This is a construction drawings file for a federal hospital renovation project. The Legionella Plumbing Project is a 100% construction document package for Building 1 at the Central Alabama Veterans Health Care System (CAVHCS) West Campus in Montgomery, Alabama, dated July 16, 2025. The project (VA Project #619-23-105) involves comprehensive plumbing system modifications across multiple floors to address Legionella risk, including dead leg demolition, domestic water system replacement, and associated fire suppression work. The U.S. Department of Veterans Affairs is the federal agency involved, with Apogee Consulting Group, P.A. serving as the design consultant.
The drawings encompass 56 plumbing sheets plus structural, architectural, mechanical, electrical, and fire suppression plans detailing work across ground through fifth floors. Construction activities are classified by infection control risk assessment (ICRA) levels, ranging from Class I (minimal precautions) to Class V (highest precautions with full containment and personal protective equipment requirements). Work is scheduled primarily during off-hours (4:00 PM to 12:00 AM) to minimize patient care disruption, with pharmacy work limited to 6:00 PM to 2:00 AM on weekdays and no weekend pharmacy work permitted. Key requirements include temporary ICRA barriers with negative air pressure systems, HEPA filtration, dust control protocols, designated entry/exit procedures with sticky mats, and coordination with infection control and facilities management. The site logistics plan specifies parking restrictions, crane lift scheduling 14 days in advance, and emergency contact procedures for utility interruptions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24726R0039 0005.docx | DOCX document | |
| 23-039-Montgomery Legionella-Pre-Bid RFIs-20260430 - COMPLETE AE Response.xlsx | XLSX spreadsheet | |
| 36C24726R0039 0004.docx | DOCX document | |
| Site Visit Sign-in April 24 2026.pdf | ||
| 36C24726R0039 0003.docx | DOCX document | |
| 23-039-Montgomery Legionella-Pre-Bid RFIs-20260430 - AE Response.xlsx | XLSX spreadsheet | |
| Construction_SOW_619-23-105_CFMOHE.docx | DOCX document | |
| 36C24726R0039 0002.docx | DOCX document | |
| Sign in 619-23-105.pdf | ||
| 36C24726R0039 0001.docx | DOCX document | |
| 36C24726R0039_1 Construction Solicitation.docx | DOCX document | |
| SF24-23a.pdf | ||
| Specs.pdf | ||
| 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING.pdf | ||
| PAST AND PRESENT PERFORMANCE QUESTIONNAIRE.pdf | ||
| Wage Rate AL20250093.txt | TXT text file | |
| Experience Modification Rate Form 2026 Revised 2 2 2026.pdf | ||
| Proposal Sheet 619-23-105 Plumbing Project Building 1.xlsx | XLSX spreadsheet | |
| CAVHCS Contractor Safety Manual.pdf | ||
| 36C24726R0039_1.docx | DOCX document |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
PROJECT SITE MAP PROJECT LOCATION MAP
PROJECT IMAGE PROJECT IMAGE PROJECT IMAGE
/1
/2
:4
:4
A
M C
U s e rs \m g a in e s .C
O R
P \D o c u m e n ts \A
-0
-V A
M o n tg o m e ry -L e g io n e lla
D e s ig n -A
L R m g a in e s A
V F
.r v t
G-001
COVER
1 4BN
LEGIONELLA PLUMBING
PROJECT BUILDING 1
CAVHCS WEST CAMPUS
215 PERRY HILL RD.
MONTGOMERY, AL 36109 JULY 16, 2025
100% CONSTRUCTION DOCUMENTS
619-23-10523-039
LEGIONELLA PLUMBING PROJECT
BUILDING 1
CAVHCS WEST CAMPUS 215 PERRY HILL RD. MONTGOMERY, AL
36109
VA PROJECT #: 619-23-105
JAB
DRAWING LIST
GENERAL
G-001 COVER 1 4
G-002 ICRA INFORMATION AND DETAILS 2 4
G-003 ICRA TABLE 3 4
G-004 SITE LOGISTICS PLAN AND LIFE SAFETY EXIT PLAN 4 4
STRUCTURAL
S-001 STRUCTURAL SYMBOLS, ABBREVIATIONS AND NOTES 1 5
S-101 PENTHOUSE PLANS 2 5
S-201 WALL SECTIONS 3 5
S-301 DETAILS 4 5
S-302 DETAILS 5 5
ARCHITECTURAL
A-001 ARCHITECTURAL SYMBOLS, ABBREVIATIONS AND NOTES 1 7
A-101 ROOF PLANS DEMOLITION AND NEW WORK 2 7
A-102 PENTHOUSE FLOOR PLANS 3 7
A-201 EXTERIOR PENTHOUSE ELEVATIONS 4 7
A-301 EXTERIOR PENTHOUSE SECTIONS 5 7
A-302 EXTERIOR PENTHOUSE DETAILS 6 7
A-303 DOOR ELEVATIONS, FRAME ELEVATIONS, SCHEDULES, AND LOUVER DETAILS 7 7
FIRE SUPPRESSION
FX001 FIRE SUPPRESSION GENERAL INFORMATION 1 3
FX101 SECOND FLOOR FIRE SUPPRESSION PLAN - AREA D 2 3
FX102 THIRD FLOOR FIRE SUPPRESSION PLAN - AREA D 3 3
PLUMBING
P-001 PLUMBING GENERAL INFORMATION 1 56
PD001.A CRAWL SPACE PLUMBING DEMOLITION PLAN - AREA A - DEAD LEG DEMOLITION 2 56
PD001.B CRAWL SPACE PLUMBING DEMOLITION PLAN - AREA B & C - DEAD LEG DEMOLITION 3 56
PD001.D CRAWL SPACE PLUMBING DEMOLITION PLAN - AREA D - DEAD LEG DEMOLITION 4 56
PD010.A CRAWL SPACE PLUMBING DEMOLITION PLAN - AREA A 5 56
PD010.B CRAWL SPACE PLUMBING DEMOLITION PLAN - AREA B & C 6 56
PD010.D CRAWL SPACE PLUMBING DEMOLITION PLAN - AREA D 7 56
PD010.E CRAWL SPACE PLUMBING DEMOLITION PLAN - BUILDING 4 8 56
PD100.A GROUND FLOOR PLUMBING DEMOLITION PLAN - AREA A 9 56
PD100.B GROUND FLOOR PLUMBING DEMOLITION PLAN - AREA B & C 10 56
PD100.D GROUND FLOOR PLUMBING DEMOLITION PLAN - AREA D 11 56
PD100.E GROUND FLOOR PLUMBING DEMOLITION PLAN - BUILDING 4 12 56
PD101.A FIRST FLOOR PLUMBING DEMOLITION PLAN - AREA A 13 56
PD101.B FIRST FLOOR PLUMBING DEMOLITION PLAN - AREA B & C 14 56
PD101.D FIRST FLOOR PLUMBING DEMOLITION PLAN - AREA D 15 56
PD102.A SECOND FLOOR PLUMBING DEMOLITION PLAN - AREA A 16 56
PD102.B SECOND FLOOR PLUMBING DEMOLITION PLAN - AREA B & C 17 56
PD102.D SECOND FLOOR PLUMBING DEMOLITION PLAN - AREA D 18 56
PD103.A THIRD FLOOR PLUMBING DEMOLITION PLAN - AREA A 19 56
PD103.B THIRD FLOOR PLUMBING DEMOLITION PLAN - AREA B & C 20 56
PD103.D THIRD FLOOR PLUMBING DEMOLITION PLAN - AREA D 21 56
PD104.A FOURTH FLOOR PLUMBING DEMOLITION PLAN - AREA A 22 56
PD104.B FOURTH FLOOR PLUMBING DEMOLITION PLAN - AREA B 23 56
PD105 FIFTH FLOOR PLUMBING DEMOLITION PLAN 24 56
PP010.A CRAWL SPACE DOMESTIC WATER PLAN - AREA A 25 56
PP010.B CRAWL SPACE DOMESTIC WATER PLAN - AREA B & C 26 56
PP010.D CRAWL SPACE DOMESTIC WATER PLAN - AREA D 27 56
PP010.E CRAWL SPACE DOMESTIC WATER PLAN - BUILDING 4 28 56
CENTRAL ALABAMA VETERANS HEALTH CARE SYSTEM WEST CAMPUS
215 PERRY HILL RD.
MONTGOMERY, AL 36109 BLDG. 1BLDG. 4
DRAWING LIST
PP100.A GROUND FLOOR DOMESTIC WATER PLAN - AREA A 29 56
PP100.B GROUND FLOOR DOMESTIC WATER PLAN - AREA B & C 30 56
PP100.D GROUND FLOOR DOMESTIC WATER PLAN - AREA D 31 56
PP100.E GROUND FLOOR DOMESTIC WATER PLAN - BUILDING 4 32 56
PP101.A FIRST FLOOR DOMESTIC WATER PLAN - AREA A 33 56
PP101.B FIRST FLOOR DOMESTIC WATER PLAN - AREA B & C 34 56
PP101.D FIRST FLOOR PLUMBING PLAN - AREA D 35 56
PP102.A SECOND FLOOR DOMESTIC WATER PLAN - AREA A 36 56
PP102.B SECOND FLOOR DOMESTIC WATER PLAN - AREA B & C 37 56
PP102.D SECOND FLOOR PLUMBING PLAN - AREA D 38 56
PP103.A THIRD FLOOR DOMESTIC WATER PLAN - AREA A 39 56
PP103.B THIRD FLOOR DOMESTIC WATER PLAN - AREA B & C 40 56
PP103.D THIRD FLOOR PLUMBING PLAN - AREA D 41 56
PP104.A FOURTH FLOOR DOMESTIC WATER PLAN - AREA A 42 56
PP104.B FOURTH FLOOR DOMESTIC WATER PLAN - AREA B 43 56
PP105 FIFTH FLOOR DOMESTIC WATER PLAN 44 56
P-301 PLUMBING SECTIONS 45 56
P-401 ENLARGED PLUMBING PLANS 46 56
P-501 PLUMBING DETAILS 47 56
P-502 PLUMBING DETAILS 48 56
P-503 PLUMBING CONTROLS 49 56
P-504 DOMESTIC WATER SCHEMATICS 50 56
P-601 PLUMBING SCHEDULES 51 56
P-602 PLUMBING SCHEDULES 52 56
P-603 PLUMBING SCHEDULES 53 56
P-901 DOMESTIC WATER RISER DIAGRAM - PART 1 54 56
P-902 DOMESTIC WATER RISER DIAGRAM - PART 2 55 56
P-903 DOMESTIC WATER RISER DIAGRAM - PART 3 56 56
MECHANICAL
M-001 MECHANICAL GENERAL INFORMATION 1 5
M-401 ENLARGED THIRD FLOOR PLAN - PENTHOUSE 2 5
M-501 MECHANICAL DETAILS 3 5
M-502 MECHANICAL CONTROLS 4 5
M-601 MECHANICAL SCHEDULES 5 5
ELECTRICAL
E-001 ELECTRICAL AND FIRE ALARM GENERAL NOTES, SYMBOL LEGENDS, AND
ABBREVIATIONS
1 5
E-401 BUILDING 1, ELECTRICAL ENLARGEMENTS 2 5
E-402 BUILDING 1, ELECTRICAL ENLARGEMENTS AND LIGHTNING PROTECTION PLANS 3 5
E-501 ELECTRICAL DETAILS 4 5
E-601 SINGLE LINE DIAGRAM AND SCHEDULES 5 5
Docusign Envelope ID: AA1EC717-F25F-48B9-AA96-81D07E2966B9
7/17/2025
INFECTION CONTROL RISK MITIGATION RECOMMENDATIONS MATRIX OF
PRECAUTIONS FOR CONSTRUCTION AND RENOVATION
INFECTION CONTROL RISK MITIGATION RECOMMENDATIONS MATRIX OF
PRECAUTIONS FOR CONSTRUCTION AND RENOVATION
3 5/8" INSULATED WALL WITH
METAL STUDS @ 16" O.C.
WALL TO EXTEND TO
UNDERSIDE OF DECK
5/8" FIRE RESISTANT GYPSUM
BOARD - BOTH SIDES
EXISTING CEILING SYSTEM
BASE - TO MATCH
EXISTING AREA
EXISTING FLOOR
UNDERSIDE OF EXISTING
DECK
C E
IL
IN
G H
E
IG
H T
V A
R
IE
S F
IE
L D
V E
R
IF
Y
W A
L L
H E
IG
H
T V
A R
IE
S
F
IE
L D
V E
R
IF
Y
5"
A
FIRE RESISTANT SEALANT,
BOTH SIDES
1-HR RATED AND
SMOKE RATED
U.L. DESIGN NO. U419 B
TEMPORARY PREFABRICATED
ICRA WALL SYSTEM. BASIS OF
DESIGN: STARC WALL SYSTEM OR
EDGEGUARD SYSTEM OR EQUAL.
EXISTING CEILING
SYSTEM TO HAVE
INTEGRATED CEILING
SEAL.
ILSM TEMPORARY BARRIER TAG
PROJECT:
PRIME CONTRACTOR:
SUB CONTRACTOR:
EMERGENCY CONTACT NO.:
BARRIER INSTALLATION DATE:
BARRIER EXPIRATION DATE:
FIRE EXTINGUISHER ON
PORTABLE FLOOR
BRACKET (ILSM MAY
REQUIRE MORE THAN
ONE).
PROVIDE STICKY MATS
(CHANGED END OF
SHIFT OR MORE IF
NECESSARY TO
MAINTAIN
CLEANLINESS).
HEPA NEGATIVE
AIR UNIT
ISOLATE AND COVER ALL
SUPPLY DIFFUSERS NOT
IN OPERATION DURING
PROJECT - COORDINATE
W/ COR
COVER ALL RETURNS
AT THE
GRATE/DIFFUSERS
SUSPENDED PLASTIC
ZIPPER WALL
CURTAIN BARRIER
POST ICRA, ILSM, FIRE
INSPECTION SHEETS
VISIBLE TO PUBLIC
FIRE PULL STATION
WITH AUDIO /
VISUAL
EXISTING WALL
BARRIER
NOTE:
A. TURN UP EXHAUST ON EXTERIOR ON SIDE. CONTRACTOR SHALL VERIFY
LOCATION OF AIR INTAKES ARE AT THE PROPER DISTANCE FROM
EXHAUST. VERIFY LOCAL JURISDICTION CODE AND VA REQUIREMENTS
FOR DISTANCE PRIOR TO STARTING WORK.
G-003
FLEX DUCT
ILSM SIGNAGE
INTERIM LIFE SAFETY MEASURES IN EFFECT
[MONTGOMERY LEGIONELLA DESIGN]
THIS EXIT IS CLOSED AND LEADS TO A
CONSTRUCTION AREA.
PLEASE USE ALL ALTERNATE EXITS AS MARKED.
1' - 5"
1/2"1/2"
/2
/2
/2
/2
/2
/2
EQ.EQ.
DUST CONTROL PLAN NOTES
1. AT THE BEGINNING OF CONSTRUCTION, THE VAMC INFECTION CONTROL GROUP SHALL CONFIRM
THE DESIGNATION FOR THIS PROJECT FOR THE CLASS OF PRECAUTIONS AND LEVEL OF
INFECTION CONTROL ACTIVITIES. THE ICRA CHART HAS BEEN COMPLETED BASED ON THE DESIGN
PARAMETERS AND CONVERSATIONS WITH THE VA COR AND/OR VAMC INFECTION CONTROL
GROUP. HARD SURFACE BARRIERS SHALL BE USED EXCEPT IN THE AREA INDICATED ON THE
PHASING PLAN WITH PLASTIC BARRIERS (MINIMUM 4MIL) TO SEAL AREA FROM NON-WORK AREA
AS LONG AS THE SPRINKLER SYSTEM IS INTACT AND ACTIVE.
2. THIS PROJECT NEEDS AN ENTRY VESTIBULE FOR CLOTHING CHANGES (PROVIDE AND LOCATE A
STAGING AREA FOR HAZMAT SUITS NEAR THE PLASTIC BARRIER ENTRANCE SPACES -
CONSTRUCTION ANTEROOM. THEY SHALL BE USED WHEN GOING INTO CONSTRUCTION AREA AND
LEAVING THE CONSTRUCTION AREA) AND TOOL STORAGE AND TIGHT SEALS SHALL BE
MAINTAINED AT THE FULL PERIMETER OF WALLS AND WALL PENETRATIONS. ANY DUST SHALL BE
IMMEDIATELY CLEANED IF TRACKED OUTSIDE OF THE CONSTRUCTION BARRIER. UPON
COMPLETION OF THE CONSTRUCTION PHASE, DUST BARRIERS SHALL BE REMOVED CAREFULLY
TO MINIMIZE SPREADING OF DUST AND THE CONTRACTOR SHALL HAVE TEMPORARY DUST
PROTECTION IN PLACE BEFORE REMOVAL OF A PERMANENT BARRIER. [AFTER EACH PHASE,
PERFORM TASKS STATED IN CONTAMINATION OF PATIENT ROOMS, SUPPLIES, EQUIPMENT AND
RELATED AREAS NOTE 2.
3. PROVIDE STICKY MATS AT THE PLASTIC BARRIER ENTRANCE SPACES (CONSTRUCTION
ANTEROOM) AND CHANGE DAILY OR MORE OFTEN AS NEEDED TO PREVENT THE SPREAD OF
DUST AND DEBRIS INTO ADJACENT CLEAN SPACE.
4. GC TO ALLOW FOR A MINIMUM OF 5'-0" WIDE HALLWAY IN ALL CASES WHERE AN ICRA BARRIER IS
BEING PLACED IN A PUBLIC CORRIDOR. IF AN ICRA BARRIER IS REQUIRED TO TEMPORARILY
BLOCK A PATH OF EGRESS, THE TIMING OF THIS WORK WILL NEED TO BE COORDINATED WITH
THE VA COR.
5. GENERAL CONTRACTOR IS REQUIRED TO REPLACE CEILING TILES AT THE END OF EACH SHIFT
FOR WORK AREAS OUTSIDE OF A RATED CONSTRUCTION BARRIER. IF THE TILES CANNOT BE
REPLACED, THE SPRINKLER SYSTEM MAY BE CONSIDERED OUT OF SERVICE IN THESE AREAS AND
1-HOUR FIRE RATED SEPARATION WILL BE REQUIRED BETWEEN THE CONSTRUCTION AREA AND
THE OCCUPIED PORTIONS OF THE BUILDING.
INTERNAL DEMOLITION AND CONSTRUCTION ACTIVITIES DUST AND DEBRIS CONTROL
1. USE CORRIDORS AS PRIMARY CONSTRUCTION ACCESS.
2. TRAFFIC CONTROL: DESIGNATED ENTRY AND EXIT PROCEDURES SHALL BE DEFINED. EGRESS
PATHS SHALL BE FREE OF DEBRIS; DESIGNATED ELEVATORS SHALL BE USED DURING
SCHEDULED TIMES; AND ONLY AUTHORIZED PERSONNEL SHALL BE ALLOWED TO ENTER THE
CONSTRUCTION ZONE. SIGNAGE SHALL DIRECT PEDESTRIAN TRAFFIC AWAY FROM THE
CONSTRUCTION AREA AND MATERIALS.
3. CONTRACTOR SHALL USE TWO CARTS TO TRANSFER CONSTRUCTION MATERIAL IN AND OUT OF
THE PROJECT - A CLEAN CART SHALL BE USED; THE NOT-SO-CLEAN CART SHALL BE USED
BETWEEN THE MAIN ENTRY AND THE CONSTRUCTION STAGING/PREP AREA.
4. DEMOLITION DEBRIS: DEBRIS SHALL BE REMOVED IN CARTS WITH TIGHTLY FITTED COVERS, USING DESIGNATED TRAFFIC ROUTES. EFFORTS SHALL BE MADE TO MINIMIZE USE OF
ELEVATORS WITH AN EMPHASIS ON TRANSPORT DURING THE LOWEST PERIOD OF ACTIVITY.
DEBRIS SHALL BE REMOVED DAILY AND AT TIMES SPECIFIED BY THE VAMC. IF CHUTES ARE USED TO DIRECT DEBRIS OUTSIDE, HIGH EFFICIENCY PARTICULATE AIR (HEPA) FILTERED NEGATIVE AIR
MACHINES SHALL BE USED, AND THE CHUTE OPENING SHALL BE SEALED WHEN NOT IN USE.
FILTERS SHALL BE BAGGED AND SEALED BEFORE BEING TRANSPORTED OUT OF THE
CONSTRUCTION AREA. THE CONTRACTOR SHALL NOT HAUL DEBRIS THROUGH PATIENT-CARE
AREAS WITHOUT PRIOR APPROVAL OF THE COR.
5. EXTERIOR WINDOWS: WINDOWS SHALL BE SEALED TO MINIMIZE INFILTRATION FROM ANY
ADJACENT EXCAVATION DEBRIS.
6. ALL FURNISHINGS AND EQUIPMENT TO REMAIN IN THE IMPACTED ROOMS SHALL BE COVERED
AND PROTECTED PRIOR TO STARTING EACH CONSTRUCTION PHASE.
VENTILATION AND ENVIRONMENTAL CONTROLS
1. AIR SYSTEM FLOW: THE COR VERIFY AND ACKNOWLEDGE CONTRACTOR WHETHER THE
CONSTRUCTION AREA USES FRESH/OUTSIDE OR RE-CIRCULATED AIR; FILTERS SHALL BE ADDED
OR RETURN VENTS COVERED AS NEEDED WITH FILTER MATERIAL OR PLASTIC. AIR MUST FLOW
FROM CLEAN TO DIRTY AREAS.
2. NEGATIVE AIR PRESSURE: THE AIR WITHIN THE CONSTRUCTION AREA SHALL BE NEGATIVE WITH
RESPECT TO SURROUNDING AREAS AND WITH NO DISRUPTION OF AIR SYSTEMS OF ADJACENT
AREAS. USE OF THE NEGATIVE AIR PRESSURE SYSTEM WITHIN THE ENCLOSURE TO REMOVE
DUST SHALL PASS AIR THROUGH AN INDUSTRIAL GRADE, PORTABLE HEPA FILTER CAPABLE OF
FILTRATION RATES OF 300-800 CUBIC FEET PER MINUTE (FT3/MIN), OR EXHAUST AIR DIRECTLY TO THE OUTSIDE IF APPROVED BY VAMC. IF EXHAUST SHALL BE TIED INTO A RE-CIRCULATED AIR
SYSTEM, A PRE-FILTER AND HEPA FILTER SHALL BE USED BEFORE EXHAUST TO PREVENT
CONTAMINATION OF THE DUCTS.
3. FOR EXHAUST DUCT ROUTING THRU CORRIDOR: INSTALL HARD DUCT WITH NON-FLANGE HANGER
HUNG FROM CEILING ABOVE, BOTTOM OF DUCT SHALL BE A MINIMUM OF 7'-2" A.F.F.
4. ADJACENT AREAS: THE STATUS OF SEALED PENETRATIONS AND INTACT CEILING SHALL BE
VERIFIED DAILY.
5. AIR EXCHANGE RATES AND PRESSURE RELATIONSHIPS: VAMC AND CONTRACTOR SHALL VERIFY AND MAINTAIN PROPER RATES IN CRITICAL AREAS NEAR CONSTRUCTION ACTIVITY AND ENSURE
AIR IS NOT BEING RE-CIRCULATED WITHOUT FILTRATION FROM THE CONSTRUCTION AREA
ELSEWHERE. PROVIDE AIR PRESSURE TESTING THROUGHOUT THE PROJECT IN THE FREQUENCY
AS IDENTIFIED BY THE COR.
CONTAMINATION OF PATIENT ROOMS, SUPPLIES, EQUIPMENT AND RELATED AREAS
1. WORKSITE CLOTHING: CONTRACTOR PERSONNEL CLOTHING SHALL BE FREE OF LOOSE SOIL AND
DEBRIS BEFORE LEAVING THE CONSTRUCTION AREA. IF PROTECTIVE APPAREL IS NOT WORN
(E.G., COVERALLS, FOOTGEAR AND HEADGEAR) A HEPA-FILTERED VACUUM SHALL BE USED TO
REMOVE DUST FROM CLOTHING BEFORE LEAVING THE BARRICADE. IF PROTECTIVE APPAREL IS
UTILIZED, THE CONTRACTOR SHALL CONSTRUCT A SPACE OR ANTEROOM FOR CHANGING
CLOTHING AND STORING EQUIPMENT (DESIGNATED AREA. ALL EQUIPMENT, TOOLS, TOOL CARTS, AND MATERIALS TRANSPORTED THROUGH OCCUPIED AREAS SHALL BE MADE FREE FROM DUST
AND MOISTURE BY VACUUMING AND WET WIPING BEFORE THEIR REMOVAL FROM THE
CONSTRUCTION ZONE OR WORK AREA.
2. POST CONSTRUCTION: DO NOT REMOVE BARRIERS AND KEEP ALL HVAC ISOLATION UNTIL
CONTRACTOR HAS CLEANED CONSTRUCTION SITE, VA EMS STAFF HAS DONE A TERMINAL
CLEANING, AND VA INFECTIOUS DISEASE CONTROL HAS INSPECTED AND APPROVED THE
CLEANING.
ICRA NOTES
IIILOW Risk Group 1
Class III
Note: Infection Control approval will be required when the Construction Activity and Risk Level indicate that
It is the Contractor's Responsibility to provide the following Infection Control Precautions depending upon the Area Class Designation
I
I
III
MEDIUM Risk Group 2
HIGH Risk Group 3
HIGHEST Risk Group 4 IV
IV
IV
IV
IV
III
IV
II
III
Patient Risk Group Table
Infection Control Matrix - Class of Precautions: Construction Project by Patient Risk
TYPE A
Construction Project Type
Major demolition and construction projects Includes, but is not limited to:
• Removal or replacement of building system component(s).
• Removal/installation of drywall partitions.
• Invasive large-scale new building construction.
• Renovation work in two or more rooms.
Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies Includes, but is not limited to:
• Removal of preexisting floor covering, walls, casework or other building components.
• New drywall placement.
• Renovation work in a single room.
• Nonexisting cable pathway or invasive electrical work above ceilings.
• The removal of drywall where a moderate amount of dust and debris is created.
• Dry sanding where a moderate amount of dust and debris is created.
• Work creating significant vibration and/or noise.
• Any activity that cannot be completed in a single work shift.
Small scale, short duration activities which create minimal dust Includes, but is not limited to:
• Work conducted above the ceiling (e.g., prolonged inspection or repair of firewalls and barriers, installation of conduit and/or cabling, and access to mechanical and/or electrical chase spaces).
• Fan shutdown/startup.
• Installation of electrical devices or new flooring that produces minimal dust and debris.
• The removal of drywall where minimal dust and debris is created.
• Controlled sanding activities (e.g., wet or dry sanding) that produce minimal dust and debris.
Inspection and Non-Invasive Activities Includes, but is not limited to:
• Removal of ceiling tile for visual inspection-limited to 1 tile per 50 square feet with limited exposure time.
• Limited building system maintenance (e.g., pneumatic tube station, HVAC system, fire suppression system, electrical and carpentry work to include painting without sanding) that does not create dust or debris.
• Clean plumbing activity limited in nature.
Type of Construction / Project Activity Table
Group 2 Medium Risk
Group 1 Low Risk
• Physical Therapy
• Radiology departments
• All patient waiting rooms
• All outpatient clinics
• Research Areas
• Respiratory Therapy
• Office areas (non-clinical)
• FES/EMS areas
I
Patient Risk Group
TYPE D
TYPE C
TYPE B
TYPE A
Group 4 Highest Risk
Group 3 High Risk
• Emergency Room
• Clinical Laboratories (specimen)
• Same Day Surgery
• Pharmacy
• Nutrition and Food
Service/Canteen
• Procedural Areas (GI)
• Inpatient Mental Health
• Any area caring for immunocompromised patients
• Cardiac Cath Lab/IR
• Central Sterile Supply
• Sterile Processing Service
• Intensive Care Units
IIII
TYPE DTYPE CTYPE B
Class IVor control procedures are necessary.
C
LA
S S
IV
During Construction Project Upon Completion of Project
1. Includes all activities required by Class III
2. Obtain Infection Control Permit from Hospital Safety Officer or Facilities Management
Maintenance and Engineering department before construction begins.
3. Construct and complete critical barriers meeting NFPA 241 requirements. Barriers must extend to the ceiling or if ceiling tile is removed, to the deck above.
4. All (plastic or hard) barrier construction activities must be completed in a manner that prevents dust release. Plastic barriers must be effectively affixed to ground and ceiling and secure from movement or damage. Apply tape that will not leave a residue to seal gaps between barriers, ceiling or floor.
5. Seal all penetrations in containment barriers, including floors and ceiling, using approved materials (UL schedule firestop if applicable for barrier type).
6. Containment units or environmental containment units (ECUs) approved for Class IV precautions in small areas totally contained by the unit and that has HEPA-filtered exhaust air.
7. Remove or isolate return air diffusers to avoid dust entering the HVAC system.
8. Remove or isolate the supply air diffusers to avoid positive pressurization of the space.
9. Negative airflow pattern must be maintained from the entry point to the anteroom and into the construction area. The airflow must cascade from outside to inside the construction area. The entire construction area must remain negatively pressurized.
10. Maintain negative pressurization of the entire workspace by use of HEPA exhaust air systems directed outdoors. Exhaust discharged directly to the outdoors that is 25 feet or greater from entrances, air intakes and windows does not require HEPA-filtered air.
11. If exhaust is directed indoors, then the system must be HEPA filtered. Prior to start of work, HEPA filtration must be verified by particulate measurement as no less than 99.97% efficiency and must not alter or change airflow/pressure relationships in other areas.
12. Exhaust into shared or recirculating HVAC systems, or other shared exhaust systems (e.g., bathroom exhaust) is not acceptable.
13. Install device (e.g., magnehelic, manometer, or digital monitoring) on exterior of work containment to continually monitor negative pressurization. The “ball in the wall” or similar apparatus are not acceptable.
14. Contain all trash and debris in the work area.
15. Nonporous/smooth and cleanable containers (with a hard lid) must be used to transport trash and debris from the construction areas. These containers must be damp-wiped cleaned and free of visible dust/debris before leaving the contained work area.
16. Worker clothing must be clean and free of visible dust before leaving the work area.
HEPA vacuuming of clothing or use of cover suites is acceptable.
17. Workers must wear shoe covers prior to entry into the work area. Shoe covers must be changed prior to exiting the anteroom to the occupied space (non-work area). Damaged shoe covers must be immediately changed.
18. Install a sticky (dust collection) mat at entrance of contained work area based on facility policy. Sticky mats must be changed routinely and when visibly soiled.
19. Consider collection of particulate data during work to monitor and ensure that contaminates do not enter the occupied spaces. Routine collection of particulate samples may be used to verify HEPA filtration efficiencies.
• Medical/Surgical Units
• Negative pressure isolation rooms
• Outpatient Chemotherapy
Areas
• Operating rooms
• Post Anesthesia Care Unit
• Dialysis
• Dental
C
LA
S S
V
1. Includes all activities required by Class IV
2. Obtain Infection Control Permit from Hospital Safety Officer or Facilities Management
Maintenance and Engineering department before construction begins.
3. Construct and complete critical barriers meeting NFPA 241 requirements. Barriers must extend to the ceiling or if ceiling tile is removed, to the deck above.
4. All (plastic or hard) barrier construction activities must be completed in a manner that prevents dust release. Plastic barriers must be effectively affixed to ground and ceiling and secure from movement or damage. Apply tape that will not leave a residue to seal gaps between barriers, ceiling or floor.
5. Seal all penetrations in containment barriers, anteroom barriers, including floors and ceiling using approved materials (UL schedule firestop if applicable for barrier type).
6. Construct anteroom large enough for equipment staging, cart cleaning, workers. The anteroom must be constructed adjacent to entrance of construction work area.
7. Personnel will be required to wear coveralls at all times during Class V work activities.
Coveralls must be removed before leaving the anteroom.
8. Remove or isolate return air diffusers to avoid dust entering the HVAC system.
9. Remove or isolate the supply air diffusers to avoid positive pressurization of the space.
10. Negative airflow pattern must be maintained from the entry point to the anteroom and into the construction area. The airflow must cascade from outside to inside the construction area. The entire construction area must remain negatively pressurized.
11. Maintain negative pressurization of the entire workspace using HEPA exhaust air systems directed outdoors. Exhaust discharged directly to the outdoors that is 25 feet or greater from entrances, air intakes and windows does not require HEPA-filtered air.
12. If exhaust is directed indoors, then the system must be HEPA filtered. Prior to start of work, HEPA filtration must be verified by particulate measurement as no less than 99.97% efficiency and must not alter or change airflow/pressure relationships in other areas.
13. Exhaust into shared or recirculating HVAC systems, or other shared exhaust systems (bathroom exhaust) is not acceptable.
14. Install device (e.g., magnehelic, manometer, or digital monitoring) on exterior of work containment to continually monitor negative pressurization. The “ball in the wall” or similar apparatus are not acceptable.
15. Contain all trash and debris in the work area.
16. Nonporous/smooth and cleanable containers (with a hard lid) must be used to transport trash and debris from the construction areas. These containers must be damp-wiped cleaned and free of visible dust/debris before leaving the contained work area.
17. Worker clothing must be clean and free of visible dust before leaving the work area anteroom.
18. Workers must wear shoe covers prior to entry into the work area. Shoe covers must be changed prior to exiting the anteroom to the occupied space (non-work area).
Damaged shoe covers must be immediately changed.
19. Install a sticky (dust collection) mat at entrance of contained work area based on facility policy. Sticky mats must be changed routinely and when visibly soiled.
20. Consider collection of particulate data during work to monitor and ensure that contaminates do not enter the occupied spaces. Routine collection of particulate samples may be used to verify HEPA filtration efficiencies.
Construction areas must be inspected by an infection preventionist or designee and engineering representative for discontinuation or downgrading of ICRA precautions.
Work Area Cleaning:
1. Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials.
2. Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces.
Removal of Critical Barriers:
1. Critical barriers must remain in place during all work involving drywall removal, creation of dust and activities beyond simple touch-up work. The barrier may NOT be removed until a work area cleaning has been performed.
2. All (plastic or hard) barrier removal activities must be completed in a manner that prevents dust release. Use the following precautions when removing hard barriers:
1. Carefully remove screws and painter tape.
2. If dust will be generated during screw removal, use hand-held HEPA vacuum.
3. Drywall cutting is prohibited during removal process.
4. Clean all stud tracks with HEPA vacuum before removing outer hard barrier.
5. Use a plastic barrier to enclose area if dust could be generated.
Negative Air Requirements:
1. The use of negative air must be designed to remove contaminates from the work area.
2. Negative air devices must remain operational at all times and in place for a period after completion of dust creating activities to remove contaminants from the work area and before removal of critical barriers.
HVAC systems:
1. Upon removal of critical barriers, remove isolation of HVAC system in areas where work is being performed.
2. Verify that HVAC systems are clean and operational.
3. Verify the HVAC systems meets original airflow and air exchange design specifications.
It is the Contractor's Responsibility to provide the following Infection Control Precautions depending upon the Area Class Designation
During Construction Project
C
LA
S S
I
Cleaning:
1. Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials.
2. Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces.
HVAC Systems:
1. Remove isolation of HVAC system in areas where work is being performed. Verify that HVAC systems are clean and operational.
2. Verify the HVAC systems meet original airflow and air exchange design specifications.
Upon Completion of Project
1. Execute work by methods to minimize raising dust from construction operations.
2. Perform noninvasive work activity as to not block or interrupt patient care.
3. Perform noninvasive work activities in areas that are not directly occupied with patients.
4. Perform noninvasive work activity in a manner that does not create dust.
5. Immediately replace any displaced ceiling tile before leaving the area and/or at end of noninvasive work activity.
C
LA
S S
II
Cleaning:
1. Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials.
2. Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces.
HVAC Systems:
1. Remove isolation of HVAC system in areas where work is being performed. Verify that HVAC systems are clean and operational.
2. Verify the HVAC systems meet original airflow and air exchange design specifications.
1. Includes all activities required by Class I
2. Perform only limited dust work and/or activities designed for basic facilities and engineering work.
3. Perform limited dust and invasive work following standing precautions procedures approved by the organization.
4. This Class of Precautions must never be used for construction or renovation activities.
5. Provide active means to prevent airborne dust from dispersing into atmosphere.
6. Water mist work surfaces to control dust while cutting.
7. Seal unused doors with duct tape.
8. Block off and seal air vents.
9. Replace adhesive walk-off mats at entrance and exit of work area. Replace used mats in accordance with manufacturer's recommendations.
10. Remove or isolate HVAC system in area where work is being done to prevent contamination of duct system.
Construction areas must be inspected by an infection preventionist or designee and engineering representative for discontinuation or downgrading of ICRA precautions.
Work Area Cleaning:
1. Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials.
2. Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces.
Removal of Critical Barriers:
1. Critical barriers must remain in place during all work involving drywall removal, creation of dust and activities beyond simple touch-up work. The barrier may NOT be removed until a work area cleaning has been performed.
2. All (plastic or hard) barrier removal activities must be completed in a manner that prevents dust release. Use the following precautions when removing hard barriers:
1. Carefully remove screws and painter tape.
2. If dust will be generated during screw removal, use hand-held HEPA vacuum.
3. Drywall cutting is prohibited during removal process.
4. Clean all stud tracks with HEPA vacuum before removing outer hard barrier.
5. Use a plastic barrier to enclose area if dust could be generated.
Negative Air Requirements:
1. The use of negative air must be designed to remove contaminates from the work area.
2. Negative air devices must remain operational at all times and in place for a period after completion of dust creating activities to remove contaminants from the work area and before removal of critical barriers.
HVAC systems:
1. Upon removal of critical barriers, remove isolation of HVAC system in areas where work is being performed.
2. Verify that HVAC systems are clean and operational.
3. Verify the HVAC systems meets original airflow and air exchange design specifications.
CONSTRUCTION ACTIVITIES SHALL BE CLASSIFIED AS FOLLOWS UNLESS NOTED OTHERWISE:
1. INSTALLATION OF CABLE TRAY IN CORRIDOR CEILINGS SHALL BE CONSIDERED CONSTRUCITON ACTIVITY TYPE B.
2. ALL CONDUIT SPECIFIED TO BE INSTALLED IN WALL SHALL BE CONSIDERED CONSTRUCTION ACTIVITY TYPE C.
3. CONSTRUCTION OF NEW ROOMS SHALL BE CONSIDERED CONSTRUCTION ACTIVITY TYPE D.
4. INSTALLATION OF NEW DOORS TO OR FROM EXISTING SPACES SHALL BE CONSIDERED CONSTRUCTION ACTIVITY TYPE C.
C
LA
S S
II
I
1. Includes all activities required by Class II
2. Obtain Infection Control Permit from Hospital Safety Officer or Facilities
Management Maintenance and Engineering department before construction begins.
3. Provide active means to prevent airborne dust dispersion into the occupied areas.
4. Means for controlling minimal dust dispersion may include hand-held HEPA vacuum devices, polyethylene plastic containment, or isolation of work area by closing room door.
5. Remove or isolate return air diffusers to avoid dust from entering the HVAC system.
6. Remove or isolate the supply air diffusers to avoid positive pressurization of the space,
7. If work area is contained, then it must be neutrally to negatively pressurized at all times.
8. Seal all doors with tape that will not leave residue.
9. Contain all trash and debris in the work area.
10. Nonporous/smooth and cleanable containers (with a hard lid) must be used to transport trash and debris from the construction areas. These containers must be damp-wiped cleaned and free of visible dust/debris before leaving the contained work area.
11. Install a sticky (dust collection) mat at entrance of contained work area based on facility policy. Sticky mats must be changed routinely and when visibly soiled.
12. Maintain clean surroundings when area is not contained by damp mopping or HEPA vacuuming surfaces.
13. Clean construction area at the end of each shift by damp mopping or HEPA Vacuum.
For Type C activities, follow procedures for Class IV.
Cleaning:
1. Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials.
2. Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces.
HVAC Systems:
1. Remove isolation of HVAC system in areas where work is being performed. Verify that HVAC systems are clean and operational.
2. Verify the HVAC systems meet original airflow and air exchange design specifications.
A
.F .F
A P
P R
O X
SUSPENDED
PLASTIC ZIPPER
WALL CURTAIN
BARRIER
POST ICRA, ILSM, FIRE
INSPECTION SHEETS
VISIBLE TO PUBLIC
PLASTIC
WINDOW
SWIVEL CASTERS
WITH TWO
LOCKING BRAKES
MOBILE CART
A D
J U
S T
A B
L E
H
E
IG
H T
HEPA NEGATIVE
AIR UNIT
EXISTING
WALL
EXISTING
CEILING
FLEX DUCT
ROOM WIDTH VARIES
REMAINING CEILING
SURFACE TO REMAIN
INTACT.
REMOVE EXISTING GYP.
BD/PLASTER CEILING
"ONLY" TO REPLACE
ABOVE CEILING PIPING.
CEILING STRUCTURE
TO REMAIN INTACT.
V A
R
IE
S
REPAIR/PATCH JOINT BETWEEN
EXIST. CEILING SURFACE AND
NEW CEILING SURFACE. MATCH
SALIANT CHARACTERISTICS OF
ADJACENT SURFACES
ROOM WIDTH VARIES
REMAINING
CEILING
SURFACE TO
REMAIN INTACT.
PROVIDE NEW GYP. BD/PLASTER
CEILING TO THE AFFECTED
LIMITS OF CONSTRUCTION.
REPAIR/REPLACE DAMAGED
STRUCTURAL FRAMING
MEMBERS AS REQUIRED.
PAINT ENTIRE CEILING OF ROOM
ONCE THE NEW PARTIAL
CEILING HAS BEEN INSTALLED.
V A
R
IE
S
FUNCTIONAL ROOM
CORRIDOR
EXISTING DOOR
TO REMAIN
STICKY MATS
WORK IN EXISTING ROOM
FLOOR PENETRATION FOR NEW
PIPING. PROVIDE FIRE STOPPING
AT ALL PENETRATIONS.
STICKY MAT
PENETRATION OF EXISTING FLOOR SLAB
CORRIDOR
PLASTIC SHEET
ICRA BARRIER
ZIPPER DOORS
ABOVE CEILING WORK IN CORRIDOR
WORK ABOVE CEILING
STICKY MAT
EXISTING WALL TO REMAIN
20'-0" MAX
C L E
A R
M
IN
REMOVED GYP BD
CEILING FOR ACCESS TO
ABOVE CEILING PIPING.
ABOVE CEILING PIPING
TO BE REMOVED AND
REPLACED.
1-HR RATED (TYPE A)
TEMPORARY BARRIER
45-MIN RATED
TEMPORARY DOOR
WORK ABOVE CEILING
REMOVED GYP. BD.
TO ACCESS IN WALL
PIPING.
EXISTING WALL
TO REMAIN
PIPING TO BE REPLACED
EXISTING WALL
TO REMAIN
EXISTING WALL
TO REMAIN
REMOVED GYP BD
CEILING FOR ACCESS
TO ABOVE CEILING
PIPING.
ZIPPER DOORS
EXISTING WALL
TO REMAIN
M A
Y V
A R
Y
C E
IL
IN
G H
E
IG
H T
1' -0
" NEW PIPING REFER TO
PLUMBING PLANS FOR
LOCATIONS.
PATCH AND REPAIR
AROUND ALL NEW IN WALL
PIPING. MATCH THE
SALIENT CHARACTERISTICS
OF THE WALL MATERIAL
AND FINISH COLOR.
DEMOLITION OF EXISTING WALL SURFACES SHALL
INCORPORATE HEPA FILTERED VACUUM ATTACHMENT(S) FOR
POWER TOOLS USED IN WORK. VACUUM UP DUST AND
DEBRIS, AND USE WET WIPES OR SPRAY CLEANER AND CLEAN
RAGS TO ENSURE AREA IS CLEAN AFTER WORK IS COMPLETE.
NOT ALL EQUIPMENT SHOWN IN THIS
DETAIL ARE APPLICABLE TO EACH ROOM.
REFER TO PLUMBING PLANS.
WIDTH VARIES
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/1
/2
:4
:4
A
M C
U s e rs \m g a in e s .C
O R
P \D o c u m e n ts \A
-0
-V A
M o n tg o m e ry -L e g io n e lla
D e s ig n -A
L R m g a in e s A
V F
.r v t
G-002
ICRA INFORMATION AND DETAILS
2 4BN
LEGIONELLA PLUMBING
PROJECT BUILDING 1
CAVHCS WEST CAMPUS
215 PERRY HILL RD.
MONTGOMERY, AL 36109 JULY 16, 2025
100% CONSTRUCTION DOCUMENTS
619-23-10523-039
JAB
SCALE: NO SCALE
ICRA BARRIER WALL TYPE
SCALE: NO SCALE
TYPICAL CONSTRUCTION PLAN LAYOUT
SCALE: NO SCALE
ILSM CONSTRUCTION EGRESS SIGNAGE
SCALE: NO SCALE
ICRA ROOM ELEVATION
SCALE: NO SCALE
ICRA MOBILE CONTAINMENT CART
SCALE: 1/4" = 1'-0"
TYPICAL HARD CEILING
DEMOLITION PLAN
SCALE: 1/4" = 1'-0"
TYPICAL HARD CEILING
REPLACEMENT DETAIL
SCALE: 1/4" = 1'-0"
TYPICAL ICRA CONDITIONS
SCALE: 1/4" = 1'-0"
TYPICAL INTERIOR WALL ELEVATION
FOR NEW PIPING
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/1
/2
:4
:5
A
M C
U s e rs \m g a in e s .C
O R
P \D o c u m e n ts \A
-0
-V A
M o n tg o m e ry -L e g io n e lla
D e s ig n -A
L R m g a in e s A
V F
.r v t
G-003
ICRA TABLE
3 4CET
LEGIONELLA PLUMBING
PROJECT BUILDING 1
CAVHCS WEST CAMPUS 215 PERRY
HILL RD. MONTGOMERY, AL 36109
JULY 16, 2025
100% CONSTRUCTION DOCUMENTS
619-23-10523-039
JAB
1 FIFTH A 5A-106A Quality Office TYPE C LOW Class II OPEN UP WALL, DRILL THRU SLAB. WORK THIS FLR AND 4TH FLR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH B 4B-118A CPAP Classroom TYPE C HIGH Class IV OPEN UP CHASR. WORK ON THIS FLR AND 3RD FLR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH B 4B-120 Move Classroom TYPE C HIGH Class IV OPEN UP CHASE. WORK ON FLRS 0-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH B 4B-133A Social Wok Suervisor Restroom TYPE C LOW Class II OPEN UP CHASE. WORK ON FLOORS 0-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH B 4B-132 Social Work Office TYPE C HIGH Class IV OPEN CHASE. WORK ON THIS FLOOR AND 3RD FLR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH B 4B-138 Exam Room TYPE C HIGH Class IV OPEN CHASE. WORK ON THIS FLOOR AND 3RD FLR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH B 4B-109 Soiled Utility TYPE C HIGH Class IV DRILL THRU SLAB, OPEN CHASE. WORK ON FLRS 0-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH B 4B-124 Office/Provider Room TYPE C HIGH Class IV OPEN UP CHASE. WORK ON FLOORS 2-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH B 4B-114 Staff Restroom TYPE C MEDIUM Class II OPEN UP WALL, WORK THIS FLOOR AND THIRD FLR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours 1 FOURTH A 4B-102 Social Work Office TYPE C HIGH Class IV DRILL THROUGH SLAB ABOVE WORK THIS FLR AND 4TH FLR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH A 4A-132 Patients TYPE C HIGH Class IV OPEN UP CHASE, DRILL THRU SLAB WORK ON FLRS 2-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH A 4A-138 PTSD Phsychologist TYPE C HIGH Class IV OPEN UP CHASE, WORK ON THIS FLR AND 3RD FLR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH A 4A-109 Soiled Utility TYPE C HIGH Class IV OPEN UP WALL, POSSIBLY DRILL THROUGH SLAB. WORK ON FLRS 0 - 4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH A 4A-124 Psychiatrist TYPE C HIGH Class IV OPEN UP CHASE, DRILL THRU SLAB. WORK ON FLRS 2-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH A 4A-115 M Platinum Clinic Nurse TYPE B HIGH Class II WORK ABOVE HARD CEILING. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FOURTH A 4A-120 Patient Waiing Room TYPE C MEDIUM Class III OPEN UP CHASE, DRILL THRU SLAB. WORK ON FLRS 2-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD B 3B-132 Education/Vitals TYPE B MEDIUM Class II OPEN UP CHASE ON THIS FLOOR. WORK ON FLOORS 0-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD B 3B-133A Physician Restroom TYPE C LOW Class II DRILL THROUGH SLAB ABOVE. WORK ON THIS FLOOR AND 4TH FLR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD B 3B-138 Physician Office / Exam Room TYPE C HIGH Class IV DRILL THROUGH SLAB ABOVE. WORK ON THIS FLOOR AND 4TH FLR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD B 3B-109 Soiled Utility TYPE C HIGH Class IV DRILL THRU SLAB , OPEN CHASE WORK ON FLRS 0-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD B 3B-124 Exam Room TYPE C HIGH Class IV OPEN UP CHASE. WORK ON FLOORS 2-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD B 3B-114 Staff Restroom TYPE B LOW Class II DRILL THROUGH SLAB. WORK THIS FLOOR AND FOURTH FLR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD B 3B-120 Lockeroom TYPE B LOW Class II OPEN UP CHASE. WORK ON FLOORS 0-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD B 3B-118 Neuro Exam Room TYPE C HIGH Class IV DRILL THOUGH SLAB ABOVE. WORK ON THIS FLOOR AND 4TH FLOOR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD A 3A-132 Pateint Room TYPE C HIGH Class IV OPEN UP CHASE, DRILL THRU SLAB. WORK ON FLRS 2-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD A 3A-138 Storage for Wheelchairs/Shower TYPE C HIGH Class IV OPEN UP CHASE. WORK ON THIS FLR AND FOURTH FLR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD A 3A-109 Soiled Utility TYPE C HIGH Class IV OPEN UP WALL, POSSIBLY DRILL THROUGH SLAB. WORK ON FLORS 0-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD A 3A-124 Patient Room TYPE C HIGH Class IV OPEN UP CHASE, DRILL THRU SLAB. WORK ON FLOORS 2-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD A 3A-115C Patient Room TYPE C HIGH Class IV WORK ABOVE HARD CEILING 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 THIRD A 3A-120 Pateint Room TYPE C HIGH Class IV OPEN UP CHASE, DRILL THRU SLAB. WORK ON FLOORS 2-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND D S2-7 Stairwelll TYPE B LOW Class II WORK IN STAIRS. DRILL THRU STAIR WALL TO INSTALL NEW SPRINKLER PIPING THAT WILL SERVE PENTHOUSE. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND D 2D-106 Decon Dressing Room TYPE C HIGHEST Class IV OPEN UP WALL. DRILL THRU SLAB. WORK ON FLOORS 0-2. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND D 2D-109 Mechanical Room TYPE B Low Class II WORK IN MECH ROOM. DRILLING THRU SLAB, WORK ON FLRS 0 - 2. Mental Helth Offices 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND C 2C-111C HAC - Inside Scrub Room TYPE C HIGHEST Class IV OPEN UP WALL, WORK ON FLOORS 2-0. Mental Health Offices 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND C 2C-108 Digestive & Endo TYPE C HIGHEST Class IV WORK ABOVE HARD CEILING. THIS FLOOR ONLY. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND C 2C-107C Toilet & Clean Linen TYPE C HIGHEST Class IV OPEN UP CHASE, DRILL THRU SLAB.WORK ON FLOORS 1,2. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND C 2C-0104 Soiled Linen - OR TYPE C HIGHEST Class IV DRILL THRU SLAB. OPEN UP CHASE AND HARD CEILING. WORK ON FLOORS 1-2. ICU 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND B 2B-146 Non-Invasive Cardiac Lab TYPE B HIGH Class II OPEN UP WALL ON THIS FLOOR, DRILL THROUGH SLAB. WORK ON FLOORS 0-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND B 2B-149 Equipment Storage TYPE B HIGH Class II DEMO WORK ABOVE HARD CEILING. Offices, Also main Patient Corridor 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND B 2B-127-3 ICU Patient Room TYPE B/C HIGHEST Class IV DRILL THROUGH SALB. WORK ON THIS FLOOR, THIRD, FOURTH. Inpatient Medical, Acute Care Unit 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND B 2B-109 TeleMental Health TYPE B HIGH Class II DRILL THRU SLAB, OPEN CHASE. WORK ON FLRS 0-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND B 2B-122 ICU Patient Room TYPE B/C HIGHEST Class IV OPEN UP CHASE, DRILL THROUGH SLAB. WORK ON FLOORS 0-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND A 2A-132 Dr. Paulk's Office TYPE B/C HIGHEST Class IV OPEN UP CHASE, DRILL THRU SLAB. WORK ON FLORS 2-4. Inpatient Medical, Acute care Unit, SSU 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND A S2-3 Stairwell TYPE B Low Class II OPEN UP WALL; POSSIBLY DRILL THROUGH SLAB. WORK ON FLOORS 0-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND A 2A-112 Nursing Station SDS TYPE B High Class II OPEN UP CHASE, DRILL THRU SLAB. WORK ON FLOORS 1-2 ICU, OR 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND A 2A-124 Pateint Room SDS TYPE B/C HIGH Class IV OPEN UP CHASE, DRILL THRU SLAB. WORK ON FLOORS 2-4. Kitchen Cart Wash, Hmodialysis down hall 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND A 2A-121 Pateint Room SDS TYPE B/C HIGH Class IV OPEN UP CHASE, DRILL THRU SLAB. WORK ON FLOORS 2-0. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 SECOND A 2A-120 Pateint Room SDS TYPE B/C HIGH Class IV OPEN UP CHASE, DRILL THRU SLAB. WORK ON FLOORS 2-4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FIRST D 1D-122 Gross Specimen Storage TYPE B High Class II OPEN UP WALL, DRILL THRU SLAB WORK ON FLOORS 0-2. Radiology (X-Ray and Patient Monitoring, MRI) 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FIRST C 1D-108 HAC TYPE B High Class II Partial Stor. Rm. Gets absorbed into A237 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FIRST C 1C-112 Medical Records TYPE B Low Class II DRILL THROUGH SLAB. WORK ON FLOORS 1-0. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FIRST C 1C-109 HR TYPE B Low Class II DRILL THRU SLAB WORK ON FLOORS 1-2. Physical Therapy 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FIRST C 1C-103 Office TYPE B Low Class II DRILL THRU SLAB WORK ON FLOORS 1-2. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FIRST B 1D-115 Pharmacy Construction TYPE B/C HIGHEST Class IV OPEN UP WALL ON THIS FLOOR, DRILL THROUGH SLAB. WORK ON FLOORS1 -4. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FIRST B 1B-105 Men's Restroom TYPE B High Class II DRILL THRU SLAB, OPEN CHASE. WORK ON FLRS 0-4. Pharmacy (In-Patient) 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FIRST B 1B-111 Occupational Therapy TYPE B High Class II OPEN UP WALL TO DEMO PIPE. THIS FLOOR ONLY. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FIRST B 1B-116 Physical Therapy Clinic TYPE B High Class II OPEN UP WALL. WORK ON GROUND FLR, THIS FLOOR, SECOND FLR, THIRD FLR, FOURTH FLR. Outpatient Clinic Area 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FIRST A 1A-114 Office - Correspondence TYPE B LOW Class II OPEN UP WALL, POSSIBLY DRILL THROUGH SLAB WORK ON FLOORS 0-4. Main Computer Room 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FIRST A 1A-116 Men's Bathroom TYPE B LOW Class II DRILL THRU SLAB, WORK ON FLOORS 1-2. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 FIRST A 1A-124C Office TYPE B LOW Class II OPEN UP CHASE, DRILL THRU SLAB. WORK ON FLOORS 2 - 0. Primary Care(TIMS/Imaging for Clinics) 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 GROUND D GD-118 ED Bathroom Men TYPE B/C HIGH Class IV OPEN UP CHASE. WORK THIS FLOOR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 GROUND D GD-133 Nursing Station ED TYPE B/C HIGH Class IV OPEN UP CHASE. WORK THIS FLOOR. 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM 4:00 PM - 12:00 AM per work area hours per work area hours
1 GROUND D GD-113 ED Bathroom - Women TYPE B/C HIGH Class IV OPEN UP CHASE.