DTFH6814B00023 Revised 4/27/15 WY FLAP 23-154(1), Fremont Lake Road

4/15/15

QUESTION #1

I didn’t see any mention of a pre-bid walk for the above project. Will there be one? When will that be?

Response: See provision 52.236-27 on page B-20.

4/24/15

QUESTION #2

The time of completion. There is an * where the days should be on page A-1 Response: On page A-1 the reference * states “Refer to Subsection 108.01 as amended in the Special Contract Requirements.”……… see page E-19 for completion date

QUESTION #3

Warranty time (There are certain documents that have to be kept for certain number of years but I couldn’t find the general warranty period) Response: No warranty, all records should be kept according to the FAR

QUESTION #4

Liquidated Damages, there were liquidated damaged for SWMP not being taken care of but that is different.

Response: See section 108 of the FP-03 for the LD’s

QUESTION #5

Do you have a start date yet?

Response: The notice to proceed is usually dependent on the awarded contractor’s responsiveness. This includes payment and performance bonds, subcontracting plans, insurance and so on. Normally they are given 3-5 weeks after bid opening. You will need to estimate the number of working days based on an estimated NTP. Unfortunately I can’t give you a firm NTP date because I do not know when it will be given.