Western Federal Lands Highway Division 610 E. Fifth Street
Vancouver, WA 98661 Phone 360-619-7700
Fax 360-619-7846
NOTICE TO PROSPECTIVE BIDDERS
RE: WA FS ERFO 2016(1)-20(3)
Darrington District Emergency Repairs, Phase I Solicitation No. DTFH7017B00033
The attached preliminary plans are being furnished to aid prospective Bidders in identifying the location and type of work for this project. The project will be advertised during a period when viewing of the project may not be possible due to snow. Therefore, prospective Offerors are encouraged to view the project during fall as conditions permit. After October 20, 2017, access will be weather dependent; contact the Mt. Baker-Snoqualmie National Forest for current road conditions and key for gate at Darrington District Office, James Mitchell, Road Manager, 360- 854-2620, jbmitchell@fs.fed.us. No Federal Highway Administration personnel will be available for show-me tours.
Project Location and Type of Work - All project works are in the Darrington District, Mt Baker-Snoqualmie National Forest, Skagit and Snohomish Counties, Washington.
• 2000-MP 39.9 – Work consists of removal of debris, grading, clean culvert, install new culvert, base, aggregate surfacing
• 2081-MP 1.3 – Work consists of removal of debris, grading, install new culvert, aggregate surfacing, and turf establishment
• 2081-MP 2.25 – Work consists of embankment, grading, aggregate surfacing, remove and reset culvert, and revegetation.
• 2083-MP 0.1 – Work consists of removal of debris, grading, install new culverts, aggregate surfacing, riprap, and turf establishment
• 2660-MP 4.1 – Work consists of removal of debris, embankment, MSE wall, riprap, clean culverts and install new culvert, grading, aggregate surfacing, turf establishment, and temporary diversion channel.
• 2660-MP 4.2 - Work consists of structural excavation, riprap, aggregate surfacing, and object markers
• 2700-MP 6.9 – Work consists of clearing, excavation, roadway reconditioning, aggregate surfacing, MSE wall, install new culvert, and wall drain.
• 2800-MP 5.3 – Work consists of clearing, structural excavation and embankment, install AOP culvert, riprap, aggregate surfacing, riprap, and turf establishment.
• 2800-MP 10.3-10.4 – Work consists of excavation and embankment, riprap, install new culvert, base, aggregate surfacing, and turf establishment.
• 2800-MP 11.0 – Work consists of excavation and embankment, grading, aggregate surfacing, install new culvert, riprap, and turf establishment.
September 1, 2017 mailto:jbmitchell@fs.fed.us
Preliminary Plans letter
• 2810-MP 2.3 – Work consists of excavation, base, asphalt concrete pavement, and rock embankment.
• 4052-MP 1.9 – Work consists of debri excavation, riprap, roadway reconditioning, aggregate surfacing, and clean culvert.
• 4052-MP 2.2 – Work consists of clearing, debri excavation, removal culvert, install new culvert, riprap, grading, and aggregate surfacing.
• 4052-MP 2.55 – Work consists of debri excavation, riprap, repair concrete ford outlet, grading, roadway reconditioning, install new culvert, and turf establishment.
• 4052-MP 3.0 – Work consists of excavation, removal of stream debris, place riprap, install new culvert, ditch reconditioning, and clean drainage structure.
• 4052-MP 3.7 – Work consists of clearing, grading, aggregate surfacing, special rock embankment, drainage, and turf establishment.
Technical Questions – All technical questions must be submitted by email plans-spec@dot.gov or FAX 360-619-7932
General Questions - Contact our office at wfl.contracts@dot.gov or at 360-619-7520.
Solicitation documents - Documents will be available during the winter of 2017/2018. Please monitor the FedBizOpps (FBO) site for actual date of solicitation release (www.fbo.gov). To receive automatic notification through FBO, select the “Watch this opportunity” feature and follow the steps as indicated.
Thank you for your interest in this project.
mailto:plans-spec@dot.gov mailto:wfl.contracts@dot.gov http://www.fbo.gov/
RE: WA FS ERFO 2016(1)-20(3)
File details come from the government source that posted it. Updated .