BidSum__Staircase_Rd.pdf PDF
Q&A_1-17-2019.pdf PDF
A002.pdf PDF
Q&A_1-15-2019.pdf PDF
Q&A_1-11-2019.pdf PDF
A001.pdf PDF
Plan_Request_for_Staircase_Road.pdf PDF
GM_04-18_Rehabilitate_Staircase_Road_WA_NPS_207(1).pdf PDF
Plan_Sheets.pdf PDF
SWPPP_WA_NPS_OLYM_207(1)_reduced.pdf PDF
IFB_Rehabilitate_Staircase_Road.pdf PDF
Preliminary-Letter_pre-ad.pdf PDF
Preliminary-Letter_pre-ad.pdf PDF
Plan_StairCase_Road_Preliminary.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WA NPS OLYM 207(1), Rehabilitate Staircase Road, Olympic National Park, Jefferson County, Washington

The work consists of Utility trenches, paving, minor drainage, retaining wall, geogrid reinforcement, microsurfacing and other small items of work.

Project length: 1.5 Miles

Tentative Fixed Completion Date: Summer 2018 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)

Estimated Price Range: $1 million to $2 million

Location: 25 Miles NW of Hoodsport, Washington

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-14

On e S ch ed ul e

Sc h

Na m e

DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes 153 Contractor Quality Control and Assurance

(yes/no) Yes 154 Contractor Sampling & Testing (yes/no) Yes 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes 157 Soil Erosion & Sediment Control Silt Fence Fiber Roll

158 Watering for Dust Control ALL

DIVISION 200 – Earthwork 201 Clearing & Grubbing 265 SY 202 Removal of Idividual Tree 10 EA 203 Removal of Sign 7 EA 204 Roadway Excavation Subexcavation Select Borrow

50 CY

3228 CY

5382 T

207 Geogrid Stabilization 9256 SY

DIVISION 250 – Slope Reinforcement and Retaining Walls 251 Riprap 6 CY 253 Gabions 650 SF

On e S ch ed ul e

Sc h

Na m e

DIVISION 300 – Aggregate and Base Courses 302 Roadway Aggregate Method 2 Ditch Reconditioning

1448 CY

750 LF

303 Aggregate Surface Reconditioning 4057 SY

DIVISION 400 – Asphalt Pavements & Surface Treatments 401 Antistrip additive, Type 3 20 T 403 Asphalt Concrete Pavement 2629 T 409 Micro Surfacing 8144 SY 412 Asphalt Tack Coat (asphalt surface treatment) 11 T 414 Asphalt Pavement Crack Sealing & Filling 0.9 Mile

DIVISION 600 – Incidental Construction 602 Culverts 535 LF 629 Rolled Erosion Control Products 70 SY 633 Sign System 120 SF 634 Permanent Pavement Markings 25,000 LF 635 Temporary Traffic Control Barricade Type 3 Tubular marker, 42” Drum Warning light Construction Sign Pilot Car

10 EA

255 EA

30 EA

6 EA

246 SF

120 Hour

636 Conduit, 2-inch PVC Utility Box, Concrete Utility Trench

15,495 LF

7 EA

5165 LF

DIVISION 200 – Earthwork
DIVISION 250 – Slope Reinforcement and Retaining Walls
DIVISION 300 – Aggregate and Base Courses