Draft Exhibit B Milestones and Liquidated Dam.pdf
PDF 229 KB Posted
- Solicitation number
- PE-66062-NONST-2027-000000493
- Issued by
- Fulton County, Georgia
About this file
This is Exhibit B of a Design-Build contract between the City of Atlanta's Department of Parks and Recreation and a contractor for the Chastain Park Parking Garage project. The exhibit establishes three intermediate contract milestones: actual construction work commencement following all approvals and permitting, phased reopening according to an approved baseline schedule, achievement of Substantial Completion within 455 calendar days from Notice to Proceed, and achievement of Final Completion within 485 calendar days from Notice to Proceed. The contractor is responsible for comprehensive project execution including design, permitting, engineering, construction, quality assurance, and facility turnover, with scope elements encompassing community engagement, demolition, site preparation, utility relocation, geotechnical investigation, detailed design submissions, schedule development, construction, testing, commissioning, and warranty support.
The contract includes liquidated damages provisions to incentivize timely performance. The contractor shall pay $500 per working day for failure to meet the Substantial Completion deadline and $1,000 per working day for failure to meet the Final Completion deadline. These liquidated damages are characterized as fair compensation for estimated delays rather than penalties. The City may withhold liquidated damages from contractor payments, offset them against other obligations, deduct them from retainage, or draw them from letters of credit or performance securities. The application of liquidated damages does not modify contract milestones or relieve the contractor of its obligation to improve progress and mitigate delays, and the City retains all additional rights and remedies available under law or the contract.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT B
CONTRACT MILESTONES AND LIQUIDATED DAMAGES
A. Intermediate Milestones. Contractor shall complete the following intermediate milestones under this Contract:
NO. CONTRACT MILESTONES
1 Actual construction work starts after all approvals and permitting are complete
2 Contractor shall reopen each phase as per the approved baseline schedule and duration on the phasing plans
3 Contractor shall achieve project Substantial Completion on or before Four Hundred Fifty Five
(455) calendar days from Notice to Proceed
4 Contractor shall achieve final completion of the entire project on or before Four Hundred and Eighty-Five (485) calendar days from Notice to Proceed
B. Liquidated Damages. The parties hereby agree that, with certainty and in good faith, liquidated damages applicable to this agreement. The parties agree that the Liquidated Damages, as set forth below, are estimated as fair compensation. It is expressly agreed that Liquidated Damages payable under this Agreement do not constitute a penalty. If Contractor fails to deliver the equipment or materials or perform the services within the times specified in this Contract for the established Milestones & Substantial Completion, or any extensions granted in writing, the Contractor shall pay to City as fixed, agreed, and Liquidated Damages for each calendar day of delay the sum(s) specified below, which amounts shall be independently calculated as follows:
NO. BASE BID CONTRACT MILESTONES LIQUIDATED DAMAGES
1 Substantial Completion $500.00 per Working Day
2 Final Completion $1,000.00 per Working Day
1. Application of Liquidated Damages not a Change. The application of Liquidated Damages shall not effect a change in the Contract milestone or relieve Contractor of its obligation to improve its progress, to achieve, or to mitigate the failure to achieve, the Contract Milestone date or stated area reopening.
2. Payment of Liquidated Damages. Payments of Liquidated Damages shall become due immediately upon failure to achieve Contract milestones. City shall be entitled to withhold from payments due, offset against other obligations, deduct from retainage, and draw down on letter(s) of credit or performance securities any and all Liquidated Damages due from Contractor.
3. No Restriction of Rights and Remedies. Nothing in this Clause shall operate to restrict any other rights and remedies available to City at law or under this Contract.