This document includes a solicitation for a construction project and a related presolicitation notice. The solicitation is for Project Number 632-19-106 to renovate and expand pharmacy spaces at the Northport VA Medical Center in Northport, New York. The estimated cost range for the project is between $1,000,000 to $5,000,000. The scope of work involves abatement, demolition, construction, alterations and installation of mechanical, electrical and fire protection systems to expand and renovate existing pharmacy spaces. The contract duration is 455 calendar days from receipt of the notice to proceed. The solicitation will be released on or around September 30, 2021 via SAM.gov and responses must be submitted in hard copy by the date specified in the solicitation. The project has an SDVOSB set-aside and is being conducted by the Department of Veterans Affairs Veterans Health Administration VISN 2.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A32A

A32

A32

A3-25A3-23A3-21

A3-24 A3-22

A3-2A

A3-2B

A3-2

A3-25A3-23A3-21

A3-24 A3-22

A425 A432A

THIRD & FOURTH FLOOR ASBESTOS

ABATEMENT PLANS

PHASE TWO 3RD FLOOR, ASBESTOS ABATEMENT

PHASE ONE 3RD FLOOR, ASBESTOS ABATEMENT

PHASE TWO 4TH FLOOR, ASBESTOS ABATEMENT

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h 6/

/2

:3

9:

P M

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

23 MAR 2021Revisions: Date:

632-19-106

79 MIDDLEVILLE ROAD, NORTHPORT, NY 11768

RENOVATE PHARMACY SPACES

THINKFORM DESIGN ARCHITECT LLC

38 EAST BROAD STREET

HOPEWELL, NJ 08525

T:855.821.0274 F:609.644.4397 Russell DiNardo, AIA NY 031521-1

NORTHPORT VAMC

Egan Environmental Consulting, Inc.

BID DOCUMENTS

KEY MAP - BLDG 200, 3RD & 4TH FLOOR

Drawing 03 of 52

200-HA100

TGE EDS

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text H

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

DECON UNIT

AutoCAD SHX Text A

AutoCAD SHX Text A

AutoCAD SHX Text H

AutoCAD SHX Text T

AutoCAD SHX Text

TEMPORARY CONSTRUCTION BARRIER

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text H

AutoCAD SHX Text H

AutoCAD SHX Text T

AutoCAD SHX Text H

AutoCAD SHX Text T

AutoCAD SHX Text

ELECTRICAL GFCI LOCATION

AutoCAD SHX Text

WATER LOCATION

AutoCAD SHX Text

2ND FLOOR CEILING PLUMBING DISCONNECTS

AutoCAD SHX Text

2ND FLOOR CEILING PLUMBING DISCONNECTS

AutoCAD SHX Text

TEMPORARY CONSTRUCTION BARRIER

AutoCAD SHX Text

TEMPORARY CONSTRUCTION BARRIER

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text A

AutoCAD SHX Text

AutoCAD SHX Text H

AutoCAD SHX Text A

AutoCAD SHX Text H

AutoCAD SHX Text T

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text A

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text T

AutoCAD SHX Text A

AutoCAD SHX Text

AutoCAD SHX Text T

AutoCAD SHX Text H

AutoCAD SHX Text A

AutoCAD SHX Text

AutoCAD SHX Text H

AutoCAD SHX Text ASBESTOS ABATEMENT LEGEND: PIPE FITTING INSULATION TO BE REMOVED. FLOOR TILE & MASTIC TO BE REMOVED (MULTIPLE LAYERS). COVE BASE AND ADHESIVE TO BE REMOVED. ROOF FLASHING TO BE REMOVED. PATH OF WASTE OUTSIDE OF BUILDING. HEPA - FILTERED NEGATIVE AIR MACHINE. AIR LOCK TENT ENCLOSURE

AutoCAD SHX Text

AutoCAD SHX Text H

AutoCAD SHX Text A

AutoCAD SHX Text T

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text Asbestos-Containing Materials Quantity Table

AutoCAD SHX Text Location

AutoCAD SHX Text Material

AutoCAD SHX Text Quantity

AutoCAD SHX Text

3RD FLOOR - ROOM A3-21

AutoCAD SHX Text

FLOOR TILE & MASTIC (MULTIPLE LAYERS)

AutoCAD SHX Text 130 S.F.

AutoCAD SHX Text

2ND FLOOR - ABOVE CEILING PLUMBING DISCONNECTS

AutoCAD SHX Text

PIPE FITTING INSULATION

AutoCAD SHX Text

10 EACH <4"

AutoCAD SHX Text

3RD FLOOR - ROOM A3-21

AutoCAD SHX Text

COVEBASE & ADHESIVE

AutoCAD SHX Text 45 S.F.

AutoCAD SHX Text

3RD FLOOR - ROOM A3-21

AutoCAD SHX Text

PIPE FITTING INSULATION

AutoCAD SHX Text

5 EACH <4"

AutoCAD SHX Text

3RD FLOOR - ROOM A3-22

AutoCAD SHX Text

FLOOR TILE & MASTIC (MULTIPLE LAYERS)

AutoCAD SHX Text 650 S.F.

AutoCAD SHX Text

3RD FLOOR - ROOM A3-22

AutoCAD SHX Text

COVEBASE & ADHESIVE

AutoCAD SHX Text 300 S.F.

AutoCAD SHX Text

3RD FLOOR - ROOM A3-22

AutoCAD SHX Text

PIPE FITTING INSULATION

AutoCAD SHX Text

10 EACH <4"

AutoCAD SHX Text

3RD FLOOR - ROOM A3-23

AutoCAD SHX Text

FLOOR TILE & MASTIC (MULTIPLE LAYERS)

AutoCAD SHX Text 130 S.F.

AutoCAD SHX Text

3RD FLOOR - ROOM A3-23

AutoCAD SHX Text

COVEBASE & ADHESIVE

AutoCAD SHX Text 45 S.F.

AutoCAD SHX Text

3RD FLOOR - ROOM A3-23

AutoCAD SHX Text

PIPE FITTING INSULATION

AutoCAD SHX Text

10 EACH <4"

AutoCAD SHX Text

3RD FLOOR - ROOM A3-24

AutoCAD SHX Text

FLOOR TILE & MASTIC (MULTIPLE LAYERS)

AutoCAD SHX Text 600 S.F.

AutoCAD SHX Text

3RD FLOOR - ROOM A3-24

AutoCAD SHX Text

COVEBASE & ADHESIVE

AutoCAD SHX Text 250 S.F.

AutoCAD SHX Text

3RD FLOOR - ROOM A3-24

AutoCAD SHX Text

PIPE FITTING INSULATION

AutoCAD SHX Text

20 EACH <4"

AutoCAD SHX Text

3RD FLOOR - ROOM A3-25

AutoCAD SHX Text

FLOOR TILE & MASTIC (MULTIPLE LAYERS)

AutoCAD SHX Text 130 S.F.

AutoCAD SHX Text

3RD FLOOR - ROOM A3-25

AutoCAD SHX Text

COVEBASE & ADHESIVE

AutoCAD SHX Text 45 S.F.

AutoCAD SHX Text

3RD FLOOR - ROOM A3-25

AutoCAD SHX Text

PIPE FITTING INSULATION

AutoCAD SHX Text

10 EACH <4"

AutoCAD SHX Text

3RD FLOOR - ROOM A32

AutoCAD SHX Text

PIPE FITTING INSULATION

AutoCAD SHX Text

5 EACH <4"

AutoCAD SHX Text

3RD FLOOR - ROOM A32A

AutoCAD SHX Text

PIPE FITTING INSULATION

AutoCAD SHX Text

10 EACH <4"

AutoCAD SHX Text

4TH FLOOR - ROOM A425

AutoCAD SHX Text

FLOOR TILE & MASTIC (MULTIPLE LAYERS)

AutoCAD SHX Text 20 S.F.

AutoCAD SHX Text

4TH FLOOR - ROOM A432A

AutoCAD SHX Text

FLOOR TILE & MASTIC (MULTIPLE LAYERS)

AutoCAD SHX Text 20 S.F.

AutoCAD SHX Text

AutoCAD SHX Text

AP100

AutoCAD SHX Text 1/8" = 1'-0"

AutoCAD SHX Text

AutoCAD SHX Text

AP100

AutoCAD SHX Text 1/8" = 1'-0"

AutoCAD SHX Text

AutoCAD SHX Text

AP100

AutoCAD SHX Text 1/8" = 1'-0"

AutoCAD SHX Text ASBESTOS ABATEMENT CONSULTANT: 14 HIGH STREET MAHWAH, NEW JERSEY 07430 Tel: (914) 320-7924 Email: tom_egan2@yahoo.com

AutoCAD SHX Text

NO SCALE

AutoCAD SHX Text N

AutoCAD SHX Text

NORTH

AutoCAD SHX Text

NORTH

AutoCAD SHX Text

NORTH

AutoCAD SHX Text

PARTIAL ASBESTOS ABATEMENT ROOF PLAN

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h 6/

/2

:3

9:

P M

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Asbestos Abatement Consultants:

Project Director

23 MAR 2021Revisions: Date:

632-19-106

79 MIDDLEVILLE ROAD, NORTHPORT, NY 11768

RENOVATE PHARMACY SPACES

THINKFORM DESIGN ARCHITECT LLC

38 EAST BROAD STREET

HOPEWELL, NJ 08525

T:855.821.0274 F:609.644.4397 Russell DiNardo, AIA NY 031521-1

NORTHPORT VAMC

TGE EDS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h 6/

/2

:3

9:

P M

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

632-19-106

79 MIDDLEVILLE ROAD, NORTHPORT, NY 11768

RENOVATE PHARMACY SPACES

THINKFORM DESIGN ARCHITECT LLC

38 EAST BROAD STREET

HOPEWELL, NJ 08525

T:855.821.0274 F:609.644.4397 Russell DiNardo, AIA NY 031521-1

NORTHPORT VAMC

TGE EDS

Egan Environmental Consulting, Inc.

BID DOCUMENTS

KEY MAP - BLDG 200 ROOF

Drawing 04 of 52

AutoCAD SHX Text

PENTHOUSE

AutoCAD SHX Text

PH-01

AutoCAD SHX Text

SVC ELEV

AutoCAD SHX Text

MACHINE RM

AutoCAD SHX Text

PH-03

AutoCAD SHX Text

PASS ELEV

AutoCAD SHX Text

MACHINE RM

AutoCAD SHX Text

PH-02

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text Q

AutoCAD SHX Text P

AutoCAD SHX Text N

AutoCAD SHX Text M

AutoCAD SHX Text L

AutoCAD SHX Text K

AutoCAD SHX Text J

AutoCAD SHX Text ASBESTOS ABATEMENT LEGEND: PIPE FITTING INSULATION TO BE REMOVED. FLOOR TILE & MASTIC TO BE REMOVED (MULTIPLE LAYERS). COVE BASE AND ADHESIVE TO BE REMOVED. ROOF FLASHING TO BE REMOVED. PATH OF WASTE OUTSIDE OF BUILDING. HEPA - FILTERED NEGATIVE AIR MACHINE. AIR LOCK TENT ENCLOSURE AREA OF WORK. AREA OF WORK HATCH

AutoCAD SHX Text

AutoCAD SHX Text H

AutoCAD SHX Text A

AutoCAD SHX Text T

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

200-HA101

AutoCAD SHX Text

NORTH

AutoCAD SHX Text

AutoCAD SHX Text

AS103

AutoCAD SHX Text 1/8" = 1'-0"

AutoCAD SHX Text ASBESTOS ABATEMENT CONSULTANT: 14 HIGH STREET MAHWAH, NEW JERSEY 07430 Tel: (914) 320-7924 Email: tom_egan2@yahoo.com

AutoCAD SHX Text

NO SCALE

AutoCAD SHX Text N

AutoCAD SHX Text

4 ROOF NW TOWER

AutoCAD SHX Text

4 ROOF NE TOWER

AutoCAD SHX Text

4 ROOF SW TOWER

AutoCAD SHX Text

4 ROOF SE TOWER

AutoCAD SHX Text

PENTHOUSE ROOF

AutoCAD SHX Text

1 ROOF

AutoCAD SHX Text

1 ROOF

AutoCAD SHX Text

1 ROOF

AutoCAD SHX Text

1 ROOF

ROOF ASBESTOS ABATEMENT PLAN

ASBESTOS ABATEMENT NOTES:

1. ALL ASBESTOS REMOVAL AREAS INDICATED ON THE PLANS AND SPECIFICATIONS

IS FOR INFORMATIONAL ASSISTANCE TO THE CONTRACTOR. ALL WORK AREAS

HAVING ASBESTOS CONTAINING MATERIALS MUST BE FIELD MEASURED AND

VERIFIED FOR ACTUAL LOCATIONS, SIZE AND QUANTITIES. ADDITIONAL PIPING

OR EQUIPMENT WHICH MAY HAVE ASBESTOS CONTAINING INSULATION MAY BE

PRESENT. THE CONTRACTOR MUST REMOVE ALL ASBESTOS CONTAINING

MATERIALS FROM ALL SPECIFIED AREAS WHETHER OR NOT SHOWN OR

ACCURATELY INDICATED. THESE SPECIFICATIONS SHALL BE USED AS A GUIDE,

AND DO NOT LIMIT THE CONTACTOR'S RESPONSIBILITY TO SEEK AND REMOVE ALL

ASBESTOS CONTAINING MATERIAL AS SPECIFIED.

2. CONTRACTOR SHALL USE EXTREME CARE AND CAUTION DURING ALL ABATEMENT

PROCEDURES. CONTRACTOR SHALL CONDUCT REMOVAL OF ALL MATERIALS

FROM THE SITE WITH A MINIMUM DISTURBANCE AND PROVIDE REGULAR

MAINTENANCE AND PROTECTION OF THE BUILDING PREMISES, STAGING AREA,

TRANSPORTATION ROUTES, ETC. THROUGHOUT THE BUILDINGS.

3. ALL BUILDING FINISHES, CONSTRUCTION EQUIPMENT OR OTHER COMPONENTS OF

THIS BUILDING WHICH ARE DAMAGED OR IN ANY WAY DISRUPTED AS A RESULT OF

THE EXECUTION OF THIS CONTRACT SHALL BE REPLACED OR RESTORED TO

ORIGINAL CONDITION.

4. CONTRACTOR SHALL PROVIDE AS MANY SHIFTS OF LABORERS AS NECESSARY TO

COMPLETE THE PROJECT IN THE AMOUNT OF TIME SPECIFIED IN THE CONTRACT

DOCUMENTS AT NO EXTRA COST.

5. ALL ASBESTOS REMOVAL SHALL BE PREFORMED IN ACCORDANCE WITH ALL

APPLICABLE FEDERAL, STATE AND LOCAL LAWS, GUIDELINES, REGULATIONS,

ORDERS AND DIRECTIVES, INCLUDING WITHOUT LIMITATIONS THOSE OF THE

RESPONSIBLE NEW YORK STATE AGENCIES; U.S. ENVIRONMENTAL PROTECTION

AGENCY (EPA), THE U.S. DEPARTMENT OF LABOR, OCCUPATIONAL SAFETY AND

HEALTH ADMINISTRATION (OSHA), NATIONAL INSTITUTE OF OCCUPATIONAL

SAFETY AND HEALTH (NIOSH), THE NEW YORK STATE DEPARTMENT OF LABOR

(NYS DOL).

6. CONTRACTOR SHALL DEVELOP AND IMPLEMENT WRITTEN STANDARD

PROCEDURES FOR ABATEMENT WORK TO ENSURE MAXIMUM PROTECTION AND

SAFEGUARDS FOR ASBESTOS EXPOSURE TO THE WORKERS, EMPLOYEES,

GENERAL PUBLIC AND THE ENVIRONMENT.

7. THE CONTRACTOR SHALL BE RESPONSIBLE FOR REMOVING ANY LIGHT FIXURES,

SUSPENDED CEILINGS, WALLS, DUCTWORK, OR ANY OBSTRUCTIONS NECESSARY

FOR THE SUCCESSFUL COMPLETION OF THE PROJECT. CONTRACTOR SHALL

CAREFULLY REMOVE, DECONTAMINATE AND REINSTALL ALL REMOVED FIXTURES,

SUPPORTING GRIDS OR ANY OTHER BUILDING STRUCTURE REMOVED BY THE

CONTRACTOR TO ACCESS ASBESTOS CONTAINING MATERIAL.

8. AIR FILTRATION DEVICE (AFD) UNITS SHALL BE EQUIPPED WITH SMOKE/HEAT

SENSOR SYSTEMS THAT WILL SHUT DOWN THE UNIT WITHIN 30 SECONDS AFTER

FIRE OR SMOKE DETECTION. AFD SENSOR UNITS MUST COMPLY WITH AMERICAN

NATIONAL STANDARDS NFPA LIFE SAFTEY CODE 101.

9. ASBESTOS REMOVAL DRAWINGS WERE PREPARED FROM EXISTING DRAWINGS

SUPPLIED BY THE OWNER AND ARE PROVIDED FOR INFORMATION ONLY. THE

CONSULTANT MAKES NO CLAIMS AS TO THEIR ACCURACY OR FOR QUANTITIES

DERIVED THROUGH THEIR USE.

10. CONTRACTOR SHALL PROVIDE ALL SCAFFOLDING, LADDERS, PLYWOOD, ETC., AS

REQUIRED AND/OR AS NECESSARY TO COMPLETE ALL WORK REQUIRED BY THE

CONTRACT DOCUMENTS.

11. CONTRACTOR SHALL PROVIDE ALL SIGNS, LABELS, WARNINGS AND POSTED

INSTRUCTIONS THAT ARE NECESSARY TO PROTECT, INFORM AND WARN PEOPLE

OF THE HAZARD FROM ASBESTOS EXPOSURE.

12. CONTRACTOR SHALL POST IN A PROMINENT AND CONVENIENT PLACE FOR THE

WORKERS, A COPY OF THE LATEST APPLICABLE REGULATIONS FORM OSHA, EPA,

NIOSH AND NYS DOL.

13. CONTRACTOR SHALL COMPLETELY PROTECT ALL CONTROLS, CONDUIT, TUBING,

ELECTRICAL PANELS, EQUIPMENT, ETC. WITHIN THE WORK AREAS.

14. THE VAMC AND THE ASBESTOS ABATEMENT CONTRACTOR SHALL MUTUALLY

AGREE UPON THE LOCATION OF THE DECONTAMINATION UNITS FOR EACH PHASE

DURING THE PRECONSTRUCTION MEETING UNLESS SHOWN ON THE

DRAWINGS.

15. SUBMIT ASBESTOS ABATEMENT PLAN IN ACCORDANCE WITH NYS

REGULATIONS AND PROJECT SPECIFICATIONS SHOWING

LOCATION AND NUMBER OF HEPA FILTERED NEGATIVE AIR

MACHINES, AIRLOCKS AND DECONTAMINATION CHAMBERS.

SUBMIT CALCULATIONS SHOWING NUMBER OF AIR CHANGES FOR

EACH CONTAINMENT AREA.

16. AS REQUIRED BY NYS CODES AND REGULATIONS, ALL ASBESTOS

REMOVALS, WITH THE EXCEPTION OF THE ROOF ABATEMENT,

SHALL BE PERFORMED WITHIN A HEPA-FILTERED NEGATIVE AIR

PRESSURE ENCLOSURE. PIPE INSULATION WORK SHALL BE

PERFORMED USING THE TENT/GLOVEBAG METHOD.

CONTRACTOR TO POST SIGNAGE IN ADVANCE IN ACCORDANCE

WITH NYS REGULATIONS AND CODES.

17. Specific areas on the 2nd floor, 3rd floor, 4th floor and roof of Building 200 will require asbestos abatement to allow for the Pharmacy renovation project. Asbestos-containing materials (ACM's) must be removed to allow for the renovation. ACM's include but are not limited to pipe fitting insulation on fiberglass insulated pipes, cove base adhesive, floor tile, mastic and roof flashing. Only the roof flashing in areas of disturbance or penetration shall be removed by the asbestos abatement contractor.

Coordinate all locations with the general contractor.

18. Scheduling of work shall be coordinated with the V.A. to avoid interruptions to the normal activities of the V.A. Asbestos Abatement for interior work will be performed off-duty hours ahall to be coordinated with COR for both Phase I and Phase II because the decontamination units will be located in the corridor. Work will begin at 5pm on a Friday and be completed by 3am Monday including clearance air testing and breakdown.

Contractor shall show activity over a weekend on the construction schedule.

19. The contractor shall prepare the Phase I and II work areas for asbestos removal using a HEPA-filtered negative air pressure tent containment in accordance with this specification and applicable codes, rules and regulations. Ceiling tiles can be removed from the work area before asbestos abatement by the general contractor.

20. The contractor shall erect isolation barriers that separate the work areas from the remainder of the building. The barriers shall be constructed of a fire retardant sheathing material of at least 5/8" thickness on the work side of the studs. The isolation barrier shall be plasticized with two (2) layers of 6-mil fire retardant plastic sheeting. The isolation barriers shall be caulked at the sheathing seams and where the sheathing meets the floor, walls and ceiling. The isolation barrier shall be constructed using fire retardant 2"x4" framing, 16 inches center-to-center, and caulked at all seams.

21. All utilities and piping shall be locked out and tagged before the contractor is to begin abatement activities.

22. All asbestos-containing materials within the contract limits must be removed and disposed of as asbestos-contaminated waste unless specifically excluded in these specifications or on the drawings.

23. The black iron supporting the drop ceilings is to remain intact throughout asbestos abatement activities.

24. All work area decontamination units (personal and waste) shall be fully framed and sheathed with fire retardant wood because they will be located in areas of public access.

25. All utilities, mechanical systems and piping shall be locked out and tagged before the contractor is to begin abatement activities.

26. All asbestos-containing materials within the contract limits must be removed and disposed of as asbestos-contaminated waste unless specifically excluded in these specifications or on the drawings.

27. The black iron supporting the drop ceilings is to remain intact throughout asbestos abatement activities.

28. All work area decontamination units (personal and waste) shall be fully framed and sheathed with fire retardant wood because they will be located in areas of public access.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Fi le

P at h 6/

/2

:3

9:

P M

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

23 MAR 2021Revisions: Date:

632-19-106

79 MIDDLEVILLE ROAD, NORTHPORT, NY 11768

RENOVATE PHARMACY SPACES

THINKFORM DESIGN ARCHITECT LLC

38 EAST BROAD STREET

HOPEWELL, NJ 08525

T:855.821.0274 F:609.644.4397 Russell DiNardo, AIA NY 031521-1

NORTHPORT VAMC

Egan Environmental Consulting, Inc.

BID DOCUMENTSASBESTOS DIAGRAMS AND NOTES

632-19-106RENOVATE PHARMACY SPACES

NORTHPORT VAMC

KEY MAP - BLDG 200, 3RD FLOOR

Drawing 05 of 52

200-HA102

TGE EDS

Egan Environmental Consulting, Inc.

AutoCAD SHX Text

10' MIN

AutoCAD SHX Text

EQUIPMENT ROOM

AutoCAD SHX Text

12' MIN

AutoCAD SHX Text

CLEAN ROOM

AutoCAD SHX Text

4'MIN

AutoCAD SHX Text

SHOWER

AutoCAD SHX Text

ROOM

AutoCAD SHX Text

8" MAX

AutoCAD SHX Text

CURTAINED DOORWAY

AutoCAD SHX Text

(3 LAYERS OF 6 MIL

AutoCAD SHX Text

POLY SHEETING WITH

AutoCAD SHX Text

WEIGHTED FLAPS)

AutoCAD SHX Text

(TYP @ AT ENTRANCE

AutoCAD SHX Text

AND EXIT)

AutoCAD SHX Text

2"X4" STUDS

AutoCAD SHX Text

2"X4" STUDS

AutoCAD SHX Text @ 48 O.C

AutoCAD SHX Text

4' MIN

AutoCAD SHX Text

AIRLOCK OF 36" MIN

AutoCAD SHX Text

WITH CURTAINED DOORWAY

AutoCAD SHX Text

CLEAN ROOM

AutoCAD SHX Text

WORK AREA

AutoCAD SHX Text A

AutoCAD SHX Text A

AutoCAD SHX Text @ 48 O.C

AutoCAD SHX Text

2"X4" STUDS

AutoCAD SHX Text

CONSTRUCTION OF A TEMPORARY SOLID BARRIER

AutoCAD SHX Text

WORKER

AutoCAD SHX Text

10. Puts on any additional

AutoCAD SHX Text clothing -deck shoes, hard hat

AutoCAD SHX Text

11. Collects necessary tools

AutoCAD SHX Text proceeds to work area

AutoCAD SHX Text

WORKER

AutoCAD SHX Text

1. Enters clean room

AutoCAD SHX Text

2. removes street clothing, places in locker

AutoCAD SHX Text

3. Puts on nylon swim suit (optional)

AutoCAD SHX Text

4. Puts on clean overalls

AutoCAD SHX Text

5. If separate disposable foot covering are

AutoCAD SHX Text used, these are put on

AutoCAD SHX Text

6. Applies tape around ankles, wrists, etc.

AutoCAD SHX Text

7. Inspects respirator, puts it on, checks fit

AutoCAD SHX Text

8. Puts on hood over respirator headstraps

AutoCAD SHX Text

9. proceeds to equipment room

AutoCAD SHX Text

21. Dries off, dresses in clean

AutoCAD SHX Text coveralls or street clothing

AutoCAD SHX Text

22. Cleans and dries respirator, AutoCAD SHX Text replaces filter (if applicable)

AutoCAD SHX Text

WORKER

AutoCAD SHX Text filters (without removing)

AutoCAD SHX Text with soap and water

AutoCAD SHX Text

19. Washes swim suit

AutoCAD SHX Text

20. Thoroughly washes body

AutoCAD SHX Text and hair

AutoCAD SHX Text

WORKER

AutoCAD SHX Text

13. Removes all clothing

AutoCAD SHX Text except respirator

AutoCAD SHX Text

14. places disposable

AutoCAD SHX Text protective clothing

AutoCAD SHX Text in a bag or bin

AutoCAD SHX Text

15. Stores any other

AutoCAD SHX Text contaminated articles

AutoCAD SHX Text

16. Proceeds to shower

AutoCAD SHX Text

NOTE: INSIDE WORK AREA WORKERS SHALL EXIT TO OUTSIDE THOUGH

AutoCAD SHX Text

DECONTAMINATION FACILITIES ONLY. ALL WORKERS TO WEAR

AutoCAD SHX Text

WORKER

AutoCAD SHX Text

12. Brushes off

AutoCAD SHX Text contamination

AutoCAD SHX Text

WORK AREA

AutoCAD SHX Text

AIRLOCK

AutoCAD SHX Text

EQUIPMENT ROOM

AutoCAD SHX Text

AIRLOCK

AutoCAD SHX Text

AIRLOCK

AutoCAD SHX Text

CLEAN ROOM

AutoCAD SHX Text

SHOWER

AutoCAD SHX Text

ROOM

AutoCAD SHX Text

ALL ASBESTOS CONTAINING MATERIALS SHALL BE

AutoCAD SHX Text

PACKED IN APPROVED CONTAINERS PRIOR TO

AutoCAD SHX Text

MOVING TO BAG STORAGE

AutoCAD SHX Text

BAGGING CHAMBER

AutoCAD SHX Text

EQUIPMENT/ WASTE

AutoCAD SHX Text

WASH ROOM

AutoCAD SHX Text

SHOWER ROOM

AutoCAD SHX Text

CLEAN ROOM

AutoCAD SHX Text

WORK AREA

AutoCAD SHX Text

CLEAN AREA

AutoCAD SHX Text

AIRLOCK

AutoCAD SHX Text

AIRLOCK

AutoCAD SHX Text

AIRLOCK

AutoCAD SHX Text

AIRLOCK

AutoCAD SHX Text

WORK AREA

AutoCAD SHX Text

AIR LOCK

AutoCAD SHX Text

SHOWER/WASH ROOM

AutoCAD SHX Text

CLEAN ROOM

AutoCAD SHX Text

AIR LOCK

AutoCAD SHX Text

CLEAN AREA

AutoCAD SHX Text

CEILING/DECKING

AutoCAD SHX Text

CAULKING

AutoCAD SHX Text

2 LAYERS OF 6 MIL

AutoCAD SHX Text

WALLS AND FLOOR

AutoCAD SHX Text

WORK AREA

AutoCAD SHX Text

CLEAN SIDE

AutoCAD SHX Text

EXISTING WALL

AutoCAD SHX Text

ELEVATION

AutoCAD SHX Text

3/8" PLYWOOD SHEET

AutoCAD SHX Text

ON WORK AREA

AutoCAD SHX Text

CEILING DECKING

AutoCAD SHX Text 2"x4" @ 16" O.C(TYP.)

AutoCAD SHX Text

CONTINUOUS CAULKING

AutoCAD SHX Text

@ EDGES & SEAMS OF

AutoCAD SHX Text

PLYWOOD SHEETS

AutoCAD SHX Text

SECTION A-A

AutoCAD SHX Text

EXISTING WALL

AutoCAD SHX Text

FLOOR

AutoCAD SHX Text

FLOOR

AutoCAD SHX Text

USE OF GLOVE BAG ENCLOSURE FOR PIPE INSULATION ABATEMENT

AutoCAD SHX Text Staple and tape securely to insure that

AutoCAD SHX Text containment bag will not break as a result

AutoCAD SHX Text of vacuum and/or weight of debris within.

AutoCAD SHX Text Tape seal tightly around

AutoCAD SHX Text the pipe at both sides

AutoCAD SHX Text

WETTING

AutoCAD SHX Text

AGENT

AutoCAD SHX Text

SIDE

AutoCAD SHX Text

PORT

AutoCAD SHX Text

GLOVE

AutoCAD SHX Text

ARMS

AutoCAD SHX Text

TOOL

AutoCAD SHX Text

BAG

AutoCAD SHX Text Hepa vacuum (secure & seal nozzle

AutoCAD SHX Text w/tape after inserting into side

AutoCAD SHX Text port of containment bag)

AutoCAD SHX Text

CEILING

AutoCAD SHX Text

CENTER AFD EXHAUST TUBE.

AutoCAD SHX Text

FIRE RETARDENT PLYWOOD

AutoCAD SHX Text

BLASTGATE MANIFOLD AND ATTACH

AutoCAD SHX Text

FLEXIBLE AFD

AutoCAD SHX Text

EXHAUST DUCT

AutoCAD SHX Text

AFD

AutoCAD SHX Text

UNIT

AutoCAD SHX Text

FLOOR

AutoCAD SHX Text

TO ADDITIONAL

AutoCAD SHX Text

AFD UNIT

AutoCAD SHX Text

DUCT TAPE

AutoCAD SHX Text

DUCT TAPE

AutoCAD SHX Text

APPLY TWO LAYERS

AutoCAD SHX Text

OF SIX MIL PLASTIC

AutoCAD SHX Text

EXISTING WALL

AutoCAD SHX Text

EXISTING WALL

AutoCAD SHX Text

CLEAN AREA

AutoCAD SHX Text

CAUTION SIGN SHALL BE PLACED

AutoCAD SHX Text

ON THE CLEAN SIDE OF THE DOOR

AutoCAD SHX Text

CAUTION LABELING SHALL IN

AutoCAD SHX Text

ACCORDANCE WITH EPA FEDERAL

AutoCAD SHX Text

REGULATIONS

AutoCAD SHX Text

APPLY TWO SHEETS

AutoCAD SHX Text

OF SIX MILL POLY

AutoCAD SHX Text

AS REQUIRED

AutoCAD SHX Text

EXISTING DOOR

AutoCAD SHX Text

BUCK

AutoCAD SHX Text

APPLY AND SECURE

AutoCAD SHX Text

SHEETS OF POLY

AutoCAD SHX Text

WITH DUCT TAPE

AutoCAD SHX Text

EXISTING DOOR TO

AutoCAD SHX Text

BE CLOSED AND SEALED

AutoCAD SHX Text

AN EMERGENCY EXIT SIGN IS TO

AutoCAD SHX Text

BE PLACED ON THE CONTAMINATED

AutoCAD SHX Text

SIDE AT ALL SPECIFIED LOCATIONS

AutoCAD SHX Text

EXISTING DOOR

AutoCAD SHX Text

THE PERIMETER OF THE DOOR IS TO

AutoCAD SHX Text

BE SEALED WITH DUCT TAPE ON THE

AutoCAD SHX Text

CONTAMINATED SIDE PRIOR TO APPLYING

AutoCAD SHX Text

THE TWO LAYERS OF POLY

AutoCAD SHX Text

APPLY AND SECURE SHEETS

AutoCAD SHX Text

OF POLY WITH DUCT TAPE

AutoCAD SHX Text

AS REQUIRED

AutoCAD SHX Text

EXISTING WALL

AutoCAD SHX Text

APPLY TWO SHEETS

AutoCAD SHX Text

OF SIX MIL POLY

AutoCAD SHX Text

EMERGENCY CRITICAL BARRIER AT DOOR

AutoCAD SHX Text

CONTAMINATED SIDE

AutoCAD SHX Text

CONSTRUCTION OF PERSONNEL DECONTAMINATION SYSTEM

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

POLY SHEETING ON

AutoCAD SHX Text

PARALLEL PERSONNEL AND WASTE DECON. ENCLOSURE SYSTEMS

AutoCAD SHX Text

PERSONNEL DECONTAMINATION SYSTEM

AutoCAD SHX Text

WINDOW AIR FILTRATION DEVICE EXHAUST

AutoCAD SHX Text

RESPIRATORS AND FULLY PROTECTIVE CLOTHING INSIDE THE

AutoCAD SHX Text

WORK AREA (INCLUDING HEAD AND FOOT WEAR)

AutoCAD SHX Text

17. Washes respirator and soaks

AutoCAD SHX Text

18. Removes respirator, washes

AutoCAD SHX Text

WASTE DECONTAMINATION ENCLOSURE SYSTEM

AutoCAD SHX Text

USING ADJUSTABLE CLAMP AND

AutoCAD SHX Text

DUCT TAPE. SEAL AIRTIGHT.

AutoCAD SHX Text

HOSE BEAD

AutoCAD SHX Text

BLASTGATE MANIFOLD AND AJUSTABLE CLAMP FOR WINDOW

AutoCAD SHX Text

ADJUSTABLE CLAMP WITH INTERNAL GASKET

AutoCAD SHX Text

12" I.D. GALVANIZED METAL

AutoCAD SHX Text

GALVANIZED METAL

AutoCAD SHX Text

GALVANIZED METAL

AutoCAD SHX Text

GALVANIZED METAL

AutoCAD SHX Text ASBESTOS ABATEMENT CONSULTANT: 14 HIGH STREET MAHWAH, NEW JERSEY 07430 Tel: (914) 320-7924 Email: tom_egan2@yahoo.com

AutoCAD SHX Text

NO SCALE

AutoCAD SHX Text N

ASBESTOS ABATEMENT CONSULTANT: 14 HIGH STREET MAHWAH, NEW JERSEY 07430 Tel: (914) 320-7924 Email: tom_egan2@yahoo.com

03of52 200-HA100
Sheets and Views
HA100
04of52 200-HA101
Sheets and Views
200HA101
05of52 200-HA102
Sheets and Views
HA 102