This is a work list and feature inventory document for the DRUM West Calamity Outlaw Project in Colorado, detailing mine opening closure and remediation work across multiple mine sites. The project encompasses the closure and stabilization of 60+ mine features, including adits, prospect adits, shafts, and subsidence features distributed across numerous named mine locations such as Radium 7, Blue Ribbon, Lee Group, Little Maverick, Sunflower, and Small Spot. The work involves various closure methods including polyurethane foam backfill, steel grates with bat ladders, corrugated steel pipe installation, cable net systems, bulkheads, and simple backfill with native rock and waste rock. Each feature is cataloged with specific dimensions (excavated, eroded, and present sizes), depth measurements, and UTM coordinates for precise geographic location. Access descriptions are provided for each mine site, ranging from highway access with vehicle travel to remote locations requiring helicopter transport or extensive hiking.

The closure specifications reference Standard Work Specifications (SWS) sections and standardized drawings for construction guidance, with particular attention to bat exclusion and habitat protection requirements noted for several locations. Notable features include varying polyurethane foam requirements ranging from 1/3 cubic yard to 4 cubic yards per opening, with some sites requiring archaeologist monitoring during construction. Several sites present specific constraints such as limited equipment access, steep terrain, downed vegetation removal, or prior maintenance issues requiring remediation. Access routes are consistently documented starting from Highway 141 north of Gateway, Colorado, with detailed turn-by-turn directions to individual mine clusters. The project appears to be a comprehensive remediation effort focused on environmental stabilization and public safety while accommodating bat habitat protection requirements.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRUM West Calamity Outlaw – Feature Work List

Feature ID Type Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

264 A1 Radium 7 Adit

Excavated:5ft by 5ft Eroded:5ft by 5ft Present:5ft by 5ft

Depth:10 ft Lining:Rock Drainage:No

Bat Grate

Construct steel grate with full bat ladder in accordance with Grated Adit Closure Standard

Work Specification (SWS) Section 11 and

13, and standard drawings No. 6 sheets 1 and 2.

684678.373, 4276627.372

264 P1 Radium 7

Prospe ct Adit

Excavated:5ft by 5ft Eroded:5ft by 5ft Present:5ft by 5ft

Depth:6 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 wtih 1 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

684658.362, 4276655.595

264 P2 Radium 7

Prospe ct Adit

Excavated:5ft by 4ft Eroded:5ft by 4ft Present:5ft by 4ft

Depth:8 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 1 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

684694.996, 4276661.993

386 Sub1 Blue

Ribbon 1 &

Subsid ence

Feature

Excavated:15ft by 10ft

Eroded:15ft by 10ft Present:15ft by 10ft

Depth:38 ft Lining:Rock Drainage:No

Grated Corrugate d Steel Pipe w Bat

Grate

Install Grated Corrugated Steel Pipe with Bat Ladder in accordance with

Corrugated Steel Pipe Adit Closure specifications Section 10, Drawing Number 5 and Number 6 sheet 2.

685953.637, 4276970.339

48” diameter 15’ long CSP w/ bat grate sealed w/ 2 cuyd PUF/backfill

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

388 A1 Blue

Ribbon 17 Adit

Excavated:6ft by 4ft Eroded:6ft by 4ft Present:6ft by 4ft

Depth:15 ft Lining:Rock +

Timber Drainage:No

Bat Grate

Construct steel grate with full bat ladder in accordance with Grated Adit Closure SWS

Section 11 and 13, and standard drawings No. 6 sheets 1 and 2.

684169.423, 4274771.441

388 A2 Blue

Ribbon 17 Adit

Excavated:5ft by 4ft Eroded:7ft by 5ft Present:7ft by 5ft

Depth:15 ft Lining:Rock +

Timber Drainage:No

Bat Grate

Construct steel grate with full bat ladder in accordance with Grated Adit Closure SWS

Section 11 and 13, and standard drawings No. 6 sheets 1 and 2.

684165.495, 4274763.331

398 A1 Lee Group Adit

Excavated:4ft by 4ft Eroded:4ft by 4ft Present:4ft by 4ft

Depth:10 ft Lining:Rock Drainage:No

Grated Corrugate d Steel Pipe w Bat

Grate

Install Grated Corrugated Steel Pipe with Bat Ladder in accordance with

Corrugated Steel Pipe Adit Closure specifications Section 10, Drawing Number 5 and Number 6 sheet 2.

684588.510, 4272669.199

36” diameter 5’ long CSP w/ bat grate sealed w/ 1 cuyd PUF/ backfill

398 A2 Lee Group Adit

Excavated:5ft by 4ft Eroded:5ft by 4ft Present:5ft by 4ft

Depth:11 ft Lining:Rock Drainage:No

Grated Corrugate d Steel Pipe w Bat

Grate

Install Grated Corrugated Steel Pipe with Bat Ladder in accordance with

Corrugated Steel Pipe Adit Closure specifications Section 10, Drawing Number 5 and Number 6 sheet 2.

684591.442, 4272678.520

36” diameter 5’ long CSP w/ bat grate sealed w/ 1 cuyd PUF/ backfill

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

398 P1 Lee Group

Prospe ct Adit

Excavated:5ft by 3ft Eroded:5ft by 3ft Present:5ft by 3ft

Depth:8 ft Lining:Rock +

Timber Drainage:No

Grated Corrugate d Steel Pipe w Bat

Grate

Install Grated Corrugated Steel Pipe with Bat Ladder in accordance with

Corrugated Steel Pipe Adit Closure specifications Section 10, Drawing Number 5 and Number 6 sheet 2.

684592.552, 4272682.863

30” diameter 5’ long CSP w/ bat grate sealed w/ 1 cuyd PUF/backfill

398 P2 Lee Group

Prospe ct Adit

Excavated:4ft by 3ft Eroded:4ft by 3ft Present:4ft by 3ft

Depth:9 ft Lining:Rock +

Timber Drainage:No

Bulkhead SWS 14 684558.206, 4272639.506

398 P3 Lee Group

Prospe ct Adit

Excavated:3ft by 4ft Eroded:3ft by 4ft Present:3ft by 4ft

Depth:5 ft Lining:Rock Drainage:No

Backfill, w Polyuretha ne Foam

SWS 2 with 1 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

684562.220, 4272643.917

399 A1 Little

Maverick 1 Adit

Excavated:5ft by 5ft Eroded:5ft by 5ft Present:5ft by 5ft

Depth:15 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 2 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

685054.737, 4271918.425

Inset backfill w/ PUF behind structure;

archeological monitor during construction.

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

399 A2 Little

Maverick 1 Adit

Excavated:4ft by 5ft Eroded:4ft by 5ft Present:4ft by 5ft

Depth:15 ft Lining:Rock Drainage:No

Grated Corrugate d Steel Pipe w Bat

Grate

Install Grated Corrugated Steel Pipe with Bat Ladder in accordance with

Corrugated Steel Pipe Adit Closure specifications Section 10, Drawing Number 5 and Number 6 sheet 2.

685054.979, 4271907.944

36” diameter 5’ long CSP w/ bat grate door, sealed w/ 1 cuyd PUF/ backfill ; archeological monitor during construction

400 A1 Little

Maverick 4 & 5

Adit

Excavated:10ft by 4ft Eroded:10ft by 4ft Present:10ft by 4ft

Depth:10 ft Lining:Rock +

Timber Drainage:No

Bat Grate

Construct steel grate with full bat ladder in accordance with Grated Adit Closure SWS

Section 11 and 13, and standard drawings No. 6 sheets 1 and 2.

683541.464, 4269753.485

400 A2 Little

Maverick 4 & 5

Adit

Excavated:8ft by 3ft Eroded:8ft by 3ft Present:8ft by 3ft

Depth:10 ft Lining:Rock +

Timber Drainage:No

Grated Corrugate d Steel Pipe w Bat

Grate

Install Grated Corrugated Steel Pipe with Bat Ladder in accordance with

Corrugated Steel Pipe Adit Closure specifications Section 10, Drawing Number 5 and Number 6 sheet 2.

683543.913, 4269752.308

30” diameter 5’ long CSP w/ bat grate sealed w/ 2 cuyd PUF/ backfill

405 A1 Little

Maverick 6 Adit

Excavated:1ft by 1ft Eroded:1ft by 1ft Present:1ft by 1ft

Depth:10 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 w 2/3 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

684373.799,

4268946.607 Bat Exclusion prior to construction

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

405 A2 Little

Maverick 6 Adit

Excavated:18ft by 5ft Eroded:18ft by 5ft Present:18ft by 5ft

Depth:10 ft Lining:Rock Drainage:No

Bat Grate

Construct steel grate with full bat ladder in accordance with Grated Adit Closure SWS

Section 11 and 13, and standard drawings No. 6 sheets 1 and 2.

684372.803, 4268958.305

411 A1 Supply 11 Adit

Excavated:8ft by 5ft Eroded:8ft by 5ft Present:8ft by 5ft

Depth:10 ft Lining:Rock Drainage:No

Backfill, Polyuretha ne Foam

SWS 2 with 2 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

688654.952, 4269762.541

Bat Exclusion prior to construction

436 A10 Fraction Adit

Excavated:3ft by 5ft Eroded:3ft by 5ft Present:3ft by 5ft

Depth:10+ ft Lining:Rock Drainage:No

Grate SWS 11 689989.315, 4276750.378

436 A9 Fraction Adit

Excavated:3ft by 5ft Eroded:3ft by 5ft Present:3ft by 5ft

Depth:10+ ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 1 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

690000.359, 4276743.855

454 Sub1 Outlaw

Economy

Subsid ence

Feature

Excavated:6ft by 15ft Eroded:6ft by 15ft Present:6ft by 15ft

Depth:13 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 4 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

690767.104, 4272073.263

Bat Exclusion prior to construction

Set bottom form at 5’ depth Good equipment access

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

457 Sub 1 Ronnie 1

Subsid ence

Feature

Excavated:6ft by 16ft Eroded:6ft by 6ft

Present:16ft by 6ft Depth:10 ft

Lining:Other Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 4 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

690102.710, 4275442.442

Set bottom form at 4 ft depth

5898 A1 Great

Hesper Adit

Excavated:5ft by 4ft Eroded:5ft by 4ft Present:5ft by 4ft

Depth:30 + ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 1 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

684515.711, 4276000.864 needs maintenance, previous company backfill eroding

5898 A2 Great

Hesper Adit

Excavated:6ft by 6ft Eroded:6ft by 6ft Present:6ft by 6ft

Depth:20 ft Lining:Rock +

Timber Drainage:No

Fence Please see google drive folder for Specifications and Photos

684640.943,

4276048.173 Fence 17’ L x 10’ H & Sign

5900 Sub1 Hidden

Treasure

Subsid ence

Feature

Excavated:3ft by 4ft Eroded:3ft by 4ft Present:3ft by 4ft

Depth:15 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 1 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

685371.527, 4277081.421

5901 A1 Sunflower Adit

Excavated:5ft by 1ft Eroded:5ft by 1ft Present:5ft by 1ft

Depth:10 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 1 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

685136.726,

4277544.504 Hand Backfill w/PUF- no equipment access

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

5901 A3 Sunflower Adit

Excavated:5ft by 6ft Eroded:5ft by 6ft Present:5ft by 6ft

Depth:50 ft Lining:Rock Drainage:No

Grated Corrugate d Steel Pipe w Bat

Grate

Install Grated Corrugated Steel Pipe with Bat Ladder in accordance with

Corrugated Steel Pipe Adit Closure specifications Section 10, Drawing Number 5 and Number 6 sheet 2.

685111.655, 4277603.145

48” diameter 25‘ CSP w/ bat grate sealed w/ 1 cuyd PUF/backfill

5901 A5 Sunflower Adit

Excavated:5ft by 6ft Eroded:5ft by 6ft Present:5ft by 6ft

Depth:10 ft Lining:Rock Drainage:No

Grated Corrugate d Steel Pipe w Bat

Grate

Install Grated Corrugated Steel Pipe with Bat Ladder in accordance with

Corrugated Steel Pipe Adit Closure specifications Section 10, Drawing Number 5 and Number 6 sheet 2.

685099.396, 4277578.802

30” diameter 5’ long CSP w/ bat grate sealed w/ 1 cuyd PUF/backfill. Backfill and ⅓ cuyd

PUF 1’ x 6” crown hole opening

5901 A6 Sunflower Adit

Excavated:5ft by 6ft Eroded:5ft by 6ft Present:5ft by 6ft

Depth:10 ft Lining:Rock Drainage:No

Grated Corrugate d Steel Pipe w Bat

Grate

Install Grated Corrugated Steel Pipe with Bat Ladder in accordance with

Corrugated Steel Pipe Adit Closure specifications Section 10, Drawing Number 5 and Number 6 sheet 2.

685099.261, 4277574.172

30” diameter 5’ long CSP w/ bat grate sealed w/ 1 cuyd PUF/ backfill

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

5901 Sub 1 Sunflower

Subsid ence

Feature

Excavated:5ft by 1ft Eroded:5ft by 1ft Present:5ft by 1ft

Depth:10 ft Lining:Rock Drainage:No

Grated Corrugate d Steel Pipe w Bat

Grate

Install Grated Corrugated Steel Pipe with Bat Ladder in accordance with

Corrugated Steel Pipe Adit Closure specifications Section 10, Drawing Number 5 and Number 6 sheet 2.

685136.726, 4277544.504

Vertical 24” diameter 5’ long CSP w/ bat grate sealed w/ 2 cuyd PUF/ backfill

5905 P1 Outlaw Mines

Prospe ct Adit

Excavated:10ft by 8ft Eroded:10ft by 8ft Present:10ft by 8ft

Depth:6 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 2 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

689659.239, 4276760.425

5906 Sub1 July

Subsid ence

Feature

Excavated:4ft by 5ft Eroded:4ft by 5ft Present:4ft by 5ft

Depth:3 ft Lining:Other Drainage:No

Backfill SWS 2 689671.480, 4276316.230

Remove & Dispose of Fence

5912 A2 Emerson

Blair Adit

Excavated:5ft by 10ft Eroded:5ft by 10ft Present:5ft by 10ft

Depth:10 ft Lining:Rock Drainage:No

Cable Net

Install Cable Net in accordance with Wire Rope Netting Closure SWS Section 16, and SWS 13, drawing 6 sheet 2 (NOTE: specification modification in bid document).

691881.016, 4272736.254

Concrete footer required

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

5912 Sub1 Emerson

Blair

Subsid ence

Feature

Excavated:1ft by 1ft Eroded:1ft by 1ft Present:1ft by 1ft

Depth:9 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 2/3 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

691782.834, 4272721.253

Excavate to 3x3 opening before installing PUF

5915 A2

Bluebird

Adit

Excavated:4ft by 5ft Eroded:4ft by 5ft Present:4ft by 5ft

Depth:10+ ft Lining:Rock Drainage:No

Grated Corrugate d Steel Pipe w Bat

Grate

Install Grated Corrugated Steel Pipe with Bat Ladder in accordance with

Corrugated Steel Pipe Adit Closure specifications Section 10, Drawing Number 5 and Number 6 sheet 2.

691534.336, 4272239.347

36 “ diameter 10’ long CSP w Bat Grate and bulkhead

5915 P2

Bluebird

Prospe ct Adit

Excavated:8ft by 4ft Eroded:8ft by 4ft Present:8ft by 4ft

Depth:4 ft Lining:Rock +

Timber Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 2 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

691537.606, 4272244.360

5915 S2

Bluebird

Shaft

Excavated:8ft by 8ft Eroded:8ft by 8ft Present:8ft by 8ft Depth:unknown ft

Lining:Other Drainage:No

Backfill SWS 2 691669.594, 4272212.974

Remove downed trees covering shaft.

Machine Backfill w waste rock. Bat Exclusion prior to construction

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

5916 A2 Klondike Adit

Excavated:10ft by 8ft Eroded:10ft by 8ft Present:10ft by 8ft

Depth:15 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 4 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

690492.383, 4270726.170

5940 A10 Small Spot Adit

Excavated:5ft by 6ft Eroded:5ft by 6ft Present:5ft by 6ft

Depth:10 ft Lining:Rock Drainage:No

Bat Grate

Construct steel grate with full bat ladder in accordance with Grated Adit Closure SWS

Section 11 and 13, and standard drawings No. 6 sheets 1 and 2.

685155.737, 4276974.937

5940 A3 Small Spot Adit

Excavated:10ft by 6ft Eroded:10ft by 6ft Present:10ft by 6ft

Depth:10 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 3 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

685041.802, 4276722.764

5940 A5 Small Spot Adit

Excavated:1ft by 2ft Eroded:1ft by 2ft Present:1ft by 2ft

Depth:10 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 2/3 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

685079.767, 4276849.181

5940 A7 Small Spot Adit

Excavated:4ft by 2ft Eroded:4ft by 2ft Present:4ft by 2ft

Depth:10 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 1 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

685010.976, 4276841.727

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

5940 A8 Small Spot Adit

Excavated:5ft by 9ft Eroded:5ft by 9ft Present:5ft by 9ft

Depth:10 ft Lining:Rock Drainage:No

Cable Net

Install Cable Net in accordance with Wire Rope Netting Closure SWS Section 16, and SWS 13, drawing 6 sheet 2 (NOTE: specification

685144.508, 4276947.841

5940 A9 Small Spot Adit

Excavated:5ft by 5ft Eroded:5ft by 5ft Present:5ft by 5ft

Depth:10 ft Lining:Rock Drainage:No

Bat Grate

Construct steel grate with full bat ladder in accordance with Grated Adit Closure SWS

Section 11 and 13, and standard drawings No. 6 sheets 1 and 2.

685148.669, 4276956.266

5940 P1 Small Spot

Prospe ct Adit

Excavated:6ft by 2ft Eroded:6ft by 2ft Present:6ft by 2ft

Depth:8 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 1 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

685023.806, 4276705.691

5940 P2 Small Spot

Prospe ct Adit

Excavated:5ft by 4ft Eroded:5ft by 4ft Present:5ft by 4ft

Depth:5 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 1 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

162708.71, 4281858.38

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

5940 P3 Small Spot

Prospe ct Adit

Excavated:4ft by 4ft Eroded:4ft by 4ft Present:4ft by 4ft

Depth:4 ft Lining:Rock Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 1 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

685010.557, 4276838.941

5940 P4 Small Spot

Prospe ct Adit

Excavated:5ft by 6ft Eroded:5ft by 6ft Present:5ft by 6ft

Depth:9 ft Lining:Rock Drainage:No

Cable Net

Install Cable Net in accordance with Wire Rope Netting Closure SWS Section 16, drawing 6 sheet 2 (NOTE: specification

685153.782, 4276965.329

5940 Sub 1 Small Spot

Subsid ence

Feature

Excavated:5ft by 5ft Eroded:5ft by 5ft Present:5ft by 5ft

Depth:30 + ft Lining:Rock Drainage:No

Grate Steel Grated Shaft SWS 8, drawing 4

685361.394,

4276788.161 Grate w Footer & Bat Cupola

6198 P1 Triangle

Prospe ct Adit

Excavated:3ft by 8ft Eroded:3ft by 8ft Present:3ft by 8ft

Depth:6 ft Lining:Rock Drainage:No

Backfill SWS 2 687804.959, 4275057.762

Modified Backfill- Dry Stack rocks for backfill at face

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

6198 P2 Triangle

Prospe ct Adit

Excavated:1ft by 4ft Eroded:1ft by 4ft Present:1ft by 4ft

Depth:6 ft Lining:Rock Drainage:No

Backfill SWS 2 687803.778, 4275056.501

Modified Backfill- Dry stack rocks

6208 A2 Hummer Adit

Excavated:1ft by 1ft Eroded:1ft by 1ft Present:1ft by 1ft

Depth:10 ft Lining:Rock +

Timber Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 1/3 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

684682.205, 4276189.469

6208 Sub1 Hummer

Subsid ence

Feature

Excavated:8ft by 5ft Eroded:8ft by 5ft Present:8ft by 5ft

Depth:6 ft Lining:Rock Drainage:No

Backfill SWS 2 684675.306, 4276142.426

Machine Backfill w adjacent waste rock pile 1 associated with 6208 A2

6209 A1 May Day Adit

Excavated:6ft by 4ft Eroded:6ft by 4ft Present:6ft by 4ft

Depth:15 ft Lining:Other Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 1 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

684599.784, 4276446.966

6209 P1 May Day

Prospe ct Adit

Excavated:8ft by 4ft Eroded:8ft by 4ft Present:8ft by 4ft

Depth:6 ft Lining:Other Drainage:No

Polyuretha ne Foam w Bulkhead

SWS 14 & SWS 9 684596.227,

4276433.312 4 cuyd PUF w/ Bulkhead Facade

Description of Mine

Opening Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

6209 Sub1 May Day

Subsid ence

Feature

Excavated:10ft by 5ft Eroded:10ft by 5ft Present:10ft by 5ft

Depth:15 ft Lining:Other Drainage:No

Backfill w Polyuretha ne Foam

SWS 2 with 3 cuyd of PUF and hand backfill to cover PUF with native rock/ waste rock

684604.579, 4276438.440

Access Descriptions

Radium 7 Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10 Road bear right on 11 5/10 travel 3.5 miles to Z2 road bear right on Z2 1 mile to sites Blue

Ribbon 1 &

Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10 Road bear right on 11 5/10 travel 3.5 miles to Z2 road bear right on Z2 mine on left (south) side of road 1/16 mile down Z2

Blue

Ribbon 17 Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10. 1.5 miles on 11 5/10 road to the Y- bear right and travel 1.75 miles on unmarked road Foot access only Mine access Accessible by 0.13-mile hike

398 Lee Group

Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10. 6 miles on 11 5/10 road to the 670 road bear right and travel 2 miles on 4 x4 road. Mine access Accessible by 0.25-mile hike. Helicopter recommended for these sites

399 Little Maverick 1

Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10. 6 miles on 11 5/10 road to the 670 road bear right and travel 2 miles on 4 x4 road. Accessible by 0.05-mile hike down a steep slope from a four-wheel-drive road. . Helicopter recommended for these sites Little

Maverick 4 & 5

Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10. 8 miles on 11 5/10 road to the road bear right 836 road and travel 2 miles on 4 x4 road. Accessible by 0.05-mile hike down a steep slope from a four-wheel-drive road

Little

Maverick 6

Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10. 8 miles on 11 5/10 road to the road bear right 836 road and travel 2 miles on 4 x4 road. Accessible by 0.05-mile hike down a steep slope from a four-wheel-drive road. West of 400 sites. Helicopter recommended for these sites 411 Supply

11 Access via Highway 141 north of Gateway 6 3/10 Road, Bear right or south on 19 5/10 Road for 4 miles, take right or head west on 895 Road for 2 miles. Mine on left side of road ½ mile off road

Fraction Access via Highway 141 north of Gateway 6 3/10 Road at the y of 6 3/10 and 19 5/10 road take a right to stay on 6 3/10- 1 mile to mine 454 Outlaw Economy Access via Highway 141 north of Gateway 6 310 Road, Bear right or south on 19 5/10 Road for 3.5 miles Mine on right 50 ft off road

Ronnie 1 Access via Highway 141 north of Gateway 6 3/10 Road, Bear right or south on 19 5/10 Road for 2.5 miles, take right at Z 2 3/10 Road. Mine on right or north die of road

5898 Great Hesper Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10 Road bear right on 11 5/10 travel 3.5 miles to Z2 road bear right on Z2 1.3 mile to sites

Hidden

Treasure Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10 Road bear right on 11 5/10 travel 3.5 miles to Z2 road bear right on Z2 .7 mile to site

Sunflower

Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10 Road bear right on 11 5/10 travel 3.5 miles to Z2 road bear right on Z2 0.7 mile on Z2- go right on unmarked 2 track. No equipment access Helicopter recommended

Outlaw Mines

Access via Highway 141 north of Gateway 6 3/10 Road at the y of 6 3/10 and 19 5/10 road take a right to stay on 6 3/10- 1.4 mile to mine

5906 July Access via Highway 141 north of Gateway 6 3/10 Road at the y of 6 3/10 and 19 5/10 road take a right to stay on 6 3/10- 1.1 mile to mine on left side of road

Emerson

Blair Access via Highway 141 north of Gateway 6 310 Road, Bear right or south on 19 5/10 Road for 3.5 miles Mine on right 50 ft off road

Emerson Bluebird

Access via Highway 141 north of Gateway 6 310 Road, Bear right or south on 19 5/10 Road for 3.5 miles Take unmarked 2 track on left head south 0.3 miles. Shaft on road, Adit and prospect in the drainage

Klondike Access via Highway 141 north of Gateway 6 310 Road, Bear right or south on 19 5/10 Road for 4 miles, take right or head west on 895 Road for 1/2 mile. Mine on left 50 ft off road

5940 Small Spot

Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10 Road bear right on 11 5/10 travel 3.5 miles to Z2 road bear right on Z2 .7 mile to site and park near cabin. No equipment access, helicopter recommended

Triangle

Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 9/10 Road bear right on 11 9/10 BLM A878B Administrative route would be used to access the Triangle locations

Hummer Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10 Road bear right on 11 5/10 travel 3.5 miles to Z2 road bear right on Z2 1.3 mile to sites

Mayday

Access via Highway 141 north of Gateway 6 3/10 Road- 10 miles to intersection with 11 5/10 Road bear right on 11 5/10 travel 3.5 miles to Z2 road bear right on Z2 1.5 mile to unmarked 2 track travel .26 miles to the west mine is 0.3 mile walk off road flat terrain

File details come from the government source that posted it. Updated .