Q&A_1-17-2019.pdf

PDF 62 KB Posted

Attached to
WA NPS OLYM 207(1), Rehabilitate Staircase Road
Solicitation number
DTFH7017B00039
Issued by

View the file

Other files

File Type Posted
BidSum__Staircase_Rd.pdf PDF
A002.pdf PDF
Q&A_1-15-2019.pdf PDF
Q&A_1-11-2019.pdf PDF
A001.pdf PDF
Plan_Request_for_Staircase_Road.pdf PDF
GM_04-18_Rehabilitate_Staircase_Road_WA_NPS_207(1).pdf PDF
Plan_Sheets.pdf PDF
SWPPP_WA_NPS_OLYM_207(1)_reduced.pdf PDF
IFB_Rehabilitate_Staircase_Road.pdf PDF
Preliminary-Letter_pre-ad.pdf PDF
Preliminary-Letter_pre-ad.pdf PDF
Plan_StairCase_Road_Preliminary.pdf PDF
PROJECT_DESCRIPTION.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. WA NPS OLYM 207(1), Project: Rehabilitate Staircase Road

# General Technical Question Answer Date

1 x With the Government shut down‐ is the road and project site open or is it behind a locked gate? Will bid be extended due to shutdown?

Bid opening will not be extended. Site is open.

1/7/19

2 x

Are the slopes that get the rolled erosion products getting hydroseeded also? I did not see this in the plans but assume they do not want them left as bare dirt?

No. Revegetation will be provided by others.

1/15/19

3 x

Why are there so many bid items doubled up with the exact same item description but slightly different quantities within each of the 4 bid schedules? Example, what is the difference between bid items B0140 and B0160, or between B0180 and B0200, or between B0460 and B0500? If they item description is exactly the same, shouldn’t the bid items be condensed down and quantities adjusted?

Bid according to the quantities shown in the bid schedules. 1/17/19