EXHIBIT 5-B, MOD B Power Supply Repair Kit Test Plan.pdf

PDF 362 KB Posted

Attached to
The Federal Aviation Administration (FAA) has a requirement for the manufacturing and assembling of Module B & C Power Supply repair kits.
Solicitation number
DTFAAC-17-R-00218
Issued by

About this file

EXHIBIT 5-B, MOD B Power Supply Repair Kit Test Plan (pdf)

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOD B, +15 / -15 VOLT POWER SUPPLY ASSY

REPAIR KIT PN 852100-RK; IFS PN 1000014382

ST

ARTICLE ACCEPTANCE TEST PLAN

AML-2000

JANUARY 31, 2017

EXHIBIT 5-B

TABLE OF CONTENTS

1.0 PURPOSE

2.0 SCOPE

3.0 RELATED DOCUMENTS

4.0 REQUIRED TEST EQUIPMENT

5.0 PROCEDURES

6.0 ACCEPTANCE TEST

7.0 ACCEPTANCE MILESTONE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . …

1.0 PURPOSE:

To provide the necessary instructions and procedures for a 1 st Article test of the MOD B Power Supply repair kit.

2.0 SCOPE:

This test plan provides the procedures for the performance verification of the +15/-15 V MOD B

Power Supply which utilizes the 1 st Article repair kit within the MOD B power supply.

3.0 RELATED DOCUMENTS:

TI 6310.39, Volume 2, Section 7.16, REPAIR OF +15/-15 VOLT MODULE B POWER SUPPLY

4.0 REQUIRED TEST EQUIPMENT:

The following test equipment or equivalent is required:

Name Quantity

Digital Multimeter, Fluke Model 8600A 1

Electronic Load, DLP 50--150--3000A (GFE) 1

Ocilloscope, Tektronix Model 2430 1

Breakout Box, 2D09845G01 1

Cable W1, 2D09841G01 1

Cable W3, 2D09843G01 1

Other patch cords and adapters A/R

Safety Cover, 2D09017G02 1

Ground Strap (GFE) 1

5.0 PROCEDURES:

The following steps will be performed prior to performing the Acceptance Test.

5.1 Remove the internal electronics of the MOD B +15/-15 Power Supply and install the MOD B repair kit contents, PN 0SXR1-852100-RK, per instructions supplied with the repair kit.

6.0 ACCEPTANCE TEST

The criteria for acceptance of the 1 st Article MOD C repair kit installed in the +15/-15 V MOD B

Power Supply Power will be based on a PASS/FAIL criteria determined by the +15/-15 V MOD B

Power Supply passing, or failing, the performance verification check extracted from TI 6310.39, Volume 2, Section 7.16, REPAIR OF +15/-15 VOLT MODULE B POWER SUPPLY 852200:.

7.16.5 Performance Verification

Connect the +15/--15 volt module B as shown in figure 7-35 and perform steps 1 through 14 of table 7-17 for performance verification.

FIGURE 7--35. +15/--15--VOLT MODULE B POWER SUPPLY, TEST SETUP A

7.0

ACCEPTANCE MILESTONE

AML-2000 will provide a PASS/FAIL notification to the vendor within thirty (30) days after receipt of st Articles (2 each).

File details come from the government source that posted it. Updated .