Shreveport
Job Corps Center Shreveport, LA
Facility Planning Report Volume II
Supporting Data
Final August 2013
Department of Labor/ Office of Job Corps
22Shreveport Job Corps Center
Shreveport
Job Corps Center Shreveport, LA
Facility Planning Report Volume II
Supporting Data
Final August 2013
Courtyard of Buildings A to G Looking East
33 Shreveport Job Corps Center
CONTENTS
SHREVEPORT JOB CORPS CENTER
FACILITY PLANNING REPORT
VOLUME I - Planning Strategy
• Existing Site Plan
• Center Statistics
INTRODUCTION
• Purpose
• Report Contents
EXECUTIVE SUMMARY
A. EXISTING CONDITIONS
• Background
• General Site Conditions
• General Building Conditions
• Preventive Maintenance
• Ownership
• Facility Assessment by Function
• Energy Issues
• Environmental Issues
• Sustainability
• Accessibility Standards
• Completed and Current Projects Since the Last Survey
• Health and Life Safety Issues
• Summary of Defi ciencies
B. RECOMMENDATIONS
• Status of the Previous (PY09) Plan
• Signifi cant Issues
• PY 12 Plan Overview
• Summary of Proposed Projects
• Regional Projects
• Proposed Site Plan
C. PLANNING ANALYSIS
• Purpose
• Planning Objectives and Assumptions
• Space Utilization Analysis
• Federal Real Property Asset Management
• Mission Dependency Site Plan
• Defi ciency Analysis
• Facility Condition Summary Report
• Building Condition by Function
• Building Condition Site Plan
VOLUME II - Supporting Data
• Vicinity Map
• Location Map
• Existing Site Plan
D. DESCRIPTIONS
• Building and Structures
• Space Utilization By Function
• NSF by Building
• Energy Report
• Environmental Management
Asbestos Report Radon Report
• Site Descriptions
• Building Descriptions
E. DEFICIENCIES
F. CORRESPONDENCE AND REPORTS
• Center Review Meeting Minutes
• Survey Brief
• RA and Student Facility Feedback Questionnaire
• Life Safety Defi ciencies Transmittal and List
• O & M Defi ciency List
• Active Warranty Report
• FRPC Performance Measures Matrix
44Shreveport Job Corps Center
55 Shreveport Job Corps Center
Shreveport Job C orps C enter
77 Shreveport Job Corps Center
D Descriptions
BUILDINGS AND STRUCTURES
00608 SHREVEPORT 08/14/2013
1Page: of Date:
A - FOOD SERVICE/EDUCATION
B - RECREATION
C - ADMINISTRATION
D - ADMIN/COUNSELING
E - EDUCATION/ADMIN
F - MEDICAL/DENTAL/DORMITORY
G - CARP/CUL ARTS/WHSE/LAUNDRY
H - FEMALE DORMITORY
M - INDUSTRIAL PAINTING VOCATION
N - WELDING VOCATION
P - VOCATION
R - OUTREACH & ADMISSIONS
S - GREEN HOUSE
Q - STORAGE
T - WELCOME CENTER
V - STORAGE
X - MAINTENANCE BAY
Name GSF
19,654 13,150 14,890 12,500
17,400
22,691
19,850
27,000 1,868 7,500 7,500 1,460
1,280
1,690
Active Active Active
Demolition Requested Demolition Requested Demolition Requested Demolition Requested
Active Active Active Active
Demolition Requested
Active Active Active
Demolition Requested
Active
StatusType
Building Building Building Building
Building
Building
Building
Building Building Building Building Building
Building Structure Structure Structure
Structure
Use Group Built Flrs Const
Assembly/Bu Assembly Residential/B Business/Res
Business/Ass
Residential/B
Business
Residential Business Business Business Business
Business Storage
Storage
Business
Fair Good Good Fair
Fair
Fair
Fair
Good Good Fair
Good Good
Good Good Good Good
Fair
ConditionAsset Number
0060800002 0060800003 0060800004 0060800005
0060800006
0060800007
0060800008
0060808045 0060800011 0060800013 0060800015 0060800017
0060808047 0060800016 0060808046 0060800021
0060808044
13 166,743
4 2,150
17 168,893
Buildings
Structures
Total
GSF
GSF
GSF
Summary
08/14/2013
Space Utilization By Function 00608 Shreveport Page: 1 of Date:
HOUSING
EDUCATION
FOOD SERVICE
RECREATION
SUGGESTED
NSF/
ENROLLEE
SUGGESTED
TOTAL
NSF
ACTUAL
TOTAL
NSF
TYPE OF SPACE
SUB TOTAL
SUB TOTAL
SUB TOTAL
SUB TOTAL
Resident Men Resident Women Total Residents
Residents 250 Non Residents 100
350Total Students
(250)
(350)
(350)
(350)
DIFFERENCE
25,000
17,800
4,900
14,000
33,955
40,079
5,790
12,380
Lounge Other Shower/Toilet Sleeping excl. SPD( rooms; beds) Storage
Academic (350) Non-Academic
20 -- ACT (Off-Ctr) 24 -- Building & Apt. Maint. + 60 -- Business Office Technologies 20 -- Carpentry + 20 -- Food Service + 30 -- Health Occupations + 20 -- Painting + 24 -- Welding +
Dining (2 Servings) Food Preparation
Aerobics/Exercise Arts & Crafts Canteen Gymnasium Miscellaneous Recreation Non-Resident Lounge Recreation Hall Recreation Storage Theater
5,881 3,251 4,163
17,049 3,611
7,899 9,523
3,247 1,483 7,642 1,323
3,343 4,767
1,950 3,840
6,882
1,456
2,500
3,000 18,000
1,500
3,500 3,500
1,200 2,400 1,500 1,200 1,200 1,500 1,800
2,800 2,100
3,381
1,163 -951
2,111
4,399 6,023
2,047 -917
6,142 -348
1,843 2,967
-850 1,740
Vocations
RESIDENT
NON-RESIDENT
(250)
(100) 15
50 12,500 1,500
8,955
22,279
-1,620
08/14/2013
Space Utilization By Function 00608 Shreveport Page: 2 of Date:
MEDICAL/DENTAL
ADMINISTRATION
STORAGE/SUPPORT
VACANT
SUGGESTED
NSF/
ENROLLEE
SUGGESTED
TOTAL
NSF
ACTUAL
TOTAL
NSF
TYPE OF SPACE
SUB TOTAL
SUB TOTAL
SUB TOTAL
SUB TOTAL
TOTAL 227 79,450 120,410
(350)
(350)
(350)
(0)
DIFFERENCE
166,743
0.72
TOTAL GSF
NET TO GROSS RATIO
3,750
7,000
7,000
1,559
4,578
9,381
12,688
Medical Only Medical/Dental
Administration
Operations & Maintenance Warehouse
Vacant
4.8 5.91
4,578
1,882 7,499
12,688
1,680 2,070
7,000
2,800 4,200
-822 -1,369
-2,422
-918 3,299
-2,191
-2,422
2,381
12,688
40,960
Net Square Footage By Building Date: 08/14/2013 Page: 1
Center: SHREVEPORT (00608) of 4
HOUSING
Sleeping excl. SPD
Lounge
Storage
Shower/Toilet
Other
Function Suggested
NSF
8,801 8,248
1,391 4,490
3,103
3,340
1,076
1,328
F - MEDICAL/DENTAL/DORMITORY
H - FEMALE DORMITORY
F - MEDICAL/DENTAL/DORMITORY
H - FEMALE DORMITORY
F - MEDICAL/DENTAL/DORMITORY
E - EDUCATION/ADMIN
H - FEMALE DORMITORY
F - MEDICAL/DENTAL/DORMITORY
H - FEMALE DORMITORY
E - EDUCATION/ADMIN
F - MEDICAL/DENTAL/DORMITORY
G - CARP/CUL ARTS/WHSE/LAUNDRY
H - FEMALE DORMITORY
Bldg Name Actual NSF Difference
17,049
5,881
3,611
4,163
3,251
Sub Total: 33,955
18,000
2,500
1,500
3,000
25,000
-951
3,381
2,111
1,163
3,251
( 250
8,955 rooms; beds rooms; beds
Page: 2
Center: SHREVEPORT (00608) of 4
EDUCATION
FOOD SERVICE
Academic
Carpentry
Health Occupations
Welding
Painting
Food Service
Non-Academic
Building & Apt. Maint.
Business Office Technologies
Dining (2 Servings)
Food Preparation
Function Suggested
NSF
2,078 1,953 1,200
7,642
4,767
3,222
1,323
5,101
1,581
3,247
1,483
1,950
3,840
A - FOOD SERVICE/EDUCATION
A - FOOD SERVICE/EDUCATION
A - FOOD SERVICE/EDUCATION
S - GREEN HOUSE
A - FOOD SERVICE/EDUCATION
F - MEDICAL/DENTAL/DORMITORY
B - RECREATION
A - FOOD SERVICE/EDUCATION
G - CARP/CUL ARTS/WHSE/LAUNDRY
A - FOOD SERVICE/EDUCATION
N - WELDING VOCATION
P - VOCATION
N - WELDING VOCATION
G - CARP/CUL ARTS/WHSE/LAUNDRY
E - EDUCATION/ADMIN
A - FOOD SERVICE/EDUCATION
E - EDUCATION/ADMIN
A - FOOD SERVICE/EDUCATION
R - OUTREACH & ADMISSIONS
C - ADMINISTRATION
C - ADMINISTRATION
A - FOOD SERVICE/EDUCATION
P - VOCATION
A - FOOD SERVICE/EDUCATION
A - FOOD SERVICE/EDUCATION
A - FOOD SERVICE/EDUCATION
Bldg Name Actual NSF Difference
7,899
7,642
4,767
3,343
1,323
9,523
3,247
1,483
1,950
3,840
Sub Total:
Sub Total:
40,079
5,790
3,500
1,500
1,200
1,800
1,500
1,200
3,500
1,200
2,400
2,800
2,100
17,800
4,900
4,399
6,142
-348
2,967
1,843
6,023
2,047
-917
-850
1,740
22,279
Page: 3
Center: SHREVEPORT (00608) of 4
RECREATION
MEDICAL/DENTAL
ADMINISTRATION
Recreation Hall
Arts & Crafts
Gymnasium
Theater
Miscellaneous Recreation
Canteen
Aerobics/Exercise
Non-Resident Lounge
Recreation Storage
Medical/Dental
Medical Only
Administration
Function Suggested
NSF
1,456
6,882
2,774
B - RECREATION
B - RECREATION
B - RECREATION
E - EDUCATION/ADMIN
B - RECREATION
B - RECREATION
B - RECREATION
E - EDUCATION/ADMIN
B - RECREATION
F - MEDICAL/DENTAL/DORMITORY
F - MEDICAL/DENTAL/DORMITORY
C - ADMINISTRATION
F - MEDICAL/DENTAL/DORMITORY
D - ADMIN/COUNSELING
Bldg Name Actual NSF Difference
1,456
6,882
4,578
Sub Total:
Sub Total:
Sub Total:
12,380
1,559
4,578
2,070
1,680
7,000
14,000
3,750
7,000
-1,369
-822
-2,422
-1,620
-2,191
-2,422
Page: 4
Center: SHREVEPORT (00608) of 4
STORAGE/SUPPORT
VACANT
Warehouse
Operations & Maintenance
Vacant
Function Suggested
NSF
7,499
1,237
7,144 1,787 1,185 2,572
G - CARP/CUL ARTS/WHSE/LAUNDRY
G - CARP/CUL ARTS/WHSE/LAUNDRY
D - ADMIN/COUNSELING
E - EDUCATION/ADMIN
C - ADMINISTRATION
M - INDUSTRIAL PAINTING VOCATION
N - WELDING VOCATION
D - ADMIN/COUNSELING
Bldg Name Actual NSF Difference
7,499
1,882
12,688
Sub Total:
Sub Total:
9,381
12,688
4,200
2,800
7,000
3,299
-918
12,688
2,381
12,688
Energy Management Report Center: SHREVEPORT (00608)
Page: 1 Date: 08/06/2013 of 3
CENTER ENERGY DATA
Yes
ENERGY CONSUMPTION ASSESSMENT
32% 51,026
59,064 74,765
ENERGY USE BY FUEL TYPE
Energy Audit :
Date of Audit :
Status of Energy Conservation Measure Recommendations :
Electric Company :
Percent Change since Baseline Year :
Natural Gas Company :
Property Status :
3/12/2002 Implemented American Electric Power Co.
Center Point Energy Company
Federally Owned (DOL)
1,912,978 6,527=
Total 9,247
MBtu
MBtu
Total $181,718 MBtu/ $19.652
BTU/GSF
BTU/GSF
BTU/GSF
Electricity
Natural Gas kWh
2,638 MCF = 2,720 MBtu
$158,818 $0.083= kWhElectricity
Natural Gas $22,900 = $8.681 MCF
ENERGY COST BY FUEL TYPE
WATER CONSUMPTION ASSESSMENT
Percent Reduction Compared to Goal:
1,000 Gallons
1,000 Gallons
FY 2012 Energy Goal:
Energy Goals are being met. Keep up the Good Work to further Reduce Energy Usage.
FY 2012 Energy Consumption:
Note: The Federal Government has set a goal of 3% Energy Consumption reduction per year in EO 13423.
3,750 3,375 4,755
- 41%
Further Reduction in Water Usage is needed to meet Water Reduction Goals.
Note:
FY 2012 Goal:
FY 2012 Water Consumption:
1,000 Gallons
FY 2003 Energy Baseline:
FY 2007 Baseline:
The Federal Government has set a goal of 2% Water Consumption reduction per year in EO 13423 compared to the FY 2007 Baseline.
Page: 2 Date: 08/06/2013 of 3
Implementing some of the below recommendations can save you 10% to 25% off your annual energy bill without negatively impacting comfort or productivity.
1. Your staff and students are the key to savings. Educate the students and staff on the why of energy saving - costs and environmental impacts. Encouraging them to actively participate in energy reduction is also important. Post reminders at exit doors and bulletin boards about energy conservation. Simple tips include:
a. Turn it down (lights, heating & cooling),
b. Turn it off (lights, computers, other equipment),
c. Keep it tight (close doors and windows, use window blinds)
2. Operations and Maintenance: Educate the O&M staff on the why of energy saving -costs and environmental impacts. Simple tips include:
a. Make sure that the Operations and Maintenance staff is properly trained for the equipment they operate.
b. Tune and clean HVAC: Perform seasonal cleanups on air conditioners, boilers and furnaces, and regularly clean cooling coils and drain pans. Get rooftop or outdoor condenser coils cleaned and maintain an appropriate filter changing schedule.
c. Check (or ask your HVAC contractor to check) your outside air dampers or economizers to verify proper ventilation. Make sure economizer controls function properly. Make sure automatic dampers close during unoccupied periods.
d. Restore automatic control: When troubleshooting a system, take time to figure out and repair the automatic controls. Today's quick fix is tomorrow's bad idea.
e. Reasonable set points: Try 68°F in the heating season and 75°F in the cooling season.
f. Schedule HVAC equipment and lighting: (weekdays, weekends, holidays, off-season). Make sure equipment runs only when it is needed and the buildings are occupied. When buildings are vacant (i.e. dormitories during the day with students in class), make sure all the lights in the building are off.
g. Seasonal (resets, schedules, and shutoffs): As the seasons change, adjust set points and schedules to match the system's response to the weather.
h. Lighting: Invest in an inexpensive light level meter to measure the foot-candles in spaces to determine whether or not they are over lit and lamps can be safely removed. Where four-lamp fixtures are in use, two lamps can usually be removed from every fixture or every other fixture. After lamps are removed, disconnect ballasts. Contact the Energy team at PBDewberry for suggested light levels for individual space types. Cleaning fixtures regularly increases light levels.
i. Utilize power management features for all computers and monitors to shut them off when idle for more than 15 minutes.
Page: 3 Date: 08/06/2013 of 3
j. Have your vending machine suppliers turn off or remove light tubes from the advertising lighting in the machine. This will save about $50 per year per vending machine.
k. Save water with low flow sink aerators (0.5gpm) and low flow shower heads (1.5gpm - 2.0gpm). This will also reduce water heating energy consumption.
l. Set your water heater to 120°F. Verify by measuring at the tap. Never go below 115°F.
m. For water heaters installed in unconditioned spaces, add insulation blankets making sure that access covers, electric connection areas, and pressure relief valves are left uncovered.
n. Caulk and fill cracks around doors and windows to reduce costly air leaks.
o. When replacing broken glass, use high transmittance, low heat gain windows.
p. Make sure automatic door closers are functioning properly to avoid drafts.
3. Buy energy efficient, buy EnergyStar (www.energystar.gov).
a. Buy EnergyStar appliances and equipment.
b. Replace burned out lightbulbs with EnergyStar labeled compact fluorescent lightbulbs (CFLs).
c. Replace broken thermostats with EnergyStar labeled programmable products.
d. Replace broken exit signs with EnergyStar LED exit signs.
Environmental Management Report
Page: 1 Date: 08/14/2013 of 1
SOLID & HAZARDOUS WASTE MANAGEMENT (RCRA)
Commercial Waste Service
HAZARDOUS MATERIALS STORAGE (EPCRA)
Yes Building N (paint, solvent), Building Q
Oil based paint (50 gals), organic solvent (25 gals), form oil (150 gals), concrete sealer (80 gals), concrete bonding agent (40 gals)
Yes
PETROLEUM UNDERGROUND STORAGE TANKS (RCRA)
N/A0
PETROLEUM ABOVEGROUND STORAGE TANKS (CWA)
ASBESTOS AND PCB MANAGEMENT (TSCA)
AIR POLLUTION CONTROL (CAA)
N/A None
Attainment
Solid Waste Disposal :
Hazardous Waste Generator :
Hazardous Waste ID :
Generator Classification :
Hazadous Materials Storage :
Hazardous Materials ID :
HazMat Storage Area :
HazMat Spill Response Plan :
Number of Regulated USTs :
Number of Un-regulated USTs :
Local Hazardous Use Permit :
LEPC Notification :
EPA Generator ID Number :
Hazardous Waste Disposal :
RCRA Compliance
ID LocationFuel Type Capacity
Number of ASTs :
Asbestos Survey Date :
Asbestos Type :
Asbestos Coordinator :
Coordinator Training Date:
Custodial/Maintenance Training :
AHERA Regulated :
Management Plan Approval :
PCB Transformer Testing :
PCB Transformers :
PCB-Contaminated Transformers :
Transformers Labelled :
Regional Air Quality :
Permitted Air Pollution Source :
Source Description :
BFI, Inc.
Yes Oil based paint (5 gals/year), organic solvent (10 gals/year)
Conditionally Exempt Small Quantity Generator
LAR000035840
Commercial Hazardous Waste Disposal Service
Safety Kleen, Longview TX
Yes Yes
Overfill Leak Corrosion
SPCC Plan Required : SPCC Plan Completed :
No N/A
12/04/1991 Friable/Non-Friable James Bowman 05/19/1992 Yes No N/A Yes Yes
ID Fuel Type Capacity Location Overfill
Prevention Secondary ContainmentTank Status
Tank Status Prevention/Detection
Asbestos-Containing Materials Inventory
Date: 08/14/2013Center : Shreveport (00608) Page: 1 of 2
Floor Finishes Floor Finishes Floor Finishes Floor Finishes
HVAC (Bldg) Heating Floor Finishes Floor Finishes
Floor Finishes Floor Finishes Floor Finishes
Heating Heating HVAC (Bldg) Heating Floor Finishes Floor Finishes
HVAC (Bldg) Floor Finishes Floor Finishes Floor Finishes Heating
Bldg System
Bldg System
Bldg System
Bldg System
Bldg System
12x12 floor tile, blue Mastic beneath 9x9 tile Mastic beneath 12x12 tile 9x9 floor tile, gray/green
Flexible duct connectors Pipe fitting insulation 9x9 floor tile, tan Mastic beneath 9x9 tile
9x9 floor tile, brown Mastic beneath 9x9 tile Linoleum
Pipe fitting insulation Asbestos cement flue Flexible duct connectors Pipe fitting insulation 9x9 floor tile, tan/blue Mastic beneath 9x9 tile
Flexible duct connectors 9x9 floor tile, tan/brown Mastic beneath 9x9 tile Linoleum, brown Pipe fitting insulation
Category Description
Category Description
Category Description
Category Description
Category Description
Sq. Ft.
Sq. Ft.
Sq. Ft.
Sq. Ft.
Ea.
Ea.
Sq. Ft.
Sq. Ft.
Sq. Ft.
Sq. Ft.
Sq. Ft.
Ea.
Sq. Ft.
Ea.
Ea.
Sq. Ft.
Sq. Ft.
Ea.
Sq. Ft.
Sq. Ft.
Sq. Ft.
Ea.
Location
Location
Location
Location
Location
Unit
Unit
Unit
Unit
Unit
Quantity
Quantity
Quantity
Quantity
Quantity
3rd floor 1st, 2nd floors 3rd floor 1st, 2nd floors
Mechanical rooms Mechanical rooms Throughout Throughout
Throughout Throughout Utility closets
Crawlspace Exhaust chase 2nd floor, ceiling 2nd floor Throughout Throughout
Penthouse mech. room Throughout Throughout 1st floor, AARP Penthouse mech. room
14000 14000
11820 11820
Building :
Building :
Building :
Building :
Building :
A - FOOD SERVICE/EDUCATION
B - RECREATION
C - ADMINISTRATION
D - ADMIN/COUNSELING
E - EDUCATION/ADMIN
Asbestos-Containing Materials Inventory
Page: 2 of 2
Floor Finishes Floor Finishes Floor Finishes Floor Finishes Heating Ceiling Finishes Heating
Bldg System 12x12 floor tile, brown/cream 9x9 floor tile, brown/blue Mastic beneath 9x9 tile Mastic beneath 12x12 tile Pipe insulation, air-cell Acoustical plaster Pipe fitting insulation
Category Description Sq. Ft.
Sq. Ft.
Sq. Ft.
Sq. Ft.
Lin. Ft.
Sq. Ft.
Ea.
Location Unit Quantity Throughout Throughout Throughout Throughout Mechanical room Throughout Mechanical room
11500 11500 11500 11500
23000
Building : F - MEDICAL/DENTAL/DORMITORY
Radon
Page: 1 of 1
A - FOOD SERVICE/EDUCATION
B - RECREATION
C - ADMINISTRATION
D - ADMIN/COUNSELING
E - EDUCATION/ADMIN
F - MEDICAL/DENTAL/DORMITORY
G - CARP/CUL ARTS/WHSE/LAUNDRY
H - FEMALE DORMITORY
M - INDUSTRIAL PAINTING VOCATION
N - WELDING VOCATION
P - VOCATION
R - OUTREACH & ADMISSIONS
S - GREEN HOUSE
Bldg Name
06/06/1990
06/06/1990
06/06/1990
06/06/1990
06/06/1990
06/06/1990
06/06/1990
06/06/1990
12/04/1991
Test Date
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
No
No
No
Radon Testing
< 4 pCi
< 4 pCi
< 4 pCi
< 4 pCi
< 4 pCi
< 4 pCi
< 4 pCi
< 4 pCi
< 4 pCi
Test Result
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
Mitigation Mitigation Date
RADON EXPLANATORY NOTES
The US Environmental Protection Agency (EPA) has established a radon action level of 4.0 picoCuries per liter (pCi/L). Occupied buildings with radon concentrations less than 4.0 pCi/L do not require radon mitigation; un-occupied buildings, or those buildings which are occupied only infrequently for brief periods of time, also do not require radon mitigation. Occupied buildings with radon concentrations greater than
4.0 pCi/L require radon mitigation and verification of radon reductions as soon as possible, with priority given to dormitories and student recreation buildings. Occupied buildings with radon concentrations greater than 20.0 pCi/L should be considered significant radon exposure hazards, and priority for mitigation should be given to buildings with these highly elevated radon concentrations.
Radon mitigation techniques include: (1) adjustment of the building HVAC system to create a positive pressure within the building; (2) sealing of foundation wall cracks, penetrations, or other openings;
(3) sealing crawlspace openings and sump pits; (4) installing an active subslab depressurization (ASD) system.
Site Description
SHREVEPORT
Aerial photograph of Shreveport Job Corps Center
Page: 1 Date: 08/14/2013 of 4
Comments:
Paving Type for Roads & Parking
The site contains minimal parking. Cars are parked on the outdoor basketball court during the day.
Paving Type for Sidewalks
Concrete Concrete
Comments:
Topography Buildings and Structures
Center is not fully enclosed by fencing. The site is very small with no space for large recreation features such as baseball or soccer. Continuously wet weather soaks the sand volleyball court.
ROADS, PARKING & SIDEWALKS
Water Source Water Authority Service Meter On-Site Treatment Plant
1. Water System
Treatment Type Storage Type Storage Capacity(Gallons)
NoMasterCity of ShreveportPublic Water Authority
None 0None
The center is provided with three master water meters, located within the property line. One meter is located near Building G. The other water meter is located near Building N and the third water meter is located near Building S.
Comments:
Comments:
Fire Hydrants On-Site Water Supply Storage Capacity
(Gallons) Pressure Source FD Response Time (Minutes)
No 0 5None Municipal
The site is served by an adequate number of fire hydrants with adequate domestic water pressure. The nearest Shreveport city fire station is 1.5 miles away from the center and the emergency response time is about five minutes.
Number of Deficiencies = 2
SITE FEATURES
UTILITIES
2. Fire Protection System
Buildings Structures13 4
Surrounding
Outdoor Recreation
Basketball, Volleyball
Location Type
Maintenance Responsibility System Capacity Adequate System Condition
Center Center Yes Good
Separate Loop
No
Ownership Maintenance Responsibility System Capacity Adequate System Condition
Utility Utility Yes Good
Ownership
Roads & Parking Adequate Roads & Parking Condition Sidewalks Adequate Sidewalk Condition
Fencing
Other Features
Page: 2 Date: 08/14/2013 of 4
Comments:
Sewage Treatment Flow
Center sewer system discharges waste into the city sanitary sewer system by means of gravity. Main line is 10" cast iron and 50+ years old. Center branch line is 4", 50+ years old. Approximate branch line length is 100'. Inside the buildings there are PVC and cast iron lines which are in fair condition.
Utility
Publicly Owned Treatment Works
Center
Gravity
Maintenance ResponsibilityOwnership
Comments: The Center Point Energy Company supplies natural gas for cooking, heating and domestic hot water. An underground distribution system is connected to three gas meters at the center. One gas meter is located on the northeast mechanical room of Building A. Another gas meter is located near the west mechanical room of Building H. The third gas meter is located at the center of Building M that serves Building N.
Center Point Energy Company
Comments: There is one natural gas fired hot water boiler in the basement of Building D which provides heating hot water to Buildings A, B, C, D, E, and F.
3. Sanitary Sewer System/ Sewage Treatment Plant
5. Fuel Distribution System
6. Central Plant
System Capacity Adequate System Condition
Yes Good
4. Storm Water System
Drain Type On-Site Storm Water Management
Surface Run-off N/A
Ownership Maintenance Responsibility System Capacity Adequate System Condition
Center No GoodCenter
Comments: Drainage system type is surface run-off to concrete channels that discharge into the storm main of the municipal system at the street. Some buildings have gutters and downspouts. Site grading is relatively flat and adequate, except for the courtyard of Buildings A-G which floods during heavy rain. During periods of heavy rain, the storm drain channels run full. Approximately three times per year, the storm main cannot take the heavy flow and overflows.
Gas Company Metering
Master
Ownership Maintenance Responsibility System Capacity Adequate System Condition
Center Center Yes Good
Type Energy Source
Heating Hot Water Natural Gas Buildings A, B, C, D, E, and F.
Bldgs Served
Ownership Maintenance Responsibility Plant Capacity Adequate Plant Condition
Center Center Yes Good
Page: 3 Date: 08/14/2013 of 4
Comments:
Electric Company PCB Trans.
Transformer Mounting Transformer Ownership
Systems Ownership Maintenance Responsibility
American Electric Power Co.
Service is brought to the center from overhead lines along Arkansas Avenue on the west and Missouri Avenue on the east. Service enters the center at multiple points along the center's western and eastern boundaries. The secondary services are both overhead and underground via pole and pad-mounted transformers. Buildings F, G, H, N, P and R are metered individually. Buildings A and B are metered as a zone with a meter located in Building A.
Buildings C, D and E are also metered as a zone with a meter located in the Building D basement mechanical room. Dormitory building H has a lightning protection system installed on the roof.
Pole and Pad Utility
Utility Utility
No
Comments:
Telephone Company
On-site Line Owner
T1 lines are brought to the center by Cingular which terminate in the main server located in Building C first floor.
Fiber optic cabling is utilized for network interconnection between the server and buildings. VoIP is utilized for both data and long distance voice communications. The server room is supported by a 10 kVA portable UPS module.
The main fire alarm control/annunciator panel (FACP) is located in the security office in Building F. The local FACPs are located in Buildings A, B, D, H and N. The panels in A, B, and D communicate to each other. Fire alarm system devices in buildings C, E and G are connected to the FACP in Building D. All local panels report to the main FACP in Building F except the panel in Building N which is a stand-alone. This panel supports fire alarm system devices in Buildings M and P. Center wide exterior mounted CCTV cameras are monitored via a color monitor in the Building F security office. Selected buildings on center have satellite TV connection.
Cingular
Maint. Responsibility
Center Center
CCTV, Cameras Monitoring is in the security office in Building F.
12.47/7.2 kV, 3-Phase, 4 Wire
240/120V and 208/120V, 3-Phase, 4 WireOverhead & Underground
Overhead & UndergroundPrimary Service
Secondary Service
Distribution Characteristics
9. Electrical (Communication/Alarm/Security)
7. Electrical (Service)
Yes
Central
VOIP
System Capacity Adequate System Condition
GoodYes
Transformer Maint Resp
Utility
System Capacity Adequate System Condition
Yes Good
Generator
None
8. Electrical (Site Lighting)
Roadways Parking Walkways Building Outdoor Sports
Mounting
Control
Pole Pole Pole Building None
Photocell, Time Clock Photocell, Time Clock Photocell, Time Clock Photocell, Time Clock None
System Ownership Maintenance Responsibility System Capacity Adequate System Condition
Utility, Center Utility, Center Yes Good
Comments: The utility company owns and maintains lights that are mounted on power poles. The center owns and maintains all other poles-mounted and building-mounted exterior lights.
ATS MTS
No No
Number of Deficiencies = 3
Fire Alarm Security
Metering Individual
Page: 4 Date: 08/14/2013 of 4
ACCESSIBILITY
Yes
The site is composed of interconnected buildings that are from different eras that pre-date ADA/UFAS.Comments:
Comments:
NoNoYes
Buildings A, C and F are more than 50 years old, but are historically unevaluated.
No
Nationally Registered Site
Site Eligible for National Register
Located in Historic District
Archaeological Significance
None.
STORAGE TANKS
Comments:
TypeStatus Location Owner Fuel Type
Capacity (Gallons) Install Date
Earthquake Risk
Low Low LowHigh HighIBC Low
LightningEarthquake Def. Authority Flooding Tornado Hurricane Forest
Fire
ID Reg.
Number of Deficiencies = 1
Accessible Parking: Accessible Slope:
Yes
Curb Cuts:
Yes
Ramps:
YesYes
Site Accessible Route:
GENERAL SITE CONDITION
Rating X Good Fair Poor
HISTORIC PRESERVATION
NATURAL HAZARDS
The site condition is not impacting the functional use of the facilities.
The site condition IS impacting the functional use of the facilities.
The site condition IS SIGNIFICANTLY impacting the functional use of the facilities.
Purpose
Active Energy Use Reduction Program
Active Water Use Reduction Program
Approximate or Measured Waste Recycled
Use of School Dude or CMMS for Preventative Maintenance
Green Purchasing Policy Practiced
Site Stormwater Absorption Measures in Place
Center has Onsite Renewable Energy (PV or Wind)
Center has a Chartered Green Committee & Roster
Center Uses Green Cleaning Practices
SUSTAINABILITY
NO
NO
NO
NO
NO
NO
NO
NO
Building Descriptions and Utilities
BUILDING A - FOOD SERVICE/EDUCATION
Building Descriptions Date: 08/06/2013Center : Shreveport (00608) Page: 1 of 68
Building: A - FOOD SERVICE/EDUCATION
BUILDING ENVELOPE
Foundation RoofBuilding
Concrete Loadbearing Masonry Steel
Brick Masonry
Wall Roof Unknown Rigid
Metal Units - Metal Frame
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors
Assembly/Business 19,654 15,152 3 Owned 1935 Not Evaluated
Comments: The building has both interior and exterior ramps. Two ramps exceed the allowable slope. The exterior ramp in the courtyard is compliant.
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
No
No
No
Yes
Yes
Yes
No
No
No
No
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Insulation4.
Exterior Doors5.
Material Drainage Year Life
Remaining Type Area Served
Single Ply Gutters and Downspouts 1997 4 Flat Entire Building
3. Roof
Entire Building
Area Served
Page: 2 of 68
Building: A - FOOD SERVICE/EDUCATION
INTERIOR FINISH
Carpet Ceramic Tile Concrete Quarry Tile Vinyl Tile
Ceramic Tile Drywall Plaster Stainless Steel Wainscot
Comments: Vinyl suspended system in kitchen.
Metal Unit - Metal Frame Wood Unit - Wood Frame
VERTICAL CIRCULATION
Metal Ladder Metal Stairs
Comments: There is a metal ladder to the roof hatch.
Single Hung - Aluminum Frame; Single Glazing;
12" X 12" Spline Acoustical Tile Plaster
Number of Deficiencies = 3
Number of Deficiencies = 1
Windows6.
Floors1. Asbestos: Yes
Interior Walls2.
3.
Interior Doors4. Number of Deficiencies = 3
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
An Ajax gas-fired water boiler (model WGB-3000, S/N 89-41158, 3,000 MBH gas input, 2,400 output, 5 HP pump) provides heating water to the air-handling units. The boiler is located in the basement of Building D. There are six vertical indoor constant volumes; 2-pipe air-handling units provide heating to the building. The indoor units are located in six mechanical rooms ranging from 2,400 to 6,000 CFM capacity; two indoor units are equipped for outdoor air ventilation. The typical air-handling units are Carrier (models 40RM-007-B600HC, 40RM-012-B600HC and 40RM-016-B600HC, built in 05/1999).
A sterling gas fired make-up air unit (model E1B-RT40A6D01A51H20B1HA, 5,000-8,000 CFM, 400 MBH input and 320 MBH output) located at loading dock provides make-up air to kitchen and dishwasher exhaust systems.
Comments:
Comments:
HVAC
Heat1.
Gas-Fired Hot Water Boiler
Gas-Fired Furnace
Single Duct
Makeup Air Unit
Two-Pipe
Two-Pipe
Electric
Electric
Natural
Mechanical
None
None
Entire Building
Kitchen
Ceilings
Page: 3 of 68
Building: A - FOOD SERVICE/EDUCATION
Mechanical
Mechanical
Mechanical
Dishwashing
Kitchen
Restroom
Comments:
Comments:
Comments:
A Loren Cook wall-mounted exhaust fan ventilates the dishwasher.
A roof-mounted utility exhaust fan ventilates the kitchen hood.
Roof and wall-mounted exhaust fans ventilate the restrooms.
Ventilation Area Served
Split Direct Expansion (Air
Cooled)
Packaged Direct
Expansion (Air Source)
Single Duct
Window Unit
Refrigerant
None
Electric
Electric
Natural
Mechanical
None
None
Entire Building
Classrooms and Offices
Exhaust Ventilation
Six vertical indoor constant volumes air-handling units with DX-cooling coils mounted on the discharge, in six mechanical rooms, coupled with six roof-mounted condensing units provide cooling to the building. Two indoor units are equipped for outdoor air ventilation. The typical condensing units (CU-1 through CU-6) are Carrier (models 38AK-012-511, 10-ton, 38AKS016-510, and 15-ton, R-22 refrigerant, built in 10/1998) and Trane (model TTA120A300FA, 10-ton, and R-22 refrigerant, built in 06/2009).
Window air conditioning units provide supplemental DX-cooling to the offices and classrooms located on the second and third floor. The typical units were built by Samsung, LG, Friedrich and range in capacity from 0.5-ton through 2-ton.
Comments:
Comments:
Ventilation2.
System Type
Number of Deficiencies = 1
Air Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
3. Number of Deficiencies = 2Air Conditioning
Page: 4 of 68
Building: A - FOOD SERVICE/EDUCATION
Two 72-gallon capacity Ruud gas-fired water heaters (model R72360, 360 MBH gas input, and 327.3 GPH recovery) provide domestic hot water to kitchen and dining area. These are located in the northwest mechanical equipment room. The hot water loop has an in-line B&G circulating pump. In addition, there are two 4-gallon capacity electric water heaters (Ariston (model GL4, 1.5 kW) provide domestic hot water to the men's and women's restrooms on the second floor. These units are located under the lavatories.
Comments:
Comments:
Cast Iron Outdoor None
The grease interceptor is 500 gallons in volume.
Electric Water Cooler Fixed Emergency Eyewash Kitchen Sink Lavatory Multi-Compartment Sink Portable Bottled Water Cooler Service Sink Sink Urinal Water Closet (Tank)
Gas (Natural)
None None ABC Type Fire Extinguisher, K Type Fire Extinguisher, Wet Chemical
Copper Copper Gas-Fired None No
Hot Water Cold Water Water Heater Water Treatment HW Storage Tank
Grease InterceptorWaste / Vent Interior Storm
Sprinkler System Stand Pipe System Fire Suppression
PLUMBING
Water Distribution1.
Sanitary Distribution2.
Fixtures3. Number of Deficiencies = 1
Fuel Distribution4.
FIRE PROTECTION
Location UL300 Compliance Status Kitchen Compliant
Comments: The kitchen hood is provided with a Zone Defense wet chemical fire suppression system (model 375) with an automatic gas shut-off valve and a shunt-trip for electric cooking equipment under the hood. The existing fire suppression system meets the requirement of Standard UL-300.
UL300 COMMERCIAL KITCHEN HOOD FIRE SUPPRESSION
Page: 5 of 68
Building: A - FOOD SERVICE/EDUCATION
Comments: Service is brought from a 300 kVA pad-mounted transformer and terminates in a 3000A switchboard located outside south of the building. A meter is installed near the transformer. The switchboard feeds an 800A and a 400A main distribution panels (MDP) located on the first floor and in the penthouse respectively. The 400A MDP serves all mechanical loads including kitchen equipment and walk-in freezer.
The 800A MDP serves all other loads via distribution panels located throughout the building. The 3000A switchboard also serves Recreation Building B.
FIRE ALARM
Comments: The fire alarm control/annunciator panel is a Simplex 4100U, located in the kitchen near the food storage.
The remote annunciator panel is located at the entrance in the corridor near Building B. This panel communicates with panel in Buildings B and D and reports to the main panel in Building F.
Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices
Audible Alarm Control/Annunciator Panel Duct Smoke Detector Heat Detector Manual Pull Station Remote Annunciator Smoke Detector Visual Alarm
Comments: Recorded footcandle levels include natural light contribution.
High Intensity Discharge (HID)
Comments: Exterior building-mounted light fixtures are controlled by time clock and photocell.
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
Offices
Food Preparation
Classrooms
Storage/Warehouse-Active
Dining/Lunch Rooms
Dishwashing
Storage Rooms
Corridors & Stairs
Toilets
Equipment Rooms (Elec/Mech)
Area Recommended Level
Recorded Level Light Type
Battery Backup Battery Backup
Main Distribution Panel 120/208V, 3-Phase, 4 Wire Panelboards, Loadcenters Receptacles, GFCI, Switches
Emergency Exit
ELECTRICAL SERVICES Number of Deficiencies = 2
Exterior Lighting1.
Interior Lighting2. Number of Deficiencies = 2
Emergency /Exit Lighting3.
LIGHTING
Page: 6 of 68
Building: A - FOOD SERVICE/EDUCATION
Comments: Major building exits are provided with security door alarms.
Connected to Main System Magnetic Door/Alarm None Satellite Dish
Telephone Security Public Address Television
GENERAL BUILDING CONDITION
Rating
Comments:
X Good Fair Poor
Interior finishes are old and worn. Kitchen quarry tile is damaged, the ceiling is stained, and staff toilet is deteriorated. The second floor lacks hot domestic water and the building lacks consistent ventilation.
COMMUNICATION
The facility condition is not impacting the functional use of the facility.
The facility condition IS impacting the functional use of the facility.
The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.
Electric Water Gas No YesZone
BUILDING UTILITY METERING
Structure: Good Exterior: Good Interior: Fair Mechanical: Fair Electrical: Good
This building has been recommended for demolition in the Long Range Development Plan.
DEMOLITION RECOMMENDATION
Type Location None None
Comments: There are gas-fired appliances in the building.
CARBON MONOXIDE DETECTION
BUILDING B - RECREATION
Page: 7 of 68
Building: B - RECREATION
BUILDING ENVELOPE
Foundation RoofBuilding
Concrete Structural Steel Steel
Brick Masonry
Wall Roof Unknown Rigid
Metal Units - Metal Frame
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors
Assembly 13,150 11,061 2 Owned 1963 Not Evaluated
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
N/A
Yes
Yes
Yes
Yes
Yes
No
No
No
No
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Insulation4. Number of Deficiencies = 1
Exterior Doors5.
Material Drainage Year Life
Remaining Type Area Served
Single Ply Gutters and Downspouts 1997 4 Flat Entire Building
3. Roof
Page: 8 of 68
Building: B - RECREATION
INTERIOR FINISH
Carpet Concrete Vinyl Tile Wood
Brick CMU Drywall Plaster
Metal Unit - Metal Frame Wood Unit - Metal Frame
VERTICAL CIRCULATION
Metal Stairs
Fixed - Steel Frame; Single Glazing;
Acoustical Tile Exposed Structure Plaster
Number of Deficiencies = 4
Windows6.
Floors1. Asbestos: Yes
Interior Walls2.
3.
Interior Doors4.
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
An Ajax gas-fired water boiler (model WGB-3000, S/N 89-41158, 3,000 MBH gas input, 2,400 output, 5 HP pump) provides heating water to the air-handling units. The boiler is located in the basement of Building D. There are two vertical indoor constant volumes; 2-pipe air-handling units provide heating to this building and Building C. The indoor unit serving the recreation hall is a Trane (model TWE090A300EL, 3,000 CFM, built in 01/2006) located in the first floor mechanical room. The indoor unit serving Building C is a Carrier (model 40RM-012-B600HC, 4,000 CFM, built in 05/1999) located in the northeast mechanical room on the first floor.
Two gas-fired rooftop packaged units provide heating and fresh air to the gymnasium and second floor recreation areas. The unit serving the gymnasium is a Trane (model YCH420AELR0B100, 350 MBH gas input, built in 01/2006. The unit serving the second floor recreation is a Trane (model YSC102A3ELACA00, 120 MBH gas input, built in 01/2006.
Comments:
Comments:
HVAC
Heat1. Asbestos: Yes
Gas-Fired Hot Water Boiler
Gas-Fired Packaged
Single Duct
Single Duct
Two-Pipe
None
Electric
Electric
Mechanical
Mechanical
None
None
Recreation Area
Gymnasium
Page: 9 of 68
Building: B - RECREATION
Mechanical
Mechanical
Toilet/Shower
Kiln Area
Comments:
Comments:
Wall-mounted exhaust fans ventilate the toilet/shower rooms.
Roof-mounted exhaust fan ventilates the exhaust hood serving the kiln area.
Ventilation Area Served
Split Direct Expansion (Air
Cooled)
Packaged Direct
Expansion (Air Source)
Single Duct
Single Duct
Refrigerant
None
Electric
Electric
Mechanical
Mechanical
None
Economizer
Recreation Area
Gymnasium
Exhaust Ventilation
Two vertical indoor constant volumes air-handling units with DX-cooling coils mounted on the discharge, in two mechanical rooms, coupled with two roof-mounted condensing units provide cooling to this building and Building C. The condensing unit serving the recreation hall is a Trane (model TTA0907300EA, R-22 refrigerant, 7.5-ton, built in 08/2002). The condensing unit serving Building C is a Carrier (model 38AK012, R-22 refrigerant, 10-ton, built in 08/2002).
Two gas-fired rooftop packaged units provide DX-cooling and fresh air to the gymnasium and second floor recreation areas. The unit serving the gymnasium is a Trane (model YCH420AELR0B100, R-22 refrigerant, 35-ton, built in 01/2006. The unit serving the second floor recreation is a Trane (model YSC102A3ELACA00, R-22 refrigerant, 8.5-ton, built in 01/2006.
Comments:
Comments:
Ventilation2.
System Type
Air Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area
3. Air Conditioning
Page: 10 of 68
Building: B - RECREATION
Three gas fired water heaters (two State model SBF75300, 75 gallon, 300 MBH input, 272.7 GPH recovery, built in 04/1998 and one Rheem model RF30091, 300 MBH gas input, 272.7 GPH recovery, built in 06/1993) provide domestic hot water to the first floor of this building and portions of Building C.
These are located in the northeast mechanical equipment room on the first floor. The hot water loop has an in-line B&G circulating pump. Another 91-gallon capacity Ruud gas-fired water heater (model G91-200, S/N URNG 1298G02518, 199.9 MBH gas input, 181.8 GPH recovery, built in 12/1998) provides domestic hot water to the second floor of this building. It is located in the second floor mechanical room.
Comments:
Cast Iron None None
Electric Water Cooler Lavatory Portable Bottled Water Cooler Service Sink Sink Urinal Water Closet (Flush Valve)
Gas (Natural)
None None ABC Type Fire Extinguisher
Copper Copper Gas-Fired None No
Hot Water Cold Water Water Heater Water Treatment HW Storage Tank
Grease InterceptorWaste / Vent Interior Storm
Sprinkler System Stand Pipe System Fire Suppression
PLUMBING Number of Deficiencies = 2
Water Distribution1.
Sanitary Distribution2. Number of Deficiencies = 1
Fixtures3. Number of Deficiencies = 1
Fuel Distribution4.
FIRE PROTECTION
Location UL300 Compliance Status N/A
Page: 11 of 68
Building: B - RECREATION
Comments: Service is brought from a 3000A switchboard located outside south of Building A. Service terminates in an 800A main distribution panel (MDP) located inside Building B. This MDP serves the entire loads via distribution panels located throughout the building. The 3000A switchboard also serves Food Service/Education Building A.
FIRE ALARM
Comments: The fire alarm control/annunciator panel is a Simplex 4100U, located in the recreation supervisor's office.
This panel communicates with panel in Buildings A and D and reports to the main panel in Building F.
Projected beam-type smoke detectors are utilized in the gymnasium.
Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices
Audible Alarm Control/Annunciator Panel Duct Smoke Detector Heat Detector Manual Pull Station Projected Beam Type Smoke Detector Smoke Detector Visual Alarm
Comments: Recorded footcandle levels include natural light contribution. Lighting in the gymnasium is provided by fluorescent light fixtures, each with (6) T5 fluorescent lamps and high efficiency reflectors.
High Intensity Discharge (HID)
Comments: Exterior building-mounted light fixtures are controlled by time clock and photocell.
T8 - Fluorescent
T8 - Fluorescent
T5 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
Compact Fluorescent
Compact Fluorescent
T12 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 and Compact Fluorescent
Offices
Recreation
Gymnasium
Storage/Warehouse-Active
Classrooms
Corridors & Stairs
Toilets
Shower
Locker Room
Equipment Rooms (Elec/Mech)
Recreation
Storage Rooms
Food Preparation
Area Recommended Level
Recorded Level Light Type
Battery Backup Battery Backup
Main Distribution Panel 120/208V, 3-Phase, 4 Wire Panelboards, Loadcenters Receptacles, GFCI, Switches
Emergency Exit
ELECTRICAL SERVICES Number of Deficiencies = 4
Exterior Lighting1.
Interior Lighting2. Number of Deficiencies = 1
Emergency /Exit Lighting3. Number of Deficiencies = 1
Page: 12 of 68
Building: B - RECREATION
Comments: Most building exits are provided with security door alarms.
Connected to Main System Magnetic Door/Alarm None Satellite Dish
Telephone Security Public Address Television
GENERAL BUILDING CONDITION
Rating
Comments:
X Good Fair Poor
Interior finishes on the second floor are in fair condition. Toilet and shower rooms are in usable but only fair condition. The arts & crafts room has water damage and is not utilized due to mold.
COMMUNICATION
The facility condition is not impacting the functional use of the facility.
The facility condition IS impacting the functional use of the facility.
The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.
Electric Water Gas No NoZone
BUILDING UTILITY METERING
Structure: Good Exterior: Good Interior: Fair Mechanical: Good Electrical: Good
Type Location None None
Comments: There are gas-fired appliances in the building.
BUILDING C - ADMINISTRATION
Page: 13 of 68
Building: C - ADMINISTRATION
BUILDING ENVELOPE
Foundation RoofBuilding
Concrete Loadbearing Masonry Wood
Brick Masonry
Wall Roof Unknown Rigid
Comments: The roof has batt insulation above the ceilings.
Metal Unit - Metal Frame Wood Unit - Metal Frame
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors
Residential/Business 14,890 10,117 3 Owned 1935 Not Evaluated
Comments: Building access is via non-compliant ramps.
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
No
No
No
Yes
Yes
Yes
Yes
No
N/A
No
No
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2. Number of Deficiencies = 1
Insulation4.
Exterior Doors5.
Material
A small section of the roof is asphalt shingle on a low-sloped gable.
Drainage Year Life
Remaining Type Area Served
Single Ply Gutters and Downspouts 1997 4 Flat Entire Building
Comments:
3. Roof
Page: 14 of 68
Building: C - ADMINISTRATION
INTERIOR FINISH
Carpet Ceramic Tile Vinyl Tile Wood
Ceramic Tile Drywall Plaster Wood Paneling
Wood Unit - Metal Frame
VERTICAL CIRCULATION
Concrete Stairs Metal Pan w/Concrete Stairs Metal Stairs
Fixed - Aluminum Frame; Single Glazing; Single Hung - Aluminum Frame; Single Glazing;
Single Hung - Vinyl Frame; Double Glazing;
12" X 12" Splined Acoustical Tile Gypsum Board
Windows6.
Floors1. Asbestos: Yes Number of Deficiencies = 1
Interior Walls2.
3.
Interior Doors4. Number of Deficiencies = 1
Page: 15 of 68
Building: C - ADMINISTRATION
Mechanical Toilet/Shower
Comments: Wall and ceiling-mounted exhaust fans ventilate the restrooms on the first and second floors.
Ventilation Area Served
Split Direct Expansion (Air
Cooled)
Packaged Direct
Expansion (Air Cooled)
Packaged Direct
Expansion (Air Source)
Single Duct
Single Duct
Window Unit
Refrigerant
None
None
Electric
Electric
Electric
Mechanical - Natural
Mechanical
Mechanical
None
None
None
Entire Building
Classrooms and Offices
Classrooms
Exhaust Ventilation
A vertical indoor constant volume air-handling unit with DX-cooling coils mounted on the discharge, located in the northeast mechanical room in Building B. The indoor unit is coupled with a roof-mounted condensing unit (Carrier model 38AK012, R-22 refrigerant, 10-ton, built in 08/2002) provides cooling to the first floor of this building.
Two rooftop-packaged units provide DX-cooling to the second and third floors. The unit (RTU-1) serving the second floor is a Carrier (model 50TJ-016, R-22 refrigerant, 15-ton capacity, built in 05/1999. The unit (RTU-2) serving the third floor is a Carrier (model 50TJ-024, R-22 refrigerant, 20-ton capacity, built in 04/1999).
Window air conditioning units provide supplemental DX-cooling to the server copying data room on the first floor and GED classrooms on the second floor. The typical unit is a LG (model LW2510ER, R- 401A refrigerant, 2-ton cooling capacity).
Comments:
Comments:
Comments:
Number of Deficiencies = 1
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
An Ajax gas-fired water boiler (model WGB-3000, S/N 89-41158, 3,000 MBH gas input, 2,400 output, 5 HP pump) provides heating water to the air-handling unit. The boiler is located in the basement of Building D. A vertical indoor constant volume, 2-pipe air-handling unit located in the northeast mechanical room in Building B, provides heating to the first floor of this building. The indoor unit is a Carrier (model 40RM-012-B600HC, 4,000 CFM, built in 05/1999).
An Ajax gas-fired water boiler (model WGB-3000, S/N 89-41158, 3,000 MBH gas input, 2,400 output, 5 HP pump) provides heating water to the air-handling unit. The boiler is located in the basement of Building D. There are two rooftop-packaged units with hot water coils provide heating to the second and third floors. The unit (RTU-1) serving the second floor is a Carrier model 50TJ-016, built in 05/1999. The unit (RTU-2) serving the third floor is a Carrier model 50TJ-024, built in 04/1999.
Ceiling-mounted electric heaters provide heating to the first floor restrooms.
Comments:
Comments:
Comments:
HVAC
Heat1.
Gas-Fired Hot Water Boiler
Gas-Fired Hot Water Boiler
Electric Resistance
Single Duct
Single Duct
Unit Heater
Two-Pipe
Two-Pipe
None
Electric
Electric
Electric
Natural
Mechanical
Natural
None
None
None
Offices
Classrooms and Offices
Rest Rooms
Ventilation2.
System Type
Number of Deficiencies = 1
Air Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area
Page: 16 of 68
Building: C - ADMINISTRATION
Three gas fired water heaters (two State model SBF75300, 75 gallon, 300 MBH input, 272.7 GPH recovery, built in 04/1998 and one Rheem model RF30091, 300 MBH gas input, 272.7 GPH recovery, built in 06/1993) provide domestic hot water to the first floor of Building B and portion of this building.
These are located in the northeast mechanical equipment room in Building B. The hot water loop has an in-line B&G circulating pump. In addition, there are two electric water heaters (Anguard, model IPZ81, 2 kW, 6-gallon capacity, built in 11/2005 and Rheem, model GE02P06SAG, 1.4 kW, 2.5-gallon capacity, built in 01/2011) provide domestic hot water to the men¿s and women¿s restrooms on the first and second floors. These units are located under the countertop.
Comments:
Cast Iron None None
Electric Water Cooler Hose Bibb Lavatory Portable Bottled Water Cooler Service Sink Shower Sink Water Closet (Tank)
None
Wet None ABC Type Fire Extinguisher
Comments: An automatic wet sprinkler system serves first floor only.
Comments: Service is brought from a 2000A switchgear located in the Building D mechanical room. Service terminates in an 600A main distribution panel (MDP) and two 200A disconnect switches located on the north exterior wall of Building C. This MDP serves loads in Building D via distribution panels located throughout the building.