This is a Schedule B Pricing Matrix document for the State of Michigan's New Haven Section 5-10 & Plank 1-1 Orphan Well Plugging Project, a 12-well project located in Gratiot and Montcalm Counties. The document establishes the rate structure for all labor, equipment, materials, and services required to plug and remediate orphan wells. Bidders must provide unit pricing for 68 line items across multiple categories, including contractor supervision, labor, drilling equipment (pole rigs, derrick rigs), well casing and tubing rentals, drilling bits, hydraulic equipment (BOPs), mud systems and fluids, wireline services, cementing services and materials, waste disposal services, heavy equipment (dozers, backhoes, excavators), and site access/restoration activities. The project requires all rated items to be priced even if not anticipated for use, with specific provisions allowing for change orders or time-and-materials billing if the scope of work changes. Bidders must submit a comprehensive project timeline assuming 10-hour work days and cannot mobilize or charge for items without prior approval from the EGLE Project Manager.

Pricing must be provided for each unit rate, and the total project cost will be calculated based on actual quantities required. Key restrictions prohibit bidders from double-billing for services (such as invoicing rig crews at both rig crew and laborer rates simultaneously), limit contractor site supervisor invoicing to one per day of onsite work, and prevent charging for rated items used to complete lump-sum work activities already included in the original scope. An overhead percentage can be applied to subcontracted services, rentals, and materials, but not to hourly or daily rates of items already listed on the matrix. Any specialized equipment, supplies, services, or materials not included in the pricing matrix require prior approval from the EGLE Project Manager and will be invoiced at cost plus the overhead percentage.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SCHEDULE B - PRICING MATRIX
New Haven Sect. 5 - 10 & Plank 1-1 Orphan Well Plugging Project (Gratiot and Montcalm County) - 12 Wells
Project Resource ItemItem DescriptionUnitPriceTotal for ProjectVendor Item?
Quantityper(Y/N)
Unit
1Contractor Site Supervisorday$0.00
2Contractor Site Supervisor mileagemile$0.00
3Per diem (meals & lodging)day$0.00
4Laborer (this rate is to be utilized but is not limited to Roustabout, Heavy Equipment Operator, Tool Hand, General Laborer type work. See note at bottom of Schedule B for more information.)hour$0.00
5Pick-up Truck mileage (all descriptions)mile$0.00
6Pole Rig-3 man crewhour$0.00
7Single Derrick Rig-3 man crewhour$0.00
8Double Derrick Rig-3 man crewhour$0.00
9Pit Liner Material (20 mil PVC)roll$0.00
10Rig Anchors (install/remove, includes all labor and materials)site$0.00
11Cellar (install./remove, includes all labor and materials)job$0.00
12Mobile Arc Welder (inc. ½” steel plate for capping)hour$0.00
13BOP Rental (hydraulic) - Includes all parts such as but not limited to accumulator, annular (hydril), pipe rams, blind rams, etc
13 A4 1/2”day$0.00
13 B5 1/2"day$0.00
13 C7”day$0.00
13 D7 5/8”day$0.00
13 E8 5/8”day$0.00
13 F9 5/8”day$0.00
13 G10 3/4"day$0.00
13 H11 3/4”day$0.00
14Tubing/Workstring (rental) - rental fees to include any necessary post use pipe inspections
14 A1.9" tubingfoot$0.00
14 B2 3/8" tubingfoot$0.00
14 C2 7/8" tubingfoot$0.00
14 DDrill Collarsfoot$0.00
15Drill Bits (rental)
15 A3.5" - 7"bit$0.00
15 B7 1/8" - 11"bit$0.00
15 C11 1/8" - 16"bit$0.00
16Well Casing
16 A5 1/2" 15.5#/ftfoot$0.00
16 B8 5/8" 24#/ftfoot$0.00
16 C10 3/4" 32#/ftfoot$0.00
16 D11 3/4" 42#/ftfoot$0.00
16 E16" 75#/ftfoot$0.00
17Power Swivel Unithour$0.00
18Power Swivel Unit Operatorhour$0.00
19Rental 100 bbl. Half Tankday$0.00
20Rental - Mud Mixing System - includes mixing system and pit(s)day$0.00
21Mud Engineerhour$0.00
22Mixed Mud Drilling Fluidbbl$0.00
23Baritesx$0.00
24Shale Shakerday$0.00
25Rental Frac Tank (water and brine storage)day$0.00
26Casing Cutters (wireline)
26 A(jet cutter) 4 1/2”job$0.00
26 B(jet cutter) 5 1/2"job$0.00
26 C(jet cutter) 7"job$0.00
26 D(jet cutter) 8 5/8"job$0.00
26 ECollar busterjob$0.00
27Casing Cutters (mechanical/hydraulic)
27 A4 ½”job$0.00
27 B5 ½”job$0.00
27 C7"job$0.00
27 D8 5/8"job$0.00
28Casing Spear
28 A3.5" - 8.625"job$0.00
28 B9" - 14"job$0.00
29Mechanical/Electrical Plugs/Fishing Tools
29 A4.5” Cast Iron Bridge Plugea.$0.00
29 B4.5” Cement Retainerea.$0.00
29 C5.5" Cast Iron Bridge Plugea.$0.00
29 D5.5” Cement Retainerea.$0.00
29 E7” Cast Iron Bridge Plugea.$0.00
29 F7” Cement Retainerea.$0.00
29 G8 5/8” Cast Iron Bridge Plugea.$0.00
29 H8 5/8” Cement Retainerea.$0.00
29 I9 5/8” Cast Iron Bridge Plugea.$0.00
29 J9 5/8” Cement Retainerea.$0.00
29 K10” Cast Iron Bridge Plugea.$0.00
29 L10” Cement Retainerea.$0.00
30Wireline Services (inc. operator, and hands/riggers)
30 AElectric logging (Gamma Log, CCL, Freepoint)job$0.00
30 ACement Bond Logjob$0.00
30 CPerforatingjob$0.00
30 DSetting Mechanical Plugsjob$0.00
31Fresh Water Chargebbl.$0.00
32Duplex/Triplex Mud Pumpday$0.00
33Cementing Services
33 ACementerhour$0.00
33 BPump Truck Operatorhour$0.00
33 CBulk Truck Operatorhour$0.00
33 DCement Pump Truck OThour$0.00
33 ECement Pump Truck Mileagemile$0.00
34Cement
34 AStandard Cement (Type 1L)sx$0.00
34 BClass H Cementsx$0.00
34 C50/50 Poz. Cementsx$0.00
34 DGas Block Additivesx$0.00
35Cement Handling Chargesx$0.00
36Cement Transportation Chargeton/mile$0.00
37Calcium Chloridesx$0.00
38Cellophane Flake (LCM)sx$0.00
39Bentonitesx$0.00
40Flarejob$0.00
41H2S Scavenger Fluidbbl$0.00
42H2S Safety Companyday$0.00
43Enclosed (sealed) frac tank for H2Sday$0.00
44Waste Disposal Services
44 AWaste Characterization – Fluids and Sludges from Tanks, Flowlines, Vessels, Drums, Secondary Containments, etc. Includes all labor, equipment, and laboratory feesLump sum$0.00
44 BPump, Transport, and Disposal of Sludge and/or Tank Bottoms. Per ton price should include all labor and equipmentton$0.00
44 CPump, Transport, and Disposal of All Generated or Collected Liquids. Per bbl price should include all labor and equipmentbbl$0.00
44 DExcavate, Transport, and Disposal of Contaminated Soil to Landfill. Per ton price should include all labor, equipmentton$0.00
45Pole Truck (tandem axle) - for moving stock tanks, etc.hour$0.00
46Crane - for lifting large heavy tanks and equipmenthour$0.00
47Dozerhour$0.00
47 ADozer - Standby Ratehour$0.00
48Backhoehour$0.00
48 ABackhoe - Standby Ratehour$0.00
49Excavatorhour$0.00
49 AExcavator - Standby Ratehour$0.00
50Skid Steerhour$0.00
50 ASkid Steer - Standby Ratehour$0.00
51Tele Handlerhour$0.00
51 ATele Handler - Standby Ratehour$0.00
5210,000 Square Feet of Composite Matsday$0.00
53Tractor & Low Boy/Float Transportationhour$0.00
54Site Access/Site Prep/Brush Hogging/Tree Clearing/Woodchipper (for location access) Includes all labor and equipment necessary to complete tasks related to accessing sites, clearing, and making them ready for equipment to plug the well.Lump Sum$0.00
55Site Restoration – Recontour and Seed Location – . Removal of gravel at well pad areas. Includes all labor and equipment necessary to complete tasks.Lump Sum$0.00
56Dump truck w/Operator (10cy dump)hour$0.00
57Dump truck w/Operator (20 cy lead dump)hour$0.00
58Dump truck w/Operator (30 cy dump or train)hour$0.00
5970 bbl. Water Truck w/ Vac. Pumphour$0.00
60120-150 bbl Water Tanker w/ Vac. Pumphour$0.00
61Water Truck Operatorhour$0.00
62Vacuum Truck/Cuscohour$0.00
63Vacuum Truck Operatorhour$0.00
64Hot Oilerhour$0.00
65Equipment – Dismantle, Remove, Scrap/Salvage (includes any related surface infrastructure, tanks, flares, heater/treaters, separators, tubulars, well pumps, pumping units, production equipment, compressors, piping, etc.). Includes all labor and equipment necessary to complete tasks.Lump Sum$0.00
66Other Infrastructure Removal – Concrete Pads, Buildings, Fencing, Gates, Electrical Infrastructure (power poles, electrical panels, etc.) Includes all labor and equipment necessary to complete tasks.Lump Sum$0.00
67Flow-Lines – Empty, Purge/Pull, Scrap/Salvage, Cut and Cap Flowlines (use of welder to be billed in line item 15, but not billed in both line item 15 and 69). Includes all labor and equipment necessary to complete tasks.Lump Sum$0.00
68Overhead % for subcontracted services, rentals, & materials%

Grand Total ($) $0.00

NOTES:
1. You must submit a project timeline as outlined in DS document. Please assume 10-hour days.
2. Provide Quantity and Price/Unit for all items listed in the Bid Table, even if the item is not likely to be used for the project. We call this 'Rated Items' and have requested the unit pricing in the event
the Scope of Work changes, a change order (aka - Amendment) is necessary, or we move to a time and materials billing.
3. Bidder cannot mobilize, use, or charge for items in the pricing matrix without prior approval from EGLE Project Manager.
4. If a ‘rated item’ is used to complete a ‘lump sum’ item work activity included in the original scope of work, it cannot be invoiced separately.
For example, if you utilize an ‘excavator’ to complete concrete pad removal (‘Other Infrastructure Removal’ bid item), you cannot charge
for the excavator or operators hours as it should have been included as part of the lump sum price for ‘Other Infrastructure Removal’
5. Only 1 Contractor Site Supervisor can be invoiced per day of onsite work.
6. Rental and/or purchase of any specialized equipment, supplies, services, or materials must have prior approval from EGLE Project Manager.
7. Overhead % cannot be added to the hourly or daily rates of items already included on Schedule B when invoicing.
8. If a material, such as 'casing' is needed to properly plug the well and is not listed on this pricing matrix, it will be invoiced at cost plus the 'Overhead %'
9. Laborer includes but is not limited to: Roustabout, Heavy Equipment Operator, Tool Hand, and other similar positions. The Laborer rate will also be used by the rig crew when they are completing work activities not assoicated
with the rig, including but not limited to: laying mats, moving equipment, loading/offloading equipment and supplies or other similar general labor duties. Rig crew cannot be invoiced at the Laborer and 'Rig Crew'
line items at the same time, as that would be double-billing.