DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

NEW ENGLAND REGIONAL OFFICE

12 NEW ENGLAND EXECUTIVE PARK

BURLINGTON, MA 01803

TECHNICAL

SPECIFICATIONS

FOR THE

RTR INSTALLATION PROJECT

at the

Logan International Airport Boston, MA

PREPARED BY:

BOSTON Communications AJW-E13A

DATE: 21-Nov-16

TABLE OF CONTENTS

SECTION
TITLE

DIVISION 1 ‑ GENERAL REQUIREMENTS

1-1
Summary Of Work
1-2
Site Access, Construction Limits, Use of Facilities And Work Hours
1-3
Coordination, Local Permits, and Testing
1-4
Government Furnished Material
1-5
Planned Contract Progress Schedule
1-6
Preconstruction Conference
1-7
Submittals
1-8
Temporary Facilities
1-9
Materials and Equipment
1-10
Contract Close Out
1-11
Safety and Health

DIVISION 2 ‑ SITE WORK

2-2
General Site Work
2-4
Excavating and Backfilling for Utility Systems

and Buildings

DIVISION 3 – CONCRETE

3-1
Concrete Formwork
3-2
Concrete Reinforcement
3-3
Cast-In-Place-Concrete
3-4
Finishing and Curing

DIVISION 13 – SPECIAL CONSTRUCTION

13-1
Antenna Tower
13-2
Shelter Installation

DIVISION 26 ‑ ELECTRICAL

26-1 26-2

26-3 Electrical Work Fiber Cable Work

Coax Cable Work

APPENDIX – A - SOIL BORING

APPENDIX - B - TOWER DESIGN

APPENDIX – C - SHELTER SPECIFICATIONS

APPENDIX - D - ANTENNA SPECS

APPENDIX - E - MASSPORT REQUIREMENTS

1-1 SUMMARY OF WORK

1-1.1 General.‑ These specifications, together with the referenced specifications, and standards specified in the Contract Documents, cover the requirements of the Federal Aviation Administration, hereinafter referred to as the Government or FAA, for certain work associated with the installation of; a 21ft x 22.5ft (exterior dimensions) concrete shelter bldg., along with a 12ft high steel antenna tower platform (16ft x 24ft with walk up stairway at one end), cable ice bridging, cable installation, underground duct bank conduits for electrical power and fiber, counterpoise grounding and lightning protection, located at the Boston Logan International Airport in Boston, MA.

1-1.2 Scope. – The Contractor shall provide the necessary labor, materials, supplies, and equipment to install:

1. one concrete equipment shelter bldg. (21' square) and a 16ft x 24ft x 12ft high steel antenna tower platform with stairway.

2. ice bridging cable tray and Heliax coax cables from the new RTR shelter to the new tower.

3. underground duct bank conduits from existing RVR shelter to new RTR shelter with:

a. Air-blown fiber and associated micro-duct/ tube cable.

b. 12 pr #19 RDUP PE-39 copper cable .

4. New 75 KVA transformer (Single Phase) with Pad.

5. New outdoor Power Distribution Rack off transformer.

(underground duct bank conduits from Power Distribution Rack to existing RVR shelter and new RTR with power cables.)

6. Excavate and install concrete footings for both the shelter bldg. and the antenna tower, place bldg., erect antenna tower along with all associated items: cable ice tray, platform, railings, stairway, antenna mounts, grounding and lightning protection, etc.; and perform site work grading as required.

Contractor’s basic work flow will consist of:

· Site layout, underground cable marking & Identification

· Soil Borings (3), along with soil data/analysis (see Appendix - A)

· Excavation, trenching, and installation of power and fiber duct banks.

· Install concrete foundations per manufacturer’s drawings for both bldg. and antenna tower structure.

· Set, assemble and complete the concrete shelter bldg. with power and fiber.

· Supply, assemble and erect the 12ft high antenna tower structure per tower design requirements.

· Install a high quality FAA Type: L-810 dual configuration steady burning red incandescent dual bulb type obstruction light with photocell (i.e. Flight Light model L-810-OB22A31). The obstruction light shall be mounted no less than 12 inches above the uppermost handrail of the tower platform.

· Supply surveyed latitude and longitude data (NAVD 88) for the center point of both the shelter bldg. and antenna tower.

· Install self-supporting overhead ice bridging/cable tray extended between the shelter and antenna platform per drawings.

· Install new 36” H x 36” W x 12”D coax cable junction box (NEMA 4X), with ground bars, grounding, and N(F) bulkhead adapters, on the tower platform.

· Install new 36”H x 36” W x 12” D coax cable junction box with two coax surge protection ground bars, grounding, and Polyphaser coax surge protectors (Polyphser PN: IS-NEMP-C0) inside the new RTR shelter.

· Install (26), ½” Heliax cables (PN: LDF4-50A) from the surge protectors in the new RT R shelter j-box to the N(F) bulkhead connectors on the tower platform j-box. All Heliax cables shall be terminated with N(M) connectors (PN:L4TNM-PS). The cables shall be connected to a surge protector in the RTR shelter j-box and N(F) bulkhead connector in the antenna tower platform j-box.

· Install 4” - GRSC’ s from 75kva transformer to Power Distribution Rack (PDR); from PDR to new RTR and to existing RVR shelter (with power cables) and from RVR shelter to RTR shelter (with fiber and copper communications cables).

· Install 1, fiber Micro-Duct distribution box in the RTR and RVR shelters.

· Install 1, fiber patch panel in the RTR and RVR shelters.

· Install 1, Dura-Line 8.5mm/6mm 4-Way Micro-Duct from the RTR to RVR; via new GRCS conduit.

· Install 1, 24 single-mode Enterprise Blown riser rated fiber cable from the RTR patch panel to the RVR patch panel; via new Micro-Duct.

· Install 1, 12 62.5/125 multi-mode Enterprise Blown riser rated fiber cable from the RTR patch panel to the RVR patch panel; via new Micro-Duct.

· Terminate all fiber cables with ST connectors and connect to fiber patch panel connector panel per drawings.

· Install 66-blocks and lightning protection in RTR and RVR shetlers.

· Install 1, 12 pair #19 RDUP PE-39 copper cable from new RTR to existing RVR; via new GRSC conduit.

· Remove existing MF RVR transformer and associated wiring.

· Install the specified underground counterpoise grounding and lightning protection system for both the shelter and tower and connect via exothermic cad-welds; refer to drawings.

· Install Dense Graded Crushed Stone (Mass DOT Spec. M2.01.7) completely under and around the perimeter (extend 3ft beyond tower and shelter) and between the tower and RTR shelter as indicated on drawings.

· Grade, level and install new topsoil and grass seeding as needed to bring any and all disturbed areas during construction back to original conditions.

Installation Procedure

During the installation, all work shall be coordinated with the on-site Contracting Officer's Representative (COR). A project schedule with anticipated installation and cutover dates shall be submitted to the on-site COR.

The Contractor shall locate and clearly mark any and all existing underground; utilities, power and communication cables, before performing soil borings and beginning any excavation procedures. The Contractor shall coordinate with the on-site COR for the exact location of the new foundation, underground conduits, conduit markers, and hand-holes/manholes.

Any shutdown of the utility power or communication services to any FAA facility will be coordinated with the on-site COR. All facility shutdowns shall be requested by the Contractor 48 hours before the desired shutdown.

There are existing power service feeds, telecommunication cables and FAA field equipment within buried underground conduits and cables. Extreme care must be taken during the excavation process so these cables are not severed or affected. Any disconnection or separation of these cables will result in an inoperable facility that will have a direct effect on air traffic. The Contractor will be fully responsible for the immediate repair and cost of any severed or damaged cables during this contract administration.

The Contractor is advised that current FAA facilities are fully operational and any unscheduled interruptions may cause aircraft accidents and loss of life. The facilities shall remain operational throughout the entire contract unless a shutdown is scheduled.

1-1.3 Intent of Specifications. - This specification identifies all labor, materials, supplies and equipment to perform the work required to modernize the facility. All work performed and all materials and equipment used shall be subject to the approval of the COR. This shall include, but not be limited to, testing, inspection, scheduling, reporting, and submittals.

1.1.4 Contract Documents/Drawings. ‑ These documents form a part of this specification:

Drawing No.
Title
BOS-501665-G001
COVER SHEET
BOS-501665-G002
GENERAL NOTES (SHEET 1 OF 2)
BOS-501665-G003
GENERAL NOTES (SHEET 2 OF 2)
BOS-501665-A001
SHELTER AND TOWER ELEVATION

BOS-501665-A002

BOS-501665-A003

BOS-501665-A004

SHELTER AND TOWER PLAN

RTR SHELTER INTERIOR

RTR SHELTER EXTERIOR

BOS-501665-C001

BOS-501665-C002

BOS-501665-C003

SITE PLAN

PROPOSED SITE PLAN

TRENCH AND DUCT DETAILS

BOS-501665-Q001
ANTENNA JUNCTION BOX DETAILS
BOS-501665-Q002
SHELTER JUNCTION BOX DETAILS

BOS-501665-E001

BOS-501665-E002

BOS-501665-S001

GROUNDING AND LIGHTNING PROTECTION

ELECTRICAL ONE LINE DIAGRAM

PLATFORM LAYOUT

1-1.4.1 Measurements: - All dimensions shall be verified, by the contractor, using actual on-site field measurements. Any discrepancies between the specifications/drawings and the existing field conditions shall be referred to the COR before any work is performed.

1-1.5 Document sources.

1-1.5.1 Federal specifications.‑ The Federal specifications, standards, supplements, amendments, and indices are prepared and issued by the General Services Administration of the Federal Government. They may be obtained from the Specifications Activity, Printed Materials Supply Division, Building 197, Naval Weapons Plant, Washington, D. C. 20407.

1-1.5.2 Applicable documents.‑ The current issues of the following documents that are in effect on the date of issuance of the request for offer form a part of this specification and are applicable herein.

1.

AIA

American Institute of Architects

2.

AISC

American Institute of Steel Construction

3.

ANSI

American National Standards Institute

4.

ACI

American Concrete Institute

5.

FS

Federal Specification

6.

OSHA

Occupational Safety and Health Administration

7.

ASTM

American Society for Testing and Materials

8.

NFPA

National Fire Protection Association

1-1.5.3 Project Coordination - The Contractor is required to coordinate all construction activities with; FAA, MASSPORT and the System Management Office (SMO) personnel through the COR. All work which effects FAA or flight operations shall be coordinated and approved by FAA personnel through the COR at least twenty-four (24) hours in advance of the scheduled work. Failure to notify and obtain the necessary approval may result in a rescheduling of the work. No claim for delay will be entertained in such case. If weather conditions or aircraft operations preclude a scheduled shutdown of an existing FAA facility or runway, the Contractor shall reschedule the work. The Contractor will be required to coordinate all power shutdowns of existing facilities with the FAA SSC office through the COR at least twenty-four (24) hours in advance.

1-1.5.4 Layout of Work - The Contractor shall lay out his/her work from the established base lines and benchmarks indicated on the drawings and shall be responsible for all measurements in connection therewith. The Contractor shall furnish, at his own expense, all stakes, templates, tools, and materials and labor as may be required in laying out any part of the work. The Contractor will be held responsible for the execution of the work to such lines and grades as may be established or indicated by the COR. It shall be the responsibility of the Contractor to maintain and preserve all stakes and other marks previously established until authorized to remove them. If such marks are destroyed by the Contractor, or through his negligence, before authorized removal, they may be replaced by the COR at his discretion. The expense of replacement will be deducted from any amounts due or to become due to the Contractor.

1-2 SITE ACCESS, CONSTRUCTION LIMITS, USE OF FACILITIES AND WORK HOURS

1-2.1 General.‑ Contractor shall be escorted at all times by FAA personnel. Access into the site is via Massport Security gates and requires a driver who is fully "Red Badged" and certified by Massport to have access to and be allowed to drive on Logan Airport. Arrangements will be made with the COR for daily access into the actual RTR site. The contractor is responsible for obtaining a valid "Red Badged" escort for the duration of this project.

1-2.1.2 Damage to site.‑ Damage to the FAA site or any abutting properties caused by the contractor's activities must be repaired by the contractor. All costs of repairs shall be paid by the contractor. After notice to proceed and prior to the commencement of construction, the contractor and the COR shall conduct joint inspections of the existing areas to be affected by the construction. Existing conditions shall be noted by both the contractor and the COR and will be used as the basis for determination of damages caused by the contractor's operations.

1-2.1.3 Contractor's use of premises.‑

1-2.1.3.1 Work Hours. - Work shall begin no earlier than 7:00 A.M. each morning Monday through Friday and shall end at 3:30 P.M. Any deviation from this work schedule shall be submitted to the COR for approval. All work beyond normal work hours shall be requested in writing to the COR 24 hours in advance. Approval of the request shall be allowed at the COR's discretion.

During construction, if the contractor plans to stop work, the contractor shall notify the COR at least 24 hours prior to that time. The contractor shall notify the COR 48 hours in advance in order to reschedule any on site activity after stopping work.

1-2.1.3.2 Airport Safety. - The Contractor shall comply with all MASSPORT safety requirements for material disposal, badges, radio transceivers, flashing lights, vehicular operations on the AOA, special insurance requirements, displaced threshold markings, crane operations, delivery schedules and requirements and construction safety plans according to OSHA or FAA requirements. MASSPORT has jurisdiction over operating procedures on and around the airport. The Contractor shall comply with the items discussed at the preconstruction conference.

1-2.1.3.3 Airport Security. - The Contractor shall meet all of the security requirements identified by MASSPORT. These requirements will be discussed further at the Preconstruction Conference.

1-2.1.3.4 Equipment Operation. - No equipment will be permitted to extend above the 20:1 obstruction clearance plane along the extended centerline of the runway when landing operations are conducted on the runway. The 20:1 obstruction clearance plane starts at the displaced threshold four hundred (400) feet inboard from the runway threshold (at the runway elevation).

1-2.1.3.5 Work Limitations. - Should air traffic activity increase, or adverse weather conditions require discontinuance of work that would interfere with air traffic, the Contractor will be required to stop such work promptly and remove any equipment or materials which may constitute interference. Said potential delays shall not result in any additional cost to the government.

1-2.1.3.6 Runway Safety Area Construction Limitations. - No construction materials and/or construction equipment shall be stored within two-hundred fifty (250) feet of the active runway centerline or within one hundred fifty (150) feet of the active taxiway centerline overnight.

No excavation will be allowed to remain open (unprotected) overnight within two hundred fifty (250) feet of the centerline of the runway nor within one hundred fifty (150) feet of the centerline of the taxiway. If the construction activity necessitates that an excavation remain open overnight within this area, the Contractor shall obtain specific written approval from the COR and MASSPORT Operations to utilize steel plates having a minimum thickness of one (1) inch to fully cover the excavation.

Outside the safety zone, over 250 feet from the centerline of the runway and over 150 feet of the centerline of the taxiway, no excavations will be allowed to remain open without the specific written approval of the airport operator and the COR. If approval has been received, the trenches and/or excavations left open overnight shall be marked with warning tape, flashing yellow construction lights, and/or other approved method of marking the construction area.

1-2.1.3.7 Storage Piles. - The location of storage piles shall be as approved by the COR and MASSPORT. Storage piles of any material shall be located so as not to interfere with access to the site.

1-2.1.3.8 Vehicles in Airport Operations Area (AOA). - No movement by the Contractor or his/her subcontractors shall be permitted within the AOA without permission from the COR, MASSPORT and air traffic. All movements within the AOA shall be discussed with the COR. All vehicles operating within the AOA shall be properly identified, and escorted by a radio equipped vehicle with a properly badged driver. AOA operations shall be discussed in detail at the preconstruction meeting.

1-2.1.3.9 Radio Communications. - Refer to Appendix C, MASSPORT Requirements.

1-2.1.3.10 Man-Hole Access. - Access to man-holes shall be coordinated with the COR, MASSPORT Operations, and MASSPORT Fire/ Crash/ Rescue. The Contractor shall follow all MASSPORT requirements for access to and work performed within man-holes. Work in the man-holes shall conform to all OSHA, MASSPORT, FAA, and local regulations.

1-2.1.3.11 Existing Utilities. - Subsurface utilities and cables, whose existence is known to the FAA, are shown on the contract drawings in approximate locations. Other utilities may not be shown on the contract drawings. The Contractor shall field verify the location of underground utilities before excavating. This shall be accomplished, in part, by coordinating with the local FAA System Support Center (SSC), the COR, and Massport Operations.

1.2.1.3.12 Excavation. - "Hand excavation" methods shall be required when within 10ft or less of known utilities and used in locating all existing utilities. The Contractor, at no additional cost to the Government shall immediately repair any damage caused by the Contractor to any and all utilities. Repairs, if necessary, shall be in accordance with the specifications, Massport and conditions stipulated by the COR.

1-2.1.3.13 Massport Contractor Requirements - Massport requires the contractor to supply an approved/valid "Red Badged" Massport Licensed Escort at all times. A minimum of one escort with a valid "Red Badge" shall be on site at all times with the contractor and sub-contractors.

1-2.1.3.14 - Contractor shall assume full responsibility for the protection and safekeeping of products stored on the site.

1-2.1.3.15 - The contractor and subcontractors shall maintain the job site in a neat and orderly condition. This includes the daily removal of rubbish, waste materials, tools, equipment, and any other debris that the COR deems necessary.

1-3 COORDINATION, LOCAL PERMITS AND TESTING

1-3.1 General.‑

1-3.1.1 Scope.- This section covers the requirements for testing and permits, inspections and approvals and coordination of construction required to complete the work.

1-3.2 Applicable Documents.- (not used).

1-3.3 Requirements.-

1-3.3.1 Project Coordination.- The contractor shall prepare a detailed schedule of work, and arrange the work so as to prevent conflicts between subcontractors. The contractor shall be responsible for coordination of the work by different trades, and all of the work of this contract. The contractor shall resolve all coordination conflicts that arise among subcontractors.

1-3.3.2 Local permits.- The contractor shall apply, pay fees, and obtain local building permits and inspections as required by the city or state. Permits shall be posted as required.

1-3.3.3 Building Codes.- Construction shall be performed in compliance with the most current editions of BOCA, UBC Building Codes, the National Electrical Code and the specifications mentioned in this document. If Contract Documents exceed code requirements, the Contract Documents shall govern.

1-3.3.4 Test and inspections.- During the progress of work make all tests for the installation required by these specifications. If applicable, perform all testing required by State or local authorities having jurisdiction of the work. Tests shall be made before systems are concealed or covered. Tests shall be made in the presence of the COR and other authorities requiring tests. Unless specified otherwise, the Contractor shall pay all costs, inspection charges, and fees required for testing the work or materials.

1-3.4 Existing Utilities.- During the progress of the work, the contractor shall provide for all existing utilities and services affected. Maintain existing outlets, switches and lighting, whether or not they are shown on the plans. Continue the existence of all impacted electrical and other services in the building as part of the finished product.

1-4 GOVERNMENT FURNISHED MATERIAL

1-4.4 GFM LIST. - There are no Government Furnished Materials for this project. The contractor shall provide all materials and hardware which are necessary to complete the installation shown on these drawings and as stated within the specifications.

1-4.5 Storage Location.- The contractor shall coordinate with MassPort Operations for permission to use the North Camp site, or other approved assigned area, as a staging area for construction materials and equipment.

1-5 PLANNED CONTRACT PROGRESS SCHEDULE

1-5.1 SCHEDULE.- The contractor shall, within 14 days from date of award of contract (unless a different time is specified in the contract), submit to the (Contracting Officer) CO and COR for approval a "Realistic and Accurate" Project Schedule, showing the basic order listed below.

1-5.2 Schedule Milestones. -

· Site layout/marking/identifications

· Surveying of site; layout tower and bldg. point coordinates

· Soil Borings & analysis

· Foundation Designs (U.S - PE certified)- for bldg. and tower

· Foundation excavations

· Conduit (duct banks), splice boxes, and cable installations

· Foundation installations

· Bldg. deliver and placement

· Tower delivery

· Tower erection

· Ice Bridging delivery/installation

· Grounding and lightning protection

· Final site grading, gravel spreading, and any repairs 1-6 PRECONSTRUCTION CONFERENCE - The contractor shall attend a preconstruction conference to be conducted by the FAA. Local procedures related to ingress-egress, use of premises, station security, construction work schedule, temporary facilities, material disposal, and the FAA SSC (Service Support Center) operations will be discussed. The time and location for the preconstruction conference shall be established by the CO after contract award.

1-7 SUBMITTALS

1-7.1 General.-

1-7.1.1 Submittal requirements.- Provide submittals where required in the individual specification sections and as required below.

1-7.1.2 Prior to the Notice to Proceed.- Specific submittal data currently listed and required by the various sections of this specification shall be submitted to the COR for approval. The following submittal items must be approved by the FAA:

· Construction Schedule

· Contractor’s preconstruction safety and health checklist

· Soil boring analysis data

· Shelter: fabrication, design, layout, exterior and interior fit-up, etc. (foundation design MA PE stamped)

· Tower fabrication: design, layout, shop drawings, antenna mounts, etc.. (foundation design- MA PE stamped drawings / tower design - PE stamped within continental US)

· junction boxes, conduits, all materials supplied / etc.

· Ice Bridging product information and installation specs

· Heliax cable product information, connectors, terminations, ground bars, etc...

· A written certification that no Asbestos Containing Material will be provided and installed by the contractor and or within the new Shelter bldg.

(Final approved "Foundation Designs", "Shelter Design" and "Tower Design" shall be provided in Micro station or CAD in addition to hard copies) 1-7.1.3 Procedure.- Two (2) complete sets of all product data shall be submitted and one set will be marked and returned to the contractor. Each product sheet, submitted for approval, shall have in the lower right hand corner, just above the title block, a 4 inch by 4 inch open space in which the COR can indicate action taken. All submittals shall be accompanied by transmittal letters identifying the contents of the copy. Submittals shall be delivered in adequate time for FAA review (10 calendar days maximum) and FAA resubmittal review (10 calendar days maximum) before the work, which the respective submittal represents, is fabricated or delivered to the site. Work requiring approval shall not be initiated prior to approval of submittal. Submittals shall be checked by the contractor and coordinated with the work of other trades involved before they are submitted for approval. Submittals incompleteness or inadequate description will be justification for disapproval. Submittals shall bear the following information:

a.

Specification page and paragraph number.

b.

Name of project and facility.

c.

Name of contractor and subcontractor or supplier.

d.

Clearly identified contents and location of work.

1-7.1.4.- By submitting product sheets, the contractor thereby represents that he has determined and verified the following:

a.

Space limitations.

b.

Coordination with equipment furnished under other specification sections.

c.

Catalog numbers and similar data.

d.

Compliance with requirements of the work and of the contract documents.

e.

Compatibility with existing facility materials and sizes.

1-7.1.5 Shop drawing approval.- The checking, marking, or approval of the shop drawings and/or product data by the COR shall not be construed as a complete check, but will indicate only that the general method of construction and detailing is satisfactory. Approval will not relieve the contractor of the responsibility for any error that may exist. The contractor shall be responsible for the dimensions and design of adequate connections, details, and satisfactory service of the item.

1-7.1.5.1 Approved as submitted.- If "approved as submitted" is marked by the COR, each copy of the shop drawings or product data will be identified as having received such approval by being stamped and dated. After submittal has been approved, no substitution will be permitted without written approval by the COR.

1-7.1.5.2 Approved as noted.- If "approved as noted" is marked by the COR, the shop drawings or product data is satisfactory contingent upon contractor acceptance of corrections, notations, or both and, if accepted, does not require resubmittal.

1-7.1.5.3 Not approved.- If "not approved" is checked by the COR, the shop drawing or submittal data does not meet job requirements and the contractor must resubmit. If shop drawings or submittal data are disapproved, the contractor shall resubmit the corrected material, in the same quantity as specified for the original submittal.

1-7.1.6 Samples.- The Government reserves the right to request samples of any products or materials proposed for use on this project. Specific samples currently listed under various sections of this specification will be required.

1-7.1.7 Resubmittal.- Resubmit all items marked “disapproved” or “resubmit” within 10 calendar days of receipt. Resubmit construction schedule each 14 days after the original approval with actual dates filled in and dates for any additional submittal or re-submittals.

1-8 TEMPORARY FACILITIES

1-8.1 General.- The contractor shall provide and pay for all temporary services and facilities as specified below and as necessary for the proper and expeditious execution of the work. Contractor shall make, or have made all connections to existing services and sources of supply as necessary and/or indicated and pay all charges for it. Contractor shall provide all labor, materials, equipment, and appurtenances necessary for the complete installation, operation, and maintenance of all temporary service systems and facilities. All work under this section shall comply with applicable laws, rules, regulations, codes, ordinances, and orders of all federal, state, and local authorities having jurisdiction for the safety of persons, materials, and property. Contractor shall remove all such temporary installations and connections when no longer necessary for the project work.

1-8.2 Lighting and Power.- Contractor shall provide lighting and power as needed by means of contractor supplied generator.

1-8.3 Dumpster.- There are no waste disposal units at the project sites. Contractor shall provide a suitable dumpster for construction waste (or remove all trash and debris from the site on a daily basis). Have container emptied with suitable frequency so that trash does not overflow and blow around site and adjacent property. A cover is required and shall be provided on the dumpster in order for the refuse not to blow out. Contractor shall be responsible for the timely, legal disposal of all construction waste. Contractor shall dispose of all removed equipment that is deemed unusable by the FAA. Determination shall be made by the COR. All construction waste shall be legally disposed of off the airport, by the Contractor.

1-8.4 Port-a-potty Service.- There are no restroom facilities at the project site. Employ a portable toilet contractor to provide one portable toilet on the job site for the duration of the contract. The paper shall be checked daily and the toilet shall be evacuated and recharged twice weekly.

1-9 MATERIALS AND EQUIPMENT

1-9.1 General.‑ Material and equipment incorporated into the work shall conform to applicable specifications and standards and comply with size, make, type, and quality specified, or as specifically approved in writing by the COR. Manufactured and fabricated products shall be designed, fabricated, and assembled in accordance with the best engineering and shop practices. Like parts of duplicate units shall be manufactured to standard sizes and gages, and shall be interchangeable. Two or more items of the same kind shall be identical and manufactured by the same manufacturer. Products shall be suitable for service conditions. Equipment capacities, sizes, and dimensions shown or specified shall be adhered to unless variations are specifically approved in writing. Do not use material or equipment for any purpose other than for which it is designed or specified. Furnish and install products specified, under options and conditions for substitution stated in this section.

1-9.1.2 Transportation and handling.‑ Products shall be delivered in undamaged condition, in manufacturer's original containers or packing, with identifying labels intact and legible. Shipments shall be inspected to ensure compliance with requirements of contract documents and approved submittals, and that products are properly protected and undamaged immediately on delivery. Provide equipment and personnel to handle products by methods to prevent soiling or damage to products or packing.

1-9.2 Asbestos Containing Materials (ACM).- The use of ACM for new material on this project is prohibited. Before the Notice to Proceed the contractor shall provide written certification to the Contracting Officer that no ACM will be used in the proposed construction.

1-10 CONTRACT CLOSE OUT

1-10.1 Acceptance of work.‑ The Contractor shall schedule a final inspection with the COR. The Contractor shall correct discrepancies noted during the final inspection, clean the premises and notify the COR that the work is ready for acceptance.

1-11 SAFETY AND HEALTH

1-11.1 Applicable Publications - The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

1-11.1.1 Code of Federal Regulations (CFR)

1-11.1.2 - OSHA General Industry Safety and Health Standards (29 CFR 1910), Publication V2206; OSHA Construction Industry Standards (29 CFR 1926). One source of these regulations is OSHA, which includes a combination of both parts 1910 and 1926 as they relate to construction safety and health. It is for sale by the Superintendent of Documents, U.S. Government Printing Office, Washington DC 20402.

1-11.1.3 - National Emission Standards for Hazardous Air Pollutants (40 CFR, Part 61)

1-11.1.4 - Federal Standard (Fed. Std.)

1-11.1.5 - Material Safety Data Sheets, Preparation and the submission of.

1-11.2 Work Covered by this Section - This section is applicable to all work covered by this contract

1-11.3 Definitions of Hazardous Materials - Refer to hazardous and toxic materials/substances included in Subparts H and Z of 29 CFR 1910; and to others as additionally defined in Fed. Std. 313. Those most commonly encountered include asbestos, polychlorinated biphenyl’s (PCBs), explosives, and radioactive material, but may include others, such as lead paint, etc.

1-11.3.1 Spray Painting - No spray painting will be allowed within the construction area, without prior approval from COR.

1-11.3.2 Smoking - No smoking will be allowed within the building. Smoking shall be confined to designated areas outside the building.

1-11.4 Quality Assurance - The contractors onsite foreman and or designated personnel shall ensure and maintain QA throughout the projects implementation.

1-11.4.1 Safety Discussion during Preconstruction Conference - Representatives of the contractor shall provide the contractor’s safety and health programs during the preconstruction conference. All safety and health provisions pertinent to the work shall be discussed with the CO and the COR at this time. The contractor shall be prepared to discuss, in detail, the measures he/she intends to take in order to control any unsafe or unhealthy conditions associated with the planned work. The contractor’s superintendent and his /her safety representative shall attend this meeting.

1-11.4.2 Compliance with Regulations - All work, including the handling of hazardous materials shall comply with applicable state and municipal safety and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply.

1-11.4.3 Contractor Responsibility - The contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of the work.

1-11.4.4 Inspections, tests and reports -

1-11.4.5 Safety Plan - The contractor shall submit a plan for maintaining a safe working environment for construction workers employed on this project, and for the rest of the personnel working in the building. As a minimum, the plan shall show scheduled inspections of equipment and job conditions to check for potential hazards. The plan shall contain a statement that current OSHA regulations on safety in the construction industry will be followed. The plan shall list the directions by automobile and the telephone number for the nearest hospital emergency room, and police and fire department numbers. The plan will be used by the COR to insure that the work is accomplished in accordance with accepted safety practices.

The COR may stop any operation that is in violation of the OSHA standards and fails to comply with the safety plan or accepted safe work practices.

1-11.5 Submittals -

1-11.5.1 Accident Reporting - A copy of each accident report, which the Contractor or subcontractors submit to insurance carriers, shall be forwarded through the COR to the CO as soon as possible after the accident occurs.

1-11.5.2 Permits - If hazardous materials are disposed of off-site, submit copies of permits from applicable Federal, State, or municipal authorities.

1-11.5.3 Material Safety Data Sheets - The material safety data sheets shall be provided for posting on the job site by the COR on every material the contractor provides including but not limited to construction adhesives, paint, solvents for cleaning and fuel, if applicable. MSDS sheets shall be as printed by the material manufacturer.

1-11.5.4 OSHA Bulletins.- Post the bulletins on construction health and safety as required by law. Post an emergency notice with telephone numbers for medical, Police, Fire, EPA, and Poison Control Center telephone numbers in the stairwell area. Submit this item prior to commencing any work.

1-11.6 Materials and Equipment - Special facilities, devices, equipment, clothing, and similar items used by the contractor in the execution of work shall comply with the applicable regulations.

1-11.7 Hazardous Materials - The contractor shall bring to the attention of the COR any material suspected of being hazardous which he/she encounters during execution of the work. A determination will be made by the COR as to whether the contractor shall perform tests, and/or if the material is found hazardous and additional protective measures are needed, a contract change may be required, subject to applicable provisions of the contract.

1-11.8 Suspension of Work - When the contractor or his/her subcontractors are notified by the COR of any unsafe conditions caused by noncompliance with the provisions of the contract, the contractor shall immediately correct the unsafe or unhealthy condition. If the contractor fails to correct the problem condition(s) to the satisfaction of the COR promptly, all or any part of the work may be suspended in accordance with AMS Clause No. 3.10.1-8, “Suspension of Work”. When, in the opinion of the COR, satisfactory corrective action has been taken to correct the unsafe and unhealthy condition, a start order will be provided immediately. No extension of time or compensation will be allowed in connection with or by reason of this type of work stoppage.

1-11.9 Protection - The contractor shall take all necessary precautions to prevent injury to the public, building occupants or his/her employees. The contractor shall take all necessary precautions to prevent public or private property damage or loss.

1-11.9.1 - Work shall not be performed in any area occupied by Federal employees unless adequate steps are taken for the protection of Federal employees.

1-11.9.2 -Whenever practicable, the work area shall be fenced, barricaded, or otherwise blocked off to prevent unauthorized entry into the work area. This includes marking off and barricading the perimeter of excavated areas until backfilled.

1-11.9.3 Alternate precautions - When the nature of the work prevents isolation of the work area, alternate precautions such as the posting of signs, the use of signal persons, the erection of barricades or similar protection around particularly hazardous operations shall be used as appropriate.

END OF SECTION 1

2-2 GENERAL SITE WORK

2-2.1 GENERAL - This section covers the requirements of general site work, consisting of excavation, trenching, backfilling, compacting, soil stabilization, grading, graveling, and clean-up.

2-2.1.1 SCOPE - Excavate for the new RTR shelter bldg. and tower foundations. Perform trenching for the new direct buried conduits for power and fiber as indicated on the contract drawings. Restore grading with approved equipment at the site as directed by the COR.

2-2.2 APPLICABLE DOCUMENTS - The following publications of the issues in effect on the date of this solicitation form a part of this section to the extent referenced.

American Society for Testing and Materials (ASTM):

D 2922-81 Test Methods for Density of Soil and Soil

Aggregate in Place by Nuclear Methods (Shallow Depth)

Federal Specification FAA-C-1391b (Installation and Splicing of Underground Cables).

2-2.3

MATERIALS -

2-2.3.1 Site Materials - Trench backfill material shall be sand and stone-free earth as specified hereinafter and shall be in accordance with Federal FAA-C-1391b (Installation and Splicing of Underground Cables), no stones larger than 2 inch contained in backfill material.

2-2.3.2 Fill Materials - All fill material shall be free from organic matter, debris, vegetation and other deleterious substances. It shall be of a quality suitable for the purpose intended and shall compact thoroughly without the presence of excessive voids when watered and compacted. Fill shall be non-expansive in nature.

2-2.4

CONSTRUCTION -

2.2.4.3 Excavation - Excavation shall take place only after complete identification of all underground cables and utilities have been properly identified at the site. Any interruption or damage to underground cables or utilities will be repaired immediately to the COR’s satisfaction at the contractors expense. Excavation procedures shall adhere to all OSHA and Safety standards (both Federal and State) with respect to slope, use of trench boxes, excavator set back, etc.

The contractor shall use extreme caution when excavating within 10ft of known underground utilities or cables. Hand digging/excavation will be required in any areas within proximity of 10ft or less from these known and identified utilities and cables.

2-2.4.4 Trenching - Underground cable and utility trenches shall be excavated where shown on the drawings. Trenches shall be excavated to a depth as indicated on the drawings. All underground cable trenching shall conform to Federal Order FAA-C-1391b (Installation and Splicing of Underground Cables). All trenches shall run as indicated and shall be the depth indicated on the drawings. Cable, conduit, or pipes shall not vary more than four (4) inches either side of the straight line layout.

2-2.4.4.1 Over Excavation - Where excavation is carried to a depth greater than required, backfilling shall be subject to approval by the COR and shall be compacted as required.

2-2.4.4.2 Wet Excavation - No additional compensation will be allowed for any sheeting, shoring, pumping, or draining required to place and keep excavations in dry condition for construction. No water shall be allowed to remain in or around any part of the work.

2-2.4.4.3 Existing Facilities - Contact local FAA personnel through the COR prior to the start of any excavation. Maintain a record of phone conversations and site meetings that take place. Additionally, prior to any excavation or trenching, utilize a cable detector to verify and locate any utilities and cable runs which may be in the vicinity of site work or crossed by the new cable runs. The existing utilities and cable runs shall be exposed by hand digging in these areas and shall be protected from any possible damage. Any damage caused by the contractor shall be immediately repaired with materials and methods approved by the COR at no additional cost to the Government.

2-2.4.4.4 Connections to Existing Utilities - Conduit feeds for both the electrical power and the communication cables (fiber) are to be installed from the existing nearby FAA facility (RVR) and co-located transformer to the new RTR building located adjacent to the new tower.

2-2.4.4.5 Trench Backfill and Fill - Layers shall not exceed loose depths of 8 inches as specified in FAA-C-1391b (Installation and Splicing of Underground Cables). Each layer shall be properly moistened and compacted, as specified herein, by power operated mechanical equipment. Where utilities are not shown to be concrete encased, the first layer of backfill shall be 3 inches sand, with no particles over 1/4 inch diameter.

2-2.4.4.6 Plastic Marking Tape - Plastic marking tape for identifying and locating underground utilities shall be acid and alkali resistant polyethylene film, 6 inches wide and 0.004 inch thick. Tape shall have foil backing to enable detection by metal detector at a depth of 3 feet. All utility lines shall be marked with a printed inscription and color as follows:

Red:

Electric Duct.

Yellow:

Fuel Line.

Orange:

Telephone and Communications.

Blue:

Water Line.

Green:

Sanitary Sewer Line.

2-2.4.5 Aggregate Base - Dense Graded Stone (FAA P-209) max stone ¾” – Mass DOT Spec M2.01.7.

2-2.4.6 Compaction - All loose or disturbed soil shall be compacted in place by approved compaction equipment with a minimum of four complete passes over the entire area.

2-2.4.7 Grading - Grade site areas to the lines and grades indicated on the drawings or as directed. Slope graded areas approximately 2% for drainage away from the structures and site area. Areas within the limit of grading shall be finish graded to fill ruts, holes, etc., and to remove surface rocks or boulders.

2-2.4.8 Pavement Removal - (Not Used)

2-2.4.9 Pavement Replacement - (Not Used)

2-2.4.10 ENVIRONMENTAL CONSIDERATIONS -

2-2.4.10.1 General. - All construction operations shall be conducted in such a manner as to prevent the pollution to air, water or land, and shall, within reasonable limits control noise and the disposal of solid waste material, as well as other pollutants.

2-2.4.10.2 Protection of water resources. - The Contractor shall control the disposal of fuels, oils, bitumens, calcium chloride, acids or harmful materials, both on and off the premises and shall comply with applicable Federal, State, County and Municipal laws concerning pollution of rivers and streams while performing work under this contract. Special measures shall be taken to prevent chemicals, fuels, oils, greases, bituminous materials, herbicides and insecticides, and surface drainage from entering public waters. Water used in on-site material processing, concrete curing, foundation and concrete cleanup, and other waste waters shall not be allowed to re-enter a stream if an increase in the turbidity of the stream could result.

2-2.4.10.3 Dust control. - The Contractor shall maintain all excavations, embankments, stockpiles, access roads, plant sites, waste areas, borrow areas, and all other work areas free from excess dust to such reasonable degree as to avoid causing a hazard or nuisance to the Using Service or to others. Approved temporary methods consisting of sprinkling, chemical treatment, or similar methods will be permitted to control dust. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs.

2-2.4.10.4 Erosion control. - Surface drainage from cuts and fills within the construction limits, whether or not completed, and from borrow and waste disposal areas, shall be graded to control erosion within acceptable limits. Temporary control measures shall be provided and maintained until permanent drainage facilities are completed and operative. The area of bare soil exposed at any one time by construction operations should be held to a minimum.

2-2.4.10.5 Post-construction cleanup. - The Contractor shall cleanup and eliminate any and all signs of temporary construction facilities such as haul roads, work areas, structures, foundations of temporary structures, stockpiles of excess or waste materials, and other vestiges of construction prior to final acceptance of the work. These disturbed areas shall be graded and filled and the areas seeded unless otherwise noted on the drawings.

2-2.5 QUALITY ASSURANCE -

2-2.5.1 - When excavations are completed, the contractor shall notify the COR for his inspection and approval prior to placement of concrete or installation of cables, ducts, conduits, or piping.

2-3 - NOT APPLICABLE

2-4 EXCAVATING AND BACKFILLING FOR UTILITY TRENCHES, TOWER AND SHELTER FOUNDATIONS

2-4.1 GENERAL -

2-4.1.1 Scope - Excavate all soil for the necessary trenches for underground conduits to be installed at the new Remote Transmitter and Receiver facility (RTR). Backfill and compact after the COR has inspected the work and authorizes it. Purchase and install the specified sand at the bottom of conduit trenches as shown on the drawings. Provide sufficient compaction of soil for installation of aggregate base course and conduit. Distribute and or remove the left over material about the site as directed by the COR.

Excavate all soil necessary for the tower and shelter foundations installation per design. Compact bottom of foundation excavations with mechanical driven vibratory compactor thoroughly prior to concrete pour. Distribute and or remove any leftover material about the site as directed by the COR.

2-4.1.2 Related Work In Other Sections - Section 26 Electrical

2-4.2 Applicable Documents - The current issues of the following documents in effect on the date of the invitation for bid form a part of this specification and are applicable to the extent specified herein.

2-4.2.1 American Society For Testing and Materials -

ASTM D698

Standard Test Methods for Moisture Density Relations of Soils and Soil Aggregate Mixtures Using 5.5 lb. Rammer and 12-inch Drop

ASTM D1556 Density of Soil in Place by the Sand-Cone Method

ASTM C33

Standard Specification For Concrete Aggregates

2-4.3 MATERIALS -

2-4.3.1 Filter/Separation Fabric - N/A 2-4.3.2 Sand - Material meeting the requirements and grading criteria for fine aggregate in ASTM C33.

2-4.3.3 Dense Graded Stone – Use MA DOT State Highway specification M2.01.7 for “Dense Graded Crushed Stone” or P-209 “Crushed Aggregate Base Course”, ¾” max size in areas as shown on drawings over filter fabric.

2-4.4 Excavation - Excavation shall be unclassified and include the removal of all materials of every name and nature, including all earth and rock of any type and obstructions of any type, either natural or man-made which may be required for the installation of all work described in the various divisions of these specifications.

2-4.4.1 Structures - Excavate to the depths and dimensions indicated for footings, foundations, slabs on grade and other structures. In the event unsuitable or unstable soil is encountered below this limit, the COR will determine the depth of removal of such soil. Cut sides and bottom of foundation excavations clean. In all instances, allow sufficient room for installation and inspection of forms. Foundation excavation bottom shall be compacted by mechanical compactor thoroughly prior to any concrete pour.

2-4.4.2 Access Road and Parking Area – North or South Security Gates to Perimeter Rd. surrounding airport..

2-4.4.3 Unauthorized excavation and low areas - Where the contractor excavates beyond the lines shown on the drawings, the contractor at no additional…

This is the start of the file's text. The full file is on GovTribe.

Other files

File Type Posted
DTFAEN 16 C 00186 Amendment 0005.pdf PDF
DTFAEN-16-R-00186 Amendment 0001 signed.pdf PDF
DTFAEN 16 C 00186 Amendment 0006.pdf PDF
BOS RTR-2016-final cnstrct drwgs.pdf PDF
DTFAEN 16 C 00186 Amendment 0004.pdf PDF
DTFAEN 16 C 00186 Amendment 0007.pdf PDF
DTFAEN-16-R-00186 SIR final copy (2).2 —
DTFAEN-16-R-00186 Amendment 0002.pdf PDF
BusinessDeclaration May 2016.pdf PDF
DTFAEN 16 C 00186 Amendment 0008.pdf PDF
Section B Bid Schedule.pdf PDF
BOS RTR PAST PERF SURVEY.doc DOC document
DTFAEN 16 C 00186 Amendment 0003.pdf PDF
MASSPORT Contractor Requirements as of August 2006.pdf PDF
BOS RTR- wage determination.pdf PDF
BusinessDeclaration May 2016.pdf PDF
BOS RTR- wage determination.pdf PDF
DTFAEN-16-R-00186 Amendment 0001 signed.pdf PDF
DTFAEN 16 C 00186 Amendment 0004.pdf PDF
Section B Bid Schedule.pdf PDF
DTFAEN 16 C 00186 Amendment 0003.pdf PDF
DTFAEN 16 C 00186 Amendment 0005.pdf PDF
DTFAEN 16 C 00186 Amendment 0007.pdf PDF
DTFAEN-16-R-00186 SIR final copy (2).2 —
DTFAEN-16-R-00186 Amendment 0002.pdf PDF
BOS RTR-2016-final cnstrct drwgs.pdf PDF
BOS RTR PAST PERF SURVEY.doc DOC document
BOS RTR Final Specs 28July16 - JT (2) (3).2 —
MASSPORT Contractor Requirements as of August 2006.pdf PDF
DTFAEN 16 C 00186 Amendment 0006.pdf PDF
BOS RTR Final Specs 28July16 - JT (2) (3).2 —
BusinessDeclaration May 2016.pdf PDF
MASSPORT Contractor Requirements as of August 2006.pdf PDF
Section B Bid Schedule.pdf PDF
DTFAEN-16-R-00186 Amendment 0001 signed.pdf PDF
BOS RTR-2016-final cnstrct drwgs.pdf PDF
DTFAEN 16 C 00186 Amendment 0005.pdf PDF
DTFAEN 16 C 00186 Amendment 0003.pdf PDF
DTFAEN 16 C 00186 Amendment 0004.pdf PDF
DTFAEN-16-R-00186 Amendment 0002.pdf PDF
BOS RTR PAST PERF SURVEY.doc DOC document
BOS RTR- wage determination.pdf PDF
DTFAEN-16-R-00186 SIR final copy (2).2 —
DTFAEN 16 C 00186 Amendment 0006.pdf PDF
BOS RTR PAST PERF SURVEY.doc DOC document
DTFAEN-16-R-00186 Amendment 0002.pdf PDF
Section B Bid Schedule.pdf PDF
MASSPORT Contractor Requirements as of August 2006.pdf PDF
BusinessDeclaration May 2016.pdf PDF
DTFAEN-16-R-00186 Amendment 0001 signed.pdf PDF
Show 40 more

Latest 50 of 108 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .