DRUM West Calamity Outlaw Bid Schedule.pdf

PDF 162 KB Posted

Attached to
PKAA, DRUM West Calamity Outlaw Project
Solicitation number
DQ1 PKAA 2027000029 2
Issued by
Mesa County, Colorado

About this file

This is a bid schedule for the DRUM West Calamity Outlaw Project (DQ1 PKAA 2027*0029) issued by the State of Colorado, with work to be performed on Bureau of Land Management (BLM) properties. The project involves mine closure work across multiple features including adits, prospects, subsidence features, and shafts. Bidders must submit complete responses addressing five primary line items: mobilization/demobilization, project safety and health planning, mine closure installations across 51 identified features, additional manual labor (not guaranteed), additional grating material (not guaranteed), and additional polyurethane foam (PUF) material (not guaranteed). The bid schedule requires offerors to provide per-unit pricing for labor at an hourly rate, materials by square footage and cubic yardage, and lump-sum amounts for mobilization and the safety plan. All bids must be submitted through Colorado's VSS (Vendor Self Service) system by July 23, 2026, with alternative submittal methods available only if VSS is unavailable per project special conditions.

The bid schedule requires offerors to complete all pages and line items with no amendments permitted; incomplete submissions will not be accepted. Closure methods specified across the 51 features include bat grates, backfill with PUF, grated corrugated steel pipe with bat grates, bulkheads, cable nets, and fence installations. Pricing must be submitted for each individual feature within Item 3.0 to establish a total mine closure cost, which feeds into the grand total bid amount. The document was updated February 24, 2026, and requires submission of complete offeror information including legal business name, address, contact details, and an authorized signature. No information regarding funding sources, set-asides, contract term, or renewal options is provided in this bid schedule document.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Schedule DRUM West Calamity Outlaw Project

DQ1 PKAA 2027*0029

July 23, 2026

Complete all pages in the spreadsheet as applicable.

Submit Bids via Colorado VSS at the following link:

Submitting Bids by mail or fax is not permitted.

If VSS is unavailable, please see project Special Conditions for alternative Bid Submittal method.

1 Job N/A

1 Job N/A

1 Job N/A

8 Hours $_________/hr

20 Square Feet $__________sqft

9 Cubic Yards $__________cuyd

Legal Business Name

Address

City, State Zip

Phone

Email

Signer Printed Name

Title

Date http://www.colorado.gov/vss

Item Description Qty Unit Per Unit Price ($) Total Price ($)

Item 1.0 - Mobilize/Demobilize

Item 2.0 - Project Safety, Health and Environmental Action Plan Item 3.0 - Install Mine Closures (See total from page 4) Item 4.0 - Additional Manual Labor-not guaranteed Item 5.0 Additional Grating Material-not guaranteed Item 6.0 Additional PUF- not guaranteed

Grand Total:

Offeror Information

Signature:

The Bid shall be signed by a person authorized to bind the Offeror.

Do not amend any part of this bid schedule all pages of this bid schedule must be returned all line items must be completed.

Updated February 24, 2026.

Bid Schedule DRUM West Calamity Outlaw Project

DQ1 PKAA 2027*0029

Item 3.0 - Install Mine Closures:

Feature ID Feature Type Closure Method Ownership Bid Amount ($)

264 A1 Adit Bat Grate BLM

264 P1 Prospect Adit Backfill w PUF BLM

264 P2 Prospect Adit Backfill w PUF BLM

386 Sub1 Subsidence Feature Grated Corrugated Steel Pipe w Bat Grate BLM

388 A1 Adit Bat Grate BLM

388 A2 Adit Bat Grate BLM

398 A1 Adit Grated Corrugated Steel Pipe w Bat Grate BLM

398 A2 Adit Grated Corrugated Steel Pipe w Bat Grate BLM

398 P1 Prospect Adit Grated Corrugated Steel Pipe w Bat Grate BLM

398 P2 Prospect Adit Bulkhead BLM

398 P3 Prospect Adit Backfill w PUF BLM

399 A1 Adit Backfill w PUF BLM

399 A2 Adit Grated Corrugated Steel Pipe w Bat Grate BLM

400 A1 Adit Bat Grate BLM

400 A2 Adit Grated Corrugated Steel Pipe w Bat Grate BLM

405 A1 Adit Backfill w PUF BLM

405 A2 Adit Bat Grate BLM

411 A1 Adit Backfill w PUF BLM

436 A10 Adit Grate BLM

436 A9 Adit Backfill w PUF BLM

454 Sub1 Subsidence Feature Backfill w PUF BLM

457 Sub 1 Subsidence Feature Backfill w PUF BLM

5898 A1 Adit Backfill w PUF BLM

5898 A2 Adit Fence BLM

5900 Sub1 Subsidence Feature Backfill w PUF BLM

5901 A1 Adit Backfill w PUF BLM

5901 A3 Adit Grated Corrugated Steel Pipe w Bat Grate BLM

5901 A5 Adit Grated Corrugated Steel Pipe w Bat Grate BLM

5901 A6 Adit Grated Corrugated Steel Pipe w Bat Grate BLM

5901 Sub 1 Subsidence Feature Grated Corrugated Steel Pipe w Bat Grate BLM

5905 P1 Prospect Adit Backfill w PUF BLM

5906 Sub1 Subsidence Feature Backfill BLM

5912 A2 Adit Cable Net BLM

5912 Sub1 Subsidence Feature Backfill w PUF BLM

5915 A2 Adit Grated Corrugated Steel Pipe w Bat Grate BLM

5915 P2 Prospect Adit Backfill w PUF BLM

5915 S2 Shaft Backfill BLM

5916 A2 Adit Backfill w PUF BLM

5940 A10 Adit Bat Grate BLM

5940 A3 Adit Backfill w PUF BLM

5940 A5 Adit Backfill w PUF BLM

5940 A7 Adit Backfill w PUF BLM

5940 A8 Adit Cable Net BLM

5940 A9 Adit Bat Grate BLM

5940 P1 Prospect Adit Backfill w PUF BLM

5940 P2 Prospect Adit Backfill w PUF BLM

5940 P3 Prospect Adit Backfill w PUF BLM

5940 P4 Prospect Adit Cable Net BLM

5940 Sub 1 Subsidence Feature Grate w/bat cupola BLM

6198 P1 Prospect Adit Backfill BLM

6198 P2 Prospect Adit Backfill BLM

6208 A2 Adit Backfill w PUF BLM

6208 Sub1 Subsidence Feature Backfill BLM

6209 A1 Adit Backfill w PUF BLM

6209 P1 Prospect Adit PUF w Bulkhead Facade BLM

6209 Sub1 Subsidence Feature Backfill w PUF BLM

Total (enter here and on Bid Schedule, Item 3.0):

Do not amend any part of this bid schedule all pages of this bid schedule must be returned all line items must be completed.