WY FLAP 23-154(1), Fremont Lake Road 5/14/2015 DTFH6814B00023 Bid Amount
Contractor Schedule A Option X Option Y Total Bid Amount 10% factor Adjusted Bid Amount American Civil Constructors (LBC) $9,553,919.00 $144,180.00 $260,350.00 $9,958,449.00 $995,844.90 $10,954,293.90 Rafter H Construction (SBC, HUBZone) $7,725,203.88 $210,550.00 $378,135.00 $8,313,888.88 $8,313,888.88 Knife River Corporation (LBC) $10,939,502.00 $104,955.00 $214,744.00 $11,259,201.00 $1,125,920.10 $12,385,121.10 Oftedal Construction (LBC) $7,129,052.30 $164,614.00 $291,217.00 $7,584,883.30 $758,488.33 $8,343,371.63 Wilkinson Construction (SBC) $9,664,412.10 $248,480.00 $397,871.00 $10,310,763.10 $10,310,763.10 Hooker Creek (SBC, HUBZone) $7,426,006.00 $146,620.00 $288,881.00 $7,861,507.00 $7,861,507.00 High Country Construction (SBC) $9,262,801.50 $199,540.00 $363,360.00 $9,825,701.50 $9,825,701.50
Tabulation of Bids Report Date: 05/14/15
1 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Contractor Responsive?
Engineer's Estimate
AMERICAN CIVIL CONSTRUCTORS
HIGH COUNTRY CONSTRUCTION, INC.
Hooker Creek, Inc
KNIFE RIVER - Northwest
Oftedal Construction, Inc
Rafter H Construction
WILKINSON CONSTRUCTION CO., INC.
Base Schedule A
$6,512,957.50
$9,553,919.00
$9,262,801.50
$7,426,006.00
$10,939,502.00
$7,129,052.30
$7,725,203.88
$9,664,412.10
Option: X
$145,000.00
$144,180.00
$199,540.00
$146,620.00
$104,955.00
$164,614.00
$210,550.00
$248,480.00
Option: Y
$309,000.00
$260,350.00
$363,360.00
$288,881.00
$214,744.00
$291,217.00
$378,135.00
$397,871.00
Contractor Responsive?
Engineer's Estimate
AMERICAN CIVIL CONSTRUCTORS
HIGH COUNTRY CONSTRUCTION, INC.
Hooker Creek, Inc
KNIFE RIVER - Northwest
Oftedal Construction, Inc
Rafter H Construction
2 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
WILKINSON CONSTRUCTION CO., INC.
Total Base Schedule A and Option(s): X
$6,657,957.50
$9,698,099.00
$9,462,341.50
$7,572,626.00
$11,044,457.00
$7,293,666.30
$7,935,753.88
3 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
$9,912,892.10
Total Base Schedule A and Option(s): XY
$6,966,957.50
$9,958,449.00
$9,825,701.50
$7,861,507.00
$11,259,201.00
$7,584,883.30
$8,313,888.88
4 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
$10,310,763.10
Total Base Schedule A and Option(s): Y
$6,821,957.50
$9,814,269.00
$9,626,161.50
$7,714,887.00
$11,154,246.00
$7,420,269.30
$8,103,338.88
5 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
$10,062,283.10
6 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Solcitation No: DTFH6814B00023
Division: Central Federal Lands
State: WY County: Sublette
Federal Land: Opened at: Lakewood
Opened by: Joe Wilson
Date: 05/14/15
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Oftedal Construction, Inc $7,129,052.30 P.O. Box 400 Miles City, MT 59301
Hooker Creek, Inc $7,426,006.00 1015 Anderson Street Red Bluff, CA 96080
Rafter H Construction $7,725,203.88 207 Georgetown Drive Rexburg, ID 83440
HIGH COUNTRY CONSTRUCTION, INC. $9,262,801.50
P.O. BOX 930
LANDER, WY 82520
AMERICAN CIVIL CONSTRUCTORS $9,553,919.00
4901 SOUTH WINDERMERE STREET
LITTLETON, CO 80120
WILKINSON CONSTRUCTION CO., INC. $9,664,412.10
1200 EAST 100 SOUTH
MORGAN , UT 84050
KNIFE RIVER - Northwest $10,939,502.00 195 East 600 South American Fork, UT 84003
Engineer's Estimate $6,512,957.50
7 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0001 15101-0000 MOBILIZATION
Oftedal Construction, Inc Lump Sum $746,800.00 Hooker Creek, Inc Lump Sum $700,000.00 Rafter H Construction Lump Sum $1,100,000.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $950,000.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $894,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $565,000.00 KNIFE RIVER - Northwest Lump Sum $2,030,000.00 Engineer's Estimate ALL LPSM Lump Sum $483,962.50
A0051 15206-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING STAKE
Oftedal Construction, Inc $74.00 $27,091.40 Hooker Creek, Inc $70.00 $25,627.00 Rafter H Construction $50.00 $18,305.00
HIGH COUNTRY CONSTRUCTION, INC. $110.00 $40,271.00
AMERICAN CIVIL CONSTRUCTORS $230.00 $84,203.00
WILKINSON CONSTRUCTION CO., INC. $231.00 $84,569.10
KNIFE RIVER - Northwest $180.00 $65,898.00 Engineer's Estimate 366.1 STA $100.00 $36,610.00
A0101 15215-1000 SURVEY AND STAKING, APPROACH ROAD
Oftedal Construction, Inc $497.00 $4,970.00 Hooker Creek, Inc $465.00 $4,650.00 Rafter H Construction $400.00 $4,000.00
HIGH COUNTRY CONSTRUCTION, INC. $1,005.00 $10,050.00
AMERICAN CIVIL CONSTRUCTORS $750.00 $7,500.00
WILKINSON CONSTRUCTION CO., INC. $800.00 $8,000.00
KNIFE RIVER - Northwest $650.00 $6,500.00 Engineer's Estimate 10 EACH $100.00 $1,000.00
A0151 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE
Oftedal Construction, Inc $497.00 $15,904.00 Hooker Creek, Inc $465.00 $14,880.00 Rafter H Construction $400.00 $12,800.00
HIGH COUNTRY CONSTRUCTION, INC. $100.00 $3,200.00
AMERICAN CIVIL CONSTRUCTORS $450.00 $14,400.00
WILKINSON CONSTRUCTION CO., INC. $600.00 $19,200.00
KNIFE RIVER - Northwest $370.00 $11,840.00 Engineer's Estimate 32 EACH $150.00 $4,800.00
8 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0201 15215-7000 SURVEY AND STAKING, PARKING AREA
Oftedal Construction, Inc $1,240.00 $9,920.00 Hooker Creek, Inc $1,150.00 $9,200.00 Rafter H Construction $1,000.00 $8,000.00
HIGH COUNTRY CONSTRUCTION, INC. $905.00 $7,240.00
AMERICAN CIVIL CONSTRUCTORS $465.00 $3,720.00
WILKINSON CONSTRUCTION CO., INC. $625.00 $5,000.00
KNIFE RIVER - Northwest $380.00 $3,040.00 Engineer's Estimate 8 EACH $200.00 $1,600.00
A0251 15216-2000 SURVEY AND STAKING, GRADE FINISHING STAKES
Oftedal Construction, Inc $74.00 $54,182.80 Hooker Creek, Inc $65.00 $47,593.00 Rafter H Construction $20.00 $14,644.00
HIGH COUNTRY CONSTRUCTION, INC. $30.00 $21,966.00
AMERICAN CIVIL CONSTRUCTORS $80.00 $58,576.00
WILKINSON CONSTRUCTION CO., INC. $65.00 $47,593.00
KNIFE RIVER - Northwest $50.00 $36,610.00 Engineer's Estimate 732.2 STA $100.00 $73,220.00
A0301 15301-0000 CONTRACTOR QUALITY CONTROL
Oftedal Construction, Inc Lump Sum $100,000.00 Hooker Creek, Inc Lump Sum $150,000.00 Rafter H Construction Lump Sum $355,782.38 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $200,000.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $228,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $80,000.00 KNIFE RIVER - Northwest Lump Sum $350,000.00 Engineer's Estimate ALL LPSM Lump Sum $110,000.00
A0351 15401-0000 CONTRACTOR TESTING
Oftedal Construction, Inc Lump Sum $130,000.00 Hooker Creek, Inc Lump Sum $180,000.00 Rafter H Construction Lump Sum $70,000.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $200,000.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $180,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $465,000.00 KNIFE RIVER - Northwest Lump Sum $300,000.00 Engineer's Estimate ALL LPSM Lump Sum $110,000.00
9 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0401 15501-0000 CONSTRUCTION SCHEDULE
Oftedal Construction, Inc Lump Sum $10,000.00 Hooker Creek, Inc Lump Sum $12,000.00 Rafter H Construction Lump Sum $25,280.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $43,000.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $25,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $45,000.00 KNIFE RIVER - Northwest Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $15,000.00
A0451 15702-1000 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL
Oftedal Construction, Inc Lump Sum $10,000.00 Hooker Creek, Inc Lump Sum $17,000.00 Rafter H Construction Lump Sum $4,500.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $30,000.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $25,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $54,000.00 KNIFE RIVER - Northwest Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00
A0501 15705-0100 SOIL EROSION CONTROL, SILT FENCE
Oftedal Construction, Inc $5.90 $182,900.00 Hooker Creek, Inc $3.50 $108,500.00 Rafter H Construction $2.20 $68,200.00
HIGH COUNTRY CONSTRUCTION, INC. $4.00 $124,000.00
AMERICAN CIVIL CONSTRUCTORS $3.00 $93,000.00
WILKINSON CONSTRUCTION CO., INC. $4.00 $124,000.00
KNIFE RIVER - Northwest $3.00 $93,000.00 Engineer's Estimate 31,000 LNFT $2.00 $62,000.00
A0551 15706-0200 SOIL EROSION CONTROL, CHECK DAM (SEDIMENT LOG)
Oftedal Construction, Inc $67.00 $18,425.00 Hooker Creek, Inc $97.00 $26,675.00 Rafter H Construction $115.00 $31,625.00
HIGH COUNTRY CONSTRUCTION, INC. $120.00 $33,000.00
AMERICAN CIVIL CONSTRUCTORS $62.00 $17,050.00
WILKINSON CONSTRUCTION CO., INC. $200.00 $55,000.00
KNIFE RIVER - Northwest $115.00 $31,625.00 Engineer's Estimate 275 EACH $100.00 $27,500.00
10 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0601 15706-0200 SOIL EROSION CONTROL, CHECK DAM (RIPRAP)
Oftedal Construction, Inc $371.00 $40,810.00 Hooker Creek, Inc $82.00 $9,020.00 Rafter H Construction $430.00 $47,300.00
HIGH COUNTRY CONSTRUCTION, INC. $280.00 $30,800.00
AMERICAN CIVIL CONSTRUCTORS $250.00 $27,500.00
WILKINSON CONSTRUCTION CO., INC. $300.00 $33,000.00
KNIFE RIVER - Northwest $500.00 $55,000.00 Engineer's Estimate 110 EACH $200.00 $22,000.00
A0651 15706-1000 SOIL EROSION CONTROL, INLET PROTECTION (> 48-INCH CULVERT)
Oftedal Construction, Inc $266.00 $532.00 Hooker Creek, Inc $360.00 $720.00 Rafter H Construction $250.00 $500.00
HIGH COUNTRY CONSTRUCTION, INC. $600.00 $1,200.00
AMERICAN CIVIL CONSTRUCTORS $250.00 $500.00
WILKINSON CONSTRUCTION CO., INC. $2,000.00 $4,000.00
KNIFE RIVER - Northwest $200.00 $400.00 Engineer's Estimate 2 EACH $500.00 $1,000.00
A0701 15706-1000 SOIL EROSION CONTROL, INLET PROTECTION
Oftedal Construction, Inc $66.50 $4,256.00 Hooker Creek, Inc $220.00 $14,080.00 Rafter H Construction $250.00 $16,000.00
HIGH COUNTRY CONSTRUCTION, INC. $400.00 $25,600.00
AMERICAN CIVIL CONSTRUCTORS $250.00 $16,000.00
WILKINSON CONSTRUCTION CO., INC. $300.00 $19,200.00
KNIFE RIVER - Northwest $130.00 $8,320.00 Engineer's Estimate 64 EACH $200.00 $12,800.00
A0751 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION ENTRANCE
Oftedal Construction, Inc $2,190.00 $13,140.00 Hooker Creek, Inc $1,400.00 $8,400.00 Rafter H Construction $2,000.00 $12,000.00
HIGH COUNTRY CONSTRUCTION, INC. $5,000.00 $30,000.00
AMERICAN CIVIL CONSTRUCTORS $2,000.00 $12,000.00
WILKINSON CONSTRUCTION CO., INC. $3,500.00 $21,000.00
KNIFE RIVER - Northwest $1,500.00 $9,000.00 Engineer's Estimate 6 EACH $2,000.00 $12,000.00
11 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0801 15802-0000 WATERING FOR DUST CONTROL
Oftedal Construction, Inc Lump Sum $77,000.00 Hooker Creek, Inc Lump Sum $59,000.00 Rafter H Construction Lump Sum $25,000.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $115,000.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $200,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $400,000.00 KNIFE RIVER - Northwest Lump Sum $70,000.00 Engineer's Estimate ALL LPSM Lump Sum $80,000.00
A0851 20101-0000 CLEARING AND GRUBBING
Oftedal Construction, Inc $3,010.00 $216,720.00 Hooker Creek, Inc $3,900.00 $280,800.00 Rafter H Construction $2,000.00 $144,000.00
HIGH COUNTRY CONSTRUCTION, INC. $6,500.00 $468,000.00
AMERICAN CIVIL CONSTRUCTORS $1,500.00 $108,000.00
WILKINSON CONSTRUCTION CO., INC. $2,100.00 $151,200.00
KNIFE RIVER - Northwest $5,500.00 $396,000.00 Engineer's Estimate 72.0 ACRE $1,500.00 $108,000.00
A0901 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Oftedal Construction, Inc Lump Sum $50,000.00 Hooker Creek, Inc Lump Sum $22,000.00 Rafter H Construction Lump Sum $65,000.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $40,000.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $20,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $90,000.00 KNIFE RIVER - Northwest Lump Sum $100,000.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00
A0951 20401-0000 ROADWAY EXCAVATION
Oftedal Construction, Inc $9.50 $1,315,750.00 Hooker Creek, Inc $9.60 $1,329,600.00 Rafter H Construction $10.00 $1,385,000.00
HIGH COUNTRY CONSTRUCTION, INC. $16.00 $2,216,000.00
AMERICAN CIVIL CONSTRUCTORS $15.50 $2,146,750.00
WILKINSON CONSTRUCTION CO., INC. $8.05 $1,114,925.00
KNIFE RIVER - Northwest $17.00 $2,354,500.00 Engineer's Estimate 138,500 CUYD $8.00 $1,108,000.00
12 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1001 20441-0000 WASTE
Oftedal Construction, Inc $7.50 $198,750.00 Hooker Creek, Inc $7.35 $194,775.00 Rafter H Construction $15.00 $397,500.00
HIGH COUNTRY CONSTRUCTION, INC. $8.00 $212,000.00
AMERICAN CIVIL CONSTRUCTORS $10.00 $265,000.00
WILKINSON CONSTRUCTION CO., INC. $5.00 $132,500.00
KNIFE RIVER - Northwest $17.00 $450,500.00 Engineer's Estimate 26,500 CUYD $16.00 $424,000.00
A1051 21101-1000 ROADWAY OBLITERATION, METHOD 1
Oftedal Construction, Inc $7.80 $7,098.00 Hooker Creek, Inc $2.00 $1,820.00 Rafter H Construction $2.75 $2,502.50
HIGH COUNTRY CONSTRUCTION, INC. $8.00 $7,280.00
AMERICAN CIVIL CONSTRUCTORS $5.00 $4,550.00
WILKINSON CONSTRUCTION CO., INC. $3.00 $2,730.00
KNIFE RIVER - Northwest $5.00 $4,550.00 Engineer's Estimate 910 SQYD $10.00 $9,100.00
A1101 25101-2000 PLACED RIPRAP, CLASS 2
Oftedal Construction, Inc $75.00 $1,875.00 Hooker Creek, Inc $28.00 $700.00 Rafter H Construction $40.00 $1,000.00
HIGH COUNTRY CONSTRUCTION, INC. $150.00 $3,750.00
AMERICAN CIVIL CONSTRUCTORS $165.00 $4,125.00
WILKINSON CONSTRUCTION CO., INC. $100.00 $2,500.00
KNIFE RIVER - Northwest $150.00 $3,750.00 Engineer's Estimate 25 CUYD $150.00 $3,750.00
A1151 30101-0000 AGGREGATE BASE
Oftedal Construction, Inc $28.00 $435,400.00 Hooker Creek, Inc $34.00 $528,700.00 Rafter H Construction $21.00 $326,550.00
HIGH COUNTRY CONSTRUCTION, INC. $38.00 $590,900.00
AMERICAN CIVIL CONSTRUCTORS $30.00 $466,500.00
WILKINSON CONSTRUCTION CO., INC. $31.50 $489,825.00
KNIFE RIVER - Northwest $26.00 $404,300.00 Engineer's Estimate 15,550 TON $23.00 $357,650.00
13 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1251 30305-3000 PULVERIZING, 6-INCH DEPTH
Oftedal Construction, Inc $371.00 $135,823.10 Hooker Creek, Inc $670.00 $245,287.00 Rafter H Construction $500.00 $183,050.00
HIGH COUNTRY CONSTRUCTION, INC. $650.00 $237,965.00
AMERICAN CIVIL CONSTRUCTORS $300.00 $109,830.00
WILKINSON CONSTRUCTION CO., INC. $650.00 $237,965.00
KNIFE RIVER - Northwest $500.00 $183,050.00 Engineer's Estimate 366.1 STA $800.00 $292,880.00
A1301 30606-0000 MAGNESIUM CHLORIDE
Oftedal Construction, Inc $157.00 $43,960.00 Hooker Creek, Inc $260.00 $72,800.00 Rafter H Construction $180.00 $50,400.00
HIGH COUNTRY CONSTRUCTION, INC. $280.00 $78,400.00
AMERICAN CIVIL CONSTRUCTORS $250.00 $70,000.00
WILKINSON CONSTRUCTION CO., INC. $76.00 $21,280.00
KNIFE RIVER - Northwest $150.00 $42,000.00 Engineer's Estimate 280 TON $90.00 $25,200.00
A1351 40101-5600 SUPERPAVE PAVEMENT, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION
ESAL
Oftedal Construction, Inc $90.50 $1,991,000.00 Hooker Creek, Inc $93.40 $2,054,800.00 Rafter H Construction $77.10 $1,696,200.00
HIGH COUNTRY CONSTRUCTION, INC. $79.00 $1,738,000.00
AMERICAN CIVIL CONSTRUCTORS $122.00 $2,684,000.00
WILKINSON CONSTRUCTION CO., INC. $145.00 $3,190,000.00
KNIFE RIVER - Northwest $90.00 $1,980,000.00 Engineer's Estimate 22,000 TON $92.00 $2,024,000.00
A1451 40105-3000 ANTISTRIP ADDITIVE, TYPE 3
Oftedal Construction, Inc $262.00 $57,902.00 Hooker Creek, Inc $270.00 $59,670.00 Rafter H Construction $210.00 $46,410.00
HIGH COUNTRY CONSTRUCTION, INC. $210.00 $46,410.00
AMERICAN CIVIL CONSTRUCTORS $350.00 $77,350.00
WILKINSON CONSTRUCTION CO., INC. $350.00 $77,350.00
KNIFE RIVER - Northwest $275.00 $60,775.00 Engineer's Estimate 221 TON $200.00 $44,200.00
14 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1551 40920-1000 FOG SEAL, EMULSIFIED ASPHALT GRADE CSS-1 OR CSS-1H, SS-1 OR SS-1H
Oftedal Construction, Inc $346.00 $17,300.00 Hooker Creek, Inc $355.00 $17,750.00 Rafter H Construction $600.00 $30,000.00
HIGH COUNTRY CONSTRUCTION, INC. $605.00 $30,250.00
AMERICAN CIVIL CONSTRUCTORS $375.00 $18,750.00
WILKINSON CONSTRUCTION CO., INC. $600.00 $30,000.00
KNIFE RIVER - Northwest $600.00 $30,000.00 Engineer's Estimate 50 TON $700.00 $35,000.00
A1601 41201-1000 TACK COAT GRADE CSS-1, CSS-1H, SS-1, OR SS-1H
Oftedal Construction, Inc $607.00 $60,700.00 Hooker Creek, Inc $625.00 $62,500.00 Rafter H Construction $700.00 $70,000.00
HIGH COUNTRY CONSTRUCTION, INC. $665.00 $66,500.00
AMERICAN CIVIL CONSTRUCTORS $800.00 $80,000.00
WILKINSON CONSTRUCTION CO., INC. $600.00 $60,000.00
KNIFE RIVER - Northwest $650.00 $65,000.00 Engineer's Estimate 100 TON $800.00 $80,000.00
A1651 60201-0600 18-INCH PIPE CULVERT
Oftedal Construction, Inc $63.50 $57,150.00 Hooker Creek, Inc $110.00 $99,000.00 Rafter H Construction $40.00 $36,000.00
HIGH COUNTRY CONSTRUCTION, INC. $165.00 $148,500.00
AMERICAN CIVIL CONSTRUCTORS $125.00 $112,500.00
WILKINSON CONSTRUCTION CO., INC. $90.00 $81,000.00
KNIFE RIVER - Northwest $75.00 $67,500.00 Engineer's Estimate 900 LNFT $55.00 $49,500.00
A1701 60201-1400 60-INCH PIPE CULVERT
Oftedal Construction, Inc $248.00 $4,960.00 Hooker Creek, Inc $210.00 $4,200.00 Rafter H Construction $170.00 $3,400.00
HIGH COUNTRY CONSTRUCTION, INC. $500.00 $10,000.00
AMERICAN CIVIL CONSTRUCTORS $365.00 $7,300.00
WILKINSON CONSTRUCTION CO., INC. $280.00 $5,600.00
KNIFE RIVER - Northwest $400.00 $8,000.00 Engineer's Estimate 20 LNFT $115.00 $2,300.00
15 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1751 60202-1100 66-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
Oftedal Construction, Inc $507.00 $43,095.00 Hooker Creek, Inc $330.00 $28,050.00 Rafter H Construction $290.00 $24,650.00
HIGH COUNTRY CONSTRUCTION, INC. $525.00 $44,625.00
AMERICAN CIVIL CONSTRUCTORS $565.00 $48,025.00
WILKINSON CONSTRUCTION CO., INC. $450.00 $38,250.00
KNIFE RIVER - Northwest $300.00 $25,500.00 Engineer's Estimate 85 LNFT $165.00 $14,025.00
A1801 60211-1500 END SECTION FOR 66-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
Oftedal Construction, Inc $1,910.00 $3,820.00 Hooker Creek, Inc $3,000.00 $6,000.00 Rafter H Construction $2,500.00 $5,000.00
HIGH COUNTRY CONSTRUCTION, INC. $1,000.00 $2,000.00
AMERICAN CIVIL CONSTRUCTORS $4,200.00 $8,400.00
WILKINSON CONSTRUCTION CO., INC. $1,800.00 $3,600.00
KNIFE RIVER - Northwest $3,000.00 $6,000.00 Engineer's Estimate 2 EACH $2,000.00 $4,000.00
A1851 60704-0000 CLEANING CULVERT IN PLACE
Oftedal Construction, Inc $2,350.00 $2,350.00 Hooker Creek, Inc $520.00 $520.00 Rafter H Construction $2,800.00 $2,800.00
HIGH COUNTRY CONSTRUCTION, INC. $5,000.00 $5,000.00
AMERICAN CIVIL CONSTRUCTORS $3,800.00 $3,800.00
WILKINSON CONSTRUCTION CO., INC. $2,500.00 $2,500.00
KNIFE RIVER - Northwest $2,500.00 $2,500.00 Engineer's Estimate 1 EACH $2,500.00 $2,500.00
A1901 61701-2000 GUARDRAIL SYSTEM G4, TYPE 4, CLASS B WOOD POSTS
Oftedal Construction, Inc $27.00 $22,275.00 Hooker Creek, Inc $29.00 $23,925.00 Rafter H Construction $27.00 $22,275.00
HIGH COUNTRY CONSTRUCTION, INC. $26.50 $21,862.50
AMERICAN CIVIL CONSTRUCTORS $150.00 $123,750.00
WILKINSON CONSTRUCTION CO., INC. $157.00 $129,525.00
KNIFE RIVER - Northwest $28.00 $23,100.00 Engineer's Estimate 825 LNFT $30.00 $24,750.00
16 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1951 61702-0800 TERMINAL SECTION TYPE TANGENT
Oftedal Construction, Inc $2,570.00 $15,420.00 Hooker Creek, Inc $2,725.00 $16,350.00 Rafter H Construction $2,500.00 $15,000.00
HIGH COUNTRY CONSTRUCTION, INC. $3,000.00 $18,000.00
AMERICAN CIVIL CONSTRUCTORS $3,800.00 $22,800.00
WILKINSON CONSTRUCTION CO., INC. $4,100.00 $24,600.00
KNIFE RIVER - Northwest $2,600.00 $15,600.00 Engineer's Estimate 6 EACH $3,500.00 $21,000.00
A2001 61901-0600 FENCE, BARBED WIRE
Oftedal Construction, Inc $12.50 $1,125.00 Hooker Creek, Inc $18.00 $1,620.00 Rafter H Construction $25.00 $2,250.00
HIGH COUNTRY CONSTRUCTION, INC. $15.00 $1,350.00
AMERICAN CIVIL CONSTRUCTORS $6.00 $540.00
WILKINSON CONSTRUCTION CO., INC. $250.00 $22,500.00
KNIFE RIVER - Northwest $11.00 $990.00 Engineer's Estimate 90 LNFT $4.00 $360.00
A2051 61903-1100 CATTLE GUARD, 32 FEET
Oftedal Construction, Inc $8,130.00 $16,260.00 Hooker Creek, Inc $24,000.00 $48,000.00 Rafter H Construction $17,000.00 $34,000.00
HIGH COUNTRY CONSTRUCTION, INC. $22,500.00 $45,000.00
AMERICAN CIVIL CONSTRUCTORS $23,000.00 $46,000.00
WILKINSON CONSTRUCTION CO., INC. $35,000.00 $70,000.00
KNIFE RIVER - Northwest $45,000.00 $90,000.00 Engineer's Estimate 2 EACH $28,000.00 $56,000.00
A2101 62201-0300 DUMP TRUCK, 12 CUBIC YARD MINIMUM CAPACITY
Oftedal Construction, Inc $96.00 $3,840.00 Hooker Creek, Inc $120.00 $4,800.00 Rafter H Construction $110.00 $4,400.00
HIGH COUNTRY CONSTRUCTION, INC. $100.00 $4,000.00
AMERICAN CIVIL CONSTRUCTORS $100.00 $4,000.00
WILKINSON CONSTRUCTION CO., INC. $105.00 $4,200.00
KNIFE RIVER - Northwest $135.00 $5,400.00 Engineer's Estimate 40 HOUR $100.00 $4,000.00
17 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A2151 62201-0400 BACKHOE LOADER, 2 CUBIC F00T MINIMUM RATED CAPACITY BUCKET, 12-INCH WIDTH
Oftedal Construction, Inc $75.00 $3,000.00 Hooker Creek, Inc $78.00 $3,120.00 Rafter H Construction $130.00 $5,200.00
HIGH COUNTRY CONSTRUCTION, INC. $65.00 $2,600.00
AMERICAN CIVIL CONSTRUCTORS $90.00 $3,600.00
WILKINSON CONSTRUCTION CO., INC. $200.00 $8,000.00
KNIFE RIVER - Northwest $122.00 $4,880.00 Engineer's Estimate 40 HOUR $120.00 $4,800.00
A2201 62201-0900 WHEEL LOADER, 2 CUBIC YARD MINIMUM RATED CAPACITY
Oftedal Construction, Inc $97.00 $3,880.00 Hooker Creek, Inc $122.00 $4,880.00 Rafter H Construction $100.00 $4,000.00
HIGH COUNTRY CONSTRUCTION, INC. $120.00 $4,800.00
AMERICAN CIVIL CONSTRUCTORS $130.00 $5,200.00
WILKINSON CONSTRUCTION CO., INC. $200.00 $8,000.00
KNIFE RIVER - Northwest $156.00 $6,240.00 Engineer's Estimate 40 HOUR $165.00 $6,600.00
A2251 62201-1400 BULLDOZER, 250HP MINIMUM FLYWHEEL POWER
Oftedal Construction, Inc $240.00 $4,800.00 Hooker Creek, Inc $205.00 $4,100.00 Rafter H Construction $140.00 $2,800.00
HIGH COUNTRY CONSTRUCTION, INC. $180.00 $3,600.00
AMERICAN CIVIL CONSTRUCTORS $200.00 $4,000.00
WILKINSON CONSTRUCTION CO., INC. $500.00 $10,000.00
KNIFE RIVER - Northwest $251.00 $5,020.00 Engineer's Estimate 20 HOUR $200.00 $4,000.00
A2301 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
Oftedal Construction, Inc $110.00 $4,400.00 Hooker Creek, Inc $137.00 $5,480.00 Rafter H Construction $150.00 $6,000.00
HIGH COUNTRY CONSTRUCTION, INC. $120.00 $4,800.00
AMERICAN CIVIL CONSTRUCTORS $150.00 $6,000.00
WILKINSON CONSTRUCTION CO., INC. $300.00 $12,000.00
KNIFE RIVER - Northwest $153.00 $6,120.00 Engineer's Estimate 40 HOUR $170.00 $6,800.00
18 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A2351 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY
Oftedal Construction, Inc $120.00 $3,600.00 Hooker Creek, Inc $140.00 $4,200.00 Rafter H Construction $130.00 $3,900.00
HIGH COUNTRY CONSTRUCTION, INC. $125.00 $3,750.00
AMERICAN CIVIL CONSTRUCTORS $200.00 $6,000.00
WILKINSON CONSTRUCTION CO., INC. $200.00 $6,000.00
KNIFE RIVER - Northwest $174.00 $5,220.00 Engineer's Estimate 30 HOUR $150.00 $4,500.00
A2401 62301-0000 GENERAL LABOR
Oftedal Construction, Inc $70.00 $5,600.00 Hooker Creek, Inc $28.00 $2,240.00 Rafter H Construction $60.00 $4,800.00
HIGH COUNTRY CONSTRUCTION, INC. $50.00 $4,000.00
AMERICAN CIVIL CONSTRUCTORS $25.00 $2,000.00
WILKINSON CONSTRUCTION CO., INC. $100.00 $8,000.00
KNIFE RIVER - Northwest $52.00 $4,160.00 Engineer's Estimate 80 HOUR $60.00 $4,800.00
A2451 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
Oftedal Construction, Inc $185.00 $14,800.00 Hooker Creek, Inc $185.00 $14,800.00 Rafter H Construction $90.00 $7,200.00
HIGH COUNTRY CONSTRUCTION, INC. $100.00 $8,000.00
AMERICAN CIVIL CONSTRUCTORS $125.00 $10,000.00
WILKINSON CONSTRUCTION CO., INC. $150.00 $12,000.00
KNIFE RIVER - Northwest $106.00 $8,480.00 Engineer's Estimate 80 HOUR $170.00 $13,600.00
A2501 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
Oftedal Construction, Inc $220.00 $17,600.00 Hooker Creek, Inc $185.00 $14,800.00 Rafter H Construction $190.00 $15,200.00
HIGH COUNTRY CONSTRUCTION, INC. $185.00 $14,800.00
AMERICAN CIVIL CONSTRUCTORS $95.00 $7,600.00
WILKINSON CONSTRUCTION CO., INC. $300.00 $24,000.00
KNIFE RIVER - Northwest $160.00 $12,800.00 Engineer's Estimate 80 HOUR $170.00 $13,600.00
19 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A2551 62407-0000 PLACING CONSERVED TOPSOIL
Oftedal Construction, Inc $2.75 $116,875.00 Hooker Creek, Inc $2.00 $85,000.00 Rafter H Construction $2.30 $97,750.00
HIGH COUNTRY CONSTRUCTION, INC. $4.30 $182,750.00
AMERICAN CIVIL CONSTRUCTORS $6.00 $255,000.00
WILKINSON CONSTRUCTION CO., INC. $9.50 $403,750.00
KNIFE RIVER - Northwest $14.00 $595,000.00 Engineer's Estimate 42,500 CUYD $7.50 $318,750.00
A2601 62510-2000 SEEDING, HYDRAULIC METHOD
Oftedal Construction, Inc $607.00 $38,241.00 Hooker Creek, Inc $660.00 $41,580.00 Rafter H Construction $1,800.00 $113,400.00
HIGH COUNTRY CONSTRUCTION, INC. $590.00 $37,170.00
AMERICAN CIVIL CONSTRUCTORS $1,250.00 $78,750.00
WILKINSON CONSTRUCTION CO., INC. $4,000.00 $252,000.00
KNIFE RIVER - Northwest $600.00 $37,800.00 Engineer's Estimate 63.0 ACRE $900.00 $56,700.00
A2651 62515-2000 MULCHING, HYDRAULIC METHOD
Oftedal Construction, Inc $3,520.00 $221,760.00 Hooker Creek, Inc $3,800.00 $239,400.00 Rafter H Construction $1,800.00 $113,400.00
HIGH COUNTRY CONSTRUCTION, INC. $3,400.00 $214,200.00
AMERICAN CIVIL CONSTRUCTORS $2,700.00 $170,100.00
WILKINSON CONSTRUCTION CO., INC. $4,000.00 $252,000.00
KNIFE RIVER - Northwest $3,400.00 $214,200.00 Engineer's Estimate 63.0 ACRE $850.00 $53,550.00
A2701 63301-0000 SIGN SYSTEM
Oftedal Construction, Inc $812.00 $40,600.00 Hooker Creek, Inc $380.00 $19,000.00 Rafter H Construction $800.00 $40,000.00
HIGH COUNTRY CONSTRUCTION, INC. $780.00 $39,000.00
AMERICAN CIVIL CONSTRUCTORS $1,100.00 $55,000.00
WILKINSON CONSTRUCTION CO., INC. $465.00 $23,250.00
KNIFE RIVER - Northwest $750.00 $37,500.00 Engineer's Estimate 50 EACH $470.00 $23,500.00
20 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A2751 63308-0000 OBJECT MARKER
Oftedal Construction, Inc $628.00 $7,536.00 Hooker Creek, Inc $60.00 $720.00 Rafter H Construction $600.00 $7,200.00
HIGH COUNTRY CONSTRUCTION, INC. $600.00 $7,200.00
AMERICAN CIVIL CONSTRUCTORS $800.00 $9,600.00
WILKINSON CONSTRUCTION CO., INC. $150.00 $1,800.00
KNIFE RIVER - Northwest $650.00 $7,800.00 Engineer's Estimate 12 EACH $100.00 $1,200.00
A2801 63309-0000 DELINEATOR
Oftedal Construction, Inc $115.00 $66,700.00 Hooker Creek, Inc $76.00 $44,080.00 Rafter H Construction $110.00 $63,800.00
HIGH COUNTRY CONSTRUCTION, INC. $110.00 $63,800.00
AMERICAN CIVIL CONSTRUCTORS $75.00 $43,500.00
WILKINSON CONSTRUCTION CO., INC. $90.00 $52,200.00
KNIFE RIVER - Northwest $60.00 $34,800.00 Engineer's Estimate 580 EACH $40.00 $23,200.00
A2851 63316-1000 REMOVE AND RESET SIGN
Oftedal Construction, Inc $681.00 $4,086.00 Hooker Creek, Inc $210.00 $1,260.00 Rafter H Construction $660.00 $3,960.00
HIGH COUNTRY CONSTRUCTION, INC. $660.00 $3,960.00
AMERICAN CIVIL CONSTRUCTORS $600.00 $3,600.00
WILKINSON CONSTRUCTION CO., INC. $500.00 $3,000.00
KNIFE RIVER - Northwest $500.00 $3,000.00 Engineer's Estimate 6 EACH $200.00 $1,200.00
A2901 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID
Oftedal Construction, Inc $0.15 $45,270.00 Hooker Creek, Inc $0.13 $39,234.00 Rafter H Construction $0.15 $45,270.00
HIGH COUNTRY CONSTRUCTION, INC. $0.14 $42,252.00
AMERICAN CIVIL CONSTRUCTORS $0.25 $75,450.00
WILKINSON CONSTRUCTION CO., INC. $1.00 $301,800.00
KNIFE RIVER - Northwest $0.13 $39,234.00 Engineer's Estimate 301,800 LNFT $0.25 $75,450.00
21 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A2951 63501-0000 TEMPORARY TRAFFIC CONTROL
Oftedal Construction, Inc Lump Sum $350,000.00 Hooker Creek, Inc Lump Sum $410,000.00 Rafter H Construction Lump Sum $800,000.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $700,000.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $500,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $25,000.00 KNIFE RIVER - Northwest Lump Sum $500,000.00 Engineer's Estimate ALL LPSM Lump Sum $100,000.00
A3001 63640-0600 RELOCATE COMMUNICATION LINE
Oftedal Construction, Inc Lump Sum $31,800.00 Hooker Creek, Inc Lump Sum $1,100.00 Rafter H Construction Lump Sum $30,000.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $25,000.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $100.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $250,000.00 KNIFE RIVER - Northwest Lump Sum $2,000.00 Engineer's Estimate ALL LPSM Lump Sum $32,000.00
Total Schedule - All Items
Oftedal Construction, Inc $7,129,052.30 Hooker Creek, Inc $7,426,006.00 Rafter H Construction $7,725,203.88
HIGH COUNTRY CONSTRUCTION, INC. $9,262,801.50
AMERICAN CIVIL CONSTRUCTORS $9,553,919.00
WILKINSON CONSTRUCTION CO., INC. $9,664,412.10
KNIFE RIVER - Northwest $10,939,502.00 Engineer's Estimate $6,512,957.50
22 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: X
Schedule Type: Options
Solcitation No: DTFH6814B00023
Division: Central Federal Lands
State: WY County: Sublette
Federal Land: Opened at: Lakewood
Opened by: Joe Wilson
Date: 05/14/15
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
KNIFE RIVER - Northwest $104,955.00 195 East 600 South American Fork, UT 84003
AMERICAN CIVIL CONSTRUCTORS $144,180.00
4901 SOUTH WINDERMERE STREET
LITTLETON, CO 80120
Hooker Creek, Inc $146,620.00 1015 Anderson Street Red Bluff, CA 96080
Oftedal Construction, Inc $164,614.00 P.O. Box 400 Miles City, MT 59301
HIGH COUNTRY CONSTRUCTION, INC. $199,540.00
P.O. BOX 930
LANDER, WY 82520
Rafter H Construction $210,550.00 207 Georgetown Drive Rexburg, ID 83440
WILKINSON CONSTRUCTION CO., INC. $248,480.00
1200 EAST 100 SOUTH
MORGAN , UT 84050
Engineer's Estimate $145,000.00
23 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0001 15101-0000 MOBILIZATION
KNIFE RIVER - Northwest Lump Sum $2,500.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $21,000.00 Hooker Creek, Inc Lump Sum $10,000.00 Oftedal Construction, Inc Lump Sum $13,100.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $10,000.00 Rafter H Construction Lump Sum $38,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $40,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,870.00
X0051 15215-1000 SURVEY AND STAKING, APPROACH ROAD
KNIFE RIVER - Northwest $100.00 $800.00
AMERICAN CIVIL CONSTRUCTORS $750.00 $6,000.00
Hooker Creek, Inc $540.00 $4,320.00 Oftedal Construction, Inc $621.00 $4,968.00
HIGH COUNTRY CONSTRUCTION, INC. $900.00 $7,200.00
Rafter H Construction $500.00 $4,000.00
WILKINSON CONSTRUCTION CO., INC. $900.00 $7,200.00
Engineer's Estimate 8 EACH $100.00 $800.00
X0101 15216-2000 SURVEY AND STAKING, GRADE FINISHING STAKES
KNIFE RIVER - Northwest $60.00 $900.00
AMERICAN CIVIL CONSTRUCTORS $80.00 $1,200.00
Hooker Creek, Inc $87.00 $1,305.00 Oftedal Construction, Inc $95.00 $1,425.00
HIGH COUNTRY CONSTRUCTION, INC. $250.00 $3,750.00
Rafter H Construction $80.00 $1,200.00
WILKINSON CONSTRUCTION CO., INC. $200.00 $3,000.00
Engineer's Estimate 15.0 STA $100.00 $1,500.00
X0151 15301-0000 CONTRACTOR QUALITY CONTROL
KNIFE RIVER - Northwest Lump Sum $2,500.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $2,000.00 Hooker Creek, Inc Lump Sum $5,000.00 Oftedal Construction, Inc Lump Sum $10,500.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $5,000.00 Rafter H Construction Lump Sum $10,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $8,500.00 Engineer's Estimate ALL LPSM Lump Sum $3,000.00
24 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0201 15401-0000 CONTRACTOR TESTING
KNIFE RIVER - Northwest Lump Sum $2,500.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $4,000.00 Hooker Creek, Inc Lump Sum $5,400.00 Oftedal Construction, Inc Lump Sum $10,100.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $10,000.00 Rafter H Construction Lump Sum $10,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $25,000.00 Engineer's Estimate ALL LPSM Lump Sum $3,000.00
X0251 15501-0000 CONSTRUCTION SCHEDULE
KNIFE RIVER - Northwest Lump Sum $500.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $500.00 Hooker Creek, Inc Lump Sum $1,500.00 Oftedal Construction, Inc Lump Sum $664.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $4,000.00 Rafter H Construction Lump Sum $4,500.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $5,000.00 Engineer's Estimate ALL LPSM Lump Sum $2,000.00
X0301 15705-0100 SOIL EROSION CONTROL, SILT FENCE
KNIFE RIVER - Northwest $2.50 $2,625.00
AMERICAN CIVIL CONSTRUCTORS $3.00 $3,150.00
Hooker Creek, Inc $3.50 $3,675.00 Oftedal Construction, Inc $5.90 $6,195.00
HIGH COUNTRY CONSTRUCTION, INC. $4.00 $4,200.00
Rafter H Construction $3.00 $3,150.00
WILKINSON CONSTRUCTION CO., INC. $4.00 $4,200.00
Engineer's Estimate 1,050 LNFT $2.00 $2,100.00
X0351 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION ENTRANCE
KNIFE RIVER - Northwest $1,000.00 $1,000.00
AMERICAN CIVIL CONSTRUCTORS $2,000.00 $2,000.00
Hooker Creek, Inc $1,400.00 $1,400.00 Oftedal Construction, Inc $2,190.00 $2,190.00
HIGH COUNTRY CONSTRUCTION, INC. $5,000.00 $5,000.00
Rafter H Construction $2,000.00 $2,000.00
WILKINSON CONSTRUCTION CO., INC. $3,500.00 $3,500.00
Engineer's Estimate 1 EACH $2,000.00 $2,000.00
25 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0401 15802-0000 WATERING FOR DUST CONTROL
KNIFE RIVER - Northwest Lump Sum $1,000.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $1,500.00 Hooker Creek, Inc Lump Sum $940.00 Oftedal Construction, Inc Lump Sum $2,300.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $20,000.00 Rafter H Construction Lump Sum $8,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
X0451 30101-0000 AGGREGATE BASE
KNIFE RIVER - Northwest $50.00 $3,000.00
AMERICAN CIVIL CONSTRUCTORS $30.00 $1,800.00
Hooker Creek, Inc $52.00 $3,120.00 Oftedal Construction, Inc $70.00 $4,200.00
HIGH COUNTRY CONSTRUCTION, INC. $40.00 $2,400.00
Rafter H Construction $35.00 $2,100.00
WILKINSON CONSTRUCTION CO., INC. $31.50 $1,890.00
Engineer's Estimate 60 TON $24.00 $1,440.00
X0501 30306-2500 PULVERIZING, 5-INCH DEPTH
KNIFE RIVER - Northwest $1.50 $6,600.00
AMERICAN CIVIL CONSTRUCTORS $1.00 $4,400.00
Hooker Creek, Inc $2.70 $11,880.00 Oftedal Construction, Inc $2.40 $10,560.00
HIGH COUNTRY CONSTRUCTION, INC. $4.00 $17,600.00
Rafter H Construction $3.25 $14,300.00
WILKINSON CONSTRUCTION CO., INC. $1.20 $5,280.00
Engineer's Estimate 4,400 SQYD $6.00 $26,400.00
X0551 30606-0000 MAGNESIUM CHLORIDE
KNIFE RIVER - Northwest $165.00 $1,650.00
AMERICAN CIVIL CONSTRUCTORS $150.00 $1,500.00
Hooker Creek, Inc $437.00 $4,370.00 Oftedal Construction, Inc $157.00 $1,570.00
HIGH COUNTRY CONSTRUCTION, INC. $225.00 $2,250.00
Rafter H Construction $180.00 $1,800.00
WILKINSON CONSTRUCTION CO., INC. $76.00 $760.00
Engineer's Estimate 10.0 TON $97.00 $970.00
26 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0601 40101-5600 SUPERPAVE PAVEMENT, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION
ESAL
KNIFE RIVER - Northwest $94.00 $66,740.00
AMERICAN CIVIL CONSTRUCTORS $115.00 $81,650.00
Hooker Creek, Inc $113.00 $80,230.00 Oftedal Construction, Inc $110.00 $78,100.00
HIGH COUNTRY CONSTRUCTION, INC. $130.00 $92,300.00
Rafter H Construction $130.00 $92,300.00
WILKINSON CONSTRUCTION CO., INC. $145.00 $102,950.00
Engineer's Estimate 710 TON $92.00 $65,320.00
X0651 40105-3000 ANTISTRIP ADDITIVE, TYPE 3
KNIFE RIVER - Northwest $235.00 $1,880.00
AMERICAN CIVIL CONSTRUCTORS $260.00 $2,080.00
Hooker Creek, Inc $270.00 $2,160.00 Oftedal Construction, Inc $262.00 $2,096.00
HIGH COUNTRY CONSTRUCTION, INC. $215.00 $1,720.00
Rafter H Construction $210.00 $1,680.00
WILKINSON CONSTRUCTION CO., INC. $350.00 $2,800.00
Engineer's Estimate 8.0 TON $200.00 $1,600.00
X0701 40920-1000 FOG SEAL, EMULSIFIED ASPHALT GRADE CSS-1 OR CSS-1H, SS-1 OR SS-1H
KNIFE RIVER - Northwest $850.00 $1,700.00
AMERICAN CIVIL CONSTRUCTORS $350.00 $700.00
Hooker Creek, Inc $355.00 $710.00 Oftedal Construction, Inc $346.00 $692.00
HIGH COUNTRY CONSTRUCTION, INC. $600.00 $1,200.00
Rafter H Construction $600.00 $1,200.00
WILKINSON CONSTRUCTION CO., INC. $600.00 $1,200.00
Engineer's Estimate 2.0 TON $700.00 $1,400.00
X0751 41201-1000 TACK COAT GRADE CSS-1, CSS-1H, SS-1, OR SS-1H
KNIFE RIVER - Northwest $850.00 $1,700.00
AMERICAN CIVIL CONSTRUCTORS $600.00 $1,200.00
Hooker Creek, Inc $625.00 $1,250.00 Oftedal Construction, Inc $607.00 $1,214.00
HIGH COUNTRY CONSTRUCTION, INC. $660.00 $1,320.00
Rafter H Construction $660.00 $1,320.00
WILKINSON CONSTRUCTION CO., INC. $600.00 $1,200.00
Engineer's Estimate 2.0 TON $800.00 $1,600.00
27 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0801 62301-0000 GENERAL LABOR
KNIFE RIVER - Northwest $52.00 $1,040.00
AMERICAN CIVIL CONSTRUCTORS $25.00 $500.00
Hooker Creek, Inc $28.00 $560.00 Oftedal Construction, Inc $70.00 $1,400.00
HIGH COUNTRY CONSTRUCTION, INC. $50.00 $1,000.00
Rafter H Construction $60.00 $1,200.00
WILKINSON CONSTRUCTION CO., INC. $100.00 $2,000.00
Engineer's Estimate 20 HOUR $60.00 $1,200.00
X0851 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
KNIFE RIVER - Northwest $106.00 $2,120.00
AMERICAN CIVIL CONSTRUCTORS $100.00 $2,000.00
Hooker Creek, Inc $185.00 $3,700.00 Oftedal Construction, Inc $185.00 $3,700.00
HIGH COUNTRY CONSTRUCTION, INC. $100.00 $2,000.00
Rafter H Construction $90.00 $1,800.00
WILKINSON CONSTRUCTION CO., INC. $150.00 $3,000.00
Engineer's Estimate 20 HOUR $170.00 $3,400.00
X0901 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
KNIFE RIVER - Northwest $160.00 $3,200.00
AMERICAN CIVIL CONSTRUCTORS $100.00 $2,000.00
Hooker Creek, Inc $185.00 $3,700.00 Oftedal Construction, Inc $220.00 $4,400.00
HIGH COUNTRY CONSTRUCTION, INC. $180.00 $3,600.00
Rafter H Construction $190.00 $3,800.00
WILKINSON CONSTRUCTION CO., INC. $300.00 $6,000.00
Engineer's Estimate 20 HOUR $170.00 $3,400.00
X0951 63501-0000 TEMPORARY TRAFFIC CONTROL
KNIFE RIVER - Northwest Lump Sum $1,000.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $5,000.00 Hooker Creek, Inc Lump Sum $1,400.00 Oftedal Construction, Inc Lump Sum $5,240.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $5,000.00 Rafter H Construction Lump Sum $8,200.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $3,000.00
28 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Total Schedule - All Items
KNIFE RIVER - Northwest $104,955.00
AMERICAN CIVIL CONSTRUCTORS $144,180.00
Hooker Creek, Inc $146,620.00 Oftedal Construction, Inc $164,614.00
HIGH COUNTRY CONSTRUCTION, INC. $199,540.00
Rafter H Construction $210,550.00
WILKINSON CONSTRUCTION CO., INC. $248,480.00
Engineer's Estimate $145,000.00
29 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: Y
Schedule Type: Options
Solcitation No: DTFH6814B00023
Division: Central Federal Lands
State: WY County: Sublette
Federal Land: Opened at: Lakewood
Opened by: Joe Wilson
Date: 05/14/15
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
KNIFE RIVER - Northwest $214,744.00 195 East 600 South American Fork, UT 84003
AMERICAN CIVIL CONSTRUCTORS $260,350.00
4901 SOUTH WINDERMERE STREET
LITTLETON, CO 80120
Hooker Creek, Inc $288,881.00 1015 Anderson Street Red Bluff, CA 96080
Oftedal Construction, Inc $291,217.00 P.O. Box 400 Miles City, MT 59301
HIGH COUNTRY CONSTRUCTION, INC. $363,360.00
P.O. BOX 930
LANDER, WY 82520
Rafter H Construction $378,135.00 207 Georgetown Drive Rexburg, ID 83440
WILKINSON CONSTRUCTION CO., INC. $397,871.00
1200 EAST 100 SOUTH
MORGAN , UT 84050
Engineer's Estimate $309,000.00
30 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: Y
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Y0001 15101-0000 MOBILIZATION
KNIFE RIVER - Northwest Lump Sum $2,500.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $24,000.00 Hooker Creek, Inc Lump Sum $11,000.00 Oftedal Construction, Inc Lump Sum $8,380.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $10,000.00 Rafter H Construction Lump Sum $32,600.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $22,978.00
Y0051 15215-7000 SURVEY AND STAKING, PARKING AREA
KNIFE RIVER - Northwest $400.00 $800.00
AMERICAN CIVIL CONSTRUCTORS $1,000.00 $2,000.00
Hooker Creek, Inc $2,700.00 $5,400.00 Oftedal Construction, Inc $3,110.00 $6,220.00
HIGH COUNTRY CONSTRUCTION, INC. $2,500.00 $5,000.00
Rafter H Construction $2,600.00 $5,200.00
WILKINSON CONSTRUCTION CO., INC. $6,000.00 $12,000.00
Engineer's Estimate 2 EACH $200.00 $400.00
Y0101 15301-0000 CONTRACTOR QUALITY CONTROL
KNIFE RIVER - Northwest Lump Sum $2,500.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $3,000.00 Hooker Creek, Inc Lump Sum $5,000.00 Oftedal Construction, Inc Lump Sum $10,500.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $5,000.00 Rafter H Construction Lump Sum $14,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $8,500.00 Engineer's Estimate ALL LPSM Lump Sum $4,000.00
Y0151 15401-0000 CONTRACTOR TESTING
KNIFE RIVER - Northwest Lump Sum $2,500.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $5,000.00 Hooker Creek, Inc Lump Sum $9,300.00 Oftedal Construction, Inc Lump Sum $12,700.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $10,000.00 Rafter H Construction Lump Sum $7,600.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $25,000.00 Engineer's Estimate ALL LPSM Lump Sum $4,000.00
31 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: Y
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Y0201 15501-0000 CONSTRUCTION SCHEDULE
KNIFE RIVER - Northwest Lump Sum $500.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $500.00 Hooker Creek, Inc Lump Sum $1,500.00 Oftedal Construction, Inc Lump Sum $664.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $4,000.00 Rafter H Construction Lump Sum $3,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $5,000.00 Engineer's Estimate ALL LPSM Lump Sum $2,500.00
Y0251 15705-0100 SOIL EROSION CONTROL, SILT FENCE
KNIFE RIVER - Northwest $2.50 $2,625.00
AMERICAN CIVIL CONSTRUCTORS $3.00 $3,150.00
Hooker Creek, Inc $3.50 $3,675.00 Oftedal Construction, Inc $5.90 $6,195.00
HIGH COUNTRY CONSTRUCTION, INC. $4.00 $4,200.00
Rafter H Construction $3.00 $3,150.00
WILKINSON CONSTRUCTION CO., INC. $4.00 $4,200.00
Engineer's Estimate 1,050 LNFT $2.00 $2,100.00
Y0301 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION ENTRANCE
KNIFE RIVER - Northwest $1,000.00 $2,000.00
AMERICAN CIVIL CONSTRUCTORS $2,000.00 $4,000.00
Hooker Creek, Inc $1,400.00 $2,800.00 Oftedal Construction, Inc $2,190.00 $4,380.00
HIGH COUNTRY CONSTRUCTION, INC. $5,000.00 $10,000.00
Rafter H Construction $2,000.00 $4,000.00
WILKINSON CONSTRUCTION CO., INC. $3,500.00 $7,000.00
Engineer's Estimate 2 EACH $2,000.00 $4,000.00
Y0351 15802-0000 WATERING FOR DUST CONTROL
KNIFE RIVER - Northwest Lump Sum $1,000.00 AMERICAN CIVIL CONSTRUCTORS Lump Sum $2,000.00 Hooker Creek, Inc Lump Sum $1,400.00 Oftedal Construction, Inc Lump Sum $2,300.00 HIGH COUNTRY CONSTRUCTION, INC. Lump Sum $15,000.00 Rafter H Construction Lump Sum $7,000.00 WILKINSON CONSTRUCTION CO., INC. Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
32 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: Y
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Y0401 30101-0000 AGGREGATE BASE
KNIFE RIVER - Northwest $50.00 $2,500.00
AMERICAN CIVIL CONSTRUCTORS $30.00 $1,500.00
Hooker Creek, Inc $55.00 $2,750.00 Oftedal Construction, Inc $79.50 $3,975.00
HIGH COUNTRY CONSTRUCTION, INC. $40.00 $2,000.00
Rafter H Construction $35.00 $1,750.00
WILKINSON CONSTRUCTION CO., INC. $31.50 $1,575.00
Engineer's Estimate 50 TON $24.00 $1,200.00
Y0451 30306-2500 PULVERIZING, 5-INCH DEPTH
KNIFE RIVER - Northwest $1.49 $16,539.00
AMERICAN CIVIL CONSTRUCTORS $1.00 $11,100.00
Hooker Creek, Inc $2.60 $28,860.00 Oftedal Construction, Inc $2.00 $22,200.00
HIGH COUNTRY CONSTRUCTION, INC. $3.30 $36,630.00
Rafter H Construction $3.25 $36,075.00
WILKINSON CONSTRUCTION CO., INC. $1.20 $13,320.00
Engineer's Estimate 11,100 SQYD $6.00 $66,600.00
Y0501 30606-0000 MAGNESIUM CHLORIDE
KNIFE RIVER - Northwest $165.00 $4,290.00
AMERICAN CIVIL CONSTRUCTORS $150.00 $3,900.00
Hooker Creek, Inc $326.00 $8,476.00 Oftedal Construction, Inc $157.00 $4,082.00
HIGH COUNTRY CONSTRUCTION, INC. $225.00 $5,850.00
Rafter H Construction $180.00 $4,680.00
WILKINSON CONSTRUCTION CO., INC. $76.00 $1,976.00
Engineer's Estimate 26.0 TON $97.00 $2,522.00
Y0551 40101-5600 SUPERPAVE PAVEMENT, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION
ESAL
KNIFE RIVER - Northwest $88.00 $158,400.00
AMERICAN CIVIL CONSTRUCTORS $100.00 $180,000.00
Hooker Creek, Inc $105.00 $189,000.00 Oftedal Construction, Inc $103.00 $185,400.00
HIGH COUNTRY CONSTRUCTION, INC. $130.00 $234,000.00
Rafter H Construction $130.00 $234,000.00
WILKINSON CONSTRUCTION CO., INC. $145.00 $261,000.00
Engineer's Estimate 1,800 TON $92.00 $165,600.00
33 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: Y
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Y0601 40105-3000 ANTISTRIP ADDITIVE, TYPE 3
KNIFE RIVER - Northwest $235.00 $4,230.00
AMERICAN CIVIL CONSTRUCTORS $275.00 $4,950.00
Hooker Creek, Inc $270.00 $4,860.00 Oftedal Construction, Inc $262.00 $4,716.00
HIGH COUNTRY CONSTRUCTION, INC. $210.00 $3,780.00
Rafter H Construction $210.00 $3,780.00
WILKINSON CONSTRUCTION CO., INC. $350.00 $6,300.00
Engineer's Estimate 18.0 TON $200.00 $3,600.00
Y0651 40920-1000 FOG SEAL, EMULSIFIED ASPHALT GRADE CSS-1 OR CSS-1H, SS-1 OR SS-1H
KNIFE RIVER - Northwest $700.00 $3,500.00
AMERICAN CIVIL CONSTRUCTORS $350.00 $1,750.00
Hooker Creek, Inc $355.00 $1,775.00 Oftedal Construction, Inc $346.00 $1,730.00
HIGH COUNTRY CONSTRUCTION, INC. $600.00 $3,000.00
Rafter H Construction $600.00 $3,000.00
WILKINSON CONSTRUCTION CO., INC. $600.00 $3,000.00
Engineer's Estimate 5.0 TON $700.00 $3,500.00
Y0701 41201-1000 TACK COAT GRADE CSS-1, CSS-1H, SS-1, OR SS-1H
KNIFE RIVER - Northwest $700.00 $3,500.00
AMERICAN CIVIL CONSTRUCTORS $600.00 $3,000.00
Hooker Creek, Inc $625.00 $3,125.00 Oftedal Construction, Inc $607.00 $3,035.00
HIGH COUNTRY CONSTRUCTION, INC. $660.00 $3,300.00
Rafter H Construction $660.00 $3,300.00
WILKINSON CONSTRUCTION CO., INC. $600.00 $3,000.00
Engineer's Estimate 5.0 TON $800.00 $4,000.00
Y0751 62301-0000 GENERAL LABOR
KNIFE RIVER - Northwest $52.00 $1,040.00
AMERICAN CIVIL CONSTRUCTORS $25.00 $500.00
Hooker Creek, Inc $28.00 $560.00 Oftedal Construction, Inc $70.00 $1,400.00
HIGH COUNTRY CONSTRUCTION, INC. $50.00 $1,000.00
Rafter H Construction $60.00 $1,200.00
WILKINSON CONSTRUCTION CO., INC. $100.00 $2,000.00
Engineer's Estimate 20 HOUR $60.00 $1,200.00
34 out of 34
Project No: WY FLAP 23-154(1)
Project Name: Fremont Lake Road
Schedule: Y
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Y0801 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
KNIFE RIVER - Northwest $106.00 $2,120.00
AMERICAN CIVIL CONSTRUCTORS $100.00 $2,000.00
Hooker Creek, Inc $185.00 $3,700.00 Oftedal Construction, Inc $185.00 $3,700.00
HIGH COUNTRY CONSTRUCTION, INC. $100.00 $2,000.00
Rafter H Construction $90.00 $1,800.00
WILKINSON CONSTRUCTION CO., INC. $150.00 $3,000.00
Engineer's Estimate 20 HOUR $170.00 $3,400.00
Y0851 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
KNIFE RIVER - Northwest $160.00 $3,200.00
AMERICAN CIVIL CONSTRUCTORS $100.00 $2,000.00
Hooker Creek, Inc $185.00 $3,700.00 Oftedal…