Text version

ID PRA CRMO 10(2), LOOP ROAD PHASE 2, Craters of the Moon National Monument and Preserve, Butte County, Idaho

The work consists of grading, base, paving, and reconstruct parking areas and other small items of work.

Project length: 1.6 MILES OF Spur Roads & 6 parking areas

Fixed Completion Date: October 15, 2010

Estimated Price Range: $3 million to $5 million

Location: Approximately 19 miles Southwest of Arco

DESCRIPTION OF WORK in US CUSTOMARY UNITS

DIVISION 150 –Project Requirements 152 Construction Survey & Staking X YES NO 153 Contractor Quality Control and Assurance X YES NO 154 Contractor Sampling & Testing X YES NO 155 Schedules for Construction Contracts (construction schedules) X YES NO 157 Soil Erosion Control Devices (erosion control devices) Sediment wattle

300 LNFT

158 Watering for Dust Control 100 MGAL

DIVISION 200 –Earthwork 201 Clearing & Grubbing LPSM 203 Removal of Structures & Obstructions (structures, demolition) Catch basin: 2 each Pipe culvert: 2 each Signs: 5 each Curb & gutter, Concrete:

3050 lnft Curb, asphalt: 13990 lnft Paved waterway: 102 lnft Sidewalk, asphalt: 1455 sqyd Sidewalk, concrete: 1170 sqft Saw cutting pavement: 650 lnft

204 Excavation & Embankment 3400 CUYD 207 Earthwork Geotextiles (geotextiles) 27 sqyd 211 Roadway Obliteration 500 sqyd

DIVISION 250 - Slope Reinforcement and Retaining Walls 251 Riprap Class 2: 20 cuyd

Ditch, class: 75 cuyd Class 5: 1000 cuyd

DIVISION 300 –Aggregate Courses 308 Minor Crushed Aggregate (crushed aggregate) 2000 ton

310 Recycled Aggregate Course (asphalt pavement recycling) 29231 sqyd

DIVISION 400 –Asphalt Pavements & Surface Treatments 401 Superpave Hot Asphalt Concrete Pavement 9000 ton 411 Asphalt Prime Coat (asphalt surface treatment) 505 ton 412 Asphalt Tack Coat (asphalt surface treatment) 20 ton

DIVISION 600 –Incidental Construction 602 Culverts & Drains (indicate one or both) Culvert: 250 lnft 604 Manholes, Inlets, & Catch Basins

(culverts & drains) (indicate which) Catch Basin: 4 each 608 Paved Waterways (culverts & drains) 1420 lnft 609 Curb & Gutter (concrete –minor structures) (indicate which) Curb, concrete, 6”:

4200 lnft Curb, concrete, 15”:

350 lnft Curb & gutter, concrete: 5300 lnft

615 Sidewalks, Drive Pads & Paved Medians (concrete –minor structures) 1800 sqyd

622 Rental Equipment X YES NO 624 Topsoil (landscaping & related items) 2320 sqyd 633 Permanent Traffic Control Devices (traffic control devices) Sign installation: 9 each

Snow pole holder: 255 each Traffic loop: 2 each

634 Permanent Pavement Markings (traffic pavement markings) 4-inch white: 12050 lnft 4-inch yellow: 33100 lnft 24-inch white: 1800 lnft Arrow, white: 6 each Accessibility symbol, white: 13 each

635 Temporary Traffic Control Barricade, type 1: 75 each Barricade, type 3: 15 each 28” cone: 200 each Warning light, type A: 10 each Warning light, type C: 10 each Plastic fence: 1050 lnft

635 Flagger Hours: 300 635 Pilot Car Hours: 200