ZOA_CWB_MAJOR_MECHANICAL - Specs.pdf

PDF 12 MB Posted

Attached to
MAJOR MECHANICAL MODERNIZATION, OAKLAND, CA ZOA
Solicitation number
DTFAWN-16-R-01856
Issued by

About this file

ZOA_CWB_MAJOR_MECHANICAL - Specs (pdf)

View the file

Other files

File Type Posted
ZOA_CWB_MAJOR_MECHANICAL - Specs.pdf PDF
SF-30 AMENDMENT.doc DOC document
1442-modernization at OAKLAND.pdf PDF
RFI RESPONSE 1 Controls Amendment part 1 REF drawings.pdf PDF
Site Visit prebid jobwalk.pdf PDF
SF-30 AMENDMENT 4.doc DOC document
FAA Response Ecorp RFI 2.docx DOCX document
SF-30 AMENDMENT 3.doc DOC document
SF-30 AMENDMENT 2.doc DOC document
Amendment 0002 Honeywell software upgrade.pdf PDF
customer satisfaction survey.docx DOCX document
DTFAWN-16-R-01856.pdf PDF
ZOA_CWB_MAJOR_MECHANICAL - Preliminary_Commissioning_Plan.pdf PDF
Site Visit (sol)revised.sol —
RFI RESPONSE 5.doc DOC document
RFI RESPONSE 3 RFI 3 FAA response.doc DOC document
ZOA_CWB_MAJOR_MECHANICAL - Dr Signed.pdf PDF
RFI RESPONSE 2 Controls Amendment part 2 REF drawings.pdf PDF
Question.doc DOC document
revised SF-30 AMENDMENT 5.doc DOC document
RFI 4 Oakland ARTCC CWB CCTR_Pre-Bid RFI 001 FAA Response Honeywell.pdf PDF
FAA Response RFI 6.doc DOC document
ZOA CWB MMS Hazmat.pdf PDF
SF-30 AMENDMENT 6.doc DOC document
DTFAWN-16-R-01856.pdf PDF
wage rates.txt TXT text file
RFI RESPONSE 4 Abide RFI.rtf RTF text file
FAA response RFI Ecorp 1.docx DOCX document
FAA Response Ecorp RFI 2.docx DOCX document
DTFAWN-16-R-01856.pdf PDF
RFI 4 Oakland ARTCC CWB CCTR_Pre-Bid RFI 001 FAA Response Honeywell.pdf PDF
customer satisfaction survey.docx DOCX document
RFI RESPONSE 1 Controls Amendment part 1 REF drawings.pdf PDF
DTFAWN-16-R-01856.pdf PDF
wage rates.txt TXT text file
SF-30 AMENDMENT 4.doc DOC document
ZOA_CWB_MAJOR_MECHANICAL - Dr Signed.pdf PDF
SF-30 AMENDMENT 3.doc DOC document
revised SF-30 AMENDMENT 5.doc DOC document
Site Visit prebid jobwalk.pdf PDF
Site Visit (sol)revised.sol —
FAA Response RFI 6.doc DOC document
Amendment 0002 Honeywell software upgrade.pdf PDF
RFI RESPONSE 2 Controls Amendment part 2 REF drawings.pdf PDF
Question.doc DOC document
RFI RESPONSE 3 RFI 3 FAA response.doc DOC document
RFI RESPONSE 4 Abide RFI.rtf RTF text file
1442-modernization at OAKLAND.pdf PDF
SF-30 AMENDMENT 2.doc DOC document
ZOA_CWB_MAJOR_MECHANICAL - Preliminary_Commissioning_Plan.pdf PDF
Show 40 more

Latest 50 of 235 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OAKLAND ARTCC (ZOA) JULY 8, 2015

CWB AND MAJOR MECHANICAL SUSTAINMENT PROJECT FINAL SUBMITTAL

FREMONT, CALIFORNIA

IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 - 1

SECTION 23 05 53 - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Equipment labels.

2. Warning signs and labels.

3. Pipe labels.

4. Stencils.

5. Valve tags.

6. Warning tags.

1.2 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Equipment Label Schedule: Include a listing of all equipment to be labeled with the proposed content for each label.

C. Valve numbering scheme.

D. Valve Schedules: For each piping system to include in maintenance manuals.

1.3 COORDINATION

A. Coordinate installation of identifying devices with completion of covering and painting of surfaces where devices are to be applied.

B. Coordinate installation of identifying devices with locations of access panels and doors.

C. Install identifying devices before installing acoustical ceilings and similar concealment.

PART 2 - PRODUCTS

2.1 EQUIPMENT LABELS

A. Metal Labels for Equipment:

1. Material and Thickness: Brass, 0.032-inch Stainless steel, 0.025-inch Aluminum, 0.032-inch or anodized aluminum, 0.032-inch minimum thickness, and having predrilled or stamped holes for attachment hardware.

IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 - 2

2. Minimum Label Size: Length and width vary for required label content, but not less than 2-1/2 by 3/4 inch.

3. Minimum Letter Size: 1/4 inch for name of units if viewing distance is less than 24 inches, 1/2 inch for viewing distances up to 72 inches, and proportionately larger lettering for greater viewing distances. Include secondary lettering two-thirds to three-fourths the size of principal lettering.

4. Fasteners: Stainless-steel rivets or self-tapping screws.

5. Adhesive: Contact-type permanent adhesive, compatible with label and with substrate.

B. Plastic Labels for Equipment:

1. Material and Thickness: Multilayer, multicolor, plastic labels for mechanical engraving, 1/16 inch thick, and having predrilled holes for attachment hardware.

2. Letter Color: White.

3. Background Color: Black.

4. Maximum Temperature: Able to withstand temperatures up to 160 deg F.

5. Minimum Label Size: Length and width vary for required label content, but not less than

2-1/2 by 3/4 inch.

6. Minimum Letter Size: 1/4 inch for name of units if viewing distance is less than 24 inches, 1/2 inch for viewing distances up to 72 inches, and proportionately larger lettering for greater viewing distances. Include secondary lettering two-thirds to three-fourths the size of principal lettering.

7. Fasteners: Stainless-steel rivets or self-tapping screws.

8. Adhesive: Contact-type permanent adhesive, compatible with label and with substrate.

C. Label Content: Include equipment's Drawing designation or unique equipment number, Drawing numbers where equipment is indicated (plans, details, and schedules), plus the Specification Section number and title where equipment is specified.

D. Equipment Label Schedule: For each item of equipment to be labeled, on 8-1/2-by-11-inch bond paper. Tabulate equipment identification number and identify Drawing numbers where equipment is indicated (plans, details, and schedules), plus the Specification Section number and title where equipment is specified. Equipment schedule shall be included in operation and maintenance data.

2.2 WARNING SIGNS AND LABELS

A. Material and Thickness: Multilayer, multicolor, plastic labels for mechanical engraving, 1/16 inch thick, and having predrilled holes for attachment hardware.

B. Letter Color: White.

C. Background Color: Red.

D. Maximum Temperature: Able to withstand temperatures up to 160 deg F.

E. Minimum Label Size: Length and width vary for required label content, but not less than 2-1/2 by 3/4 inch.

IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 - 3

F. Minimum Letter Size: 1/4 inch for name of units if viewing distance is less than 24 inches, 1/2 inch for viewing distances up to 72 inches, and proportionately larger lettering for greater viewing distances. Include secondary lettering two-thirds to three-fourths the size of principal lettering.

G. Fasteners: Stainless-steel rivets or self-tapping screws.

H. Adhesive: Contact-type permanent adhesive, compatible with label and with substrate.

I. Label Content: Include caution and warning information, plus emergency notification instructions.

2.3 PIPE LABELS

A. General Requirements for Manufactured Pipe Labels: Preprinted, color-coded, with lettering indicating service, and showing flow direction.

B. Pretensioned Pipe Labels: Precoiled, semirigid plastic formed to partially cover circumference of pipe and to attach to pipe without fasteners or adhesive.

C. Self-Adhesive Pipe Labels: Printed plastic with contact-type, permanent-adhesive backing.

D. Pipe Label Contents: Include identification of piping service using same designations or abbreviations as used on Drawings, pipe size, and an arrow indicating flow direction.

1. Flow-Direction Arrows: Integral with piping system service lettering to accommodate both directions, or as separate unit on each pipe label to indicate flow direction.

2. Lettering Size: At least 1-1/2 inches high.

2.4 STENCILS

A. Stencils: Prepared with letter sizes according to ASME A13.1 for piping; minimum letter height of 1-1/4 inches for ducts; and minimum letter height of 3/4 inch for access panel and door labels, equipment labels, and similar operational instructions.

1. Stencil Material: Fiberboard or metal.

2. Stencil Paint: Exterior, gloss, acrylic enamel black unless otherwise indicated. Paint may be in pressurized spray-can form.

3. Identification Paint: Exterior, acrylic enamel in colors according to ASME A13.1 unless otherwise indicated.

2.5 VALVE TAGS

A. Valve Tags: Stamped or engraved with 1/4-inch letters for piping system abbreviation and 1/2-inch numbers.

IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 - 4

1. Tag Material: Brass, 0.032-inch Stainless steel, 0.025-inch Aluminum, 0.032-inch or anodized aluminum, 0.032-inch minimum thickness, and having predrilled or stamped holes for attachment hardware.

2. Fasteners: Brass wire-link or beaded chain; or S-hook.

B. Valve Schedules: For each piping system, on 8-1/2-by-11-inch bond paper. Tabulate valve number, piping system, system abbreviation (as shown on valve tag), location of valve (room or space), normal-operating position (open, closed, or modulating), and variations for identification. Mark valves for emergency shutoff and similar special uses.

1. Valve-tag schedule shall be included in operation and maintenance data.

2.6 WARNING TAGS

A. Warning Tags: Preprinted or partially preprinted, accident-prevention tags, of plasticized card stock with matte finish suitable for writing.

1. Size: 3 by 5-1/4 inches minimum.

2. Fasteners: Reinforced grommet and wire or string.

3. Nomenclature: Large-size primary caption such as "DANGER," "CAUTION," or "DO

NOT OPERATE."

4. Color: Yellow background with black lettering.

PART 3 - EXECUTION

3.1 PREPARATION

A. Clean piping and equipment surfaces of substances that could impair bond of identification devices, including dirt, oil, grease, release agents, and incompatible primers, paints, and encapsulants.

3.2 EQUIPMENT LABEL INSTALLATION

A. Install or permanently fasten labels on each major item of mechanical equipment.

B. Locate equipment labels where accessible and visible.

3.3 PIPE LABEL INSTALLATION

A. Piping Color-Coding: Painting of piping is specified in Section 09 91 23 "Interior Painting."

B. Stenciled Pipe Label Option: Stenciled labels may be provided instead of manufactured pipe labels, at Installer's option. Install stenciled pipe labels with painted, color-coded bands or rectangles, complying with ASME A13.1, on each piping system.

IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 - 5

1. Identification Paint: Use for contrasting background.

2. Stencil Paint: Use for pipe marking.

C. Locate pipe labels where piping is exposed or above accessible ceilings in finished spaces;

machine rooms; accessible maintenance spaces such as shafts, tunnels, and plenums; and exterior exposed locations as follows:

1. Near each valve and control device.

2. Near each branch connection, excluding short takeoffs for fixtures and terminal units.

Where flow pattern is not obvious, mark each pipe at branch.

3. Near penetrations through walls, floors, ceilings, and inaccessible enclosures.

4. At access doors, manholes, and similar access points that permit view of concealed piping.

5. Near major equipment items and other points of origination and termination.

6. Spaced at maximum intervals of 50 feet along each run. Reduce intervals to 25 feet in areas of congested piping and equipment.

7. On piping above removable acoustical ceilings. Omit intermediately spaced labels.

D. Pipe Label Color Schedule:

1. Chilled-Water Piping:

a. Background Color: Black.

b. Letter Color: White.

2. Condenser-Water Piping:

a. Background Color: Black.

b. Letter Color: White.

3. Refrigerant Piping:

a. Background Color: Black.

b. Letter Color: White.

4. Heating Water Piping:

a. Background Color: Black.

b. Letter Color: White.

3.4 VALVE-TAG INSTALLATION

A. Install tags on valves and control devices in piping systems, except check valves; valves within factory-fabricated equipment units; shutoff valves; faucets; convenience and lawn-watering hose connections; and HVAC terminal devices and similar roughing-in connections of end-use fixtures and units. List tagged valves in a valve schedule.

B. Valve-Tag Application Schedule: Tag valves according to size, shape, and color scheme and with captions similar to those indicated in the following subparagraphs:

IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 - 6

1. Valve-Tag Size and Shape:

a. Chilled Water: 1-1/2 inches, round.

b. Condenser Water: 1-1/2 inches, round.

c. Refrigerant: 1-1/2 inches, round.

d. Hot Water: 1-1/2 inches 2 inches, round.

2. Valve-Tag Color:

a. Chilled Water: Green.

b. Condenser Water: Green.

c. Refrigerant: Natural.

d. Hot Water: Natural.

3. Letter Color:

a. Chilled Water: White.

b. Condenser Water: White.

c. Refrigerant: White.

d. Hot Water: White.

3.5 WARNING-TAG INSTALLATION

A. Write required message on, and attach warning tags to, equipment and other items where required.

END OF SECTION 23 05 53

Oakland ARTCC (ZOA) Control Wing Basement Renovation & Chillers/Cooling Tower Replacement (Major Mechanical) Project - Specifications
00 01 10 - Table of Contents
Division 01 - General Requirements
01 11 00 Summary of Work
01 14 00 Work Restrictions
01 25 00 Substitution Procedures
01 31 00 Project Management & Coordination
01 32 00 Construction Progress Documentation
01 33 00 Submittal Procedures
01 35 13 Special Project Procedures
01 35 29 Health, Safety, and Emergency Response Procedures
01 35 53 Security Regulations
01 45 00 Quality Control
01 50 00 Temporary Facilities & Controls
01 61 00 Common Product Requirements
01 66 00 Product Storage & Handling Requirements
01 73 00 Execution
01 73 29 Cutting & Patching
01 74 19 Construction Waste Management
01 74 23 Final Cleaning
01 77 00 Closeout Procedures
01 78 23 Operation & Maintenance Data
01 78 39 Project Record Documents
01 79 00 Demonstration & Training
01 91 13 General Commissioning Requirements
Division 02 - Existing Conditions
02 41 19 Selective Demolition
02 82 00 Asbestos Abatement & LCC Demolition
Division 03 - Concrete
03 01 30 - Maintenance of Cast-In-Place Concrete
03 30 00 - Cast-In-Place Concrete
Division 05 - Metals
05 12 00 Structural Steel Framing
05 50 00 Metal Fabrications
05 52 13 Pipe & Tube Railings
05 53 13 Bar Gratings
Division 06 - Wood, Plastics & Composites
06 10 00 Miscellaneous Rough Carpentry
06 16 00 Sheathing
06 41 16 Plastic Laminate-Faced Architectural Cabinets
06 65 29 Plastic Fascia & Soffits
Division 07 - Thermal & Moisture Protection
07 54 23 Thermoplastic Polyolefin (TPO) Roofing
07 71 00 Roof Specialties
07 84 13 Penetration Firestopping
07 84 46 Fire-Resistive Joint Systems
07 92 00 Joint Sealants
Division 08 - Openings
08 11 13 Hollow Metal Doors & Frames
08 31 13 Access Doors & Frames
08 71 00 Door Hardware
08 80 00 Glazing
08 91 19 Fixed Louvers
Division 09 - Finishes
09 22 16 Non-Structural Metal Framing
09 29 00 Gypsum Board
09 29 84 Prefinished Gypsum Board
09 51 13 Acoustical Panel Ceilings
09 65 13 Rubber Base & Accessories
09 65 19 Resilient Tile Flooring
09 67 23 Resinous Flooring
09 69 00 Access Flooring
09 84 33 Sound-Absorbing Wall Units
09 91 23 Interior Painting
Division 10 - Specialties
10 14 23 Panel Signage
10 26 00 Wall & Door Protection
10 26 16 Edge Bumper Guards
10 44 13 Fire Protection Cabinets
10 44 16 Fire Extinguishers
10 81 13 Bird Control Devices
Division 21 - Fire Suppression
21 13 13 Fire Suppression Systems
Division 22 - Plumbing
22 05 00 Common Work Results for Plumbing
22 05 13 Common Motor Requirements for Plumbing Equipment
22 05 17 Sleeves and Sleeve Seals for Plumbing Piping
22 05 19 Meters & Gages for Plumbing Piping
22 05 23 General-Duty Valves for Plumbing Piping
22 05 29 Hangers & Supports for Plumbing Piping and Equipment
22 05 48 Vibration & Seismic Controls for Plumbing Piping and Equipment
22 05 53 Identification for Plumbing Piping and Equipment
22 07 19 Plumbing Piping Insulation
22 11 16 Domestic Water Piping
22 11 19 Domestic Water Piping Specialties
22 13 16 Sanitary Waste & Vent Piping
22 13 19 Sanitary Waste Piping Specialties
22 34 00 Fuel-Fired, Domestic Water Heaters
22 45 00 Emergency Plumbing Fixtures
22 47 00 Drinking Fountains & Water Coolers
Division 23 - Heating, Ventilating, and Air Conditioning
23 05 00 Common Work Results for HVAC
23 05 13 Common Motor Requirements for HVAC Equipment
23 05 19 Meters & Gages for HVAC Piping
23 05 23 General-Duty Valves HVAC Piping
23 05 29 Hangers & Supports for HVAC Piping and Equipment
23 05 48 Vibration & Seismic Controls for HVAC Piping and Equipment
23 05 53 Identification for HVAC Piping and Equipment
23 05 93 Testing, Adjusting, and Balancing
23 07 13 Duct Insulation
23 07 19 HVAC Equipment & Piping Insulation
23 09 00 Instrumentation & Controls for HVAC
23 11 13 Facility Natural-Gas Piping
23 21 11 Hydronic Piping
23 21 13.13 Underground Hydronic Piping
23 21 23 Hydronic Pumps
23 25 00 HVAC Water Treatment
23 30 00 Air Duct Accessories
23 31 13 Metal Ducts
23 34 23 HVAC Power Ventilators
23 37 13 Diffusers, Registers, and Grilles
23 41 13 Panel Air Filters
23 64 16 Centrifugal Water Chillers
23 65 00 Cooling Towers
23 73 13 Modular Indoor Central Station Air Handling Units
23 81 23 Computer Room Air Conditioners
23 82 39 Propeller Unit Heaters
23 84 13 Humidifiers
Division 26 - Electrical
26 05 00 Common Work Results for Electrical
26 05 19 Low-Voltage Electrical Power Conductors and Cables
26 05 26 Grounding & Bonding for Electrical Systems
26 05 29 Hangers & Supports for Electrical Systems
26 05 33 Raceway & Boxes for Electrical Systems
26 05 48 Seismic Controls for Electrical Systems
26 05 53 Identification for Electrical Systems
26 09 23 Lighting Control Devices
26 18 39 Low Voltage Motor Controller
26 22 00 Low Voltage Transformers
26 24 16 Panelboards
26 27 26 Wiring Devices
26 28 16 Enclosed Switches & Circuit Breakers
26 29 23 Variable Frequency Drive
26 41 13 Lightning Protection for Structures
26 43 13 Surge Protection for Low-Voltage Electrical Power Circuits
26 51 00 Interior Lighting
26 56 00 Exterior Lighting
Division 27 - Communications
27 15 00 Communications Horizontal Cabling
27 51 16 Public Address & Mass Notification Systems
Division 28 - Electronic Safety & Security
28 31 00 Fire Detection & Alarm
Division 31 - Earthwork
31 20 00 Earth Moving
31 50 00 Excavation Support & Protection
Division 32 - Exterior Improvements
32 12 16 Asphalt Paving
32 13 13 Concrete Paving
32 17 23 Pavement Markings
32 31 13 Chain Link Fences & Gates