This document contains draft basis of design drawings and specifications for a GE Healthcare X5700 medical imaging system. The drawings indicate placement and interconnection of system components, but are not construction documents. They reference a mandatory pre-installation manual to specify site design and readiness requirements. Key requirements include a secure equipment area, power for test equipment, restrooms, and refuse removal capacity. The customer must arrange any rigging or facility modifications needed for equipment delivery.
A related special notice announces an upcoming solicitation from the USACE Little Rock District for an initial outfitting project at Camp Pendleton, CA. The total set-aside contract value is estimated between $5-10 million. The simplified acquisition procedures of FAR Part 13 will be used in conjunction with commercial items procedures of FAR Part 12 for a request for quote. The requirement is reserved for Service-Disabled Veteran-Owned Small Businesses. The estimated solicitation date is January 15, 2021. Project information will be available on ProjNet from December 15, 2020 through December 31, 2021 for questions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| DRAFT 6.8.1 PN14021 AREA 13 MEDICAL CLINIC-spc1of3.pdf | ||
| DRAFT Staging and Area Map.pdf | ||
| DRAFT 6.8.1 PN14021 AREA 13 MEDICAL CLINIC-spc3of3.pdf | ||
| DRAFT 6.8.1 PN14021 AREA 13 MEDICAL CLINIC-spc2of3.pdf | ||
| DRAFT Attachment (014) - Program for Design 13 Area Marine Centered Medical.pdf | ||
| DRAFT 6.4.1 PN14021 AREA 13 MEDICAL CLINIC-dwgs2of2.pdf | ||
| DRAFT Statement of Work.docx | DOCX document | |
| DRAFT X5700 Full Cut Sheet.pdf | ||
| DRAFT P021 AREA 13 MEDICAL CLINIC - Final CID Submittal.pdf | ||
| DRAFT P021 AREA 13 MEDICAL CLINIC - Final SID Submittal.pdf | ||
| DRAFT 6.8.1 PN14021 AREA 13 MEDICAL CLINIC - Final Medical Equipment.pdf | ||
| DRAFT 6.7 PRICE SCHEDULE_PN14021_CP_13Area_ACC.xlsx | XLSX spreadsheet | |
| DRAFT 6.4.1 PN14021 AREA 13 MEDICAL CLINIC-dwgs1of2.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Any deviation from these drawings must be communicated in writing to and reviewed by your local GE Healthcare Installation Project Manager prior to making changes.
Make arrangements for any rigging, special handling, or facility modifications that must be made to deliver the equipment to the installation site. If desired, your local GE Healthcare Installation Project Manager can supply a reference list of rigging contractors.
New construction requires the following; 1. Secure area for equipment, analysis, 4. Restrooms.
Provide for refuse removal and disposal (e.g. crates, cartons, packing)
2. Power for drills and other test equipment, 3. Capability for image
Contact a radiation physicist or consultant to specify radiation containment requirements.
RAD Site Planning
GE Healthcare Customer Site Readiness
Requirements Drawing Index
A mandatory component of this drawing set is the GE Healthcare Pre Installation manual. Failure to reference the Pre Installation manual will result in incomplete documentation required for site design and preparation.
Pre Installation documents for GE Healthcare products can be accessed on the web at:
www.gehealthcare.com/siteplanning
These sheets are a document set and should not be separated.
Electrical information and references are contained on all sheets.
GE Equipment Delivery Requirements
The items on the GE Healthcare Site Readiness Checklist are REQUIRED to facilitate equipment delivery to the IS site. Equipment will not be delivered if these requirements are not satisfied.
* REQUIRED REFERENCE *
Pre Installation Manual
These drawings indicate the placement and interconnection of the listed equipment components. These drawings are not construction or site preparation drawings. Customer remains ultimately responsible for preparing the site to accommodate the operation of such equipment in compliance with GE Healthcare's written specifications and all applicable federal, state, and/or local requirements.
X5700
² ²
File details come from the government source that posted it. Updated .