Specifications: 12-018539 CAI Replace AHU2-5.pdf

PDF 586 KB Posted

Attached to
SIR/RFO DTFAAC-17-R-02323 Miscellaneous Mechanical Construction Services
Solicitation number
DTFAAC-17-R-02323
Issued by

About this file

Specifications: 12-018539 CAI Replace AHU2-5 (pdf)

View the file

Other files

File Type Posted
Standard Form (SF) 25A, Payment Bond.SF —
Contractor's Release.pdf PDF
Past Performance Information Form.pdf PDF
Standard Form (SF) 25, Performance Bond.SF —
Chapter 33 Construction Safety Chapter.pdf PDF
Statement of Work (SOW) 06.01.2016.SOW —
Table of Contents 06.01.2016.pdf PDF
Q&A DTFAAC-17-R-02323.pdf PDF
Business Declaration.pdf PDF
Amendment 2 documents.pdf PDF
Wage Rate Decision OK160049 09.02.2016.pdf PDF
Screening Information Request (SIR).SIR —
Proposal Form CAI Replace AHU2-5.doc DOC document
Specifications: 12-018539 CAI Replace AHU2-5.pdf PDF
Past Performance Survey.pdf PDF
Drawing: 12-018539 CAI Replace AHU2-5.pdf PDF
Operational Control Documents Combined.pdf PDF
Client Authorization Letter.pdf PDF
Amendment A001 complete.pdf PDF
Pre Bid Site Visit Attendee List.pdf PDF
Contractor's Release.pdf PDF
Screening Information Request (SIR).SIR —
Wage Rate Decision OK160049 09.02.2016.pdf PDF
Standard Form (SF) 25, Performance Bond.SF —
Table of Contents 06.01.2016.pdf PDF
Client Authorization Letter.pdf PDF
Drawing: 12-018539 CAI Replace AHU2-5.pdf PDF
Pre Bid Site Visit Attendee List.pdf PDF
Past Performance Information Form.pdf PDF
Operational Control Documents Combined.pdf PDF
Business Declaration.pdf PDF
Q&A DTFAAC-17-R-02323.pdf PDF
Specifications: 12-018539 CAI Replace AHU2-5.pdf PDF
Chapter 33 Construction Safety Chapter.pdf PDF
Past Performance Survey.pdf PDF
Standard Form (SF) 25A, Payment Bond.SF —
Statement of Work (SOW) 06.01.2016.SOW —
Proposal Form CAI Replace AHU2-5.doc DOC document
Past Performance Survey.pdf PDF
Business Declaration.pdf PDF
Contractor's Release.pdf PDF
Past Performance Information Form.pdf PDF
Proposal Form CAI Replace AHU2-5.doc DOC document
Operational Control Documents Combined.pdf PDF
Standard Form (SF) 25A, Payment Bond.SF —
Pre Bid Site Visit Attendee List.pdf PDF
Chapter 33 Construction Safety Chapter.pdf PDF
Screening Information Request (SIR).SIR —
Drawing: 12-018539 CAI Replace AHU2-5.pdf PDF
Statement of Work (SOW) 06.01.2016.SOW —
Show 40 more

Latest 50 of 101 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FAA W.O. 2012018539 July, 2016

TABLE OF CONTENTS - 1

PROJECT MANUAL

TABLE OF CONTENTS

PROJECT SPECIFICATIONS

DIVISION 7 – THERMAL AND MOISTURE PROTECTION

07221 ROOF INSULATION

07400 ROOFING

07620 SHEET-METAL FLASHING AND TRIM

07651 FLEXIBLE FLASHING AND SHEET METAL

DIVISION 15 – MECHANICAL

15040 MECHANICAL DEMOLITION

15060 PIPE AND PIPE FITTINGS

15100 VALVES

15240 VIBRATION AND EXPANSION COMPENSATION

15250 MECHANICAL INSULATION

15635 VARIABLE SPEED MOTOR CONTROL

15800 CUSTOM AIR HANDLING UNITS

15890 METAL DUCTWORK

15898 TESTING AND BALANCING – MECHANICAL SYSTEMS

15900 HVAC INSTRUMENTATION AND CONTROLS

END TABLE OF CONTENTS

07221-1

SECTION 07221

ROOF INSULATION

PART 1 GENERAL

1.01 RELATED DOCUMENTS

A. Documents affecting work of this Section include, but are not necessarily limited to, General Requirements, bidding documents and drawings.

1.02 SUMMARY

A. This portion of the specification describes materials and workmanship required for the installation of insulation board.

B. All materials described herein shall be furnished and installed by the roofing contractor unless specifically noted otherwise.

C. Roof Areas covered under this section: As shown on the drawings.

1.03 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Insulation shall be delivered to the site in an undamaged and dry condition. Material received that is not dry or is otherwise damaged shall be rejected.

B. Storage under polyethylene or similar non-breathing film stock shall not be permitted.

C. Proper storage on or off the site shall be the responsibility of the roofing contractor.

D. Any unused insulation remaining on the roof at the end of the workday shall be returned to storage.

1.04 INSULATION - GENERAL

A. All insulation materials must be approved by the warrantor of primary roof membrane materials. Samples should be provided to the manufacturer and written approval from the warrantor of primary roof membrane materials is required before ordering these materials for the project.

B. Insulation boards shall be full size except when cutting is required at roof edges and openings. Boards that are broken, cracked, have been exposed to moisture, or are otherwise damaged shall not be used.

C. The proper installation and fit of wood nailers, blocking, and other rough carpentry in appropriate locations shall be verified prior to installation of roof insulation.

D. Caution shall be exercised with construction traffic to avoid damage to new insulation.

Breaking or crushing of insulation is unacceptable and any damaged insulation shall be replaced at the roofing contractor's expense.

E. Insulation shall be laid with end joints staggered and all joints tight; however, boards shall not be forced into place.

07221-2

F. No more insulation shall be installed during any 8 hour work period than can be covered by all plies of roofing during that same work period. At the end of the work period, temporary edge seals shall be installed to protect the roof insulation. Upon resumption of work, they must be removed. Such seals shall consist of strips of roofing felt applied and topcoated with specified interply adhesive.

G. Insulation surfaces shall be cleared of all debris before roofing is placed.

H. All precautions should be made to prevent bitumen drippage during and after application of insulation and roofing materials.

PART 2 PRODUCTS

1.01 INSULATION

A. Insulation Types:

1. First Layer: Polyisocyanurate

2. Second Layer: Polyisocyanurate

3. Tapered edge strip: ASTM C728-82, perlite. tapered from 1-5/8 inch to 1/8 inch

(on twelve inch dimension), size 12 x 48 inches or as approved by the system warrantor’s representative

B. Cants: ASTM C728-82, perlite.

C. Fasteners:

1. ES Products Inc. Bristol, RI

2. ITW Buildex Itasca, IL

3. Olympic Manufacturing Group Inc. New Rochelle, NY

4. Simplex Nails Americus, GA

5. Powers Rawl, Powers Fastening Inc. New Rochelle, NY

6. Construction Fasteners Wyomissing, PA

PART 3 – EXECUTION

1.01 CONDITION OF DECK

A. Prior to installing insulation, deck must be inspected and accepted by the roofing contractor and roofing system warrantor. Contractor must verify deck slopes and determine if insulation stops and/or backnailing is required by the warranty supplier based on the system being installed. All deficiencies must be corrected prior to start of work.

B. The roofing contractor shall perform all other work of preparing the deck. When insulation is applied, the deck shall be dry and free of dew, frost, ice, and snow.

C. The roofing contractor shall notify the building owner's representative of any improper installations.

1.02 THERMAL INSULATION

A. First Layer:

1. Insulation shall be secured to meet FM I-90 requirements according to membrane manufacturer's FM listings. Refer to FM Loss Prevention Data Sheet 1-29 for increased fastener requirements at perimeter and corners.

07221-3

2. Install additional fasteners to ensure insulation is firm under foot.

3. Drive mechanical fasteners as recommended by fastener manufacturer.

Fastener must properly engage the deck, secure the insulation and not damage the insulation surface or facer.

B. Insulation installation requirements:

1. Stagger joints at least six inches.

2. Install insulation boards in courses parallel to roof edges, mopping surface up.

3. Firmly butt each insulation board to surrounding boards. Do not jam or deform boards.

4. Maximum elevation variation between boards at joints: 1/8 inch.

5. Cut and fit insulation boards where roof deck intersects vertical surfaces. Cut board 1/4 inch from vertical surface.

6. All boards installed shall be 18 inches in length or width, minimum.

7. Promptly spread any adhesive that may accumulate on insulation surface to achieve smooth surface for roofing installation.

C. If warranty supplier requires backnailing of the plies due to slope, wood insulation stops or nailers shall be provided.

1. The wood nailer thickness shall be equal to the thickness of the insulation so that a smooth transition between the top surface of the membrane substrate and the top surface of the wood nailer is achieved.

2. Spacing of the wood nailers shall not exceed the recommendations of the warranty supplier.

1.03 TAPERED EDGE INSTALLATION

A. Tapered edge strips shall be adhered with the specified insulation adhesive.

B. Tapered edge strips are to be installed around all drains to form a continuous 48-inch square sump.

C. Tapered edge strips shall be used at perimeter roof edge where nailer and gravel stop is raised.

1.04 CANTS/WOOD COMPONENTS

A. Cant strips shall be installed at all 90-degree angles where the horizontal installation of insulation meets the vertical sides of roof penetrations and walls. Cants must be installed prior to application of membrane and flashings.

B. Contractor is responsible for supplying all perimeter wood (blocking and nailers as detailed on the drawings) and as necessary to meet new insulation heights.

END OF SECTION

07221-4

07400-1

SECTION 07400

ROOFING

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. SBS-modified bituminous membrane roofing.

B. Cover board.

C. Roof insulation.

D. Vapor retarder.

1.02 RELATED SECTIONS

A. Division 07 Section "Sheet Metal Flashing and Trim" for metal roof penetration flashings, flashings, and counterflashings.

1.03 REFERENCES

A. Roofing Terminology: Refer to the following publications for definitions of roofing work related terms in this Section:

1. ASTM D 1079 “Terminology Relating to Roofing and Waterproofing.”

2. Glossary of NRCA's "The NRCA Roofing and Waterproofing Manual.”

3. Roof Consultants Institute “Glossary of Roofing Terms” for definition of terms related to roofing work in this Section.

B. Sheet Metal Terminology and Techniques: SMACNA Architectural Sheet Metal Manual.

1.04 DESIGN CRITERIA

A. General Design Criteria: Installed roofing membrane system shall remain watertight; and resist specified wind uplift pressures, thermally induced movement, and exposure to weather without failure.

B. Material Compatibility: Roofing materials shall be compatible with one another under conditions of service and application required, as demonstrated by roofing system manufacturer based on testing and field experience.

C. Wind Uplift Performance: Roofing system shall be identical to systems that have been successfully tested by a qualified testing and inspecting agency to resist wind uplift pressure calculated in accordance with ASCE-7 and International Building Code 2009.

D. FMG Listing: Roofing membrane, base flashings, and component materials shall comply with requirements in FMG 4450 and FMG 4470 as part of a roofing system and that are listed in FMG's “RoofNav" for Class 1 or noncombustible construction, as applicable. Identify materials with FMG markings.

E. LEED Credits:

1. Roofing system shall be eligible for LEED Credit SS 7.1 and/or SS 7.2.

2. Insulation and cover board materials shall contribute to LEED credit MR 4.1.

3. Insulation package shall contribute to LEED EA credit.

4. Materials with minimal VOC shall contribute to LEED credit EQ 4.

F. T24/CRRC-1:

1. Roofing system shall comply with the requirements of Title 24.

2. Roofing membrane shall be tested by CRRC-1.

1.05 SUBMITTALS

A. Product Data: Manufacturer’s data sheets for each product to be provided.

07400-2

B. Detail Drawings: Provide roofing system plans, elevations, sections, details, and details attachment to other Work, including:

1. Base flashings, cants, and membrane terminations.

2. Tapered insulation, including slopes.

3. Crickets, saddles, and tapered edge strips, including slopes.

4. Insulation fastening patterns.

C. Verification Samples: Provide for each product specified.

D. Maintenance Data: Refer to Johns Manville’s latest published documents on www.specJM.com.

E. Guarantees: Special guarantees specified in this Section.

1.06 QUALITY ASSURANCE

A. Installer Qualifications: A qualified firm that is approved, authorized, or licensed by roofing system manufacturer to install manufacturer's product and that is eligible to receive the specified manufacturer's guarantee.

B. Manufacturer Qualifications: A qualified manufacturer that has FMG approval for roofing system identical to that used for this Project.

C. Testing Agency Qualifications: An independent testing agency with the experience and capability to conduct the testing indicated, as documented according to ASTM E 548.

D. Test Reports:

1. Roof drain and leader test or submit plumber’s verification.

2. Core cut (if requested).

3. Roof deck fastener pullout test.

E. Moisture Survey:

1. Submit prior to installation, results of a non-destructive moisture test of roof system completed by approved third party. Utilize one of the approved methods:

a. Infrared Thermography

b. Nuclear Backscatter

F. Source Limitations: Obtain all components from the single source roofing system manufacturer guaranteeing the roofing system. All products used in the system shall be labeled by the single source roofing manufacturer issuing the guarantee.

G. Fire-Test-Response Characteristics: Provide roofing materials with the fire-test-response characteristics indicated as determined by testing identical products per test method below by FMG, or another testing and inspecting agency acceptable to authorities having jurisdiction.

Materials shall be identified with appropriate markings of applicable testing and inspecting agency.

1.07 DELIVERY, STORAGE, AND HANDLING

A. Deliver roofing materials in original containers with seals unbroken and labeled with manufacturer's name, product brand name and type, date of manufacture, and directions for storage.

B. Store liquid materials in their original undamaged containers in a clean, dry, protected location and within the temperature range required by roofing system manufacturer.

C. Protect roof insulation materials from physical damage and from deterioration by sunlight, moisture, soiling, and other sources. Comply with insulation manufacturer's written instructions for handling, storing, and protecting during installation.

D. Handle and store roofing materials and place equipment in a manner to avoid permanent deflection of deck.

1.08 PROJECT CONDITIONS

A. Weather Limitations: Proceed with installation only when current and forecasted weather conditions permit roofing system to be installed in accordance with manufacturer's written instructions and guarantee requirements.

07400-3

1.09 GUARANTEE

A. Provide manufacturer's system guarantee equal to Johns Manville's Peak Advantage No Dollar

Limit Roofing System Guarantee.

1. Single-Source special guarantee includes roofing plies, base flashings, liquid applied flashing, roofing membrane accessories, and other single-source components of roofing system marketed by the manufacturer.

2. Guarantee Period: 10 years from date of Substantial Completion.

3. Wind Rider: Guarantee shall not exclude coverage for wind events up to 90 mph.

4. Hail Rider: Guarantee shall have no exclusions for hail events up to 2 inches

5. Accidental Puncture Rider: Guarantee shall provide coverage for accidental puncture for up to 16 billed repair hours per year for the life of the guarantee.

B. Installer’s Guarantee: Submit roofing Installer's guarantee, signed by Installer, covering Work of this Section, including all components of roofing system, for the following guarantee period:

1. Guarantee Period: Two Years from date of Substantial Completion.

PART 2 - PRODUCTS

2.01 SBS-MODIFIED ASPHALT-SHEET MATERIALS

A. Roofing Membrane Sheet: ASTM D 6164, Grade S, Type I, polyester-reinforced SBS-modified asphalt sheet; smooth surfaced; suitable for application method specified. Basis of Design:

Johns Manville DynaBase or to match existing roof system.

B. Roofing Membrane Cap Sheet ASTM D 6163, Grade G, Type I, glass-fiber-reinforced SBS-modified asphalt sheet; granular surfaced; suitable for application method specified. Basis of Design DynaGlas FR or to match existing.

2.02 BASE FLASHING SHEET MATERIALS - SBS

A. Backer Sheet: ASTM D 4601, Type II, asphalt-impregnated and -coated, glass-fiber sheet, dusted with fine mineral surfacing on both sides. Basis of Design: PermaPly 28 or to match existing.

B. Backer Sheet: ASTM D 6164, Grade S, Type I, polyester-reinforced] [ASTM D 6163, Grade S, Type I, glass-fiber-reinforced] [ASTM D 6162, Grade S, Type II, composite polyester- and glass-fiber-reinforced], SBS-modified asphalt sheet; smooth surfaced; suitable for application method specified. Basis of Design: DynaBase or to match existing.

C. Flashing Sheet: [ASTM D 6164, Grade G, Type II, polyester-reinforced] [ASTM D 6163, Grade G, Type I, glass-fiber-reinforced] [ASTM D 6221, Grade G, Type I, composite polyester-and glass-fiber-reinforced] [ASTM D 6298, embossed aluminum foil surfaced, glass-fiber-reinforced], SBS-modified asphalt sheet; granular surfaced; suitable for application method specified. Basis of Design: DynaClad or to match existing.

D. Liquid Applied Flashing: A liquid and fabric reinforced flashing system created with a stitch-bonded polyester scrim and a two-component, moisture cured, elastomeric, liquid applied flashing material, consisting of an asphalt extended urethane base material and an activator.

Basis of Design: PermaFlash System

2.03 AUXILIARY ROOFING MEMBRANE - BITUMINOUS

A. General: Auxiliary materials recommended by roofing system manufacturer for intended use and compatible with built-up roofing.

B. Asphalt Primer: ASTM D 41. Basis of Design: Asphalt Primer C. Asphalt Roofing Cement: ASTM D 4586, asbestos free, of consistency required by roofing system manufacturer for application. Basis of Design: Bestile Industrial Roof Cement.

http://www.specjm.com/files/pdf/DynaBaseRS4111.pdf http://www.specjm.com/files/pdf/DynaGlasFRrs4104.pdf http://www.specjm.com/products/roofing/permaply28.asp?system=burbituminous&type=hot http://www.specjm.com/files/pdf/DynaBaseRS4111.pdf http://www.specjm.com/files/pdf/DynaClad_RS_4116.pdf http://www.specjm.com/products/roofing/permaflash.asp?system=burbituminous&type=hot http://www.specjm.com/files/pdf/AsphaltPrimerRS2065.pdf http://www.specjm.com/files/pdf/BestileIndustrialCementv2RS2029.pdf

07400-4

D. Cold-Applied Adhesive: Roofing system manufacturer's asphalt-based, two-component, asbestos-free, cold-applied adhesive specially formulated for compatibility and use with membrane applications. Basis of Design: MBR Bonding Adhesive

E. Cold-Applied Flashing Adhesive: Roofing system manufacturer's asphalt-based, two-component, asbestos-free, trowel-grade, cold-applied adhesive specially formulated for compatibility and use with flashing applications. Basis of Design: MBR Flashing Cement

F. Mastic Sealant: As required by Johns Manville.

G. Fasteners: Factory-coated steel fasteners and metal or plastic plates meeting corrosion-resistance provisions in FMG 4470, designed for fastening roofing membrane components to substrate, tested by manufacturer for required pullout strength, and provided by the roofing system manufacturer. Basis of Design: All Purpose Fasteners and Plates

H. Roofing Granules: Ceramic-coated roofing granules matching specified cap sheet, provided by roofing system manufacturer.

I. Coating: Acrylic elastomeric coating with unique bleed-blocking properties particularly well suited for coating over asphalt surfaces. Basis of Design: JM CR Seam Coating

J. Miscellaneous Accessories: Provide miscellaneous accessories recommended by roofing system manufacturer.

2.04 REFLECTIVE AND WATERPROOF COATING

A. Elastomeric Coating: ASTM D 6083. A multipurpose, acrylic elastomeric coating for use over a variety of substrates with bleed-blocking properties for coating over asphalt surfaces. Basis of Design: TopGard 4000

2.05 WALKWAYS

A. Walkway Pads: Mineral-granule-surfaced, reinforced modified asphalt composition, slip-resisting pads, manufactured as a traffic pad for foot traffic provided by roofing system manufacturer, with a pad size of 32 inch x 32 inch. Basis of Design: Johns Manville DynaTred

2.06 COVER BOARD

A. Perlite Board: ASTM C 728; composed of expanded perlite, cellulosic fibers, binders and waterproofing agents with top surface seal-coated. Basis of Design: +/-1/2"-1” DuraBoard to match existing adjacent coverboard.

2.07 ROOF INSULATION

A. General: Preformed roof insulation boards that comply with requirements and referenced standards, selected from manufacturer's standard sizes and of thicknesses indicated.

B. Polyisocyanurate Board Insulation: ASTM C 1289, Type II, Basis of Design: ENRGY 3

1. Provide insulation package with R Value greater than the minimum required by applicable

Building Code.

2. Provide insulation package to flush out with the face of the existing adjacent insulation surfaces.

2.08 TAPERED INSULATION

A. Tapered Insulation: ASTM C 1289, provide factory-tapered insulation boards fabricated to slope to match the slope of existing adjacent insulation. Basis of Design: Tapered ENRGY 3.

2.09 INSULATION ACCESSORIES

A. General: Roof insulation accessories recommended by insulation manufacturer for intended use and compatible with membrane roofing.

http://www.specjm.com/files/pdf/MBRBondingAdhesiveRS4711.pdf http://www.specjm.com/products/roofing/permaflash.asp?system=burbituminous&type=hot http://www.specjm.com/files/pdf/AllPurposeFastenersRS7174.pdf http://www.specjm.com/files/pdf/TopGard4000rs2129.pdf http://www.specjm.com/products/roofing/dynatred.asp?system=burbituminous&type=hot http://www.specjm.com/files/pdf/DuraBoardRoofInsulationRS5091.pdf http://www.specjm.com/products/roofing/enrgy3.asp?system=burbituminous&type=hot http://www.specjm.com/products/roofing/tenrgy3.asp?system=burbituminous&type=hot

07400-5

B. Provide factory preformed saddles, crickets, tapered edge strips, and other insulation shapes where indicated for sloping to drain. Fabricate to slopes indicated.

C. Fasteners: Factory-coated steel fasteners and metal or plastic plates meeting corrosion-resistance provisions in FMG 4470, designed for fastening roof insulation to substrate, and furnished by roofing system manufacturer. Basis of Design: UltraFast Fasteners and Plates

D. Cold Fluid-Applied Adhesive: Manufacturer's No VOC, two-component cold fluid-applied adhesive formulated to adhere roof insulation to substrate. Basis of Design: MBR Bonding Adhesive

E. Urethane Adhesive: Manufacturer’s two component urethane adhesive formulated to adhere insulation to substrate. Basis of Design: JM Two-Part Urethane Insulation Adhesive

F. Insulation Cant Strips: ASTM C 728, perlite insulation board. Basis of Design:

G. Wood Nailer Strips: Comply with requirements in Division 06 Section "Miscellaneous Rough

Carpentry."

2.10 VAPOR RETARDER

A. SBS Vapor Retarder: ASTM D 6163, Grade S, Type I, glass-fiber-reinforced SBS-modified asphalt sheet; smooth surfaced; suitable for application method specified. Basis of Design:

DynaBase

PART 3 - EXECUTION

3.01 EXAMINATION

A. Examine substrates, areas, and conditions for compliance with requirements affecting performance of roofing system:

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.02 PREPARATION

A. Clean and remove from substrate sharp projections, dust, debris, moisture, and other substances detrimental to roofing installation in accordance with roofing system manufacturer's written instructions.

B. Prevent materials from entering and clogging roof drains and conductors and from spilling or migrating onto surfaces of other construction.

C. Prime surface of concrete deck with asphalt primer at a rate recommended by roofing manufacturer and allow primer to dry.

D. Proceed with installation only after unsatisfactory conditions have been corrected.

3.03 RE-ROOF PREPARATION

A. Remove all roofing membrane, surfacing, coverboards, insulation, fasteners, asphalt, pitch, adhesives, etc.

1. Remove an area no larger than can be re-roofed in one day.

B. Tear out all base flashings, counterflashings, pitch pans, pipe flashings, vents and like components necessary for application of new membrane.

C. Raise (disconnect by licensed craftsmen, if necessary) all HVAC units and other equipment supported by curbs to conform with the following:

1. Modify curbs as required to provide a minimum 8" base flashing height measured from the surface of the new membrane to the top of the flashing membrane.

2. Nail top of flashing and install new metal counterflashing prior to re-installation of unit.

3. Perimeter nailers must be elevated to match elevation of new roof insulation.

D. Immediately remove all debris from roof surface. Demolished roof system may not be stored on the roof surface.

E. Proceed with installation only after unsatisfactory conditions have been corrected.

http://www.specjm.com/files/pdf/UltrafastFastenersNplatesRS7099.pdf http://www.specjm.com/files/pdf/MBRBondingAdhesiveRS4711.pdf http://www.specjm.com/files/pdf/MBRBondingAdhesiveRS4711.pdf http://www.specjm.com/files/pdf/2-Part_UIA_IRS-4504.pdf http://www.specjm.com/files/pdf/DynaBaseRS4111.pdf

07400-6

3.04 VAPOR-RETARDER INSTALLATION

A. Install modified bituminous vapor retarder sheet according to roofing manufacturer's written instructions, starting at low point of roofing system. Extend roofing membrane sheets over and terminate beyond cants, installing as follows:

1. Unroll roofing membrane sheets and allow them to relax for minimum time period required by manufacturer.

B. Laps: Accurately align roofing membrane sheets, without stretching, and maintain uniform side and end laps. Stagger end laps. Completely bond and seal laps, leaving no voids.

1. Repair tears and voids in laps and lapped seams not completely sealed.

C. Completely seal vapor retarder at terminations, obstructions, and penetrations to prevent air movement into membrane roofing system.

3.05 INSULATION INSTALLATION

A. Coordinate installation of roof system components so insulation and cover board is not exposed to precipitation or left exposed at the end of the workday.

B. Comply with roofing system manufacturer's written instructions for installation of roof insulation and cover board.

C. Insulation Cant Strips: Install and secure preformed 45-degree insulation cant strips at junctures of roofing membrane system with vertical surfaces or angle changes greater than 45 degrees per manufacturer’s instruction.

D. Install tapered insulation under area of roofing to conform to slopes indicated.

E. Install insulation boards with long joints in a continuous straight line with end joints staggered between rows, abutting edges and ends between boards. Fill gaps exceeding 1/4 inch with like material.

F. Install one or more layers of insulation under area of roofing to achieve required thickness.

Where overall thickness is 4” or greater, install 2 or more layers with joints of each succeeding layer staggered from joints of previous layer a minimum of 6 inches in each direction.

G. Trim surface of insulation boards where necessary at roof drains so completed surface is flush and does not restrict flow of water.

H. Install tapered edge strips at perimeter edges of roof that do not terminate at vertical surfaces.

I. Adhered Insulation: Install each layer of insulation and cover board and adhere to substrate as follows:

1. Install each layer in a two-part cold fluid-applied adhesive according to roofing system manufacturer’s instruction.

2. Install each layer in a two-part urethane adhesive according to roofing system manufacturer’s instruction.

J. Proceed with installation only after unsatisfactory conditions have been corrected.

3.06 COVER BOARD INSTALLATION

A. Coordinate installing membrane roofing system components so cover board is not exposed to precipitation or left exposed at the end of the workday.

B. Comply with membrane roofing system manufacturer's written instructions for installing roof cover board.

C. Install cover board with long joints of cover board in a continuous straight line with end joints staggered between rows, abutting edges and ends between boards. Fill gaps exceeding 1/4 inch (6 mm) with cover board.

1. Cut and fit cover board within 1/4 inch of nailers, projections, and penetrations.

D. Trim surface of cover board where necessary at roof drains so completed surface is flush and does not restrict flow of water.

07400-7

1. Install tapered edge strips at perimeter edges of roof that do not terminate at vertical surfaces.

E. Adhered Cover Board: Adhere cover board to substrate as follows:

1. Install using a cold fluid-applied adhesive according to roofing system manufacturer’s instruction.

2. Install in a two-part urethane adhesive according to roofing system manufacturer’s instruction.

F. Proceed with installation only after unsatisfactory conditions have been corrected.

3.07 ROOFING MEMBRANE INSTALLATION, GENERAL

A. Install roofing membrane in accordance with roofing system manufacturer's written instructions, applicable recommendations of the roofing manufacturer and requirements in this Section.

B. Start installation of roofing membrane in presence of roofing system manufacturer's technical personnel.

C. Where roof slope exceeds 1/2 inch per 12 inches (1:24, contact the membrane manufacturer for installation instructions regarding installation direction and backnailing D. Cooperate with testing and inspecting agencies engaged or required to perform services for installing roofing system.

E. Coordinate installing roofing system so insulation and other components of the roofing membrane system not permanently exposed are not subjected to precipitation or left uncovered at the end of the workday or when rain is imminent.

1. Provide tie-offs at end of each day's work to cover exposed roofing membrane sheets and insulation with a course of coated felt set in roofing cement or hot roofing asphalt with joints and edges sealed.

2. Complete terminations and base flashings and provide temporary seals to prevent water from entering completed sections of roofing system.

3. Remove and discard temporary seals before beginning work on adjoining roofing.

F. Substrate-Joint Penetrations: Prevent roofing asphalt from penetrating substrate joints, entering building, or damaging roofing system components or adjacent building construction.

G. Proceed with installation only after unsatisfactory conditions have been corrected.

3.08 SBS-MODIFIED BITUMINOUS MEMBRANE INSTALLATION

A. Install one modified bituminous roofing membrane sheet and cap sheet according to roofing manufacturer's written instructions, starting at low point of roofing system. Extend roofing membrane sheets over and terminate beyond cants, installing as follows:

1. Adhere to substrate in cold-applied adhesive according to roofing system manufacturer’s instruction.

2. Unroll roofing membrane sheets and allow them to relax for minimum time period required by manufacturer.

B. Laps: Accurately align roofing membrane sheets, without stretching, and maintain uniform side and end laps. Stagger end laps. Completely bond and seal laps, leaving no voids.

1. Repair tears and voids in laps and lapped seams not completely sealed.

2. Apply roofing granules to cover exuded bead at laps while bead is hot.

C. Install roofing membrane sheets so side and end laps shed water.

3.09 FLASHING AND STRIPPING INSTALLATION

A. Install base flashing over cant strips and other sloping and vertical surfaces, at roof edges, and at penetrations through roof, and secure to substrates according to roofing system manufacturer's written instructions and as follows:

1. Prime substrates with asphalt primer if required by roofing system manufacturer.

07400-8

2. Backer Sheet Application: Install backer sheet and adhere to substrate in approved adhesive applied at rate required by roofing system manufacturer.

3. Backer Sheet Application: Install backer sheet and self adhere to substrate as required by roofing system manufacturer.

4. Flashing Sheet Application: Adhere flashing sheet to substrate in approved adhesive applied at rate required by roofing system manufacturer.

5. Flashing Sheet Application: Adhere flashing sheet to substrate in approved asphalt roofing cement; apply cement at rate required by roofing system manufacturer.

B. Extend base flashing up walls or parapets a minimum of 8 inches (200 mm) above roofing membrane and 4 inches (100 mm) onto field of roofing membrane.

C. Mechanically fasten top of base flashing securely at terminations and perimeter of roofing.

1. Seal top termination of base flashing with a strip of glass-fiber fabric set in MBR Flashing cement.

3.10 WALKWAY INSTALLATION

A. Walkway Pads: Mineral-granule-surfaced, reinforced modified asphalt composition, slip-resisting pads, manufactured as a traffic pad for foot traffic provided by roofing system manufacturer, with a pad size of 32” x 32”. Basis of Design: Johns Manville DynaTred

3.11 FIELD QUALITY CONTROL

A. Testing Agency: Owner will engage a qualified independent testing and inspecting agency to perform roof tests and inspections and to prepare test reports.

B. Final Roof Inspection: Arrange for roofing system manufacturer's Registered Roof Observer (RRO) to inspect roofing installation on completion and submit report to Architect.

C. Repair or remove and replace components of roofing system where test results or inspections indicate that they do not comply with specified requirements.

D. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.

3.12 PROTECTION AND CLEANING

A. Protect roofing system from damage and wear during remainder of construction period.

B. Clean overspray and spillage from adjacent construction using cleaning agents and procedures recommended by manufacturer of affected construction.

3.13 MANUFACTURER’S PROJECT SPECIFIC REQUIRMENTS

A. Prior to making repairs, notify Johns Manville Guarantee Services (800-922-5922) of intent to make repairs, and reference Guarantee Number ANM111067743. Any contractor bidding this project is required to be a Peak Advantage Contractor with Johns Manville and have written consent from Johns Manville to make repairs to this facility.

B. Any changes or modifications (to the scope of work listed below) required by Johns Manville in order to maintain existing guarantee and system integrity will supersede the written scope.

C. Upon completion of work, contact Johns Manville Guarantee Services to schedule a FIELD inspection.

D. Guy Anchor Repair:

1. Cut a 2’-0” x 2’-0” square area around existing guy wire anchors in the existing roof system, down to existing decking.

2. Remove material from repair area and dispose of properly.

3. Cut off existing cable supports, flush with existing deck surface, and remove.

4. Clean deck substrate of dust, debris, moisture and other substances detrimental to installation of repair roof materials, according to Manufacturer’s written instructions.

Remove any sharp projections.

07400-9

5. Proceed with installation of repair materials only after satisfactory conditions have been met.

6. Contact Manufacturer for instruction on securement of existing roofing system/insulation at perimeter of repair area so as to maintain system integrity.

7. At repair area, install new ENRGY3® Polyisocyanurate rigid insulation, of like thickness, to existing decking in JM One-Step two-part adhesive, per Manufacturer’s instruction.

8. Over new Polyiso, install a new cover board, to match existing type and thickness, in a uniform coverage of two-part MBR Flashing Cement.

9. Install two (2) layers of DynaBase base sheet, each in a uniform coverage of two-part MBR Flashing Cement, over new cover board.

10. Polyiso, cover board, and DynaBase to be cut to match size of repair area, with gaps no larger than ¼” at perimeter.

11. Over top layer of DynaBase and perimeter of existing cap sheet at repair area, install a single layer of DynaGlasFR cap sheet in a uniform coverage of two-part MBR Flashing Cement. DynaGlasFR cap sheet to be cut so that all edges extend a minimum of 12” past outside edges of repair area.

E. Existing Equipment Curbs Repair:

1. Cut an area of roofing around existing equipment curbs large enough to perform work listed, down to existing deck surface.

2. Remove material from repair area and dispose of properly.

3. Remove existing equipment curbs, flush with existing concrete deck surface, and dispose of properly.

4. Clean deck substrate of dust, debris, moisture and other substances detrimental to installation of repair roof materials, according to Manufacturer’s written instructions.

Remove any sharp projections.

5. Proceed with installation of repair materials only after satisfactory conditions have been met.

6. Contact Manufacturer for instruction on securement of existing roofing system/insulation at perimeter of repair area so as to maintain system integrity.

7. At repair area, install new ENRGY3® Polyisocyanurate rigid insulation, of like thickness, to existing decking in JM One-Step two-part adhesive, per Manufacturer’s instruction.

8. Over new Polyiso, install a new cover board, to match existing type and thickness, in a uniform coverage of two-part MBR Flashing Cement.

9. Install two (2) layers of DynaBase base sheet, each in a uniform coverage of two-part MBR Flashing Cement, over new cover board.

10. Polyiso, cover board, and DynaBase to be cut to match size of repair area, with gaps no larger than ¼” at perimeter.

11. Over top layer of DynaBase and perimeter of existing cap sheet at repair area, install a single layer of DynaGlasFR cap sheet in a uniform coverage of two-part MBR Flashing Cement. DynaGlasFR cap sheet to be cut so that all edges extend a minimum of 12” past outside edges of repair area.

END OF SECTION 07400

07400-10

07620-1

SECTION 07620

SHEET METAL FLASHING AND TRIM

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Flashings, counter flashings, gutters, downspouts, sheet metal roofing, and fabricated sheet metal items, as indicated in Schedule.

B. Reglets and accessories.

C. Precast concrete splash pads.

1.02 RELATED SECTIONS

A. Section 07631 - Gutters and Downspouts.

B. Section 07900 - Joint Sealers.

C. Section 09900 - Paints and Coatings: Field painting.

1.03 REFERENCES

A. ASTM A 653/A 653M - Standard Specification for Steel Sheets, Zinc-Coated (Galvanized) or

Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process; 1997.

B. ASTM B 32 - Standard Specification for Solder Metal; 1996.

C. ASTM B 209 - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate;

1996.

D. ASTM B 209M - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate

(Metric); 1995.

E. ASTM D 4586 - Standard Specification for Asphalt Roof Cement, Asbestos-Free; 1993.

F. SMACNA (ASMM) - Architectural Sheet Metal Manual; Sheet Metal and Air Conditioning

Contractors' National Association; 1993, Fifth Edition.

1.04 SUBMITTALS

A. See Section 01300 - Administrative Requirements, for submittal procedures.

B. Shop Drawings: Indicate material profile, jointing pattern, jointing details, fastening methods, flashings, terminations, and installation details.

1.05 QUALITY ASSURANCE

A. Perform work in accordance with SMACNA Architectural Sheet Metal Manual requirements and standard details, except as otherwise indicated.

B. Maintain one copy of each document on site.

07620-2

C. Fabricator and Installer Qualifications: Company specializing in sheet metal work with five years of documented experience.

1.06 PRE-INSTALLATION CONFERENCE

A. Convene one week before starting work of this section.

1.07 DELIVERY, STORAGE, AND HANDLING

A. Stack material to prevent twisting, bending, and abrasion, and to provide ventilation. Slope metal sheets to ensure drainage.

B. Prevent contact with materials which may cause discoloration or staining.

PART 2 PRODUCTS

2.01 SHEET MATERIALS

A. Galvanized Steel: ASTM A 653/A 653M, with G90/Z275 zinc coating; 0.02 inch thick steel.

B. Pre-Finished Galvanized Steel: ASTM A 653/A 653M, with G90/Z275 zinc coating; 0.02 inch core steel, shop pre-coated with modified silicone coating of color as selected.

C. Pre-Finished Aluminum: ASTM B 209 (ASTM B 209M); 0.032 inch thick; plain finish shop pre coated with fluoropolymer coating of color as selected.

2.02 ACCESSORIES

A. Fasteners: Galvanized steel, with soft neoprene washers.

B. Primer: Zinc chromate type.

C. Protective Backing Paint: Zinc chromate alkyd.

D. Sealant: Type specified in Section 07900.

E. Plastic Cement: ASTM D 4586, Type I.

F. Solder: ASTM B 32; Sn50 (50/50) type.

2.03 FABRICATION

A. Form sections true to shape, accurate in size, square, and free from distortion or defects.

B. Fabricate cleats of same material as sheet, minimum 4 inches wide, interlocking with sheet.

C. Form pieces in longest possible lengths.

D. Hem exposed edges on underside 1/2 inch; miter and seam corners.

E. Form material with flat lock seams, except where otherwise indicated. At moving joints, use sealed lapped, bayonet-type or interlocking hooked seams.

F. Fabricate corners from one piece with minimum 18 inch long legs; seam for rigidity, seal with sealant.

07620-3

G. Fabricate vertical faces with bottom edge formed outward 1/4 inch (6 mm) and hemmed to form drip.

PART 3 EXECUTION

3.01 EXAMINATION

A. Install surface mounted reglets true to lines and levels. Seal top of reglets with sealant.

B. Back paint concealed metal surfaces with protective backing paint to a minimum dry film thickness of 15 mil.

3.03 INSTALLATION

A. Conform to drawing details:

B. Insert flashings into reglets to form tight fit. Secure in place with lead wedges. Pack remaining spaces with lead wool. Seal flashings into reglets with sealant.

C. Secure flashings in place using concealed fasteners. Use exposed fasteners only where permitted.

D. Apply plastic cement compound between metal flashings and felt flashings.

E. Fit flashings tight in place. Make corners square, surfaces true and straight in planes, and lines accurate to profiles.

F. Solder metal joints for full metal surface contact. After soldering, wash metal clean with neutralizing solution and rinse with water.

3.04 FIELD QUALITY CONTROL

A. See Section 01400 - Quality Requirements, for field inspection requirements.

B. Inspection will involve surveillance of work during installation to ascertain compliance with specified requirements.

07620-4

07651-1

SECTION 07651

FLEXIBLE FLASHING AND SHEET METAL

1.01 RELATED DOCUMENTS:

A. Documents affecting work of this Section include, but are not necessarily limited to, General Requirements, bidding documents and drawings.

1.02 GENERAL

A. This portion of the specification sets forth the general requirements and describes materials and workmanship for installing the flashings and sheet metal on the roofing systems specified.

B. All materials described herein shall be furnished and installed by the roofing contractor unless specifically noted otherwise.

C. This section is for work on roofs: As shown on the drawings.

D. Work shall be in accordance with Architectural Sheet Metal Manual, latest edition, as issued by Sheet Metal and Air Conditioning Contractors' National Association, Inc., (SMACNA).

PART 2 - PRODUCTS

2.01 MECHANICAL FASTENERS

A. Sheet Metal to Masonry

1. Tapcon 1/4 inch diameter, Phillips flat head anchor with EPDM washer by Buildex Div. of ITW, Itasca, IL.

2. Length: Sufficient to provide 1-1/4 inch embedment.

B. Sheet Metal to Curbs

1. Fab-lok Fac 10-8 stainless steel screw, aluminum sleeve by Fabco Fastening Systems, West Newton, PA.

C. Stainless sheet steel to wood blocking:

1. Roofing nails: galvanized steel wire, flat head, diamond point, round, barbed shank.

2. Length: Sufficient to penetrate wood blocking 1-1/4 inches minimum.

D. Galvanized sheet steel to wood blocking:

1. Roofing nails; galvanized steel wire, flat head, diamond point, round, barbed shank.

2. Length: Sufficient to penetrate wood blocking 1-1/4 inches minimum.

E. Base Flashing to Masonry

1. Masonry nail by Simplex Nail, Inc., Americus, GA.

2. Round Cap Masonry Nail by Hillwood Mfg. co., Cleveland, OH.

2.02 METAL FLASHING

A. Plumbing vents:

1. Prefabricated plumbing vent flashings, 4 lb lead

07651-2

B. Pitch pan and bonnets:

1. Stainless steel: 24 gage - Type 304, ASTM A167

C. Reglet sealant:

Eco Caulking, Ecology Roof Systems, Inc.

Test Typical Value Test Method Rheological Properties @ 40° & 122°F No flow, no deformation ASTM C 920 Extrusion Rate 7 seconds ASTM C 920 Hardness Properties 40 ASTM C 920 Weight Loss 9% ASTM C 920 Tack Free Time 30 Hours ASTM C 920 Stain & Color Change No visible change, no stain ASTM C 920 Durability - Cyclic Movement Less than 1-1/2 in2 ASTM C 920 Adhesion & Cohesion Total Bond Loss Bubble Formation Less than 1/16" diameter ASTM C 920 Adhesion-In-Peel Aluminum 18-22 pli ASTM C 920

Concrete 20-25 pli Brick 19-23 pli No adhesion loss

Accelerated Aging No cracks greater than #2 on ASTM C 920 U.V. and Cold Temperature Bond Test

Asbestos Content 0% EPA 600/R-93/116

D. Wall Counterflashing Systems:

1. 24 Gauge Galvanized Steel

E. Roof to Wall Expansion Joint

1. C-S Group, Model BRJW

2. Nystrom EC Series

3. MM Systems ER Series

F. Gravel stop and fascia systems: Shop fabricated metal components per SMACNA standards approved by the roofing manufacturer.

1. 24 Gauge Kynar 500 Coated Galvanized Steel

G. Coping and Area divider covers: Shop fabricated metal components per SMACNA standards approved by the roofing manufacturer.

H. Expansion joint covers: Shop fabricated metal components per SMACNA standards approved by the roofing manufacturer

1. 24 Gauge Galvanized Steel

2.03 FLEXIBLE FLASHINGS:

A. Flashing ply sheet:

Flashing Base Ply Felt: Ecology Roof Systems, Inc.

Test Typical Value Test Method Breaking Strength (Strip) 110 lbf/in., MD ASTM D 5726

80 lbf/in., CMD Elongation (Strip) 40%, MD ASTM D 5726

45%, CMD

Breaking Strength (Grab) 275 lbf., MD ASTM D 5034

07651-3

230 lbf., CMD Elongation (Grab) 41%, MD ASTM D 5034

47%, CMD

Tear Strength 70 lbf., MD ASTM D 5726

60 lbf., CMD Asbestos Content 0% EPA/600/R-93/116 Fire Resistance Pass ASTM E 108 / UL 790 Weight 7.4 oz/yd2 ASTM D 3776 Thickness 45 mils ASTM D 1777

1. Flashing Top Ply:

E 554 Granule, Ecology Roof Systems, Inc.

Test Typical Value Test Method Thickness, mils (mm) 160 (4.0) ASTM D 5147 / D 6162 Maximum Load, 73.4 + 3.6°F (23 + 2°C), lbf/in (kN/m) 340 (59.54) MD ASTM D 5147 / D 6162

309 (54.12) XMD

Elongation at Maximum Load, 73.4 +

3.6°F (23 + 2°C), % 20.0 MD ASTM D 5147 / D 6162

17.0 XMD

Elongation at Break, 73.4 + 3.6°F

(23 + 2°C), % 75.0% MD ASTM D 5147 / D 6162

93.0 XMD

Tear Strength at 73.4 + 3.6°F (23 + 2°C), lbf (N) 496 (2,207) MD ASTM D 5147 / D 6162

502 (2,234) XMD

Tensile Strength at 0°F + 3.6°F (-18 + 2°C), lbf/in. 482 (84.41) MD ASTM D 5147 / D 6162

472 (82.66) XMD

Low Temperature Elongation at Maximum Load, 0°F + 3.6°F (-18 + 2°C), % 7.0 MD ASTM D 5147 / D 6162

6.0 XMD

Dimensional Stability, % 0.5 ASTM D 5147 / D 6162 Compound Stability, °F (°C) 230 (110) ASTM D 5147 / D 6162 Granule Embedment (Grams Loss) < 1.5 (Actual) ASTM D 5147 / D 6162 Net Mass per Unit Area, lb/100 ft.

(g/m2) 110 (5,370) ASTM D 5147 / D 6162 Asbestos Zero EPA/600/R-93/116 Fire Resistance Pass, Class A UL 790 / ASTM E 108 Length (Average) 32.8 ft. (10 m) Tape Measure

B. Adhesives and coatings:

1. Flashing adhesive:

Type III Asphalt, ASTM D 312

2. Reflective coating:

Eco Aluminum Shield, Ecology Roof Systems, Inc.

Test Typical Value Test Method Asbestos Content 0% EPA 600/R-93/116 Metallic Aluminum by Weight 15% ASTM D 2824 Non-Volatile Matter (NVM) 50% ASTM D 2824 Flash Point 100°F, minimum ASTM D 3278 Fire Rating Pass, Class A UL 790 / ASTM E 108 Uniformity & Consistency Acceptable as described ASTM D 2824 Stormer Viscosity (100 gm. driving load) 24 sec./100 rev. ASTM D 2824 Solar Reflectance 0.69 ASTM C 1549 Emissivity 0.40 ASTM C 1371

07651-4

C. Accessories:

1. Reinforcing fabric: Ecology Roof Systems, Inc.

Eco Glass Mesh II, Test Typical Value Test Method Weight 9.0 lbs./ 100 sq. ft. ASTM D 1668 Fabric Count 10 x 10 ASTM D 1668 Tensile (Warp and Fill Directions) 75 lbf/in., min. ASTM D 1668 Moisture Absorption None ASTM D 1668

2. Asphalt mastic:

Eco ARM, Ecology Roof Systems, Inc.

Test Typical Value Test Method Asbestos Content 0% EPA 600/R-93/116 Non-Volatile Matter by Weight 76-82% ASTM D 4586 Viscosity @ 77°F 450,000 - 950,000 cps ASTM D 2196 Density @ 77°F 9.5 - 10.0 lb/gal. ASTM D 1475 Resistance to Sag @ 140°F 1/8" maximum ASTM D 4586 Adhesion to Wet Surfaces 55% ASTM D 3409 Moisture by Weight 1.5% ASTM D 4586 Mineral or Other Stabilizers by Weight 38% ASTM D 4586 Asphalt by Weight 40% ASTM D 4586 Uniformity & Workability Acceptable as described ASTM D 4586 Behavior @ 140°F No blistering ASTM D 4586 Pliability @ 32°F No cracking/separation ASTM D 4586 Eco Elastic, Ecology Roof Systems, Inc.

Test Typical Value Test Method Asbestos Content 0% EPA 600/R-93/116 Non-Volatile Matter by Weight 76-82% ASTM D 4586 Tensile Strength @ 77°F 32-40 psi ASTM D 412 Elongation @ 77°F 100% ASTM D 412 Resistance to Sag @ 140°F 1/8" maximum ASTM D 4586 Adhesion to Wet Surfaces 75% ASTM D 3409 Moisture by Weight 2.0% ASTM D 4586 Mineral or Other Stabilizers by Weight 35% ASTM D 4586 Asphalt by Weight 43% ASTM D 4586 Uniformity & Workability Acceptable as described ASTM D 4586 Behavior @ 140°F No blistering ASTM D 4586 Pliability @ 32°F No cracking/separation ASTM D 4586

3. Asphalt primer:

Eco Rapid Dry Primer SP, Ecology Roof Systems Test Typical Value Test Method Asbestos Content 0% EPA/600/R-93/116 Viscosity 30 - 60 cps ASTM D 2196 Density 7.2 lbs/gal. ASTM D 1475 Solids by Weight 43% ASTM D 4479 Flash Point 101ºF minimum ASTM D 93

4. Flashing tape:

Eco Tape Seal, Ecology Roof Systems, Inc.

Test Typical Value Test Method Solids by Weight 100% ASTM D 1353 Rubber Modifier Polyisobutylene Fourier Transform-Infrared

(Butyl Rubber) Spectrosocopy Hardness Shore ”A” 20 durometer @ 77°F ASTM D 2240

6. Pipe Supports; Miro Industries Pillow Block Pipestand, Model No. 24-R with pipe straps.

07651-5

PART 2 - EXECUTION

3.01 BASE FLASHINGS

A. Preparation:

1. Remove existing flashing materials to substrate. Replace damaged material in like kind.

2. Prime vertical substrate with asphalt primer at approximate rate of one gallon per 125 - 150

sq. ft.

3. Install new roofing two inches beyond top edge of cant.

B. Base ply(s):

1. Fully adhere two (2) plies of specified base flashing completely to flashing substrate, cant, and roofing. Flashing should extend a minimum of 8" and maximum of 14” above finished roof membrane.

C. Cap ply:

1. Fully adhere a flashing top ply over base ply(s) in specified flashing adhesive.

a. Flashings may be adhered in specified flashing adhesive or torch applied up to 12" high.

b. Flashings must be adhered in specified asphalt mastic or fully adhered with torch applied above 12" in height.

2. Mechanically fasten top of flashing to substrate, fasten minimum of 8 inches on center.

3. Seal top edge with a 4 inch wide stripping membrane embedded in alternating courses of specified Asphalt Mastic.

4. Strip in bottom edge of flashing with 4 inch wide stripping membrane and specified flashing adhesive.

5. Surface flashing with specified protective coating (if specified).

6. Install specified counterflashing system as per detail drawings.

D. Additional instructions for mineral surface flashing cap.

1. Snap a chalk line 6” from the toe of cant out onto roof membrane.

2. Measure the distance from the chalk line up the wall to where flashing will be terminated.

On sloped roofs, take two measurements 1 meter (39” ) apart.

3. Measure down length of a roll of specified membrane, and cut, in cross machine direction, a section same length. If roof is sloped, start at the bottom, and transfer height measurement to cutting of the flashing cap. Each section is 1 meter (39”) in width.

4. Apply section in specified adhesive using a strapping method, overlapping the exposed smooth selvage with each new section. Bottom of flashing cap must be lined up 6” from toe of cant, on chalk line.

5. The salvage of the last section should be cut flush to the mineral surface prior to the application, ensuring that total flashing surface is mineral surfaced.

6. All areas where excessive adhesive is exposed on side laps may be coated with specified heat reflective coating or granules sprinkled in as flashing sections are installed.

E. Additional instructions for metal clad flashing cap

1. Calculate the length of membrane required covering the flashing or curb.

07651-6

2. Use 39” wide (roll width) strips of membrane cut from length of roll and install in a…