WESTERN FEDERAL LANDS HIGHWAY DIVISION
DETAIL APPROVED FOR USE 11/2001
REVISED: 9/2005 1/2007 10/2009 10/2014
W101-1
AND ABBREVIATIONS
PLAN SYMBOLS
W west drwg(s).
dist.
diaph.
diag.
dia.
DHV
D exp. jt.
exc.
EW
ER
EQ or eq.
EP
emb.
elev.
El. 94.16 ft e
E expansion joint excavation edge of water edge of road equation edge of pavement embankment elevation elevation with number superelevation rate east drawing(s) distance diaphragm diagonal diameter design hourly volume diameter galv.
ga.
galvanized gage (gauge)
HW
hex.
hdwl.
high water hexagon headwall ftg.
ft3 ft2 flg.
fin.
footing cubic foot (feet) square foot flange finish jt.
ID
joint inside diameter
LW
lt. or LT
Ls
LPSM
long.
LNFT
lat.
lam.
L low water left length of spiral lump sum longitudinal linear foot (feet) latitude lamination length of curve
NC
N normal crown north
OG
OD
o. to o.
o. c.
original ground outside diameter out to out on center pvmt.
PT
PST
PSC
PS
POT
POS
POC
pl.
PI
PCS
PCC
PC
pavement point of tangent point of spiral to tangent point of spiral to curve point of tangent to spiral point on tangent point on spiral point on curve plate point of intersection point of curve to spiral point of compound curve point of curve rte.
rt. or RT reqd.
reinf.
rdwy.
R/W
R.
R route right required reinforcement roadway right-of-way range radius typ.
Ts
TS
thd.
TBM
T.
T typical tangent distance (spiraled curve) point of tangent to spiral thread temporary bench mark township tangent distance
VPI
vph
V vertical point of intersection vehicles per hour design speed yd3 yd2 cubic yard(s) square yard sym.
STS
struc.
stiff.
stgr.
std.
STA, Sta.
ST
SS
SRS
SQYD
SQFT
spa.
SLRY
shldr.
sec.
SC
SADT
S symmetrical point of spiral to tangent spiral structural stiffener stringer standard station point of spiral to tangent point of spiral to spiral (no curve) point of spiral to reverse spiral square yard square foot spacing, spaces or spaced slurry unit shoulder section point of spiral to curve seasonal average daily traffic south
CUYD
culv.
CUFT
cubic yard(s) culvert cubic foot (feet) mon.
min.
MGAL
max.
matl.
monument minimum thousand gallon maximum material A
M p r il c m y fi le s p w p r o d u c ti o n d w a e f2 a b .d g n
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
DETAIL
U.S. CUSTOMARY DETAIL
STATE PROJECT
NUMBER
SHEET
A.2 WA FS ERFO 2016(1)-22(1)WA
BH
CP GPS
JH
TP
DI
36 31
6 1
36 31
6 1
SEC.
SEC.
EL. 1234.56
N
E
RIP
G G
W W
DI
T T
NOTE:
NO SCALE
on the appropriate plan sheet.
Other symbols used in the plans will be shown in a legend 1.
Property Line w/Found Property Corner
Section Corner (Found, Projected)16
Section Line16
Section Corner (Found, Projected)4
Section Line4
Parcel Number
National Park Boundary
National Forest Boundary
National Wildlife Refuge Boundary
Trail
Lake, Pond or Reservoir; Marshland
Spring or Seep
Material Source; Bore Hole; Test Pit
Section Line
Indian Reservation Boundary
Existing Roadway (Road, Paved, Gravel)
Section Corner (Found, Projected)
Large Creek or River
Spot Elevation; Coordinate Grid Tick
Above Ground Tank; Underground Tank
Treeline; Individual Trees
Boulder; Well; Satellite Dish; Grave
Cooking Grate; Garbage Can; Picnic Table
Flagpole; Fire Hydrant
Gas & Water Meter; Gas & Water Valve
Silt Fence
National Boundary
State Boundary
County Boundary
City Boundary
Township or Range Line
BLM Lands Boundary
Railroad
Intermittent Drainage or Small Creek
Control Point (Terrestrial and GPS); Jump Hub θs Ø
∆c spiral central angle diameter curve central angle total central angle approach ahead average daily traffic abutment appr.
AH
ADT
abut.
bearing bridge balance point bench mark back brg.
br.
BP
BM
BK
ctrs.
CS
cont.
constr. jt.
conn.
conc.
col.
CMP
clr.
cc or c. to c.
centers point of curve to spiral continuous construction joint connection concrete column corrugated metal pipe clear centerline center to center mile post main line
M.P.
M.L.
STEAM = steam, T = telephone, TV = CATV, W = water
P = power, SA = sanitary sewer, SD = storm drain, SS = storm sewer, FM = force main, FO = fiber optic, G = gas, IRR = irrigation, O = oil, UP = transformer or junction box, WF = water fountain
EM = electric meter, T = telephone pedestal, TV = CATV pedestal, Light, Support w/Anchor)
Poles (Power, Telephone, Joint Use,
- no symbol -
EXISTING PROPOSED
Transition
Toe of Fill
Top of Cut wall face
CL
North Arrow
Fence
Gate with Fence
Cattleguard
Guardrail
Retaining Wall
Pipe Culvert (arrow shows flow)
Pipe Culvert with End Section
Pipe Culvert with Headwall
Underdrain
Concrete Barrier
Slope Stake Limits
Pipe Culvert with Drop Inlet
Box Culvert
Delineators
Underground Utilities
Overhead/Above Ground Utilities
Signs (single, double post; portable)
Miscellaneous Utility Features
Building
Right-of-Way Line with Monument
Permanent Easement
Construction Easement
Riprap
Fiber Roll or Wattle
20100510
SCALE IN MILES
FR 23-MP 12.6
SITE #1 FR 23- MP 18.0
SITE #2
FR 2322- MP 0.2
SITE #7
SITE # 5 FR 23- MP 23.6
SITE #8 FR 23- MP 23.5
SITE #4 FR 23-MP 23.4
SITE #3 FR 23- MP 22.3
FR 2324- MP 0.1
SITE #6
Mi lesTo
M or to n
M ile s
T o P a ck w o o d
VICINITY MAP
A.3
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 a c .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
B
H u s c h k a
M c I n to s h
C h e c k e d b y
D e s ig n e d b y
M il e s
T o W h it e S a lm o n
Sheet and Description
Section C Section D Section E Section F Section G Section H Section I Section J Section K Section L Section M
Site 1 23-12.6
Site 2 23-18.0
Site 3 23-22.3
Site 4 23-23.4
Site 5 23-23.6
Site 6 2324-0.1
Site 7 2322-0.2
Site 8 23-23.5 Drainage
Temporary Traffic Control
Miscellaneous ALLOWANCE Bid Schedule
A0020 15101-0000 MOBILIZATION LPSM ALL
A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING LPSM ALL
A0060 15301-0000 CONTRACTOR QUALITY CONTROL LPSM ALL
A0080 15401-0000 CONTRACTOR TESTING LPSM ALL
A0100 15501-0000 CONSTRUCTION SCHEDULE LPSM ALL
A0120 15705-0100 SOIL EROSION CONTROL, SILT FENCE LNFT 330 330
A0140 15705-1400 SOIL EROSION CONTROL, FIBER ROLL LNFT 446 70 120 140 300 140 140 90 194 1,640
A0160 20101-0000 CLEARING AND GRUBBING ACRE 0.8 0.1 0.2 0.3 0.6 0.1 0.1 0.1 2.4
A0180 20301-1900 REMOVAL OF PIPE CULVERT EACH 2 1 2 1 6
A0200 20302-1200 REMOVAL OF GUARDRAIL LNFT 50 50
A0220 20315-0000 SAWCUTTING PAVEMENT LNFT 48 44 36 36 36 36 20 18 274
A0240 20401-0000 ROADWAY EXCAVATION CUYD 145 453 472 284 29 182 128 91 1,784
A0260 20401-0000 ROADWAY EXCAVATION (Channel excavation) CUYD 333 33 896 33 1,295
A0280 20401-0000 ROADWAY EXCAVATION (Unsuitable excavation, debris) CUYD 1,111 106 523 151 189 2,080
A0300 20403-0000 UNCLASSIFIED BORROW CUYD 2,537 795 399 136 2,393 148 235 122 935 7,700
A0320 20435-1000 BACKFILL, SELECT GRANULAR
(Structural Backfill, bedding material) CUYD 531 460 991
A0340 20702-0100 GEOTEXTILE FILTER, CLASS 1, TYPE A SQYD 2,716 36 73 100 408 111 60 626 4,130
A0360 25101-0300 PLACED RIPRAP, METHOD A, CLASS 3 CUYD 35 73 37 83 22 250
A0380 25101-0400 PLACED RIPRAP, METHOD A, CLASS 4 CUYD 60 10 70
A0400 25101-0500 PLACED RIPRAP, METHOD A, CLASS 5 CUYD 637 916 29 228 1,810
A0420 25101-0700 PLACED RIPRAP, METHOD A, CLASS 7 CUYD 4,782 958 5,740
A0440 30201-1000 ROADWAY AGGREGATE, METHOD 1 CUYD 246 43 61 59 145 41 26 17 92 730
A0460 40301-0000 ASPHALT CONCRETE PAVEMENT (Type 1) TON 165 20 32 40 101 30 18 12 62 480
A0480 55201-1200 STRUCTURAL CONCRETE, CLASS S (SEAL) CUYD 42 17 59
A0500 57501-0000 MINOR BRIDGE WORK(Site 7) LPSM ALL ALL A0520 57501-0000 MINOR BRIDGE WORK(Site 8) LPSM ALL ALL
A0540 60201-1500 66-INCH PIPE CULVERT LNFT 74 74
A0560 60201-1600 72-INCH PIPE CULVERT LNFT 68 68
A0580 60220-2550 9 FEET SPAN, 8 FEET RISE PRECAST
REINFORCED CONCRETE BOX CULVERT LNFT 50 49 99
A0600 61601-1000 SLOPE PAVING, CONCRETE SQYD 166 144 310
A0620 61701-0150 GUARDRAIL SYSTEM G2, TYPE 1, CLASS
A STEEL POSTS LNFT 50 50
A0640 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM
CAPACITY HOUR 10 10 10 10 10 10 10 10 80
-A pr -2
1:
P M c:
\m yf ile s\ pw
_p ro du ct io n\ d0
_w a-ef
1_ ba .x ls x]
Sh ee t SUMMARY OF QUANTITIES - Schedule A
A M E N D
Line Item No.
Pay Item Number Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated
Quantity
STATE PROJECT
B.1WA FS ERFO 2016(1)-22(1)WA
NUMBER
Sheet and Description
Section C Section D Section E Section F Section G Section H Section I Section J Section K Section L Section M
Site 1 23-12.6
Site 2 23-18.0
Site 3 23-22.3
Site 4 23-23.4
Site 5 23-23.6
Site 6 2324-0.1
Site 7 2322-0.2
Site 8 23-23.5 Drainage
Temporary Traffic Control
Miscellaneous ALLOWANCE Bid Schedule
A0660 62201-0700 BACKHOE LOADER, 1 CUBIC YARD
MINIMUM CAPACITY FRONTEND BUCKET,
10 CUBIC FOOT MINIMUM CAPACITY
BACKHOE BUCKET, 90 HP MINIMUM
FLYWHEEL HOUR 10 10 10 10 10 10 10 10 80
A0680 62301-0000 GENERAL LABOR HOUR 10 10 10 10 10 10 10 10 80
A0700 62405-0500 PLACING CONSERVED TOPSOIL, 8-INCH
DEPTH SQYD 297 63 360
A0720 62502-0000 TURF ESTABLISHMENT SQYD 934 312 224 1,470
A0740 62601-1070 ALNUS RUBRA, RED ALDER, 18-INCH TO
36-INCH HEIGHT, CONTAINER GROWN EACH 15 9 24
A0760 62601-1100 ACER MACROPHYLLUM, BIG LEAF MAPLE,
1-INCH TO 1 1/2-INCH CALIPER,
BALLED AND BURLAPPED EACH 15 15
A0780 62608-0200 HOLODISCUS DISCOLOR, OCEANSPRAY, 1
GALLON, CONTAINER GROWN EACH 90 90
A0800 62613-0180 MAHONIA AQUIFOLIUM, TALL OREGON
GRAPE, 1 GALLON EACH 110 25 135
A0820 62616-1850 PSEUDOTSUGA MENZIESII, DOUGLAS FIR,
48-INCH TO 60-INCH HEIGHT, BALLED
AND BURLAPPED EACH 15 15
A0840 62630-0400 PLANTINGS, WETLAND PLANT, CONTAINER
GROWN (Vine Maple) EACH 90 25 115
A0860 62630-0400 PLANTINGS, WETLAND PLANT, CONTAINER
GROWN (Baldhip Rose) EACH 110 25 135
A0880 62630-0400 PLANTINGS, WETLAND PLANT, CONTAINER
GROWN (Red Huckleberry) EACH 25 25
A0900 62635-2000 CUTTINGS, WILLOW STAKING EACH 40 40
A0920 63501-0000 TEMPORARY TRAFFIC CONTROL LPSM ALL ALL
A0940 64703-4000 MITIGATION, LOG BARRIER (Engineered log jam) EACH 2 1 3
A0960 64703-5000 MITIGATION, ROOT WAD (Woody debris) EACH 9 9
Estimated Quantities
Remarks and/or Determination of Estimated
Quantity
-A pr -2
1:
P M c:
\m yf ile s\ pw
_p ro du ct io n\ d0
_w a-ef
1_ ba .x ls x]
Sh ee t (2
SUMMARY OF QUANTITIES - Schedule A
A M E N D
Line Item No.
Pay Item Number Pay Item Description Unit
STATE PROJECT
B.2WA FS ERFO 2016(1)-22(1)WA
NUMBER
1:
NO SCALE
Shldr Travel Way Shldr
1:
1.
1:3
Water level
C o n s tr u c ti o n l im it s
C le a r in g l im it s
Placed riprap class 5
2%2%
1:3
Unclassified borrow
20' min.
LC
7' 2'
Existing ground
Existing ground
SITE #1 FR 23, MILEPOST 12.6
Geotextile filter class 1, type A
15'±
Ditch Restoration
C o n s tr u c ti o n l im it s
Turf Establishment
Placed riprap class 7
2.5'
10'channel bottom
2' min. below
:1
:1
LOOKING NORTH
C.1
STATE PROJECT
NUMBER
SHEET
B .B a s e .U
S c m y fi le s p w p r o d u c ti o n d
W o r k d d .c e l
WA FS ERFO 2016(1)-22(1)
M a y
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
TYPICAL SECTION
Turf Establishment
5'
Varies 8' - 12'2'
8" top soil type 1, 3" compacted depth
Asphalt concrete pavement
8" compacted depth method 1, Roadway aggregate, 10'±68'247'67'8'±
382'
Construction
NO SCALE
CISPUS RIVER
PLAN VIEW
GRAVEL BAR
Toe of fill
Edge of water/scarp
Approxim ate see Typical Section Sheet C.1
Reconstruct roadway, NO SCALE
NOTE:
Ditch restoration
Top of cut entering construction area
Prevent stream flow from entering construction area
Prevent stream flow from
Existing channel as directed by the Contracting Officer.
Grape, and Baldhip Rose shrubs at 3-feet on center
2. Co-mingle Vine Maple, Oceanspray, Tall Oregon
Contracting Officer.
Fir trees at 10-feet on center as directed by the
1. Plant Big Leaf Maple, Red Alder, and Douglas access road as follows:
Replant cleared temporary
CONSTRUCTION SEQUENCE
5. Complete road repair per plan.
4. Install erosion control per Sheet C.3.
3. Install engineer log jam.
2. Construct permanent diversion channel.
1. Construct temporary construction access.
CHANNEL DIVERSION
PERMANENT
N
FR 23, MP 12.6
PLAN / SITE #1
(engineered log jam) wood barrier
Install mitigation, isolate work area
Contractor shall
Existing ditch, (typ.)
ditch flowline, (typ.)
Match existing existing pavement
Edge of items.
prior to backfilling channel. This work is incidental to other bid
National Oceanic and Atmospheric Administration procedures, Remove fish per Washington Department of Fish and Wildlife and to fit field conditions.
Site not surveyed. Horizontal alignment is a representation. Adjust
2.
1.
C.2
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 fa .d g n
WA FS ERFO 2016(1)-22(1)
P
A p r il
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
Sawcut (typ.)
see Sheet M.5 for details per location, (typ.)
(woody debris) 3 each, Mitigation, root wad
LC
every 10' along toe of riprap
Install Willow stake cuttings temporary construction access
Clear and grub for 15' wide of restored road embankment place removal materials at base
X 300' long starter channel -
Excavate 15' wide X 2' deep
Adjust to fit field conditions.
Site not surveyed. Horizontal alignment is a representation.
NOTE:
1.
Construction
382'
NO SCALE
CISPUS RIVER
GRAVEL BAR
Toe of fill
FR 23, MP 12.6
SITE #1
Roadway repairs
Work area
Ditch restoration
Top of cut after planting is complete access road at each end
Install silt fence across entering construction area
Prevent stream flow from
CHANNEL DIVERSION
PERMANENT
entering construction area
Prevent stream flow from
Edge of water/scarp
(engineered log jam - 2 each)
Mitigation, wood barrier
Existing channel
Isolated repair work area
Approxim ate
N
PLAN
EROSION CONTROL
C.3
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 d a .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y existing pavement
Edge of
LC
(woody debris) 3 each, (typ.)
Mitigation root wad
Existing ditch (typ.)
temporary access road
15' wide
LEGEND:
Travel Way
1.
5 1:1.5
NO SCALE
Shldr Shldr
2% 2%
22' min.
LC
Existing ground
Existing ground
4' 4'
SITE #2 FR 23, MILEPOST 18.0
24'± 20'± ditch flowline
Match existing ditch flowline
Match existing
Unclassified borrow (typ.)
D.1
STATE PROJECT
NUMBER
SHEET
B .B a s e .U
S c m y fi le s p w p r o d u c ti o n d
W o r k d d .c e l
WA FS ERFO 2016(1)-22(1)
M a y
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
TYPICAL SECTION
LOOKING NORTH
Install 66" pipe culvert type 1, 3" compacted depth
Asphalt concrete pavement
8" compacted depth
Roadway aggregate, method 1, embankment debris, 50' wide X 75'long
Remove woody and washout
NOTE:
Place riprap around pipe inlet and outlet.
Adjust to fit field conditions.
Site not surveyed. Horizontal alignment is a representation.
2.
1.
NO SCALE
N
PLAN VIEW
Top of bank
50' of pavement
Existing edge
Approximate
See Typical Section Sheet D.1
Reconstruct roadway, LCConstr.
washout embankement debris
Remove woody and to match existing (typ.)
Restore gravel shoulder washout embankement debris
Remove woody and
5.5'
5.5'
Scarp (typ.)
FR 23, MP 18.0
PLAN / SITE #2
D.2
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 fb .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
Sawcut (typ.)
Toe of fill, (typ.)
corrugated metal pipe
Remove existing 36"
48" corrugated metal pipe
Remove existing class 1, type A (typ.). See Note 2
3' depth over geotextile filter, Placed riprap class 3, Install 66" pipe culvert
Construction
Site not surveyed. Horizontal alignment is a representation.1.
NO SCALE
N of pavement
Existing edge
Approximate
FR 23, MP 18.0
SITE #2
Toe of slope (typ)
Roadway repairs
50'
Scarp (typ)
D.3
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 d b .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
PLAN
EROSION CONTROL
LEGEND:
Work area
Fiber roll
Construction LC
1.
1:1.5
Shldr Shldr
NO SCALE
2% 2%
Unclassified borrow
Remove boulder debris
Existing ground
LC
Existing ground
2' 2'
SITE #3, FR 23 MILEPOST 22.3
26' 20' 25'
LOOKING SOUTH
E.1
STATE PROJECT
NUMBER
SHEET
B .B a s e .U
S c m y fi le s p w p r o d u c ti o n d
W o r k d d .c e l
WA FS ERFO 2016(1)-22(1)
M a y
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
TYPICAL SECTION
Install 72" pipe culvert
8" compacted depth
Roadway aggregate, method 1, type 1, 3"compacted depth
Asphalt concrete pavement
18' (min.)
Traveled Way
Site not surveyed. Horizontal alignment is a representation.1.
NO SCALE
N
100'±
PLAN VIEW
Existing toe of slope
Existing toe of slope
Regrade channel of pavement
Existing edge
Approximate
Remove boulder debris
See Typical Section Sheet E.1
Reconstruct roadway.
Scarp (typ.)
6' 6'
FR 23, MP 22.3
PLAN / SITE #3
E.2
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 fc .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
Sawcut (typ.)
LC Construction
Top of fill (typ.)
pipe culvert
Remove existing 72" pipe culvert
Install 72" filter class 1, type A (typ.)
3' depth over geotextile
Placed riprap class 3, Place riprap around pipe inlet and outlet.
Adjust to fit field conditions.
Site not surveyed. Horizontal alignment is a representation.
2.
1.
NO SCALE
N
100'± of pavement
Existing edge
(typ)
Top of fill
Approximate
LCConstr.
Existing toe of slope (typ)
FR 23, MP 22.3
SITE #3
Roadway repairs Scarp (typ)
E.3
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 d c .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
PLAN
EROSION CONTROL
LEGEND:
Work area
Fiber roll
NO SCALE
Shldr
1:1.5 1:
18' min.
Shldr
2'2'
Existing ground
LC
SITE #4, FR 23 MILEPOST 23.4
Unclassified borrow
18'10' 5'
Geotextile filter class 1, type A
2% * 2% *
* NOTE: Transition to match top of culvert.
F.1
STATE PROJECT
NUMBER
SHEET
B .B a s e .U
S c m y fi le s p w p r o d u c ti o n d
W o r k d d .c e l
WA FS ERFO 2016(1)-22(1)
M a y
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
TYPICAL SECTION
LOOKING NORTH
embankment washout debris
Remove woody and under asphalt lift (typ.)
Key slope paving box culvert (open box with grate), see Sheet F.2 precast reinforced concrete concrete
Install 9' span, 8' rise
3" depth (typ.)
Slope paving, concrete type 1, 3" compacted depth
Asphalt concrete pavement, 8" compacted depth method 1, Roadwat aggregate, Placed riprap, class 3
Site not surveyed. Horizontal alignment is a representation.1.
NO SCALE
100'
30'
PLAN VIEW
SECTION B-B
SECTION A-A
unyielding condition to dense and
Compact subgrade unyielding condition to dense and
Compact subgrade structural fill
Key-in
108"
18' grate (typ.)
Removable steel
B B
N
1:2 1:1.5
Scarp
Approximate
Structural backfill culvert with grate
Precast concrete open
Reinforced concrete pavement
5 foot centers
Weep hole @ and Section A-A, this sheet
See Typical Section Sheet F.1
Reconstruct roadway.
culvert with grate
Precast concrete open box
LEGEND:
FR 23, MP 23.4
PLAN / SITE #4
F.2
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 fd .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
CULVERT DESIGN NOTE:
existing pavement
Edge of
ConstructionLC
A
A
D12XD12 welded wire fabric (typ.)
3" depth w/12" X 12"
Slope paving, concrete
Sawcut (typ.)
Precast culvert section (typ.)
bedding material
Min 4" compacted bedding material
Min 4" compacted type 1, 3" compacted depth
Asphalt concrete pavement,Removable steel grate (typ.)
corrugated metal pipes
Remove 2 existing 48" culvert (open box with grate) precast reinforced concrete box
Install 9' span, 8' rise
Provide watertight joints between precast segments of box culvert.10.
Welded connections will not be permitted.9.
within bottom slab of culvert.
Provide 3-inch min. clearance to re-bars8.
2.0 KSF (strength limit state)
1.5 KSF (service limit state)
Bearing pressures shall not exceed:7.
Provide a minimum wall thickness of 10-inch and minimum slab thickness of 8-inch.6.
Passive earth pressure coefficient is 3.0.5
Active earth pressure coefficient is 0.33.4.
Unit weight of compacted imported structural fill is 125pcf.3.
Live load surchage 4-feet 0-inch.2.
Design Secifications, 7th edition.
Culvert and grade to be designed in accordance with AASHTO LRFD Bridge1.
Contractor to design precast concrete culvert in accordance with the following:
filter class 1, type A
2' depth over geotextile
Approximate
NOTE:
FR 23, MP 23.4
SITE #4
Toe of fill (typ.)
Reinforced concrete pavement
Work area
Fiber roll
Scarp
PLAN
EROSION CONTROL
Adjust to fit field conditions.
Site not surveyed. Horizontal alignment is a representation. 1.
LEGEND:
culvert (open box with grate) reinforced concrete box
9' span, 8' rise precast existing pavement
Edge of filter class 1, type A
2' depth over geotextile
Placed riprap class 3, ConstructionLC
Roadway repairs
100'
F.3
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 d d .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
1:1.5
Ditch
1:3
Embankment
NO SCALE
Parking
2% 2%
Varies
Unclassified borrow
18' min.
C le a r in g l im it s li m it s
C o n s tr u c ti o n
6' 21'
12'
Existing ground
LC
Existing ground
8'
SITE #5, FR 23 MILEPOST 23.6
LOOKING SOUTH
Planting Area
Turf Establishment
1:
5'
:1
C o n s tr u c ti o n l im it s
:1
5'
G.1
STATE PROJECT
NUMBER
SHEET
B .B a s e .U
S c m y fi le s p w p r o d u c ti o n d
W o r k d d .c e l
WA FS ERFO 2016(1)-22(1)
M a y
H u s c h
T
L
C h e c k e d b y
D e s ig n e d b y
TYPICAL SECTION
channel bottom
2' min. below
Geotextile filter class 1, type A
Placed riprap class 5 type 1, 3" compacted depth
Asphalt concrete pavement
8" compacted depth
Roadway aggregate, method 1, PLAN VIEW
GRAVEL BAR
50' 75' 50' of pavement
Existing edge
Approximate
See Typical Section Sheet G.1
Reconstruct roadway, 255'
LC
Scarp
'Top of cut
Ditch restoration
FR 23, MP 23.6
PLAN/SITE #5
NOTE:
PERMANENT DIVERSION CHANNEL
EAST CANYON CREEK
CONSTRUCTION SEQUENCE
4. Complete road repair per plan.
3. Install erosion control per Sheet G.3.
2. Install engineer log jam.
1. Construct permanent diversion channel.
(engineered log jam) 1 each
Install mitigation wood barrier
G.2
STATE PROJECT
NUMBER
SHEET
B .B a s e .U
S c m y fi le s p w p r o d u c ti o n d
W o r k d d .c e l
WA FS ERFO 2016(1)-22(1)
M a y
H u s c h
C h e c k e d b y
D e s ig n e d b y
1.5' deep channel
Excavate 30' wide by
Sawcut (typ.)
Existing ditch (typ.)
ditch flowline (typ.)
Match existing
3' on center.
Baldhip Rose, and Huckleberry shrubs at
2. Co-mingle Vine Maple, Tall Oregon Grape,
1. Plant Red Alder trees at 10' on center.
Replant 1:3 slope as follows:
Adjust to fit field conditions.
Site not surveyed. Horizontal alignment is a representation.
Construction
GRAVEL BAR
of pavement
Existing edge
Approximate 255'
LC
Toe of fill
FR 23, MP 23.6
SITE #5
Roadway repairs
Ditch restoration
Top of cut
PERMANENT DIVERSION CHANNEL
EAST CANYON CREEK
work area
Isolated repair
1.5 feet deep channel
Excavate 30 feet wide by
Replant 1:3 slope
(engineered log jam) 1 each
Mitigation wood barrier
NOTE:
G.3
STATE PROJECT
NUMBER
SHEET
B .B a s e .U
S c m y fi le s p w p r o d u c ti o n d
W o r k d d .c e l
WA FS ERFO 2016(1)-22(1)
M a y
H u s c h
C h e c k e d b y
D e s ig n e d b y
Adjust to fit field conditions.
Site not surveyed. Horizontal alignment is a representation.
PLAN
EROSION CONTROL
LEGEND:
Work area
Fiber roll
Existing ditch (typ.)
Construction
1:1.5
Shldr Shldr
18' min.
LC
Existing ground
SITE #6, FR 2324 MILEPOST 0.1
LOOKING NORTH
1:
Remove boulder debris
10'
Excavate new channel class 3 (typ.)
Placed riprap
(t y p
* NOTE: Transition to match top of culvert.
2% * 2% *
H.1
STATE PROJECT
NUMBER
SHEET
B .B a s e .U
S c m y fi le s p w p r o d u c ti o n d
W o r k d d .c e l
WA FS ERFO 2016(1)-22(1)
M a y
H u s c h
C h e c k e d b y
D e s ig n e d b y
TYPICAL SECTION
Traveled Way type A (typ.)
Geotextile filter class 1, type 1, 3" compacted depth
Asphalt concrete pavement, 8" compacted depth
Roadway aggregate, method 1, Existing ground box culvert (open box with grate). See Sheet H.2 for details
Install 9' span, 8' rise precast reinforced concrete
2'12' 2' 15'
Site not surveyed. Horizontal alignment is a representation.1.
NO SCALE
PLAN VIEW
Grade new channel
35'± unyielding condition to dense and
Compact subgrade structural fill
Key-in
108"
SECTION B-B
18' grate (typ.)
Removable steel unyielding condition to dense and
Compact subgrade
N
SECTION A-A
1:1.5
30'
Approximate
(Typ.)
Scarp
Structural backfill culvert with grate
Precast concrete open S h ld r ty p
Reinforced concrete pavement and Section A-A, this sheet
See Typical Section Sheet H.1
Reconstruct roadway.
1:
30' 25'± culvert with grate
Precast concrete open box
5'
Placed riprap class 3 class 1, type 4
Geotextile filter
20' 20'
T R
IB
U T
A R
Y
E A S
T C
A N
Y O
N C
R E E
K section (typ.)
Precast culvert
LEGEND:
H.2
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 ff .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
C h e c k e d b y
D e s ig n e d b y
FR 2324, MP 0.1
PLAN / SITE #6
Sawcut (typ.)
filter class 1, type A (typ.)
2' depth over geotextile
Placed riprap class 3, ConstructionLC
48" pipe culvert
Remove existing existing pavement
Edge of culvert (open box with grate) precast reinforced concrete box
Install 9' span, 8' rise
8' wide X 10' deep X 10' long
Excavate new channel
Key under asphalt concrete (typ.)
D12XD12 welded wire fabric.
3" depth w/12" X 12"
Slope paving, concrete
CULVERT DESIGN NOTE:
Contractor to design precast concrete culvert in accordance with the following:
Provide watertight joints between precast segments of box culvert.
Welded connections will not be permitted.
within bottom slab of culvert.
Provide 3-inch min. clearance to re-bars
2.0 KSF (strength limit state)
1.5 KSF (service limit state)
Bearing pressures shall not exceed:
Provide a minimum wall thickness of 10-inch and minimum slab thickness of 8-inch.
Passive earth pressure coefficient is 3.0.
Active earth pressure coefficient is 0.33.
Unit weight of compacted imported structural fill is 125pcf.
Live load surchage 4-feet.
Design Secifications, 7th edition.
Culvert and grade to be designed in accordance with AASHTO LRFD Bridge
10.
9.
8.
7.
6.
5.
4.
3.
2.
1.
concrete 3" depth (typ.)
Slope paving, 5' centers
Weep hole @ bedding material compacted
Min 4" bedding material
Min 4" compacted type 1, 3" compacted depth
Asphalt concrete pavement, Removable steel grate (typ.)
A A
S h ld r ty p
N Approximate
Toe of fill (typ.)
100'
Roadway repairs
FR 2324, MP 0.1
SITE #6
Reinforced concrete pavement
Work area
Fiber roll
NOTE:
PLAN
EROSION CONTROL
Adjust to fit field conditions.
Site not surveyed. Horizontal alignment is a representation. 1.
H.3
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 d d .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
LEGEND:
existing pavement
Edge of
ConstructionLC culvert (open box with grate) precast reinforced concrete box
9' span, 8' rise
Scarp (typ.)
filter class 1, type A (typ.)
2 foot depth over geotextile
NO SCALE
2% 2%
Unclassified borrow
LC
Existing ground
Existing ground
SITE #7, FR 2322 MILEPOST 0.2
LOOKING NORTH
16.5'
I.1
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 d d .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
C h e c k e d b y
D e s ig n e d b y
TYPICAL SECTION
Repair guardrail
15' min.
Traveled Way type 1, 3" compacted depth
Asphalt concrete pavement
8" compacted depth
C A
N Y
O N C
R E
E K
EXISTING EAST CANYON CREEK #2 BRIDGE
PLAN
ELEVATION
70'-4"
50'
SECTION A-A
Approximate
71' Centerline Brg. to Centerline Brg.
Sawcut log existing
Remove construction protected during to be preserved and
Existing guardrail bridge railing
Existing thrie beam of pavement
Existing edge steel posts system G2, type 1, class A
Reconstruct existing guardrail
S p a c e s between holes
P ½, centered
Ø
H o le s
DETAIL A
Angle Detail
L
LP ½
DETAIL B
Wingwall
E m b e d m e n t
M in
½ ty p backwall
Abutment top of rock
Approximate
Reset existing wall
1'-0" right similar
Left wingwall shown, Wingwall Connection if required connections. Reconnect using Detail B
Preserve & protect existing wingwall finish roadway grade top of abutment to
Jack bridge to match
See Detail B
Level
Approximate top of rock
Stage 1, 3
Stage 2
L6X6X½
Drill and bond
See Detail A, L6X6
½"Ø Anchor @ 1'-0"
Drill and bond
CONSTRUCTION SEQUENCE NOTE:
1A
21A 1 1
1 3
33 3 and wingwall footing
Bottom of abutment
Placed riprap class 5 concrete class S (seal)
Limits of structural structural concrete class S (seal)
Reset and attach wingwall. Place on new concrete class S (seal)
Limits of structural class S (seal) on rock
Structural concrete
10' m in3 see Detail B wing wall to abutment, Attach existing of structural seal concrete.
Remove jacks and construct remainder
Construct structural concrete class S (seal).
bottom of footing at approximately 3 tons.
Jack end of wingwall to maintain level at
Minimize opening for jacks (1.5 feet max) beams, timber decking and railing.
is 40 tons. This includes abutment, steel
Estimated total jacking weight of abutment
Jack abutment and remove existing fill.
sub-base
Remove and recompact
Existing ground
Existing abutment
Unclassified borrow
SECTION B-B
B
B
Top of road
10'12'
Typical Section Sheet I.1
See Section B-B and
Reconstruct roadway, Placed riprap class 5
NOTE:
1.
I.2
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 d d .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
G r if fi n
C h e c k e d b y
D e s ig n e d b y
FR 2322, MP .02
SITE #7
PLAN AND ELEVATION
a representation. Adjust to fit field conditions.
Site not surveyed. Horizontal alignment and elevation are
LC
Existing ground (rock) concrete abutments (typ.)
Existing precast wingwall (typ.)
Existing precast A
A
C A
N Y
O N C
R E
E K
50'
Approximate of pavement
Existing edge
FR 2322, MP 0.2
SITE #7
EXISTING EAST CANYON CREEK #2 BRIDGE
C A
N Y
O N C
R E
E K construction protected during to be preserved and
Existing guardrail
Typical Section Sheet I.1
See Section B-B and
Reconstruct roadway, structural concrete class S (seal)
Reset and attach wingwall. Place on new concrete class S (seal)
Limits of structural class 5
Placed riprap
NOTE:
PLAN
EROSION CONTROL
Adjust to fit field conditions.
Site not surveyed. Horizontal alignment is a representation. 1.
I.3
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 d d .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
LEGEND:
Work area
Fiber roll wingwall (typ.)
Existing precast
Limits of structural concrete class S (seal)
Reconstruct existing guardrail system
NO SCALE
2% 2%
18' min.
1:1.53
LC
Existing groundExisting ground
SITE #8, FR 23 MILEPOST 23.5
LOOKING NORTH
J.1
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 d d .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
C h e c k e d b y
D e s ig n e d b y
TYPICAL SECTION
with unclassified borrow damaged embankment
Overexcavate and replace type 1, 3" compacted depth
Asphalt concrete pavement
8" compacted depth
PLAN
ELEVATION
EXISTING EAST CANYON CREEK BRIDGE
E A S
T C
A N
Y O
N C
R E E
K
20'
N
35' with FP-14 204.10, 204.11 compacted in accordance with onsite material enbankment and backfill
Overexcavate damaged
Existing gabion existing ACP
Sawcut
Low water level of pavement
Existing edge
Existing ground
Sheet J.1
See Typical Section
Reconstruct roadway, #8 Anchor centerline
Anchors
A n ch o rs @
'-6
'-6
P la ce to a v o id fo o tin g s under gabion class S (seal)
Structural concrete class 1, type A
Geotextile filter
Placed riprap class 4
M in into largest diameter rock at toe of slope is not encountered, anchor reinforcement reinforcement to top of riprap. If basalt into basalt. Trim or field bend top of
(ASTM A706) a minimum of 1 foot-0 inch
Drill and bond #8X6'-0" reinforcement class 4
Placed riprap footing gabion
Existing bridge bent
Existing
NOTE:
1.
J.2
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 d d .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
G r if fi n
C h e c k e d b y
D e s ig n e d b y
FR 23, MP 23.5
SITE #8
PLAN AND ELEVATION
are a representation. Adjust to fit field conditions.
Site not surveyed. Horizontal alignment and eletation
E A S
T C
A N
Y O
N C
R E E
K
EXISTING EAST CANYON CREEK BRIDGE
N
Approximate
FR 23, MP 23.5
SITE #8
#8 Anchor
A n ch o rs @
'-6
'-6
P la ce to a v o id fo o tin g s
20' 35' bridge bent
Existing
NOTE:
PLAN
EROSION CONTROL
Adjust to fit field conditions.
Site not surveyed. Horizontal alignment is a representation. 1.
J.3
STATE PROJECT
NUMBER
SHEET
m y fi le s p w p r o d u c ti o n d w a e f2 d d .d g n
WA FS ERFO 2016(1)-22(1)
A p r il
H u s c h
M c I n to
C h e c k e d b y
D e s ig n e d b y
LEGEND:
Work area
Fiber roll
Anchors centerline
Placed riprap, class 4 gabion footing
Existing
10.4 x 16 20301 -1900
20435 -1000
25101 -3000
60201 -1500
60201 -1600
60220 -2550
Station
ES
TI
M A
TE
D M
A X
IM
U M
C O
V
ER
S
TR
U C
TU
R A L
EX
C A V A
TI
O N
R
EM
O V A L
O F
PI
PE
C U
LV
ER
T
B A C K
FI
LL
S
EL
EC
T
G R A N
U
LA
R
PL
A C
ED
R
IP
R A P, C
LA
S S
-I
N C
H P
IP
E
C U
LV
ER
T
-I
N C
H P
IP
E
C U
LV
ER
T
FE
ET
S
PA
N
FE
ET
R
IS
E
PR
EC
A S T
R
EI
N
FO
R C
ED
O
N C R
ET
E B O
X C
U
LV
ER
T
S K
EW
A N
G
LE
A llo w ab le P ip e
M at er ia l (S ee k ey b el ow
B
EV
EL
S
1V :n
H
B
EV
EL
S
1V :n
H
REMARKS
See below for numbered notes
FEET CUYD EACH CUYD CUYD LNFT LNFT LNFT Lt Rt Site #2 23-18.0 11 2 35 74 Site #3 23-22.3 11 1 73 68 Site #4 23-23.4 2 531 37 50 Site #6 2324-0.1 1 460 83 49
PROJECT TOTAL 0 6 991 228 74 68 99
Allowable Pipe Material
NOTE: A Aluminum
1. Plastic pipe is not allowed when final installation is exposed. Furnish metal end sections for AS Aluminized steel all plastic pipe including those specified with bevels. See Std. 602-5 for acceptable cell class. C Concrete
GS Galvanized steel P Plastic (blank) a x/__ Any appropriate materia except __
PAY ITEM NUMBER
TABULATION OF DRAINAGE QUANTITIES
Note: The quantities shown hereon are approximate and are subject to field adjustments.
STATE PROJECT
K.1 c:
\m yf ile s\ pw
_p ro du ct io n\ d0
_w a-ef
1e a.
xl sx ]S he et
-A pr -2
1:
P M
T.
L a 4/
B
H us ch ka
4/
D es ig ne d by
C he ck ed b y:
NUMBER
SHEET
WA FS ERFO 2016(1)-
22(1)
WA
2.
3.
4.
METAL ROUND PIPE CULVERT
METAL PIPE ARCH CULVERT
FILL HEIGHT AND METAL THICKNESS TABLE FOR HELICAL LOCKSEAM AND WELDED SEAM PIPE CULVERT
FILL HEIGHT AND METAL THICKNESS TABLE FOR HELICAL LOCKSEAM AND WELDED SEAM PIPE CULVERT
STEEL ALUMINUM
EQUI-
VALENT
DIAMETER
MINIMUM
CORNER
RADIUS
MINIMUM
COVERSPAN x RISE
PIPE ARCH
SIZE
PIPE ARCH
SIZE
SPAN x RISE
EQUI-
VALENT
DIAMETER
MINIMUM
CORNER
RADIUS
MINIMUM
COVER
MINIMUM
COVERDIAMETER
PIPE
SIZE
PIPE
SIZE
DIAMETER
MINIMUM
COVER
ALUMINUMSTEEL
When directed, camber pipe culverts upward from a chord through the inlet and outlet inverts an ordinate amount equal to 1% of the pipe length. Develop camber on a parabolic curve. If the midpoint elevation on the parabolic curve as designed exceeds the elevation of the inlet invert, reduce the amount of camber or increase the pipe culvert gradient.
special analysis by the CO.
The fill heights in the table are for helical lockseam and welded seam pipe only.
Fill heights for culvert pipe with annular corrugations are more restrictive than those of helical lockseam and welded seam pipe.
Obtain approval before furnishing annular corrugation pipe.
Measure minimum cover from the top of the pipe culvert to the subgrade for flexible pavements, and to the top of the pavement for rigid pavements. Measure maximum fill height from the top of the pipe to the top of the pavement for both flexible and rigid pavement.
602-1
STANDARD APPROVED FOR USE 12/1993
REVISED: 4/1994 6/2005
METAL PIPE CULVERT
Fill heights exceeding 100 feet require
" CORRUGATIONS2
1" x 3
22 3" x 1" CORRUGATIONS
METAL THICKNESS (INCH/GAGE)
0.060/160.075/140.105/120.135/10 0.164/8 0.060/160.075/140.105/120.135/10 0.164/8
MAXIMUM FILL HEIGHT ABOVE TOP OF PIPE (FEET)INCHES INCHES
" CORRUGATIONS2
1" x 3
22 3" x 1" CORRUGATIONS 5" x 1" CORRUGATIONS
METAL THICKNESS (INCH/GAGE)
0.064/160.079/140.109/120.138/10 0.168/8 0.064/160.079/140.109/120.138/10 0.168/8 0.064/160.079/140.109/120.138/10 0.168/8
MAXIMUM FILL HEIGHT ABOVE TOP OF PIPE (FEET)INCHES
INCHES
INCHES
142 x 91
137 x 87
128 x 83
117 x 79
112 x 75
103 x 71
95 x 67
87 x 63
83 x 57
81 x 59
77 x 52
73 x 55
71 x 47
66 x 51
64 x 43
60 x 46
57 x 38
49 x 33
42 x 29
35 x 24
28 x 20
24 x 18
21 x 15
17 x 13
INCHES
INCHES
3.5
INCHES
" CORRUGATIONS2
1" x 3
22 3" x 1" CORRUGATIONS
METAL THICKNESS (INCH/GAGE)
5" x 1" CORRUGATIONS
0.064/160.079/140.109/120.138/10 0.168/8 0.079/140.109/120.138/10 0.168/8 0.079/14
MAXIMUM FILL HEIGHT ABOVE TOP OF PIPE (FEET)
0.109/120.138/10 0.168/8
INCHES INCHES INCHES
103 x 71
95 x 67
87 x 63
81 x 59
73 x 55
66 x 51
64 x 43
60 x 46
57 x 38
49 x 33
42 x 29
35 x 24
28 x 20
24 x 18
21 x 15
17 x 13
INCHES
3.5
" CORRUGATIONS2
1" x 3
METAL THICKNESS (INCH/GAGE)
3" x 1" CORRUGATIONS
0.135/100.105/120.075/14
MAXIMUM FILL HEIGHT ABOVE TOP OF PIPE (FEET)
0.060/160.135/100.105/120.075/140.060/16
STATE PROJECT
NUMBER
SHEET
K.2
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
FS ERFO 2016(1)-22(1)WA
B o r d e r .U
S c m y fi le s p w p r o d u c ti o n d F L
H C e ll s .d g n li b
F e b r u a r y
FEDERAL LANDS HIGHWAY
U.S. CUSTOMARY STANDARD
STANDARD
When directed, camber pipe culverts upward from a chord through the inlet and outlet inverts an ordinate amount equal to 1% of the pipe length. Develop camber on a parabolic curve. If the midpoint elevation on the parabolic curve as designed exceeds the elevation of the inlet invert, reduce the amount of camber or increase the pipe culvert gradient.
H equals the diameter of all round pipe culverts or the rise dimension of all pipe arch culverts.
See Section 704 for bedding and backfill requirements.
1.
2.
3.
Construct piping plug of impermeable backfill material at the pipe culvert inlet where granular material is used for backfill. Width may be adjusted to tie into impervious material.
MULTIPLE PIPE INSTALLATION
PIPING PLUG
BELOW NATURAL GROUND OR
TRENCH EXCAVATION IN EMBANKMENT
ON UNSTABLE MATERIAL
ABOVE AND BELOW
NATURAL GROUND
ON NATURAL GROUND
ABOVE NATURAL GROUND
ON UNYIELDING MATERIAL
PIPE BEDDING
ELEVATION
SECTION A-A
LEGEND:
Bedding material (uncompacted)
Impermeable backfill material.
BEDDING DEPTH
MINIMUM SPACING
SPACING
DIAMETER
or SPAN
PIPE SIZE (H) DEPTH
Roadway embankment Roadway embankment
Natural ground
Toe plate Toe plate
Natural ground Natural ground
Roadway embankment
Roadway excavation
Natural ground
H
Width
H H
H H
H H
H H
H
H
H
Finished subgrade Finished subgrade
Natural ground
Finished subgrade
Pipe culvert
Embankment slope
High water elevation treatment
Culvert end
Piping plug before trench excavation embankment height
Finished subgrade or
Original natural ground surface
A
A
Finished subgrade
Roadway embankment
Roadway embankment
Finished subgrade trench excavations
Embankment material placed in layers
Compacted backfill material placed in layers not backfill in accordance with Section 614.
depth table
See bedding excavation in trench
HH
compact in layers not over compressible material. Lightly and replace with selected fine
Remove unyielding material fill material properly compacted with approved granular foundation firm bearing soil and replace
Remove unstable material to
Bedding
Bedding
Bedding
Bedding
H
Half diameter or whichever is less
(see table)
Minimum spacing or Span
Diameter or Span
Diameter section
Metal endMetal end section
602-3
STANDARD APPROVED FOR USE 12/1993
DRAFT: 10/2014
REVISED: 4/1994 6/2005
or 36" (max.) for embankment installations not exceeding 6" compacted depth.
exceeding 6" compacted depth. Or lean concrete
> 54"
12" to 54"
6"
4"
18" (min.)
6" in uncompacted depth.
* Reduce to 18" for
UP to 48"
48" and UP
24" span or 36", PIPE CULVERT BEDDING
METAL AND PLASTIC
2'-0" ±
1'-0" ±
18" ±
18" ±18"±
(min.)
6"
(min.)
6"
12" (min.), 24" (max.)
"/foot of cover,2 minimum
1'-0"
STATE PROJECT
NUMBER
SHEET
K.3
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
FS ERFO 2016(1)-22(1)WA
B o r d e r .U
S c m y fi le s p w p r o d u c ti o n d F L
H C e ll s .d g n li b
F e b r u a r y
FEDERAL LANDS HIGHWAY
U.S. CUSTOMARY STANDARD
STANDARD
NOTE:
2H or 12' (max.)
2H or 12' (max.) 2H or 12' (max.) 2H or 12' (max.) 2H or 12' (max.)
2H or 12' (max.)2H or 12' (max.)
2H or 12' (max.) 2H or 12' (max.)
G20-2
G20-2
G20-2
G20-1
See Note 11
G20-1
See Note 11
M in o r R o a d
M a jo r R o a d
W20-1
See Note 10
W20-1
See Note 10
W20-1 over
W16-8P
See Note 9
W20-1 over
W16-8P
See Note 9
W20-1
Ro ad N am e
SIGN SPACING TABLE
ROAD TYPE
DISTANCE BETWEEN
A B C
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
ROAD WORK
END
WORK
ROAD
AHEAD
ROAD WORK
END
ROAD WORK
END
ROAD WORK
END
WORK
ROAD
AHEAD
WORK
ROAD
AHEAD
W20-1
See Note 10
W20-1
See Note 10
G20-2
Erect all project advance warning signs before starting construction work.
Not all details shown on the temporary traffic control sheets may be applicable to this project. The Contractor may add or delete information and details in this traffic control plan as necessary to accommodate actual operations.
Where advance warning signs, placed as shown, interfere with permanent signs, locate the warning signs as determined by the CO for best results. Vary messages as required.
Additional or different message signs may be required to fit the actual construction conditions.
Install advisory speed plates under the W20 series warning signs as needed to indicate a maximum recommended speed through the construction area.
Ensure all sign supports exposed to impact by traffic meet the requirements of
NCHRP-350 or MASH for crashworthiness.
Maintain two-way traffic during all non-work hours except as approved by the CO.
Do not store traffic control devices along the roadway when not in use. Cover post-mounted signs when not applicable.
If W20-1 is placed on a roadway other than that on which the actual construction work occurs, include a supplementary plaque indicating the name of the road on which the construction does occur (applies to major roads only).
The message on the W20-1 signs may be "ROAD WORK AHEAD" or may specify the distance to the work area in feet or in miles. Install an additional W20-1 each end of the project. Show the distance on the G20-1 sign to the nearest whole mile.
If signing on a roadway under a jurisdiction other than the client agency, verify that an encroachment permit has been obtained.
State standards may be used as an alternative if approved by the CO.
Refer to the Section 635 of the Special Contract Requirements for allowable retroreflective sheeting types.
Expressway / Freeway
A
B
C
(S ee S ig n
Sp ac in g
Ta bl e)
ADVANCE
W
ARNI
NG
AREA
as d et er m in ed b y th e
CO
W or k zo ne A re a of In flu en ce
Pr oj ec t L im its
A
A
(S ee S ig n
Sp ac in g
Ta bl e)
ADVANCE
W
ARNI
NG
AREA
A
A
ROAD NAME
ROAD NAME
ROAD WORK
NEXT xx MILES
WORK
ROAD
xxxxxxx
WORK
ROAD
xxxxx
WORK
ROAD
xxxxxxx
WORK
ROAD
xxxxxxx
ROAD WORK
NEXT xx MILES
W13-1P
(optional)
W13-1P
(optional) xx
MPH
xx
MPH
STANDARD APPROVED FOR USE 6/2005
DRAFT: 6/2014
REVISED:
For work zones that are 2 miles or more in length, install G20-1 signs at signs "B" feet apart according to the Sign Spacing Table.
sign when approach speeds exceed 50 MPH. When used place the two W20-1
Rural greater than 50 MPH
Urban and Rural 35 MPH to 50 MPH
Urban and Rural 30 MPH and less
SIGNS IN FEET
635-1
ADVANCE SIGNING
TEMPORARY TRAFFIC CONTROL
STATE PROJECT
NUMBER
SHEET
L.1
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
WA FS ERFO 2016(1)-22(1)WA
U S
C
J D
C S P r o je c ts T
R N
W F L
C o w lR e p C
A D G I S C
A D S
H E
E T S w a e f2 n a .d g n
M a r c h
FEDERAL LANDS HIGHWAY
U.S. CUSTOMARY STANDARD
Traffic flow
Traffic flow
Signs are shown for one direction of travel only. Place devices similar to those depicted for the opposite direction of travel.
Final location and spacing of signs and devices may be changed to fit field conditions as approved by the CO.
For pilot car operation, mount the "PILOT CAR FOLLOW ME" (G20-4) sign at a conspicuous location on the rear of vehicle. Prominently display the name of the Contractor on the pilot car.
If closure is completely within the project limits, eliminate the "ROAD
WORK AHEAD" (W20-1) and "END ROAD WORK" (G20-2) signs.
For night time flagging operation, provide floodlighting at flagger stations.
Do not allow equipment, materials, or vehicles to be parked or stored in the buffer space.
(See Length and
Spacing Table)
LENGTH AND SPACING TABLE
APPROACH
SPEED* 1.
2.
3.
4.
5.
6.
(See Length and
Spacing Table)
WORK SPACE
G20-2
See Note 4
W20-1
See Note 4
W3-4
W16-2P
(optional)
W20-7
SIGN SPACING TABLE
ROAD TYPE
DISTANCE BETWEEN
A B C
* Approach speed based on the regulatory posted speed, not the advisory speed.
BUFFER SPACE
BUFFER SPACE
LENGTH
NOTE:
Expressway / Freeway
WORK
ROAD
AHEAD
BE
PREPARED
TO STOP
ROAD WORK
END
xxx
FEET
ADVANCE WARNING AREA (See Sign Spacing Table)
TERMINATION AREAVARIABLEBUFFER SPACEABC
(optional)
A
Flagger location
Flagger location
635-5
STANDARD APPROVED FOR USE 6/2005
DRAFT: 8/2013
REVISED:
MPH
FEET
Rural greater than 50 MPH
Urban and Rural 35 MPH to 50 MPH
Urban and Rural 30 MPH and less
SIGNS IN FEET
(WITH FLAGGERS)
ROAD CLOSURE LAYOUT
TEMPORARY TRAFFIC CONTROL
STATE PROJECT
NUMBER
SHEET
L.2
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
WA FS ERFO 2016(1)-22(1)WA
U S
C
J D
C S P r o je c ts T
R N
W F L
C o w lR e p C
A D G I S C
A D S
H E
E T S w a e f2 n b .d g n
M a r c h
FEDERAL LANDS HIGHWAY
U.S. CUSTOMARY STANDARD
Traffic flow
Traffic flow
See Note 4
W20-1 W20-7W20-4
See Note 4
G20-2
Spacing Table)
(See Length and
(optional)
WORK SPACE (optional)(optional)
(optional)
W13-1P
(optional)
W16-2P
7.
6.
5.
4.
3.
2.
1.
the buffer space.
Do not allow equipment, materials, or vehicles to be parked or stored in
Requirements, Section 156.
For project specific minimum width, refer to the Special Contract
For night time flagging operation, provide floodlighting at flagger stations.
WORK AHEAD" (W20-1) and "END ROAD WORK" (G20-2) signs.
If closure is completely within the project limits, eliminate the "ROAD name of the contractor on the pilot car.
a conspicuous location on the rear of vehicle. Prominently display the
For pilot car operation, mount the PILOT CAR FOLLOW ME (G20-4) sign at conditions as approved by the CO.
Final location and spacing of signs and devices may be changed to fit field those depicted for the opposite direction of travel.
Signs are shown for one direction of travel only. Place devices similar to
LENGTH AND SPACING TABLE
SPEED*
APPROACH
AREA
TAPER
SPACE
BUFFER
SPACE
WORK
CHANNELIZING DEVICE
not the advisory speed.
Approach speed based on the regulatory posted speed, *
SIGN SPACING TABLE
ROAD TYPE
DISTANCE BETWEEN
A B C
LENGTH
BUFFER SPACE
NOTE:
Expressway / Freeway
WORK
ROAD
AHEAD
ONE LANE
ROAD
AHEAD
xx
MPH
xxx
FEET
ROAD WORK
END
ATAPER AREABUFFER SPACEVARIABLEBUFFER SPACETAPER AREAABC
(See Length and Spacing Table)ADVANCE WARNING AREA (See Sign Spacing Table) TERMINATION AREA
Device spacing
BUFFER SPACE
Channelizing devices
Flagger location
Flagger location
635-6
STANDARD APPROVED FOR USE 6/2005
DRAFT: 8/2013
REVISED:
MPH FEET
Rural greater than 50 MPH
Urban and Rural 35 MPH to 50 MPH
Urban and Rural 30 MPH and less
SIGNS IN FEET
(WITH FLAGGERS)
SINGLE LANE CLOSURE LAYOUT
TEMPORARY TRAFFIC CONTROL
SPACING IN FEET
50' - 100' 50' - 100' (optional)
See Note 6
10' min.
STATE PROJECT
NUMBER
SHEET
L.3
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
WA FS ERFO 2016(1)-22(1)WA
U S
C
J D
C S P r o je c ts T
R N
W F L
C o w lR e p C
A D G I S C
A D S
H E
E T S w a e f2 n c .d g n
M a r c h
FEDERAL LANDS HIGHWAY
U.S. CUSTOMARY STANDARD
POST AND GEOTEXTILE INSTALLATION DETAIL
SILT FENCE INSTALLATION AT TOE OF FILL
Fi ll slo pe
T o e o f s lo p e
PLAN
ELEVATION
4.
3.
2.
1.
T o e o f s lo p e
Fi ll sl op e
ELEVATION
PLAN
PLAN
PLAN
END DETAIL
END POSTS DETAIL
POSTS AT JOINTS
Varies
Varies
Geotextile
Steel or wood post
Backfilled and compacted soil fo r s p a c in g
S e e N o te
Limits of clearing
(undisturbed)
Existing ground
Silt fence reinforcement
REVISED: 10/2016
DETAIL APPROVED FOR USE --/----
WESTERN FEDERAL LANDS HIGHWAY DIVISION
SILT FENCE
W157-1
U.S. CUSTOMARY DETAIL
DETAIL
STATE PROJECT
NUMBER
SHEET
M.1
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
FS ERFO 2016(1)-22(1)WA
U S
C c m y fi le s p w p r o d u c ti o n d w a e f2 s a .d g n
O c to b e r
NOTE:
Staple or tie
Section B
Geotextile fabric, Tie top of posts together driven tightly together.
Steel or wood posts
Steel or wood post
Staple or tie
Geotextile fabric
Fasten fabric to posts around each post one full turn.
Fold geotextile fabric See Note 3
End Posts Detail
End posts, see
End Posts Detail
End posts, see
See Note 3 fabric, Section A
Geotextile
Flow
Flow
Flow running around the ends.
Curve ends of silt fence upgrade to prevent water from as possible.
Install silt fence to follow the ground contours as closely does not slide down, supporting posts.
All types must ensure silt fence remains attached to, and manufacturer's recommendations for installation procedures.
as long as specified dimensions are satisfied. Follow
Alternate preassembled silt fence options will be allowed m in m in m in
6-foot (max.) spacing without silt fence reinforcement.
10-foot (max.) spacing with silt fence reinforcement.
4" min.
6" min. trench
Spacing Slope
STAKES REQUIRED
1:1
1:2
1:3
1:4 or flatter for each roll
Stakes required
FIBER ROLL SPACING
Fiber roll length
Fl ow
T o e o f fi ll s lo p e
ELEVATION
PLAN
disturbed areas
Runoff from
INSTALLATION BEYOND TOE OF SLOPE
INSTALLATION ALONG SLOPES
FIBER ROLL STAKING DETAIL
PROPERLY STAKED AND ENTRENCHED FIBER ROLL
Existing ground (typ.)
Fiber roll
Flow direction
Slope
Direction of runof f from distur bed area s sp ac in g ch ar t
S ee F ib er R ol l
Fiber roll ff o n ur f o n oi t c er i
D along contours
Install fiber rolls
Fiber roll
Slope
Fi ll slo pe
Direction of runoff ground
Existing soil to match ground level
Backfilled and compacted
Flow larger than fiber roll wood stakes. See Note 2.
Pay lim its
Pay lim its
SLOPE PROTECTION INSTALLATION
ALTERNATE FIBER ROLL JOINT DETAIL
FIBER ROLL LAPPING DETAIL
on uphill side of fiber roll
Place excavated material Stagger joints (typ.)
2.
1.
permanent installations. Do not crush fiber roll while staking.
roll is secure to slope. Live stakes may be used for and install fiber rolls
Step 1: Excavate trench Step 2: Backfill soil against fiber rolls
DRAFT: 7/2016
REVISED:
DETAIL APPROVED FOR USE 10/2014
WESTERN FEDERAL LANDS HIGHWAY DIVISION
FIBER ROLL
(FT)
(FT)
W157-21
2" (min.) Excavate trench 2"
1" x 1" or 1" Ø
U.S. CUSTOMARY DETAIL
DETAIL
STATE PROJECT
NUMBER
SHEET
M.2
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
FS ERFO 2016(1)-22(1)WA
U S
C c m y fi le s p w p r o d u c ti o n d m s
W .d g n
J u ly ove rlap
12" (m in.)
t o m in m in
1" x 1" Wood stake as specified in plans
3' min. or
3' (min.)
Drive stakes at each end and at 4-foot spacing until fiber fiber roll and space stakes at 4-foot max.
6-inches from fiber roll end angles towards the adjacent
Overlap fiber rolls 12-inch minimum. Drive stakes at
PLASTIC LINED DIVERSION CHANNEL
RIPRAP LINED DIVERSION CHANNEL
TEMPORARY CULVERT
DIVERSION CHANNEL
SECTION B-B
SECTION A-A
SECTION A-A SECTION B-B
SECTION B-B
PLAN
W
B
W
B
W
B B
W
T T
Ø when scheduled)
Silt fence (typ.
Roadway embankment
Roadway embankment
Temporary culvert backfill
Subgrade
Bedding
Sandbags
Riprap lining Riprap lining backflow into natural channel
Use sandbags to prevent
Permanent natural channel
Earthwork limits when scheduled)
Silt fence (typ.
See Note 5
Permanent culvert
Roadway centerline temporary barrier
Use sandbags to construct
SandbagsPlastic liner
SSSS
SS SS
D
D D
D
SS
SS
SS SS
1.
2.
3.
4.
5.
FlowFlow
FlowFlow
Plastic liner when scheduled)
Silt fence (typ.
When specified replace the portion of the diversion channel through the roadway embankment with temporary culvert.
This is the start of the file's text. The full file is on GovTribe.