Updated Feb2011_PROJECT DESCRIPTION_ID PFH 88-1(1) Yankee Fork Road.pdf
PDF 29 KB Posted
- Attached to
- ID PFH 88-1(1) Yankee Fork Road Federal contract opportunity
- Solicitation number
- DTFH70-11-B-00001
About this file
Updated Project Description (2/14/11)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A001_YankeeForkRoad.pdf | ||
| A001_YankeeForkRoad.pdf | ||
| Phys Data Request Form_Yankee.pdf | ||
| 1fbo_IFB1__YankeeFork.pdf | ||
| http //www.wfl.fhwa.dot.gov/contracting/construction/plans/yankee-fork-road/ | — | |
| Plans Request Form_Yankee.pdf | ||
| 2fbo_IFB2__YankeeFork.pdf | ||
| Prelim Ltr_ID PFH 88-1(1) Yankee Fork Road.pdf | ||
| Prelim Plans_Yankee Fork Road2.pdf | ||
| PROJECT DESCRIPTION_ID PFH 88-1(1) Yankee Fork Road.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Description for: ID PFH 88-1(1) Yankee Fork Road, Salmon- Challis National Forest, Custer County, Idaho
Revised 2/14/2011 – See BLUE for changes.
The work consists of asphalt overlay, drainage, MSE retaining walls, rock fall protection fence, bridge repair rail, curb repair, cleaning/repainting steel girders, and other small items of work.
Project length: 3.1 miles
Fixed Completion Date: Approximately September 29, 2011
Estimated Price Range: $3 million to $5 million
Location: 144 miles northeast of Boise, Idaho near Sunbeam, ID
DESCRIPTION OF WORK in US CUSTOMARY UNITS
DIVISION 150 – Project Requirements 152 Construction Survey & Staking X YES NO 153 Contractor Quality Control and Assurance X YES NO 154 Contractor Sampling & Testing X YES NO 155 Schedules for Construction Contracts (construction schedules) X YES NO 157 Soil Erosion Control Devices (erosion control devices)
Silt fence Sediment Wattle
500 LNFT
1,450 LNFT
DIVISION 200 – Earthwork 203 Removal of Structures & Obstructions (structures, demolition)
Pipe Culvert Removal Sign Removal MSE Wall Guardrail – Steel Bridge Rail
2 EACH
5 EACH
6 EACH
2 EACH
250 LNFT
204 Excavation & Embankment Excavation Embankment Ditch excavation
160 LNFT
10 CUYD
50 LNFT
DIVISION 250 - Slope Reinforcement and Retaining Walls 253 Gabions & Revet Mattresses 1,500 SQFT 255 Mechanically Stabilized Earth Walls (retaining walls) 2,100 SQFT
DIVISION 300 – Aggregate Courses 303 Road Reconditioning
Ditch Reconditioning 14,600 1,300 LNFT 308 Minor Crushed Aggregate (crushed aggregate) 700 TON
ID PFH 88-1(1) Yankee Fork Road
DIVISION 400 – Asphalt Pavements & Surface Treatments 401 Superpave Hot Asphalt Concrete Pavement
Antistrip
6,650 TON
70 TON
403 Hot Asphalt Concrete Pavement (asphalt concrete pavement) 2,300 TON 404 Minor Hot Asphalt Concrete (asphalt concrete pavement) 450 TON 413 Asphalt Pavement Milling 4,100 SQYD
DIVISION 550 – Bridge Construction 556 Bridge Railing Steel – Thrie Beam 213 LNFT 563 Painting (structures, painting)Exterior Bridge girders ALL Lump Sum 566 Shotcrete 310 SQYD 575 Minor Bridge Work
Concrete Repair Joint Replacement
All Lump Sum All Lump Sum
DIVISION 600 – Incidental Construction 602 Culverts (indicate one or both)
18” Pipe Culvert 24” Pipe Culvert 36” Pipe Culvert
116 LNFT
40 LNFT
100 LNFT
607 Cleaning Culvert in-place 18 Each 607 Reconditioning Drainage Sturcture 2 Each 609 Curb (concrete – minor structures) (indicate which)
Concrete 18 LNFT 617 Guardrail
Terminal Section Structure Transition Railing
4 EACH
91 LNFT
633 Sign System 54 SqFt 634 Permanent Pavement Markings (traffic pavement markings)
Permanent Pavement Markings, Type A Solid White Permanent Pavement Markings, Type A Solid Yellow Type B stop line
66,000 LNFT
66,000 LNFT
70 SqFt
635 Temporary Traffic Control Barricade Tubular marker Drum Raised Pavement Marker Construction Sign Flagger
2 Each 80 Each 42 Each 3,280 Each 309 SqFt Hours: 2,500
651 Rockfall Protection Fence 550 LNFT
| DIVISION 150 – Project Requirements |
| DIVISION 400 – Asphalt Pavements & Surface Treatments |
| DIVISION 550 – Bridge Construction |
| DIVISION 600 – Incidental Construction |
File details come from the government source that posted it. Updated .