings and couplings being schedule 80
• All fittings shall be welded. There shall be no interior interferences from fabrication or welding work.
• Contractor shall use all existing pipe hangers if possible. Painting and insulation of pipe work shall be exactly as sections removed and replaced. All fastening hardware shall be same size and new.
• Contractor shall reinstall all items removed. Contractor shall remove all protection. Contractor shall clean all debris and dirt made by repair work.
• Connections at the drop line to refit as follows:
1. Flange the top of the drop line and add a tee
2. Pipe to each side of the tee with pee traps
3. Run new pipe to these connections
4. Remove the other piping and pee traps as needed
• Deck drains to be changed to allow debris to be collected in the drain and be cleaned rather than draining directly into the drain pipe and blocking same
• Add deck drain in location where water collects and no deck drain exists
• Connect new deck drain fittings to drain pipe with supports as needed
STATEMENT OF WORK
Prior to commencing work, contractor shall conduct a joint inspection with the Owners Representative and Contractor's representative to verify that proper protection of all areas of the vessel where work will be done.
Contractor is responsible for all labor, material, transportation, staging and rigging to access piping in the overhead near 03-133-01
Contractor to open all overhead panels and remove any interferences and return same as found.
Contractor is responsible for ship check to determine actual piping configuration and necessary staging, lighting, ventilation and length of piping and any other considerations necessary to complete the work. Any information included in this statement of work is an estimate and may not completely describe the needs of the job.
Contractor to provide all necessary blowers and ducting to ventilate this area as Cadets are housed in adjacent areas. Ventilation to be maintained to evacuate any hotwork fumes generated from the removal and installation of new graywater piping.
Contractor to provide a chemist to get hotwork permit and to maintain same during the duration of the job.
Contractor to use Sch 80 piping with 150# rated flanges with welded connections both outside and inside the flange. Welding to be done by an ABS certified welder.
Certificates to be made available at time of solicitation and anytime they are demanded by regulatory or COR or Chief Engineer.
Contractor to be prepared to test the final assembly to a minimum of 60psi or pressure that is required by ABS. Tests to be witnessed by COR and/or Chief Engineer and attending ABS surveyor.
Contractor to use Stainless Steel 316 fasteners and new Non-Asbestos gaskets when making up new piping flanges.
Upon completion of all work to the satisfaction of the COR and Chief Mate or Chief Engineer, remove all equipment and materials, close up overhead panels and reinstall interferences that were removed for access
Contractor shall dispose of all grit, scale, and waste generated in the course pipe renewal operations in accordance with Federal, State, and local regulations as applicable.
DELIVERABLES
Contractor to supply receipts for materials showing that they are of proper type and ABS approved
Supply photos of final job in all tanks for future reference of graywater piping in closed ballast tank(s)
Item No 5 – SR No 5186727 – Heating 35# Steam Isolation Valves
SR No 5186727 – 35psi Heating Steam Isolation and Drains
ABSTRACT
Existing isolation valves for State Room heating steam and drain points are in areas that are not accessible. In some spaces, heating steam cannot be secured to heaters.
Contractor to supply and install isolation valves and drains in designated areas.
REFERENCES
Ship’s Blue prints
LOCATION / DESCRIPTION
Location:
Throughout the Ship
Description:
Refer to the Statement of Work for locations to renew or install isolation and drain valves
GOVERNMENT FURNISHED EQUIPMENT / MATERIAL / SERVICES
None
STATEMENT OF WORK
Target areas are approximate. Actual installation of any one valve may be moved a bit for easier access. If in doubt get First Assistant Engineer approval
1) 01-99-01 ( med store room/office overhead ) 1-1/4" x 150# flanged gate valve
2) 01-99-02 ( port side door/ passage way overhead, outside of CG locker) 1" x 150# flanged gate valve
3) 01-55-01 ( stbd side fwd house psgwy overhead/Outside of door ) 1-1/4" x 150# flanged gate valve
4) 01-55-02 ( port side fwd house psgwy overhead ) Valve size to be confirmed
5) 03-98-01 (stbd side aft house psgwy overhead at door ) 3/4" x 150# flanged gate valve
6) 03-98-02 ( port side aft house psgwy overhead at closet ) 1-1/4” x 150# flanged gate valve
Job includes all new valves and installation of same including any interference removal and refitting of pipe
Contractor to prove final assembly using 1.5 times the system pressure
DELIVERABLES
Marked up blueprint showing actual location(s) of new valves either the COTR ($5000 or less) or the Contracting Officer (over $5000)
Contractor to provide cost breakdowns as they relate to labor, material, subcontractors
Item No 6 – SR No 0302097 – Clean 3 Pee Traps & 6 Grease Traps
SR No 0302097 Clean Three (3) MSD Pee Traps & Six (6) Grease Traps
ABSTRACT
Contractor to open and clean all three (3) of the 8 inch Pee Traps mounted in line on the 8 inch blackwater lines to the Marine Sewage Devices. Disassembly and reassembly, disposal of collected debris and new gaskets and cleaned up fasteners plus all labor, materials and transportation and rigging are included.
Contractor to open and clean the Six (6) Grease Traps in the Galley area and dispose of all debris and cleaning materials properly
REFERENCES
Blueprints in ship’s library
LOCATION AND DESCRIPTION
Location:
One (1) Pee trap in the Forward MSD Room (Gymnasium)
Two (2) Pee traps in the AMD space just forward of the Shaft Alley
Six (6) Grease Traps in the Galley area
Description:
Contractor to coordinate with Chief Engineer 24 hours in advance to secure the sewage system and then isolate the line to be opened. Contractor to protect all adjacent equipment and cover catwalks and openings into the bilge spaces to prevent sewage from spilling onto or into same. Open and clean out debris, then reassemble and close up with new gaskets.
Contractor to coordinate with the Chief Engineer 24 hours in advance to secure the Galley to allow all the Grease Traps to be opened and cleaned and inspected.
STATEMENT OF WORK
MSD Pee Traps
Contractor to provide all labor, materials, transportation and rigging and disposal services to perform the work describe under this item.
Contractor is responsible for ship checking and verifying dimensions prior to bid submission and notice to proceed.
Contractor shall reattach all existing pipe hangers and add new pipe hangers where good engineering practice warrants. After completion of work, contractor shall reinstall any and all interferences and shall install new and repair, renew or replace any removed, damaged or missing pipe insulation in way of installation.
Contractor will be responsible for all repaired or renewed piping to be leak checked at working pressure by COTR or First Engineer
All piping shall be painted to match vessel’s existing paint scheme using a minimum of one (1) coat of primer and two (2) coats of paint. Color and type of paint to be approved by Chief Mate
Contractor is responsible for all necessary costs for protecting the area being worked in, collecting and disposing of any collected sewage, and clean-up of the area once the repairs are completed.
Contractor is responsible for all Personal Protective Equipment, Tape and plastic or tarps to cover adjacent equipment to the Pee Traps and bilge openings and other necessary protection for opening the sewage lines in the lower engine room.
Contractor to arrange with Chief Engineer to isolate any particular section of the blackwater piping to be renewed at least 24 hours in advance. This is absolutely necessary to insure that the area being worked on can be isolated.
Grease Traps
Contractor to coordinate the cleaning of the Galley Grease Traps with the Chief Engineer. This job must take into account that all cleaning and solutions and must agree with the operation of the Marine Safety Device (MSD) which the Grease Traps and Gray Water drains to. All cleaning solutions must be approved by the Chief Engineer. Best solutions are Hot Water and Cleaning solutions that are approved by the MSD Manufacturer.
Contractor to open the top of the Grease Trap (6 each) and photo the “as-found” condition and have Chief Engineer and/or COR inspect same
Contractor to use shop vacuums and receptacles to capture and contain the grease that is found in the grease traps. All the grease found in the individual grease traps must be removed and then Hot Water is to be used to prove flow thru each trap and be witnessed by the Chief Engineer
If the Contractor elects to use a professional subcontractor to pump out the Grease Traps, the proper paperwork must be produced for pumping materials over the water and proper protections must be taken to make sure there is spill protection and scuppers are plugged
Contractor to supply and install new gaskets if the ones removed are found to be marked or cut or hard and no longer reliable for sealing the traps. Fasteners to be cleaned up and lubricated with thread lubricant or new fasteners to be inserted at close up
DELIVERABLES
Photos and any notes of problems encountered during the cleaning of the Pee traps.
Information to be used for annual cleaning guides for the same job
Item No 7 – In House Piping Repairs
SR No 0302132 – In House Piping Repairs
The following repairs are to be done under the guidelines of the Terms and Conditions for Hotwork and coordination with the crew for isolating and shutting down systems for access to the repairs. All repairs will require the contractor to remove overhead panels and possibly other interference removal so contractor needs to take notice of access and other equipment or covering that needs to be removed and then reinstalled
A hotwork permit is required each day and post hotwork fire watch is needed to insure that no latent heat or smoldering debris starts a fire after contractor has left either the COTR ($5000 or less) or the Contracting Officer (over $5000)
Contractor to provide cost breakdowns as they relate to labor, material, subcontractors
Item No 8 – Supplementary Labor
50hrs @ $_____/Hr = $_________
Item No 9 – Supplementary Materials
$10,000