T A B U L A T I O N O F B I D S < Don't show > A
Project No : CA FLAP PLU CR411(1)
Project Name : Bucks Lake Road Slope Stabilization Solcitation No:
State : CA County : Plumas County Federal Location : Plumas National Forest
Opened at: 2:00pm Opened by: Jeremiah Rogers Date: 1/12/2017
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed:
Title:
Date:
Contract Awarded to: Award Date:
Contract Number: Data is Public
Contractor Comment Bid Amount Responsive
Engineer's Estimate 2,282,750.00$
Hat Creek Construction 1,989,989.00$
Timberworks 2,269,748.00$
Lamon 2,394,518.80$
Tikigaq 2,417,194.00$
Dig It Construction 2,509,050.10$
McCullough Constructio 3,021,522.09$
DTFH6817C00013
DTFH6816B00027
Hat Creek Construction
2/14/2017 FHWA Confidential Page 1 of 2
Contractor Comment Bid Amount Responsive
Steelhead Constructors 3,036,470.00$
2/14/2017 FHWA Confidential Page 2 of 2
Total of Bid Items: 2,282,750.00$ -12.8% 1,989,989.00$
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount
15101-0000 Line A0020 ALL LPSM 266,464.00$ 266,464.00$ 195,000.00$
15201-0000 Line A0040 ALL LPSM 40,000.00$ 40,000.00$ 15,700.00$
15215-3000 Line A0060 2 EACH 1,500.00$ 3,000.00$ 3,940.00$
15301-0000 Line A0080 ALL LPSM 15,000.00$ 15,000.00$ 140,000.00$
15401-0000 Line A0100 ALL LPSM 45,000.00$ 45,000.00$ 85,000.00$
15501-0000 Line A0120 ALL LPSM 10,000.00$ 10,000.00$ 4,862.00$
15705-0100 Line A0140 1,310 LNFT 7.00$ 9,170.00$ 13,100.00$
15705-1400 Line A0160 60 LNFT 15.00$ 900.00$ 1,800.00$
15706-0200 Line A0180 25 EACH 250.00$ 6,250.00$ 3,750.00$
15802-0000 Line A0200 ALL LPSM 30,000.00$ 30,000.00$ 25,000.00$
20101-0000 Line A0220 3.1 ACRE 3,000.00$ 9,300.00$ 15,500.00$
20220-1000 Line A0240 20 EACH 1,400.00$ 28,000.00$ 10,000.00$
20301-0200 Line A0260 40 EACH 250.00$ 10,000.00$ 2,800.00$
Engineer's Estimate
70.00$
500.00$
5,000.00$
25,000.00$
150.00$
30.00$
10.00$
4,862.00$
85,000.00$
1,970.00$
Hat Creek Construction & Materials, Inc
15,700.00$
195,000.00$
MOBILIZATION
CONSTRUCTION SURVEY AND STAKING
SURVEY AND STAKING, DRAINAGE STRUCTURE
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, FIBER ROLL
SOIL EROSION CONTROL, CHECK DAM
WATERING FOR DUST CONTROL
CLEARING AND GRUBBING
REMOVAL, INDIVIDUAL TREE
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
REMOVAL OF BOULDER
CONTRACTOR QUALITY CONTROL
140,000.00$
2/14/2017 Page 1 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount
Engineer's Estimate Hat Creek Construction & Materials, Inc
20301-0700 Line A0280 20 EACH 50.00$ 1,000.00$ 400.00$
20301-1900 Line A0300 2 EACH 1,500.00$ 3,000.00$ 1,100.00$
20301-2400 Line A0320 5 EACH 200.00$ 1,000.00$ 500.00$
20302-1200 Line A0340 1,200 LNFT 8.00$ 9,600.00$ 7,800.00$
20302-1300 Line A0360 440 LNFT 25.00$ 11,000.00$ 4,400.00$
20401-0000 Line A0380 4,100 CUYD 40.00$ 164,000.00$ 94,300.00$
20420-0000 Line A0400 23,800 CUYD 30.00$ 714,000.00$ 618,800.00$
20720-0300 Line A0420 24,500 SQYD 5.00$ 122,500.00$ 61,250.00$
25101-2200 Line A0440 10 CUYD 350.00$ 3,500.00$ 5,000.00$
30202-2000 Line A0460 3,600 TON 50.00$ 180,000.00$ 100,800.00$
40301-0100 Line A0480 1,420 TON 150.00$ 213,000.00$ 177,500.00$
41102-1000 Line A0500 6,500 SQYD 1.25$ 8,125.00$ 5,200.00$
41105-0000 Line A0520 10 TON 75.00$ 750.00$ 2,000.00$ 200.00$
0.80$
125.00$
28.00$
500.00$
2.50$
26.00$
23.00$
10.00$
6.50$
100.00$
550.00$
20.00$
REMOVAL OF SIGN
REMOVAL OF GUARDRAIL
REMOVAL OF GUARDRAIL, CONCRETE BARRIER
PRIME COAT, METHOD 1
BLOTTER
ROADWAY EXCAVATION
EMBANKMENT CONSTRUCTION (RSS)
REINFORCEMENT GEOSYNTHETIC, TYPE 3
PLACED RIPRAP, METHOD B, CLASS 2
ROADWAY AGGREGATE, METHOD 2
ASPHALT CONCRETE PAVEMENT, TYPE 1
REMOVAL OF DELINEATOR
REMOVAL OF PIPE CULVERT
2/14/2017 Page 2 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount
Engineer's Estimate Hat Creek Construction & Materials, Inc
41201-0000 Line A0540 3 TON 800.00$ 2,400.00$ 5,700.00$
60201-0800 Line A0560 205 LNFT 150.00$ 30,750.00$ 27,675.00$
60210-0800 Line A0580 4 EACH 500.00$ 2,000.00$ 3,200.00$
61701-4500 Line A0600 1,313 LNFT 35.00$ 45,955.00$ 48,581.00$
61702-1500 Line A0620 2 EACH 3,000.00$ 6,000.00$ 8,000.00$
62201-0200 Line A0640 10 HOUR 120.00$ 1,200.00$ 1,250.00$
62201-0550 Line A0660 10 HOUR 150.00$ 1,500.00$ 1,190.00$
62201-0950 Line A0680 10 HOUR 140.00$ 1,400.00$ 1,690.00$
62201-2850 Line A0700 10 HOUR 160.00$ 1,600.00$ 1,560.00$
62201-3350 Line A0720 10 HOUR 170.00$ 1,700.00$ 1,700.00$
62301-0000 Line A0740 40 HOUR 75.00$ 3,000.00$ 2,640.00$
62302-1000 Line A0760 20 HOUR 150.00$ 3,000.00$ 3,000.00$
62302-1100 Line A0780 20 HOUR 150.00$ 3,000.00$ 3,540.00$ 177.00$
150.00$
66.00$
170.00$
156.00$
169.00$
119.00$
125.00$
4,000.00$
37.00$
800.00$
135.00$
1,900.00$
TACK COAT
24-INCH PIPE CULVERT
END SECTION FOR 24-INCH PIPE CULVERT
GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS (NON-BLOCKED)
GENERAL LABOR
SPECIAL LABOR, HIRED TECHNICAL SERVICES
SPECIAL LABOR, HIRED SURVEY SERVICES
TERMINAL SECTION, TYPE MGS TANGENT
DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY
BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
MOTOR GRADER, 12 FOOT MINIMUM BLADE
HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY
2/14/2017 Page 3 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount
Engineer's Estimate Hat Creek Construction & Materials, Inc
62401-0300 Line A0800 2,280 SQYD 5.00$ 11,400.00$ 15,048.00$
62405-0300 Line A0820 8,200 SQYD 3.00$ 24,600.00$ 45,920.00$
62511-2000 Line A0840 8,200 SQYD 2.00$ 16,400.00$ 9,020.00$
62516-2000 Line A0860 4,600 SQYD 2.00$ 9,200.00$ 3,220.00$
62901-1100 Line A0880 2,750 SQYD 10.00$ 27,500.00$ 12,650.00$
63301-0000 Line A0900 4 EACH 500.00$ 2,000.00$ 1,996.00$
63308-2000 Line A0920 4 EACH 300.00$ 1,200.00$ 260.00$
63402-0300 Line A0940 2.7 MILE 3,500.00$ 9,450.00$ 6,480.00$
63501-2000 Line A0960 ALL LPSM 25,000.00$ 25,000.00$ 13,550.00$
63502-0700 Line A0980 50 EACH 25.00$ 1,250.00$ 1,250.00$
63502-1300 Line A1000 100 EACH 65.00$ 6,500.00$ 4,500.00$
63502-1600 Line A1020 4 EACH 250.00$ 1,000.00$ 600.00$
63503-0400 Line A1040 1,100 LNFT 40.00$ 44,000.00$ 33,000.00$ 30.00$
150.00$
45.00$
25.00$
13,550.00$
2,400.00$
65.00$
499.00$
4.60$
0.70$
1.10$
5.60$
6.60$
TEMPORARY TRAFFIC CONTROL, CONE
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER
MULCHING, HYDRAULIC METHOD
ROLLED EROSION CONTROL PRODUCT, TYPE 4
SIGN SYSTEM
OBJECT MARKER, TYPE 2
PAVEMENT MARKINGS, TYPE B, SOLID
TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNAL SYSTEM
FURNISHING AND PLACING TOPSOIL, 4-INCH DEPTH
PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
SEEDING, HYDRAULIC METHOD
2/14/2017 Page 4 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount
Engineer's Estimate Hat Creek Construction & Materials, Inc
63503-0700 Line A1060 1,736 LNFT 1.00$ 1,736.00$ 3,472.00$
63503-1000 Line A1080 2,000 LNFT 5.00$ 10,000.00$ 8,000.00$
63504-1000 Line A1100 165 SQFT 30.00$ 4,950.00$ 4,125.00$
63506-0500 Line A1120 700 HOUR 70.00$ 49,000.00$ 45,570.00$
63610-2800 Line A1140 1,100 LNFT 25.00$ 27,500.00$ 71,500.00$
63621-1000 Line A1160 2 EACH 1,000.00$ 2,000.00$ 4,600.00$ 2,300.00$
65.00$
65.10$
25.00$
4.00$
2.00$
TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
TEMPORARY TRAFFIC CONTROL, FLAGGER
CONDUIT, 4-INCH, PVC
UTILITY BOX, PULLBOX
TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
2/14/2017 Page 5 of 20
Total of Bid Items:
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
15101-0000 Line A0020 ALL LPSM
15201-0000 Line A0040 ALL LPSM
15215-3000 Line A0060 2 EACH
15301-0000 Line A0080 ALL LPSM
15401-0000 Line A0100 ALL LPSM
15501-0000 Line A0120 ALL LPSM
15705-0100 Line A0140 1,310 LNFT
15705-1400 Line A0160 60 LNFT
15706-0200 Line A0180 25 EACH
15802-0000 Line A0200 ALL LPSM
20101-0000 Line A0220 3.1 ACRE
20220-1000 Line A0240 20 EACH
20301-0200 Line A0260 40 EACH
MOBILIZATION
CONSTRUCTION SURVEY AND STAKING
SURVEY AND STAKING, DRAINAGE STRUCTURE
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, FIBER ROLL
SOIL EROSION CONTROL, CHECK DAM
WATERING FOR DUST CONTROL
CLEARING AND GRUBBING
REMOVAL, INDIVIDUAL TREE
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
REMOVAL OF BOULDER
CONTRACTOR QUALITY CONTROL
-0.6% 2,269,748.00$ 4.9% 2,394,518.80$
Unit Price Amount Unit Price Amount
62,580.00$ 125,000.00$
11,000.00$ 19,500.00$
2,020.00$ 3,000.00$
86,225.00$ 98,000.00$
49,000.00$ 10,000.00$
5,000.00$ 18,000.00$
7,925.50$ 8,646.00$
363.00$ 900.00$
1,250.00$ 10,300.00$
68,000.00$ 69,000.00$
15,500.00$ 7,750.00$
10,100.00$ 9,000.00$
3,880.00$ 5,200.00$ 97.00$ 130.00$
505.00$ 450.00$
5,000.00$ 2,500.00$
68,000.00$ 69,000.00$
50.00$ 412.00$
6.05$ 15.00$
6.05$ 6.60$
5,000.00$ 18,000.00$
49,000.00$ 10,000.00$
11,000.00$ 19,500.00$
1,010.00$ 1,500.00$
Timberworks Lamon
62,580.00$ 125,000.00$
86,225.00$ 98,000.00$
2/14/2017 Page 6 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
20301-0700 Line A0280 20 EACH
20301-1900 Line A0300 2 EACH
20301-2400 Line A0320 5 EACH
20302-1200 Line A0340 1,200 LNFT
20302-1300 Line A0360 440 LNFT
20401-0000 Line A0380 4,100 CUYD
20420-0000 Line A0400 23,800 CUYD
20720-0300 Line A0420 24,500 SQYD
25101-2200 Line A0440 10 CUYD
30202-2000 Line A0460 3,600 TON
40301-0100 Line A0480 1,420 TON
41102-1000 Line A0500 6,500 SQYD
41105-0000 Line A0520 10 TON
REMOVAL OF SIGN
REMOVAL OF GUARDRAIL
REMOVAL OF GUARDRAIL, CONCRETE BARRIER
PRIME COAT, METHOD 1
BLOTTER
ROADWAY EXCAVATION
EMBANKMENT CONSTRUCTION (RSS)
REINFORCEMENT GEOSYNTHETIC, TYPE 3
PLACED RIPRAP, METHOD B, CLASS 2
ROADWAY AGGREGATE, METHOD 2
ASPHALT CONCRETE PAVEMENT, TYPE 1
REMOVAL OF DELINEATOR
REMOVAL OF PIPE CULVERT
-0.6% 2,269,748.00$ 4.9% 2,394,518.80$
Unit Price Amount Unit Price Amount
Timberworks Lamon
500.00$ 500.00$
1,300.00$ 6,200.00$
500.00$ 460.00$
7,860.00$ 10,800.00$
7,700.00$ 3,960.00$
57,400.00$ 168,100.00$
835,380.00$ 1,047,200.00$
67,375.00$ 79,625.00$
1,120.00$ 2,820.00$
122,400.00$ 154,800.00$
244,240.00$ 166,140.00$
32,500.00$ 9,100.00$
10,000.00$ 5,000.00$ 1,000.00$ 500.00$
5.00$ 1.40$
172.00$ 117.00$
34.00$ 43.00$
112.00$ 282.00$
2.75$ 3.25$
35.10$ 44.00$
14.00$ 41.00$
17.50$ 9.00$
6.55$ 9.00$
100.00$ 92.00$
650.00$ 3,100.00$
25.00$ 25.00$
2/14/2017 Page 7 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
41201-0000 Line A0540 3 TON
60201-0800 Line A0560 205 LNFT
60210-0800 Line A0580 4 EACH
61701-4500 Line A0600 1,313 LNFT
61702-1500 Line A0620 2 EACH
62201-0200 Line A0640 10 HOUR
62201-0550 Line A0660 10 HOUR
62201-0950 Line A0680 10 HOUR
62201-2850 Line A0700 10 HOUR
62201-3350 Line A0720 10 HOUR
62301-0000 Line A0740 40 HOUR
62302-1000 Line A0760 20 HOUR
62302-1100 Line A0780 20 HOUR
TACK COAT
24-INCH PIPE CULVERT
END SECTION FOR 24-INCH PIPE CULVERT
GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STE
GENERAL LABOR
SPECIAL LABOR, HIRED TECHNICAL SERVICES
SPECIAL LABOR, HIRED SURVEY SERVICES
TERMINAL SECTION, TYPE MGS TANGENT
DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACIT
BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RA
WHEEL LOADER, 3 CUBIC YARD MINIMUM RATE
MOTOR GRADER, 12 FOOT MINIMUM BLADE
HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMU
-0.6% 2,269,748.00$ 4.9% 2,394,518.80$
Unit Price Amount Unit Price Amount
Timberworks Lamon
3,000.00$ 4,500.00$
16,400.00$ 32,800.00$
800.00$ 1,200.00$
47,924.50$ 48,581.00$
8,000.00$ 8,000.00$
1,250.00$ 1,100.00$
1,120.00$ 2,000.00$
1,860.00$ 2,200.00$
1,360.00$ 2,000.00$
2,560.00$ 2,200.00$
2,520.00$ 3,520.00$
4,800.00$ 2,700.00$
3,520.00$ 5,520.00$ 176.00$ 276.00$
240.00$ 135.00$
63.00$ 88.00$
256.00$ 220.00$
136.00$ 200.00$
186.00$ 220.00$
112.00$ 200.00$
125.00$ 110.00$
4,000.00$ 4,000.00$
36.50$ 37.00$
200.00$ 300.00$
80.00$ 160.00$
1,000.00$ 1,500.00$
2/14/2017 Page 8 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
62401-0300 Line A0800 2,280 SQYD
62405-0300 Line A0820 8,200 SQYD
62511-2000 Line A0840 8,200 SQYD
62516-2000 Line A0860 4,600 SQYD
62901-1100 Line A0880 2,750 SQYD
63301-0000 Line A0900 4 EACH
63308-2000 Line A0920 4 EACH
63402-0300 Line A0940 2.7 MILE
63501-2000 Line A0960 ALL LPSM
63502-0700 Line A0980 50 EACH
63502-1300 Line A1000 100 EACH
63502-1600 Line A1020 4 EACH
63503-0400 Line A1040 1,100 LNFT
TEMPORARY TRAFFIC CONTROL, CONE
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGH
TEMPORARY TRAFFIC CONTROL, CONCRETE BAR
MULCHING, HYDRAULIC METHOD
ROLLED EROSION CONTROL PRODUCT, TYPE 4
SIGN SYSTEM
OBJECT MARKER, TYPE 2
PAVEMENT MARKINGS, TYPE B, SOLID
TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNA
FURNISHING AND PLACING TOPSOIL, 4-INCH D
PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
SEEDING, HYDRAULIC METHOD
-0.6% 2,269,748.00$ 4.9% 2,394,518.80$
Unit Price Amount Unit Price Amount
Timberworks Lamon
45,600.00$ 13,680.00$
36,900.00$ 24,600.00$
7,380.00$ 4,100.00$
3,220.00$ 1,380.00$
12,650.00$ 19,250.00$
2,000.00$ 1,720.00$
300.00$ 320.00$
4,725.00$ 216.00$
20,100.00$ 18,000.00$
900.00$ 1,000.00$
3,500.00$ 6,800.00$
574.00$ 564.00$
115,500.00$ 24,200.00$ 105.00$ 22.00$
143.50$ 141.00$
35.00$ 68.00$
18.00$ 20.00$
20,100.00$ 18,000.00$
1,750.00$ 80.00$
75.00$ 80.00$
500.00$ 430.00$
4.60$ 7.00$
0.70$ 0.30$
0.90$ 0.50$
4.50$ 3.00$
20.00$ 6.00$
2/14/2017 Page 9 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
63503-0700 Line A1060 1,736 LNFT
63503-1000 Line A1080 2,000 LNFT
63504-1000 Line A1100 165 SQFT
63506-0500 Line A1120 700 HOUR
63610-2800 Line A1140 1,100 LNFT
63621-1000 Line A1160 2 EACH
TEMPORARY TRAFFIC CONTROL, CONSTRUCTIO
TEMPORARY TRAFFIC CONTROL, FLAGGER
CONDUIT, 4-INCH, PVC
UTILITY BOX, PULLBOX
TEMPORARY TRAFFIC CONTROL, PAVEMENT MAR
TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
-0.6% 2,269,748.00$ 4.9% 2,394,518.80$
Unit Price Amount Unit Price Amount
Timberworks Lamon
6,076.00$ 2,256.80$
8,000.00$ 7,200.00$
5,115.00$ 5,610.00$
56,875.00$ 64,400.00$
133,100.00$ 42,900.00$
1,000.00$ 1,000.00$ 500.00$ 500.00$
121.00$ 39.00$
81.25$ 92.00$
31.00$ 34.00$
4.00$ 3.60$
3.50$ 1.30$
2/14/2017 Page 10 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
15101-0000 Line A0020 ALL LPSM
15201-0000 Line A0040 ALL LPSM
15215-3000 Line A0060 2 EACH
15301-0000 Line A0080 ALL LPSM
15401-0000 Line A0100 ALL LPSM
15501-0000 Line A0120 ALL LPSM
15705-0100 Line A0140 1,310 LNFT
15705-1400 Line A0160 60 LNFT
15706-0200 Line A0180 25 EACH
15802-0000 Line A0200 ALL LPSM
20101-0000 Line A0220 3.1 ACRE
20220-1000 Line A0240 20 EACH
20301-0200 Line A0260 40 EACH
MOBILIZATION
CONSTRUCTION SURVEY AND STAKING
SURVEY AND STAKING, DRAINAGE STRUCTURE
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, FIBER ROLL
SOIL EROSION CONTROL, CHECK DAM
WATERING FOR DUST CONTROL
CLEARING AND GRUBBING
REMOVAL, INDIVIDUAL TREE
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
REMOVAL OF BOULDER
CONTRACTOR QUALITY CONTROL
5.9% 2,417,194.00$ 9.9% 2,509,050.10$
Unit Price Amount Unit Price Amount
275,000.00$ 240,000.00$
70,000.00$ 46,000.00$
20,000.00$ 3,000.00$
25,000.00$ 82,000.00$
105,000.00$ 91,000.00$
34,000.00$ 4,500.00$
8,253.00$ 10,152.50$
600.00$ 1,170.00$
5,625.00$ 3,800.00$
90,000.00$ 79,000.00$
11,904.00$ 40,597.60$
16,500.00$ 6,060.00$
1,480.00$ 8,740.00$ 37.00$ 218.50$
825.00$ 303.00$
3,840.00$ 13,096.00$
90,000.00$ 79,000.00$
225.00$ 152.00$
10.00$ 19.50$
6.30$ 7.75$
34,000.00$ 4,500.00$
105,000.00$ 91,000.00$
240,000.00$
70,000.00$ 46,000.00$
10,000.00$ 1,500.00$
Tikigaq Dig It Construction
275,000.00$
25,000.00$ 82,000.00$
2/14/2017 Page 11 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
20301-0700 Line A0280 20 EACH
20301-1900 Line A0300 2 EACH
20301-2400 Line A0320 5 EACH
20302-1200 Line A0340 1,200 LNFT
20302-1300 Line A0360 440 LNFT
20401-0000 Line A0380 4,100 CUYD
20420-0000 Line A0400 23,800 CUYD
20720-0300 Line A0420 24,500 SQYD
25101-2200 Line A0440 10 CUYD
30202-2000 Line A0460 3,600 TON
40301-0100 Line A0480 1,420 TON
41102-1000 Line A0500 6,500 SQYD
41105-0000 Line A0520 10 TON
REMOVAL OF SIGN
REMOVAL OF GUARDRAIL
REMOVAL OF GUARDRAIL, CONCRETE BARRIER
PRIME COAT, METHOD 1
BLOTTER
ROADWAY EXCAVATION
EMBANKMENT CONSTRUCTION (RSS)
REINFORCEMENT GEOSYNTHETIC, TYPE 3
PLACED RIPRAP, METHOD B, CLASS 2
ROADWAY AGGREGATE, METHOD 2
ASPHALT CONCRETE PAVEMENT, TYPE 1
REMOVAL OF DELINEATOR
REMOVAL OF PIPE CULVERT
5.9% 2,417,194.00$ 9.9% 2,509,050.10$
Unit Price Amount Unit Price Amount
Tikigaq Dig It Construction
260.00$ 600.00$
4,000.00$ 1,034.00$
800.00$ 805.00$
7,380.00$ 9,180.00$
4,950.00$ 4,400.00$
45,510.00$ 202,950.00$
714,000.00$ 868,700.00$
111,720.00$ 87,955.00$
1,570.00$ 2,500.00$
151,632.00$ 126,000.00$
206,255.00$ 181,760.00$
10,010.00$ 8,125.00$
3,590.00$ 1,500.00$ 359.00$ 150.00$
1.54$ 1.25$
145.25$ 128.00$
42.12$ 35.00$
157.00$ 250.00$
4.56$ 3.59$
30.00$ 36.50$
11.10$ 49.50$
11.25$ 10.00$
6.15$ 7.65$
160.00$ 161.00$
2,000.00$ 517.00$
13.00$ 30.00$
2/14/2017 Page 12 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
41201-0000 Line A0540 3 TON
60201-0800 Line A0560 205 LNFT
60210-0800 Line A0580 4 EACH
61701-4500 Line A0600 1,313 LNFT
61702-1500 Line A0620 2 EACH
62201-0200 Line A0640 10 HOUR
62201-0550 Line A0660 10 HOUR
62201-0950 Line A0680 10 HOUR
62201-2850 Line A0700 10 HOUR
62201-3350 Line A0720 10 HOUR
62301-0000 Line A0740 40 HOUR
62302-1000 Line A0760 20 HOUR
62302-1100 Line A0780 20 HOUR
TACK COAT
24-INCH PIPE CULVERT
END SECTION FOR 24-INCH PIPE CULVERT
GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STE
GENERAL LABOR
SPECIAL LABOR, HIRED TECHNICAL SERVICES
SPECIAL LABOR, HIRED SURVEY SERVICES
TERMINAL SECTION, TYPE MGS TANGENT
DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACIT
BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RA
WHEEL LOADER, 3 CUBIC YARD MINIMUM RATE
MOTOR GRADER, 12 FOOT MINIMUM BLADE
HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMU
5.9% 2,417,194.00$ 9.9% 2,509,050.10$
Unit Price Amount Unit Price Amount
Tikigaq Dig It Construction
3,600.00$ 4,800.00$
32,390.00$ 20,295.00$
1,440.00$ 1,400.00$
73,528.00$ 55,146.00$
5,600.00$ 9,200.00$
1,350.00$ 1,250.00$
1,200.00$ 1,300.00$
1,750.00$ 1,400.00$
1,850.00$ 1,500.00$
1,600.00$ 1,400.00$
2,480.00$ 2,600.00$
3,240.00$ 2,600.00$
3,240.00$ 3,700.00$ 162.00$ 185.00$
162.00$ 130.00$
62.00$ 65.00$
160.00$ 140.00$
185.00$ 150.00$
175.00$ 140.00$
120.00$ 130.00$
135.00$ 125.00$
2,800.00$ 4,600.00$
56.00$ 42.00$
360.00$ 350.00$
158.00$ 99.00$
1,200.00$ 1,600.00$
2/14/2017 Page 13 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
62401-0300 Line A0800 2,280 SQYD
62405-0300 Line A0820 8,200 SQYD
62511-2000 Line A0840 8,200 SQYD
62516-2000 Line A0860 4,600 SQYD
62901-1100 Line A0880 2,750 SQYD
63301-0000 Line A0900 4 EACH
63308-2000 Line A0920 4 EACH
63402-0300 Line A0940 2.7 MILE
63501-2000 Line A0960 ALL LPSM
63502-0700 Line A0980 50 EACH
63502-1300 Line A1000 100 EACH
63502-1600 Line A1020 4 EACH
63503-0400 Line A1040 1,100 LNFT
TEMPORARY TRAFFIC CONTROL, CONE
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGH
TEMPORARY TRAFFIC CONTROL, CONCRETE BAR
MULCHING, HYDRAULIC METHOD
ROLLED EROSION CONTROL PRODUCT, TYPE 4
SIGN SYSTEM
OBJECT MARKER, TYPE 2
PAVEMENT MARKINGS, TYPE B, SOLID
TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNA
FURNISHING AND PLACING TOPSOIL, 4-INCH D
PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
SEEDING, HYDRAULIC METHOD
5.9% 2,417,194.00$ 9.9% 2,509,050.10$
Unit Price Amount Unit Price Amount
Tikigaq Dig It Construction
31,464.00$ 50,160.00$
65,600.00$ 49,200.00$
30,012.00$ 5,740.00$
16,192.00$ 4,370.00$
18,012.50$ 14,437.50$
1,720.00$ 2,800.00$
528.00$ 700.00$
5,670.00$ 5,440.50$
27,700.00$ 9,000.00$
1,250.00$ 1,400.00$
10,000.00$ 5,500.00$
192.00$ 600.00$
69,300.00$ 35,200.00$ 63.00$ 32.00$
48.00$ 150.00$
100.00$ 55.00$
25.00$ 28.00$
27,700.00$ 9,000.00$
2,100.00$ 2,015.00$
132.00$ 175.00$
430.00$ 700.00$
6.55$ 5.25$
3.52$ 0.95$
3.66$ 0.70$
8.00$ 6.00$
13.80$ 22.00$
2/14/2017 Page 14 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
63503-0700 Line A1060 1,736 LNFT
63503-1000 Line A1080 2,000 LNFT
63504-1000 Line A1100 165 SQFT
63506-0500 Line A1120 700 HOUR
63610-2800 Line A1140 1,100 LNFT
63621-1000 Line A1160 2 EACH
TEMPORARY TRAFFIC CONTROL, CONSTRUCTIO
TEMPORARY TRAFFIC CONTROL, FLAGGER
CONDUIT, 4-INCH, PVC
UTILITY BOX, PULLBOX
TEMPORARY TRAFFIC CONTROL, PAVEMENT MAR
TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
5.9% 2,417,194.00$ 9.9% 2,509,050.10$
Unit Price Amount Unit Price Amount
Tikigaq Dig It Construction
4,340.00$ 1,302.00$
6,600.00$ 11,000.00$
5,362.50$ 5,280.00$
43,400.00$ 56,000.00$
20,570.00$ 31,900.00$
974.00$ 900.00$ 487.00$ 450.00$
18.70$ 29.00$
62.00$ 80.00$
32.50$ 32.00$
3.30$ 5.50$
2.50$ 0.75$
2/14/2017 Page 15 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
15101-0000 Line A0020 ALL LPSM
15201-0000 Line A0040 ALL LPSM
15215-3000 Line A0060 2 EACH
15301-0000 Line A0080 ALL LPSM
15401-0000 Line A0100 ALL LPSM
15501-0000 Line A0120 ALL LPSM
15705-0100 Line A0140 1,310 LNFT
15705-1400 Line A0160 60 LNFT
15706-0200 Line A0180 25 EACH
15802-0000 Line A0200 ALL LPSM
20101-0000 Line A0220 3.1 ACRE
20220-1000 Line A0240 20 EACH
20301-0200 Line A0260 40 EACH
MOBILIZATION
CONSTRUCTION SURVEY AND STAKING
SURVEY AND STAKING, DRAINAGE STRUCTURE
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, FIBER ROLL
SOIL EROSION CONTROL, CHECK DAM
WATERING FOR DUST CONTROL
CLEARING AND GRUBBING
REMOVAL, INDIVIDUAL TREE
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
REMOVAL OF BOULDER
CONTRACTOR QUALITY CONTROL
32.4% 3,021,522.09$ 33.0% 3,036,470.00$
Unit Price Amount Unit Price Amount
282,242.34$ 304,585.00$
69,468.08$ 10.00$
2,000.00$ 2,000.00$
152,453.08$ 65,000.00$
138,206.08$ 57,000.00$
62,323.08$ 5,000.00$
6,733.40$ 11,790.00$
406.80$ 780.00$
5,441.50$ 2,125.00$
90,123.08$ 30,000.00$
46,825.19$ 26,350.00$
11,810.00$ 13,500.00$
3,713.60$ 19,000.00$ 92.84$ 475.00$
590.50$ 675.00$
15,104.90$ 8,500.00$
90,123.08$ 30,000.00$
217.66$ 85.00$
6.78$ 13.00$
5.14$ 9.00$
62,323.08$ 5,000.00$
138,206.08$ 57,000.00$
282,242.34$ 304,585.00$
69,468.08$ 10.00$
1,000.00$ 1,000.00$
McCullough Construction Steelhead Constructors
152,453.08$ 65,000.00$
2/14/2017 Page 16 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
20301-0700 Line A0280 20 EACH
20301-1900 Line A0300 2 EACH
20301-2400 Line A0320 5 EACH
20302-1200 Line A0340 1,200 LNFT
20302-1300 Line A0360 440 LNFT
20401-0000 Line A0380 4,100 CUYD
20420-0000 Line A0400 23,800 CUYD
20720-0300 Line A0420 24,500 SQYD
25101-2200 Line A0440 10 CUYD
30202-2000 Line A0460 3,600 TON
40301-0100 Line A0480 1,420 TON
41102-1000 Line A0500 6,500 SQYD
41105-0000 Line A0520 10 TON
REMOVAL OF SIGN
REMOVAL OF GUARDRAIL
REMOVAL OF GUARDRAIL, CONCRETE BARRIER
PRIME COAT, METHOD 1
BLOTTER
ROADWAY EXCAVATION
EMBANKMENT CONSTRUCTION (RSS)
REINFORCEMENT GEOSYNTHETIC, TYPE 3
PLACED RIPRAP, METHOD B, CLASS 2
ROADWAY AGGREGATE, METHOD 2
ASPHALT CONCRETE PAVEMENT, TYPE 1
REMOVAL OF DELINEATOR
REMOVAL OF PIPE CULVERT
32.4% 3,021,522.09$ 33.0% 3,036,470.00$
Unit Price Amount Unit Price Amount
McCullough Construction Steelhead Constructors
315.20$ 240.00$
5,069.88$ 2,400.00$
688.00$ 625.00$
7,452.00$ 8,400.00$
6,305.20$ 3,080.00$
153,217.00$ 86,100.00$
929,152.00$ 1,594,600.00$
97,755.00$ 53,900.00$
1,470.10$ 1,750.00$
177,372.00$ 136,800.00$
253,640.40$ 215,840.00$
4,875.00$ 8,775.00$
2,500.00$ 4,000.00$ 250.00$ 400.00$
0.75$ 1.35$
178.62$ 152.00$
49.27$ 38.00$
147.01$ 175.00$
3.99$ 2.20$
39.04$ 67.00$
37.37$ 21.00$
14.33$ 7.00$
6.21$ 7.00$
137.60$ 125.00$
2,534.94$ 1,200.00$
15.76$ 12.00$
2/14/2017 Page 17 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
41201-0000 Line A0540 3 TON
60201-0800 Line A0560 205 LNFT
60210-0800 Line A0580 4 EACH
61701-4500 Line A0600 1,313 LNFT
61702-1500 Line A0620 2 EACH
62201-0200 Line A0640 10 HOUR
62201-0550 Line A0660 10 HOUR
62201-0950 Line A0680 10 HOUR
62201-2850 Line A0700 10 HOUR
62201-3350 Line A0720 10 HOUR
62301-0000 Line A0740 40 HOUR
62302-1000 Line A0760 20 HOUR
62302-1100 Line A0780 20 HOUR
TACK COAT
24-INCH PIPE CULVERT
END SECTION FOR 24-INCH PIPE CULVERT
GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STE
GENERAL LABOR
SPECIAL LABOR, HIRED TECHNICAL SERVICES
SPECIAL LABOR, HIRED SURVEY SERVICES
TERMINAL SECTION, TYPE MGS TANGENT
DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACIT
BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RA
WHEEL LOADER, 3 CUBIC YARD MINIMUM RATE
MOTOR GRADER, 12 FOOT MINIMUM BLADE
HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMU
32.4% 3,021,522.09$ 33.0% 3,036,470.00$
Unit Price Amount Unit Price Amount
McCullough Construction Steelhead Constructors
3,600.00$ 2,325.00$
21,197.00$ 29,725.00$
1,765.52$ 3,000.00$
54,568.28$ 49,894.00$
8,000.00$ 8,400.00$
1,400.00$ 1,300.00$
1,450.00$ 1,400.00$
1,750.00$ 1,900.00$
1,750.00$ 2,000.00$
2,000.00$ 2,100.00$
3,600.00$ 2,800.00$
3,500.00$ 3,000.00$
3,500.00$ 4,500.00$ 175.00$ 225.00$
175.00$ 150.00$
90.00$ 70.00$
200.00$ 210.00$
175.00$ 200.00$
175.00$ 190.00$
145.00$ 140.00$
140.00$ 130.00$
4,000.00$ 4,200.00$
41.56$ 38.00$
441.38$ 750.00$
103.40$ 145.00$
1,200.00$ 775.00$
2/14/2017 Page 18 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
62401-0300 Line A0800 2,280 SQYD
62405-0300 Line A0820 8,200 SQYD
62511-2000 Line A0840 8,200 SQYD
62516-2000 Line A0860 4,600 SQYD
62901-1100 Line A0880 2,750 SQYD
63301-0000 Line A0900 4 EACH
63308-2000 Line A0920 4 EACH
63402-0300 Line A0940 2.7 MILE
63501-2000 Line A0960 ALL LPSM
63502-0700 Line A0980 50 EACH
63502-1300 Line A1000 100 EACH
63502-1600 Line A1020 4 EACH
63503-0400 Line A1040 1,100 LNFT
TEMPORARY TRAFFIC CONTROL, CONE
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGH
TEMPORARY TRAFFIC CONTROL, CONCRETE BAR
MULCHING, HYDRAULIC METHOD
ROLLED EROSION CONTROL PRODUCT, TYPE 4
SIGN SYSTEM
OBJECT MARKER, TYPE 2
PAVEMENT MARKINGS, TYPE B, SOLID
TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNA
FURNISHING AND PLACING TOPSOIL, 4-INCH D
PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
SEEDING, HYDRAULIC METHOD
32.4% 3,021,522.09$ 33.0% 3,036,470.00$
Unit Price Amount Unit Price Amount
McCullough Construction Steelhead Constructors
22,366.80$ 14,820.00$
34,768.00$ 28,700.00$
10,250.00$ 7,790.00$
6,900.00$ 3,450.00$
13,750.00$ 13,750.00$
3,030.00$ 2,000.00$
726.00$ 400.00$
7,385.01$ 4,860.00$
105,723.07$ 35,000.00$
2,160.00$ 1,000.00$
5,400.00$ 7,500.00$
420.20$ 800.00$
57,541.00$ 41,800.00$ 52.31$ 38.00$
105.05$ 200.00$
54.00$ 75.00$
43.20$ 20.00$
105,723.07$ 35,000.00$
2,735.19$ 1,800.00$
181.50$ 100.00$
757.50$ 500.00$
5.00$ 5.00$
1.50$ 0.75$
1.25$ 0.95$
4.24$ 3.50$
9.81$ 6.50$
2/14/2017 Page 19 of 20
Project No: CA FLAP PLU CR411(1)
Project Name: Bucks Lake Road Slope Stabilization CQ = "Contract Quantity"
Item No. Quantity Unit
63503-0700 Line A1060 1,736 LNFT
63503-1000 Line A1080 2,000 LNFT
63504-1000 Line A1100 165 SQFT
63506-0500 Line A1120 700 HOUR
63610-2800 Line A1140 1,100 LNFT
63621-1000 Line A1160 2 EACH
TEMPORARY TRAFFIC CONTROL, CONSTRUCTIO
TEMPORARY TRAFFIC CONTROL, FLAGGER
CONDUIT, 4-INCH, PVC
UTILITY BOX, PULLBOX
TEMPORARY TRAFFIC CONTROL, PAVEMENT MAR
TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
32.4% 3,021,522.09$ 33.0% 3,036,470.00$
Unit Price Amount Unit Price Amount
McCullough Construction Steelhead Constructors
6,510.00$ 3,906.00$
5,900.00$ 15,000.00$
7,174.20$ 4,950.00$
46,039.00$ 52,500.00$
64,240.00$ 30,250.00$
1,600.00$ 2,000.00$ 800.00$ 1,000.00$
58.40$ 27.50$
65.77$ 75.00$
43.48$ 30.00$
2.95$ 7.50$
3.75$ 2.25$
2/14/2017 Page 20 of 20