MOD C, + 5 VOLT POWER SUPPLY ASSY REPAIR
KIT PN 852200-RK; IFS PN 100006008
ST
ARTICLE ACCEPTANCE TEST PLAN
AML-2000
SEPTEMBER 9, 2016
EXHIBIT 5-C
TABLE OF CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 RELATED DOCUMENTS
4.0 REQUIRED TEST EQUIPMENT
5.0 PROCEDURES
6.0 ACCEPTANCE TEST
7.0 ACCEPTANCE MILESTONE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . …
1.0 PURPOSE:
To provide the necessary instructions and procedures for a 1 st Article test of the MOD C Power Supply repair kit.
2.0 SCOPE:
This test plan provides the procedures for the performance verification of the +5V MOD C Power
Supply which utilizes the 1 st Article repair kit within the MOD C power supply.
3.0 RELATED DOCUMENTS:
TI 6310.39, Volume 2, Section 7.17, REPAIR OF +5-VOLT MODULE C POWER SUPPLY 852200
4.0 REQUIRED TEST EQUIPMENT:
The following test equipment or equivalent is required:
Name Quantity
Digital Multimeter, Fluke Model 8600A 1
Electronic Load, DLP 50--150--3000A (GFE) 1
Ocilloscope, Tektronix Model 2430 1
Breakout Box, 2D09845G01 1
Cable W1, 2D09841G01 1
Cable W3, 2D09843G01 1
Other patch cords and adapters A/R
Safety Cover, 2D09017G02 1
Ground Strap (GFE) 1
5.0 PROCEDURES:
The following steps will be performed prior to performing the Acceptance Test.
5.1 Remove the internal electronics of the MOD C +5 Power Supply and install the MOD C repair kit contents, PN 0SXR1-852200-RK, per instructions supplied with the repair kit.
6.0 ACCEPTANCE TEST
The criteria for acceptance of the 1 st Article MOD C repair kit installed in the +5V MOD C Power
Supply Power will be based on a PASS/FAIL criteria determined by the +5V MOD C Power Supply passing, or failing, the performance verification check extracted from TI 6310.39, Volume 2, Section
7.17, REPAIR OF +5-VOLT MODULE C POWER SUPPLY 852200:.
7.17.5 Performance Verification
Connect the +5--volt module C power supply as shown in figure 7--38, and perform steps 1 through 7 of table 7-18 for performance verification.
FIGURE 7--38. +5--VOLT MODULE C POWER SUPPLY, TEST SETUP
7.0 ACCEPTANCE MILESTONE
AML-2000 will provide a PASS/FAIL notification to the vendor within thirty (30) days after receipt of st Articles (2 each).