AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A002 05/18/2018 N/A See box 14
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X DTFH7017B00033
9B. DATED (SEE ITEM 11)
04/19/2018
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
N/A
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
N/A D OTHER (Specify type of modification and authority)
N/A E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
WA FS ERFO 2016(1)-20(3), Darrington District Emergency Repairs, Phase I
This amendment revises the following physical data:
FSR 2081 MP 2.25
FSR 2083 MP 0.1
See page 2
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A002, dated 05/18/2018 Project No. WA ERFO 2016(1)-20(3) Solicitation No. DTFH7017B00033 Darrington District Emergency Repairs, Phase I
REVISIONS ARE AS FOLLOWS:
CONTRACT CLAUSES
Page C-79:
Adds FSR 2081 MP 2.25 (A002) and FSR 2083 MP 0.1 (A002) to FAR Clause 52.236-4, Physical Data (Apr 1984).
Deletes FSR 2081 MP 2.25 and FSR 2083 MP 0.1 to FAR Clause 52.236-4, Physical Data (Apr 1984).
ENCLOSURES
Pages:
C-79
Physical Data:
FSR 2081 MP 2.25 (A002).pdf FSR 2083 MP 0.1 (A002).pdf
ATTACHMENTS:
C-79 and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
(b) The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.
52.236-4 Physical Data (Apr 1984)
Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by: N/A..
(b) Weather conditions: N/A.
(c) Transportation facilities: N/A.
(d) Hydrological data consisting of flow rates, water surface elevations, velocities, and hydraulic permit information may be inspected at Western Federal Lands Highway Division, Contracts Section, 610 East Fifth Street, Vancouver, Washington 98661.
(e) Geotechnical data, design data, and environmental information consisting of the following, will be posted with the solicitation.
(1) FSR 2081 MP 1.3
(2) FSR 2081 MP 2.25 (2) FSR 2081 MP 2.25 (A002)
(3) FSR 2083 MP 0.1 (3) FSR 2083 MP 0.1 (A002)
(4) FSR 2660 MP 4.1
(5) FSR 2700 MP 6.9 Earthwork Site 3
(6) FSR 2700 MP 6.9
(7) FSR 2800 MP 5.3 Earthwork
(8) FSR 2800 MP 5.3
(9) FSR 4052 MP 1.9 Earthwork
(10) FSR 4052 MP 2.2 Earthwork
(11) FSR 4052 MP 2.2
(12) FSR 4052 MP 2.55 Earthwork
(13) FSR 4052 MP 2.55
(14) FSR 4052 MP 3.0 Earthwork
(15) FSR 4065 MP 1.15
(16) FSR_2800_MP_5-3_Dar_AOP_Hydraulics_Memo_Combined-1
(17) GM34-17 Darrington Emergency Repairs 2016, PH-1 Geotechnical Recommendations
(18) SWPPP-WA FS ERFO 2016(1)-20(3) Darrington District Phase 1
(19) wa-fserfo2016012003_HydReport_20170719
52.236-5 Material and Workmanship (Apr 1984)
(a) All equipment, material, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract. References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may, at its option, use any equipment, material, article, Contract Clauses WA FS ERFO 2016(1)-20(3), Darrington District Emergency Repairs, Phase I
Revised by Amendment A002