DQ_Wallace Bond Claim PA Project-1-Final (Rev).doc
DOC document 124 KB Posted
- Solicitation number
- DQ1 PHAA 2015001097 5
- Issued by
- Baca County, Denver City, Colorado
About this file
This is a Documented Quotation issued by the Colorado Department of Natural Resources, Oil and Gas Conservation Commission (COGCC) for plugging and abandonment services on three oil wells located in Baca County, Southeast Colorado, approximately 15 miles southeast of Walsh, Colorado. The project, designated PHAA-2015-1097 (Wallace Bond Claim Project), involves the plugging and abandonment of three wells: Watkins #1A, Newman #1-7, and Hume #17-1. Each well requires installation of three cement plugs, including cast iron bridge plugs, cement retainers, and surface plugs. Key deliverables include mobilization/demobilization services, plug and abandonment labor and equipment on an hourly basis, 171 sacks of cement for all three wells, perforation services (three sets total), installation of three cement retainers, installation of three cast iron bridge plugs, and solid and liquid waste management. A pre-bid meeting and site showing were scheduled for Friday, April 3, 2015 at 12:30 PM at the Newman #1-7 well site. Bids were due Friday, April 10, 2015 at 4:00 PM, submitted to the Department of Natural Resources Purchasing Agent Allan Smith. Project execution was required between April 15, 2015 and June 1, 2015, with completion and equipment removal by June 7, 2015 at 5:00 PM. Award was to be made to the low responsive and responsible bidder meeting all specified requirements and criteria.
Pricing is structured as lump sum and unit price bids on a Bid Schedule provided by COGCC. Mobilization/demobilization costs are lump sum per project location. Plug and abandon work is billed hourly, with standby time reimbursed at 75 percent of the hourly rate. Cement is paid per 94-pound sack installed. Perforation services, cement retainers, and cast iron bridge plugs are paid per unit installed. Solid waste management is a lump sum payment, while liquid waste management is paid per load (up to 130 barrels per load). A resident bidder preference and a 5 percent preference for Service Disabled Veteran Owned Small Businesses (SDVOSBs) officially registered with the U.S. Department of Veterans Affairs are available. The COGCC Project Manager, Diana Burn, was designated to supervise the work and inspect all work items for compliance with design specifications. Daily job logs documenting progress, personnel, materials, equipment, and time allocations were required for payment authorization.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MAP_PRE BID MEETING ON SITE MEET UP LOCATION.pdf | ||
| Photo_Wallace Watkins #1.jpg | JPG image | |
| BID SCHEDULE - Wallace Bond Claim PA Project.doc | DOC document | |
| Photo_Wallace Newman #1-7.jpg | JPG image | |
| DNR POGeneralConditions.pdf | ||
| Special Provisions 1-1-09.pdf | ||
| POTerms&Conditions1-1-09.pdf | ||
| Amendment #2, Wallace-Chapman Mobilization-Demobilization.docx | DOCX document | |
| BIDDER LIST OF EQUIPMENT OFFERED_WALLACE BOND CLAIM PA PROJECT.doc | DOC document | |
| WBD Hume 17-1.pdf | ||
| WBD Watkins 1A.pdf | ||
| Photo_Wallace Hume #17-1.jpg | JPG image | |
| WBD Newman 1-7.pdf | ||
| Amendment # 1, Wallace-Chapman Mobilization-Demobilization.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Colorado Department of Natural Resources
DOCUMENTED QUOTATION
Wallace Bond Claim Project-Three Wells to PA Re-entry, Plugging and Abandonment Project
PHAA-2015-1097
1.0 GENERAL CONDITIONS
The Colorado Oil and Gas Conservation Commission (COGCC) is bidding this project using an informal Documented Quotation procedure in coordination with the Colorado Department of Natural Resources Purchasing Office. This request for Documented Quotation incorporates the Special Conditions described herein. The attached Wellbore Diagram Drawings, Bid Schedule, General Conditions for Purchase Orders (attached), Purchase Order Terms and Conditions, List of Equipment Offered Form, and other Contract Documents described in the General Conditions for Purchase Orders are hereby incorporated by reference.
1.1 PROJECT WORK SUMMARY AND LOCATION
There are three oil wells to be plugged and abandoned and all are located in Baca County or Southeast Colorado and about fifteen miles SE of Walsh, Colorado and a couple miles from the KS state line. Plans are to set three plugs in each well to include (1) a cast iron bridge plug above the perforations with two sacks of cement on top (2) perforate and cement squeeze across the surface casing shoe with forty sacks (3) surface plug to include fifteen sacks of cement.
| Well |
| Location |
| API # |
| Date Drilled |
| Total Depth |
| Casings |
| Watkins #1A |
| SENW 20 32S 41W |
| 009-05147 |
| 1961 |
| 3350' |
| 8 5/8 1470' T/cmt 0' 4 1/2 3267' T calc/2750' |
| Newman #1-7 |
| SWNE 7 32S 41W |
| 009-05175 |
| 1962 |
| 3250' |
| 7.000 1266' T /cmt 0' 4 1/2 3250' T calc/2865' |
| Hume #17-1 |
| SWSE 17 32S 41W |
| 009-06442 |
| 1985 |
| 5500' |
| 8 5/8 1497' T/cmt 0' 5 1/2 4131' T calc/2505' |
| Well |
| Perfs |
| Formation |
| Tubing (Assumed) |
| Watkins #1A |
| 3139'-3156' |
| Topeka |
| 103 jts 2 3/8" OD 4.7 # EUE |
| Newman #1-7 |
| 3161'-3181' |
| Topeka |
| 104 jts 2 3/8" OD 4.7 # EUE |
| Hume #17-1 |
| 3141'-4030' |
| Topeka KS City Drum Marmaton |
| 131 jts 2 3/8" OD 4.7 # EUE |
1.2 PRE‑BID MEETING AND SITE SHOWING
Bidders shall visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, including average climatic conditions and the general and local conditions which can affect the work or the cost thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work.
An informational pre-bid meeting and on site showing will be held on Friday, April 3, 2015 at 12:30 PM . Contractors are requested to register for the pre-bid meeting and site showing with Diana Burn, COGCC Supervising Engineer East, @ 894-2100 x 5106 prior to Thursday, April 2, 2015 at 5:00 PM so we have a head count. The COGCC representative will meet prospective bidders at the Newman #1-7 well site at the scheduled time. The site is located approximately 18-20 miles SE of Walsh, Colorado and three quarters (3/4) of a mile NW of the intersection of county roads (CR) 55 & V.00 (map provided).
The purpose of the Pre-Bid meeting is to afford potential bidders the opportunity to inspect the project site and access conditions. Bids will be considered from all contractors whether or not they attend the pre-bid meeting and site showing. Bidders are cautioned that, notwithstanding any remarks or clarifications given at this meeting and site showing, all terms and conditions of the contract documents remain unchanged unless they are changed by written amendment issued by the OWNER. If the answers to questions or any amendment to the Contract Documents create ambiguities, it is the responsibility of the bidder to seek clarification prior to submitting a bid.
1.3 BID SUBMITTAL
The bid due date for this project is Friday, April 10, 2015 at 4:00 PM. Bids will be accepted by mail, facsimile, hand carried or via e-mail as a Word or .pdf file attachment and must be sent to the Department of Natural Resources Purchasing Agent:
Allan Smith, Purchasing Agent
Department of Natural Resources Purchasing Office
1313 Sherman Street #423
Denver, CO. 80203
Phone: (303) 866-3292 X8631
Fax: (303) 866-5575
Email: allan.smith@state.co.us
A responsive bid must include the following:
1. BID SCHEDULE, properly completed (COGCC format provided)
2. CONTRACTOR’S Equipment, Personnel and Materials Rate Schedule
3. List of Equipment Offered Form
Bids will not be accepted directly by the COGCC. Bids must be submitted to the Department of Natural Resources Purchasing Office, as indicated above.
1.4 LIST OF EQUIPMENT OFFERED
The List of Equipment Offered Form must be returned with each bid. All equipment to be used on the project must be listed. The CONTRACTOR must own, have a current lease for the equipment intended to be used to perform the work, or must furnish a statement of arrangements to rent, or otherwise procure, adequate equipment to perform the work. Inclusion of a piece of equipment on the List of Equipment Offered represents a commitment to devote that piece of equipment to the project work for the entire duration of the project. If several contractors propose to join together to perform the work under this contract, equipment owned or controlled by each should be listed and the PRINCIPAL REPRESENTATIVE identified. A contract will not be awarded to a bidder who in the opinion of the PROJECT MANAGER (a) does not have adequate equipment, or (b) does not have firm and satisfactory arrangements to obtain adequate equipment to perform the work described in this Documented Quotation.
1.5 BID AWARD
Award will be made with reasonable promptness, by written notice to the low responsive and responsible bidder whose bid meets the requirements and criteria set forth in this Documented Quotation. These criteria will include, but not be limited to the lowest GRAND TOTAL PRICE, corrected if necessary for errors in price extension and/or addition, and capability to meet the performance time requirements. In the case of mathematical discrepancies, the unit price shall govern. The GRAND TOTAL PRICE will be used for comparing bids only.
1.6 RESIDENCE BIDDER PREFERENCE
When a contract for commodities or services is to be awarded to a bidder, a resident bidder shall be allowed a preference against a nonresident bidder equal to the preference given or required by the state in which the nonresident bidder is a resident.
1.7 SERVICE DISABLED VETERAN OWNED SMALL BUSINESSES (SDVOSBs) PREFERENCE
SDVOSBs, who are incorporated or organized in Colorado or maintain a place of business or have an office in Colorado and who are officially registered and verified as a SDVOSB by the Center for Veteran Enterprise within the U.S. Department of Veterans Affairs. (www.vip.vetbiz.gov) , may receive a 5% preference on their bid. This preference applies only to the price, and the SDVOSBs must still meet all other qualifications required in the bid.
SDVOSBs claiming this preference shall submit documentation of SDVOSB certification issued through the U.S. Department of Veterans Affairs in their response to the solicitation. Bid submissions without this documentation will not be given a preference.
1.8 PURCHASE ORDER CONTRACT
A Purchase order contract will be issued to the awarded bidder. The Purchase Order Contract will include all documents defined in Section 1 of DEFINITIONS of the GENERAL CONDITIONS FOR PURCHASE ORDERS.
1.9 PERFORMANCE TIME REQUIREMENTS
The project shall be started and completed between April 15, 2015 and June 1, 2015. CONTRACTOR shall prosecute the work diligently and complete the work and have equipment removed from the project location, as described in this Documented Quotation, no later than June 7, 2015 at 5:00 PM. The time stated for completion shall include cleanup, as defined in Section 27 of the GENERAL CONDITIONS FOR PURCHASE ORDERS, and final inspection by the PROJECT MANAGER.
1.10 PROJECT OBSERVATION
The PROJECT MANAGER will be at the project site to supervise plugging activities and ensure that each work item is completed and constructed to design specifications. The PROJECT MANAGER will be available during regular business hours (8:00 A.M. to 5:00 P.M.) on weekdays. Any additional inspections will not be scheduled on weekend days or holidays without prior approval of the PROJECT MANAGER. It is the CONTRACTOR’S responsibility to schedule inspections with the PROJECT MANAGER so as not to delay the work.
2.0 PROJECT WORK DESCRIPTION
The following work description applies to the plugging and abandonment of the Watkins #1A well in Baca County, formerly operated by Wallace Oil and Gas, Inc.
The work assumes use of steel pits for circulation and cement returns. If CONTRACTOR intends to use earthen pits for plugging and abandonment, then pits must be lined, and CONTRACTOR will be responsible for permitting, constructing, maintaining, and closing the plugging pits in accordance with COGCC’s 900-series and 1000-series rules.
Global Positioning System well location data has been measured by COGCC staff. CONTRACTOR will not be responsible for obtaining this data.
2.1
WATKINS #1A
2.1.1
DESCRIPTION & SUMMARY
Well site photo(s) will be provided with bidding package
| Well |
| Location |
| API # |
| Date Drilled |
| Total Depth |
| Casings |
| Watkins #1A |
| SENW 20 32S 41W |
| 009-05147 |
| 1961 |
| 3350' |
| 8 5/8 1470' T/cmt 0' 4 1/2 3267' T calc/2750' |
| Well |
| Perfs |
| Formation |
| Tubing (Assumed) |
| Watkins #1A |
| 3139'-3156' |
| Topeka |
| 103 jts 2 3/8" OD 4.7 # EUE |
2.1.2
MATERIALS
Refer to Section 3.0 – Measurement and Payment.
2.1.3
EXECUTION
1. Contact PROJECT MANAGER, Diana Burn, 303-894-2100 x 5106, Diana.burn@state.co.us to schedule a start date and to coordinate any schedule changes.
2. Test or set rig anchors.
3. MIRU work over rig, and all other needed equipment.
4. Measure & record the Braden head pressure; report to Project Manager
5. NU BOP pipe rams on top and blind rams on bottom, pressure test high and low.
6. Kill well, pull rods, pump and tubing; tally out & lay down.
7. Run 4 ½” bit and casing scraper to TD.
8. Plug #1:
Set CIBP within 50’ of the top pay zone perf and spot two (2) sx cmt on top.
Pressure test the casing 1000 psig.
9. Plug #2:
Perforate 4 ½” OD casing at 1520’ w/ 2 jspf with 90-120 degree spacing.
Set cast iron cement retainer (CICR) at 1470’; pressure CICR, tubing and casing.
Pump 40 sx cmt (15.8 ppg; 1.15 cu ft/sk Class G "neat")
Thirty-five (35) sx under CICR & four (5) sx on top
10. Plug #3:
Fifteen (15) sx cmt
11. Conclusion:
Cut surface casing off at least 4’ below ground surface, weld on plate with weep hole.
Back fill excavation.
RDMO drill rig and CONTRACTOR equipment.
Remove or cut off and bury all anchors at least 3’ below ground surface.
2.2
NEWMAN #1-7
2.2.1
DESCRIPTION & SUMMARY
Well site photo(s) will be provided with bidding package
| Well |
| Location |
| API # |
| Date Drilled |
| Total Depth |
| Casings |
| Newman #1-7 |
| SWNE 7 32S 41W |
| 009-05175 |
| 1962 |
| 3250' |
| 7.0 1266' T /cmt 0' 4 1/2 3250' T calc/2865' |
| Well |
| Perfs |
| Formation |
| Tubing (Assumed) |
| Newman #1-7 |
| 3161'-3181' |
| Topeka |
| 104 jts 2 3/8" OD 4.7 # EUE |
2.2.2
Refer to Section 3.0 – Measurement and Payment.
2.2.3
EXECUTION
1. Contact PROJECT MANAGER, Diana Burn, 303-894-2100 x 5106, Diana.burn@state.co.us to schedule a start date and to coordinate any schedule changes.
2. Test or set rig anchors.
3. MIRU work over rig, and all other needed equipment.
4. Measure & record the Braden head pressure; report to Project Manager
5. NU BOP pipe rams on top and blind rams on bottom, pressure test high and low.
6. Kill well, pull rods, pump and tubing; tally out & lay down.
7. Run 4 ½” bit and casing scraper to TD.
8. Plug #1:
Set CIBP within 50’ of the top pay zone perf and spot two (2) sx cmt on top
Pressure test the casing 1000 psig.
9. Plug #2:
Perforate 4 ½” OD casing at 1316’ w/ 2 jspf with 90-120 degree spacing.
Set cast iron cement retainer (CICR) at 1266’; pressure CICR, tubing and casing.
Pump 40 sx cmt (15.8 ppg; 1.15 cu ft/sk Class G "neat")
Thirty-five (35) sx under CICR & four (5) sx on top
10. Plug #3:
Fifteen (15) sx cmt
11. Conclusion:
Cut surface casing off at least 4’ below ground surface, weld on plate with weep hole.
Back fill excavation.
RDMO drill rig and CONTRACTOR equipment.
Remove or cut off and bury all anchors at least 3’ below ground surface.
2.3
HUME #1-7
2.3.1
DESCRIPTION & SUMMARY
Well site photo(s) will be provided with bidding package
| Well |
| Location |
| API # |
| Date Drilled |
| Total Depth |
| Casings |
| Hume #17-1 |
| SWSE 17 32S 41W |
| 009-06442 |
| 1985 |
| 5500' |
| 8 5/8 1497' T/cmt 0' 5 1/2 4131' T/calc/2505' |
| Well |
| Perfs |
| Formation |
| Tubing (Assumed) |
| Hume #17-1 |
| 3141'-4030' |
| Topeka KS City Drum Marmaton |
| 131 jts 2 3/8" OD 4.7 # EUE |
2.3.2
Refer to Section 3.0 – Measurement and Payment.
2.3.3
EXECUTION
1. Contact PROJECT MANAGER, Diana Burn, 303-894-2100 x 5106, Diana.burn@state.co.us to schedule a start date and to coordinate any schedule changes.
2. Test or set rig anchors.
3. MIRU work over rig, and all other needed equipment.
4. Measure & record the Braden head pressure; report to Project Manager
5. NU BOP pipe rams on top and blind rams on bottom, pressure test high and low.
6. Kill well, pull rods, pump and tubing; tally out & lay down.
7. Run 5 ½” bit and casing scraper to TD.
8. Plug #1:
Set CIBP within 50’ of the top pay zone perf and spot two (2) sx cmt on top
Pressure test the casing 1000 psig.
9. Plug #2:
Perforate 5 ½” OD casing at 1547’ w/ 2 jspf with 90-120 degree spacing.
Set cast iron cement retainer (CICR) at 1497’; pressure CICR, tubing and casing.
Pump 40 sx cmt (15.8 ppg; 1.15 cu ft/sk Class G "neat")
Thirty-five (35) sx under CICR & four (5) sx on top
10. Plug #3:
Fifteen (15) sx cmt
11. Conclusion:
Cut surface casing off at least 4’ below ground surface, weld on plate with weep hole.
Back fill excavation.
RDMO drill rig and CONTRACTOR equipment.
Remove or cut off and bury all anchors at least 3’ below ground surface.
3.0 MEASUREMENT AND PAYMENT
CONTRACTOR shall furnish all labor, materials, tools, equipment, appurtenances, incidentals and all services necessary to perform all work required at the lump sum or unit prices for the items listed below beginning in Section 3.1. These items refer to and are the same items as listed in the Bid Schedule. They constitute all of the pay items for the completion of the work. Each lump sum and unit price bid will be deemed to include an amount considered by CONTRACTOR to be adequate to cover CONTRACTOR’S overhead and profit for each separately identified item.
Quantities of work shall be measured in the field by the CONTRACTOR and verified by the PROJECT MANAGER. CONTRACTOR’S original daily job logs, field notes, computations, and other records for the purpose of measuring quantities shall be furnished to the PROJECT MANAGER within two (2) working days of completion and may be used by the PROJECT MANAGER to the extent necessary in determining the proper amount of payments due to the CONTRACTOR. The CONTRACTOR shall retain a copy of the daily job logs, original notes, computations, and records furnished to the PROJECT MANAGER.
CONTRACTOR’S daily job logs shall include accurate records of the daily progress of the work and shall record the progress on a format acceptable to PROJECT MANAGER. Daily job logs shall include at a minimum the following information:
1. CONTRACTOR name, project name, date of field work
2. Identify by individual, all CONTRACTOR and SUBCONTRACTOR personnel on-Site for the day.
3. Summarize the work completed, including plugging procedures, and the materials used.
4. List the major equipment used to complete the work.
5. Provide an hourly tally for time on-location, including a separate hourly tally for any standby time.
6. Identify all standby time including but not limited to; repairs or maintenance, breakdown, accidents, time spent waiting-on-cement and work stoppage directed by PROJECT MANAGER or OWNER.
7. CONTRACTOR’S superintendent shall sign the completed daily job log upon completion.
Applications for Payment shall be submitted to the PROJECT MANAGER for review and approval at least five (5) working days prior to final submission to OWNER.
Payment will be made for actual quantities at the unit prices listed on the Bid Schedule only when approved and verified by the PROJECT MANAGER. If a change order is approved, which includes work for items not listed in this section, and then unit costs listed on CONTRACTOR’S Rate Schedule will be considered by the PROJECT MANAGER when authorizing payment.
3.1
MOBILIZATION/DEMOBILIZATION
3.1.1 DESCRIPTION
This specification covers the CONTRACTOR'S operations for:
1. Payment of premiums for bonds and insurance acquired specifically for this project, including premiums for performance and payment bonds.
2. Obtaining and acquiring any permits necessary to complete this project.
3. Movement of CONTRACTOR'S personnel, equipment, operation supplies, and incidentals to the project site.
4. Establishment of necessary temporary facilities, including sanitation facilities, and any required temporary utilities, at the project site.
5. Preparatory work at the project sites, including excavation of the Braden head access on each well, and hot tapping Braden head access if Braden head valves are not present or are not functional.
6. Demobilization of CONTRACTOR'S equipment and all other facilities, final project cleanup.
7. Any travel time and per diem for CONTRACTOR’S crew or SUBCONTRACTOR’S crew.
3.1.2 EXECUTION
Upon receipt of Notice to Proceed, the CONTRACTOR shall furnish, mobilize, move in and install such temporary works and equipment necessary for the successful completion of the work. CONTRACTOR shall operate and maintain such temporary works and equipment for the duration of work at each project location. CONTRACTOR shall provide for movement of CONTRACTOR’S personnel and supplies to and from each project location on a daily basis. Any preparatory work at each project location necessary to move in and position CONTRACTOR’S equipment shall be included as mobilization.
Upon completion of the work under this contract, the CONTRACTOR shall remove all temporary facilities and equipment. The CONTRACTOR shall remove from the vicinity of the work and haul all rubbish, trash, garbage, and debris to a county-approved disposal site. Additionally, the CONTRACTOR shall remove from the vicinity all unused materials, and the like, belonging to the CONTRACTOR or used under the CONTRACTOR'S direction during construction. The contractor shall fill and dress all holes and disturbances made for convenience, and leave all areas in good order and condition, subject to final inspection and approval by the PROJECT MANAGER.
3.1.3 MEASUREMENT AND PAYMENT
Measurement shall be made based on each mobilization to and demobilization from each project location or this bid item. Payment at the bid price shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature to mobilize to and demobilize from each project location.
3.2 PLUG AND ABANDON
3.2.1 DESCRIPTION
This specification covers the CONTRACTOR’S time on-location for labor and equipment required to complete the work specified in Section 2.0 – Project Work Description. Hourly unit costs shall include all costs that the CONTRACTOR deems necessary to complete the work for which payment is not otherwise specifically itemized on the Bid Schedule. Materials used to complete the work are described in subsequent sections of this Documented Quotation, and therefore are not itemized in this section.
The CONTRACTOR shall provide the following minimum personnel, equipment, and services:
· Provide a Superintendent with whom the PROJECT MANAGER and OWNER can communicate and who will supervise the work and be fully responsible for the performance thereof. The Superintendent shall be present at the project site whenever work is being performed at the project site.
· Provide an experienced crew sufficient to operate CONTRACTOR’S equipment in a safe and diligent manner.
· Provide work over rig with tubing handling tools. Provide the tubing work string. Provide pumps, a power swivel and drill bit(s). Provide drilling fluid additives, and mixing equipment.
· Provide sufficient fresh water to kill the well, pressure test and circulate the well
· Provide two (2) steel pits for drilling fluids, circulated fluid and wash up fluid. Separate payment will not be approved for the installation, monitoring, maintenance, closure, and reclamation of earthen pits. If CONTRACTOR chooses to use a lined earthen pit, rather than a steel pit, then all associated costs for the plugging pit shall be incorporated into the unit cost for this bid item.
· Provide welder services and materials necessary to cut casing strings and weld plates.
Any additional equipment or services that the contractor deems necessary to complete the work specified in Section 2.0 – Project Work Description shall be included in the CONTRACTOR’S List of Equipment Offered, and if these equipment or services are used to complete the work, then the cost for these services shall be incidental to the hourly unit cost for the Plug and Abandon line item on the Bid Schedule.
3.2.2 EXECUTION
Refer to Section 2.0 – Project Work Description.
3.2.3 MEASUREMENT AND PAYMENT
The CONTRACTOR shall submit daily job logs to the PROJECT MANAGER to verify hourly quantities for plug and abandon labor, equipment and services. Payment will be based on the total number of hours listed on the daily job logs and verified by the PROJECT MANAGER at the bid price, except as noted below. Standby time will be paid at a unit rate equal to seventy-five (75) percent of the bid price for hourly time. Payment shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature to plug and abandon the well.
3.3 CEMENT SERVICES
3.3.1 DESCRIPTION
The CONTRACTOR shall provide cement services, including circulating, and one hundred seventy-one (171) sacks of cement mixed with sufficient water to achieve a density of 15.8 ppg and a yield of 1.15 cu ft yield per sack. The CONTRACTOR shall provide water on location in sufficient quantities to circulate the wellbore and mix the cement. The CONTRACTOR shall also provide a means to transport water to and store water on location.
Cement plugs shall be installed by the CONTRACTOR at various depths, as described in Section 2.0 – Project Work Description. Cement shall be Southwest Portland G common cement without additives. Any changes in the type of cement must be approved by the PROJECT MANAGER. Cement shall be mixed to American Petroleum Institute standards, such that the slurry design will achieve a minimum compressive strength of three hundred (300) psi after twenty-four (24) hours and eight hundred (800) psi after seventy-two (72) hours measured at ninety-five (95) degrees Fahrenheit and at eight hundred (800) psi.
3.3.2 EXECUTION
Refer to Section 2.0 – Project Work Description.
3.3.3 MEASUREMENT AND PAYMENT
The CONTRACTOR shall submit daily job logs to the PROJECT MANAGER to verify cement quantities. Cement shall be measured by 94-pound sacks. Payment will be based on the total sacks of cement installed, as listed on the daily job logs and verified by the PROJECT MANAGER at the bid price. Payment shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature for cement services, including water. Water used for circulating and mixing cement shall be considered incidental to the unit cost for cement services.
3.4 SOLID WASTE MANAGEMENT
3.4.1 DESCRIPTION
All solid materials, including materials that solidify from circulated wellbore fluids, or solids that come in contact with wellbore fluids shall be considered oil and gas exploration and production (E&P) solid waste. The CONTRACTOR shall provide a means to temporarily store E&P solid waste on site, and the storage process shall be designed such that the E&P waste shall not come in contact with native soils, surface water, or well pad fill. The CONTRACTOR shall provide a means to handle and transport E&P solid waste to a licensed off-site disposal facility.
3.4.2 EXECUTION
Refer to Section 2.0 – Project Work Description.
3.4.3 MEASUREMENT AND PAYMENT
Measurement will be based upon 100% completion of solids storage, handling, transportation, and disposal. CONTRACTOR shall provide a disposal certificate from a county-approved disposal facility to the PROJECT MANAGER for solids disposal. Lump sum payment at the bid price shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature to complete solid waste management.
3.5 LIQUID WASTE MANAGEMENT
3.5.1 DESCRIPTION
All liquids that are circulated from the wellbore shall be considered oil and gas E&P liquid waste. The CONTRACTOR shall provide a means to temporarily store E&P liquid waste on site, and the storage process shall be designed such that the E&P waste shall not come in contact with native soils, surface water, or well pad fill. The CONTRACTOR shall provide a means to handle and transport E&P liquid waste to a licensed off-site disposal facility. Disposal of any unused circulation fluid is also covered under this item.
3.5.2 EXECUTION
Refer to Section 2.0 – Project Work Description.
3.5.3 MEASUREMENT AND PAYMENT
Measurement will be per load (up to 130 barrels for each load) of liquids disposal. CONTRACTOR shall provide a disposal certificate from an approved E&P disposal facility to the PROJECT MANAGER for solids disposal. Payment will be based on the total loads of liquid disposed, as listed on the daily job logs and verified by the PROJECT MANAGER at the bid price. Payment shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature for E&P liquid disposal.
3.6 PERFORATION SERVICES
3.6.1 DESCRIPTION
The CONTRACTOR shall perforate a total of three (3) sets of squeeze holes at various depths, as described in Section 2.0 – Project Work Description. Perforations shall be four (3) shots per set, with one (1) foot perforated per set, and a 0.38-inch shot diameter and evenly phased in a circle
(90 or 120 degrees apart)
3.6.2 EXECUTION
Refer to Section 2.0 – Project Work Description.
3.6.3 MEASUREMENT AND PAYMENT
The CONTRACTOR shall submit daily job logs to the PROJECT MANAGER to verify quantities for perforation sets. Payment will be based on the total number of sets perforated, as listed on the daily job logs and verified by the PROJECT MANAGER at the bid price.
Payment shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature to perforate squeeze holes.
3.7 CEMENT RETAINERS
3.7.1 DESCRIPTION
The CONTRACTOR shall provide and install three (3) Weatherford or Bolt 10,000 psi differential
CICR’s, or equivalent, as approved by the PROJECT MANAGER, at the depths specified in
Section 2.0 – Project Work Description. The CONTRACTOR shall place cement on top of the
CICR’s as specified in Section 2.0 – Project Work Description.
3.7.2 EXECUTION
Refer to Section 2.0 – Project Work Description.
3.7.3 MEASUREMENT AND PAYMENT
The CONTRACTOR shall submit daily job logs to the PROJECT MANAGER to verify quantities for cement retainers. Payment will be based on the total number of cement retainers installed, as listed on the daily job logs and verified by the PROJECT MANAGER at the bid price. Payment shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature for cement retainers. Measurement and payment for cement placed on top of CICR’s shall be in accordance with Section 3.6 – Cement Services.
3.8 CAST IRON BRIDGE PLUGS
3.8.1 DESCRIPTION
The CONTRACTOR shall provide and install three (3) Alpha Midget #2 CIBP, or equivalent, as approved by the PROJECT MANAGER, at various depths, as described in Section 2.0 – Project
Work Description. The CONTRACTOR shall place cement on top of the CIBP’s as specified in
Section 2.0 – Project Work Description.
3.8.2 EXECUTION
Refer to Section 2.0 – Project Work Description.
3.8.3 MEASUREMENT AND PAYMENT
The CONTRACTOR shall submit daily job logs to the PROJECT MANAGER to verify quantities for CIBP’s. Payment will be based on the total number of CIBP’s installed, as listed on the daily job logs and verified by the PROJECT MANAGER at the bid price. Payment shall constitute full compensation for all of the CONTRACTOR’S costs of whatever nature for CIBP’s. Measurement and payment for cement placed on top of CIBP’s shall be in accordance with Section 3.6 –
Cement Services.
4.0
LIST OF ATTACHMENTS
DNR General Conditions for Purchase Order
Special Provisions
PO Terms and Conditions
Bid Schedule List of Equipment Offered Pre-bid Meeting Map WBD Hume 17-1