Div00 - Front End.pdf
PDF 1 MB Posted
- Attached to
- Pre-Solicitation Notice Competitive 8(a) - SP-POL-SRM-Edwards AFB - MSS-Transfer line-Hydrant 3
- Solicitation number
- W9128F24R0053
About this file
This is a request for proposal for a construction project at Edwards Air Force Base in Kern County, California. The solicitation is open to all 8(a) participants and involves installing a positive meter, fencing, asphalt pavement, and replacing a diesel fuel storage tank at the Military Service Station. Proposals are due by 2:00 PM on April 9, 2024 and must be submitted electronically. The government will evaluate proposals based on the offeror's specialized experience with similar projects and the proposed construction schedule. The lowest priced technically acceptable proposal will be selected for award.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Title: SP-POL-SRM-Edw ards AFB - MSS-Transfer line-Hydrant 3
This solicitation is open to all 8(a) firms (SBA Requirement Number:MT1704488252E)
Location: Edw ards AFB, Kern County, CA
Scopt of Work w ill be sent in seperate attachment w ith other relatable attachments.
TIMOTHY B BOYTE 402-995-2589
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
12-Feb-2024
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________365 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________09 Apr 2024 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
W9128F
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W9128F24R0053 78
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W9128F24R0053
Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Facility 10902
FFP
Facility 10902 - (Fuel Pipeline) – (MC) – Includes all work to install meter at valve pit number 1.
FOB: Destination
PSC CD: Y1GC
NET AMT
0002 1 Job Facility 10103
FFP
Facility 10103 - (Hydrant 3) – (MC) – Includes all work to install fencing at Hydrant 3.
0003 1 Job Facility 10639
FFP
Facility 10639 - (Hydrant 3) – (MC) – Includes all work to install asphalt at Hydrant 3.
0004 1 Job Facility 10335
FFP
Facility 10335 - (Diesel Storage Tank) – (MR) – Includes all work to replace Diesel fuel tank at the Military Service Station, including platform(s) and stairs. Includes temporary Diesel fueling that meets all California regulations and follows what is stated in section 5.10 of the mechanical section within this scope of work.
0005 1 Job Facility 10366
FFP
Facility 10366 - (Liquid Fuel Stand, Unloading) – (MR) – Includes all work to replace the Diesel Truck Offload at the Military Service Station.
0006 1 Job Facility 10336
FFP
Facility 10336 - (Mogas Fuel Tank 4) – (MR) – Includes all work to replace Mogas fuel tank at the Military Service Station, including platform(s) and stairs. Includes temporary Mogas fueling that meets all California regulations and follows what is stated in section 5.10 of the mechanical section within this scope of work.
0007 1 Job Facility 10366
FFP
Facility 10366 - (Liquid Fuel Stand, Unloading) – (DEMO) – Includes all work to demolish truck offload associated with Mogas Tank 5 at the Military Service Station.
0008 1 Job Facility 10366
FFP
Facility 10366 - (Liquid Fuel Stand, Unloading) – (MR) – Includes all work to replace the Mogas Truck Offload associated with Mogas Tank 4 at the Military Service Station.
0009 1 Job OPTION Facility 10337
FFP
Facility 10337 - (Mogas Fuel Tank 5) – (MR) – Includes all work to replace Mogas fuel tank at the Military Service Station, including platform(s) and stairs.
The Government reserves the right to exercise the options within 60 days after issuance of Notice to Proceed. See FAR 52.217-5 Evaluation of Options. Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available. Exercising this option will not extend the period of performance..
CLAUSES INCORPORATED BY REFERENCE
52.217-5 Evaluation Of Options JUL 1990
NOTES
1. Offerors must insert a price on all numbered items of the CLIN pricing schedule. Prices include both design and construction. Failure to do so may result in the offer being unacceptable. Additions will be subject to verification by the Government. In case of variation between the Job (lump-sum) prices and the total amount, the lump-sum prices will be considered the price. In case of variation between the unit prices and the extensions, the unit prices will be considered the price submitted. Abbreviations: Minor Construction (MC); Maintenance and Repair (MR); Demolition (DEMO).
2. Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available.
Section 00 21 00 - Instructions
INSTRUCTION TO OFFERORS
1.1 SOLICITATION RESTRICTIONS
1.1.1 GENERAL CONTRACTOR
This solicitation is open to all 8(a) participants in accordance with SBA acceptance letter number: MT1704488252E
1.1.2 ESTIMATED CONSTRUCTION COST
The estimated construction cost of this project is between $5,000,000 and $10,000,000.
1.1.3 SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS
See FAR 52.215-1 INSTRUCTIONS TO OFFERORS-COMPETITIVE ACQUISTION, subparagraph "(c) Submission, modification, revision, and withdrawal of proposals."
below for acceptable methods. Note: Electronic commerce or facsimile are not acceptable methods, unless indicated otherwise.
1.1.4 SUBMISSION DEADLINE AND INSTRUCTIONS
Submit offers electronically, to Timothy Boyte, Contract Specialist, and Jae Chang, Contracting Officer, no later than the time and date as specified in Section 00 10 00, Page 1, in accordance with the instructions below.
1.1.4.1 Electronic Submission
Reference Section 00 22 00 EVALUATION CRITERIA for requirements.
1.1.5 RETURN ADDRESS REQUIREMENTS
Offeror(s) must ensure that ALL mail sent to the Omaha District, U.S. Army Corps of Engineers, either pre-contract or post-contract award, has a return mailing address on the outside of the envelope, package, box, etc. ANY MAIL addressed to the U.S. Army Corps of Engineers, including but not limited to bids, modifications to bids, proposals, revised proposals, bid guarantees, bonds, correspondence, etc., will be REJECTED by the US Army Corps of Engineers mail room facility located at 1616 Capitol Avenue, Omaha Nebraska 68102-4901 if it does not contain a return mailing address.
1.1.6 CAD AND ELECTRONIC DESIGN FILES (PROVIDED)
If provided, the CAD survey files and other electronic design files are provided on an as-is basis. Any Government provided survey, and the other electronic design files are provided to assist the Contractor in preparing their proposal using their own commercially purchased software. The Contractor shall take all professionally prudent and reasonable actions to verify the accuracy of the data provided and shall assume all liability from the use of these files. The Contractor shall be responsible for obtaining any other software necessary to view the files provided. No other CAD design files will be provided for proposal preparation other than those provided at the time of RFP issuance or an amendment. No assistance with the files will be provided
1.2 COPIES OF SOLICITATION DOCUMENT AND AMENDMENTS
Copies of the solicitation and amendments are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to the U.S. General Services Administration website at:
https://sam.gov/
It shall be the Contractor's responsibility to check the websites for any amendments.
The offeror shall submit in the proposal all requested information specified in this solicitation. There will be no public opening of the proposals received as a result of this solicitation.
A list of interested vendors (potential offerors and subcontractors) is available on the sam.gov web site listed above (registration required).
1.3 OFFEROR'S QUESTIONS AND COMMENTS
Questions and/or comments relative to these documents should be submitted via Bidder Inquiry as indicated below. See instructions on when e-mail or mailing is appropriate. Mailing address is shown on the Standard Form SF 1442, Item 8, unless directed otherwise.
Questions and/or comments relative to these bidding (proposal) documents that is proprietary in nature or if Bidder Inquiry system (See Below) is out of service should be submitted to the Contract Specialist:
Contract Specialist - Primary POC: Timothy Boyte Timothy.b.boyte@usace.army.mil
1.3.1 BIDDER INQUIRY
Technical inquiries and questions relating to technical requirements, proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at: https://www.projnet.org/projnet/ No Later Than ten (10) calendar days before due date of proposals, in order that they may be given consideration or actions taken prior to receipt of offers. The Bidder Inquiry system is to be used to ask and receive answers to all non-proprietary questions.
To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team.
All timely questions and approved answers will be made available through ProjNet.
The Solicitation Number is: W9128F24R0053 The Bidder Inquiry Key is: 3HCJE8-ZYZNVZ
a. Registration for ProjNet Bidder Inquiry Access
If you are already registered, go to Entering Bidder Inquiries in ProjNet Bidder Inquiry System below.
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Email. Enter the email address you would like to use for communication.
5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
b. Entering Bidder Inquiries in ProjNet Bidder Inquiry System
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address you used to register previously in ProjNet.
6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
8. Follow online screen instructions to enter specific bidder inquiries for the project.
c. The Bidder Inquiry System will be unavailable for new inquires after ten
(10) calendar days before due date of proposals in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
d. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone
(Chicago). The telephone number for the Call Center is 800-428-HELP.
f. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.
1.3.2 PLAN HOLDER'S LIST
For Viewing a List of Interested Vendors (i.e. planholders List) and Receiving Notifications or e-mail of changes regarding a solicitation, U.S. General Services Administation has these features available ( https://sam.gov/). For this solicitation, go to https://sam.gov/ and register as a vendor or enter user name and password to login. If you wish for General Contractors, Subcontractors, Suppliers, Plan Rooms or Print Shops to have the ability to contact you, click on the "Add me to Interested Vendors" for the solicitation.
1.4 GENERAL DESCRIPTION OF WORK
Scope of project includes all work required to install positive meter, fencing, asphalt pavement, and replace diesel fuel storage tank at the Military Service Station located at Edwards AFB, California. Work shall be in accordance with Request for Proposal documents issued with this solicitation.
1.5 PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION AND CONTRACT AWARD See
Section 00 22 00 EVALUATION CRITERIA.
1.6 SOURCE SELECTION BOARD (SSB)
The Proposal evaluation will be based exclusively on the merits and content of the proposal and any subsequent discussion required.
1.7 FEDERAL, STATE AND LOCAL TAXES
It is the Contractor's responsibility to investigate applicable federal, state and local taxes and any specific exemptions that may exist. This includes any applicable Value-Added Taxes (VAT), sales, use, and excise taxes. See General Conditions (Contract Clause) 52.229-3 FEDERAL, STATE AND LOCAL TAXES.
1.8 TAXES - STATE OF CALIFORNIA
1.8.1 EXCISE TAX
There is an excise tax on the total gross receipts of all prime contractors and subcontractors engaged in realty improvement contracts.
1.8.2 USE TAX
Government furnished construction material used by the Contractor in the performance of the work is subject to use tax. The value of the material furnished is set forth in the SECTION 01 30 00.24 OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS provision "Government Furnished Property."
1.8.3 INFORMATION
The "excise" and "use" taxes shall be included in the price or prices bid. For information concerning the taxes contact: http://dor.sd.gov/
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT
USED)
-- End of Section --
52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.211-2 Availability of Defense Specifications, Standards, and Data
Item Descriptions in the Acquisition Streamlining and Standardization Information System (ASSIST) Website
SEP 2023
52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.215-16 Facilities Capital Cost of Money JUN 2003 52.222-5 Construction Wage Rate Requirements--Secondary Site of the
Work
MAY 2014
52.225-10 Notice of Buy American Requirement--Construction Materials
MAY 2014
52.225-12 Notice of Buy American Requirement - Construction Materials Under Trade Agreements
MAY 2014
252.204-7008 Compliance With Safeguarding Covered Defense Information Controls
OCT 2016
252.215-7008 Only One Offer DEC 2022 252.215-7013 Supplies and Services Provided by Nontraditional Defense
Contractors
JAN 2023
CLAUSES INCORPORATED BY FULL TEXT
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
(End of provision)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
The government will hold an organized site visit on Tuesday, March 5, 2024, at 1000 local time.
(c) Participants will meet at—
Edwards AFB Visitor Center (west gate), 1004 Rosamond Blvd RSVP to the POC listed by close of business on Friday, March 1, 2024.
Richard.morris.6@us.af.mil (Cc: Seth.A.Kiely@usace.army.mil ) – Subject: MSS, Transfer Line, Hydrant 3 Contractor Site Visit.
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any Defense Federal Acquisition Regulation (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
Section 00 22 00 - Supplementary Instructions
EVALUATION CRITERIA
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 22 00
REQUEST FOR PROPOSAL (RFP)
W9128F-24-R-0053
INSTRUCTIONS, SUBMISSION REQUIREMENTS AND EVALUATION
1. WHO MAY SUBMIT
This solicitation is available to all 8(a) participants.
2. GENERAL REQUIREMENTS
In order to effectively and equitably evaluate the submitted proposal, the Contracting Officer must receive information sufficiently detailed to clearly indicate compliance with the proposal submission requirements. The price proposal submitted in response to this request will be evaluated using one or more of the proposal analysis techniques identified in FAR 15.404-1(b).
The government will hold an organized site visit on Tuesday, March 5, 2024, at 1000 local time. Participants will meet at the following location:
Edwards AFB Visitor Center (west gate), 1004 Rosamond Blvd RSVP to the POC listed by close of business on Friday, March 1, 2024.
Richard.Morris.6@us.af.mil (Cc: Seth.A.Kiely@usace.army.mil) – Subject: MSS, Transfer Line, Hydrant 3 Contractor Site Visit.
3. SUBMISSION DEADLINE
Proposals shall be received by the USACE Contracting Activity no later than 1400 CST, Tuesday, April 9, 2024. Proposals shall be submitted electronically to the contract Specialist per the instructions in Section 00 21 00.
Contract Specialist: timothy.b.boyte@usace.army.mil Contracting Officer: Jae.H.Chang@usace.army.mil
4. SUBMITTAL REQUIREMENTS
8.5”x 11” page size; font no smaller than font 10 size. The requirements specified in the solicitation are considered minimum requirements. A proposal that fails to comply with the minimum technical and submittal requirements may not be eligible for award. Submit no more than three (3) pages (single sided) for Volume 1, Factor 1, and submit a Gantt Chart for Factor 2.
SUBMITTAL REQUIREMENTS
Volume 1: Technical Proposal Factor 1: Specialized Experience Factor 2: Proposed Contract Duration and Summary Schedule Volume 2 Pricing Factor 3: Price
IT IS IMPERATIVE THAT NONE OF THE PRICING OR VOLUME 2 INFORMATION SHOW UP IN
VOLUME 1.
4.1 VOLUME 1: TECHNICAL (VOLUME 1) SUBMISSION REQUIREMENTS
4.1.1 Factor 1: SPECIALIZED EXPERIENCE
1. Offeror shall submit a maximum three (3) projects, completed within the last 7 years from the date of this RFP that collectively show the following work activities. The Government will accept performance by the prime contractor or its key subcontractor/teaming partner. One project shall be from the prime contractor. All projects submitted must show demonstrated experience IAW UFC 3-460-01 & AW 78-24-28.
2. Installation of positive displacement meter, and piping IAW UFGS 33 52 43.13.
3. Installation of security fencing and gates for DoD.
4. Replacement of asphalt cement concrete IAW DoD specification UFGS 32 12
16.
5. Installation or replacement of UL 2085 10,000 – 20,000 gal above ground storage tank IAW DoD specifications listed herein.
6. Installation or replacement of DoD fueling truck offload.
a. Project total cost, at completion, shall total $1,000,000 or greater for each project.
b. The submitted project experience shall include:
1. description of the project and location
2. final construction cost
3. date when the construction of the project was completed.
4.1.2 Factor 2: PROPOSED CONTRACT DURATION AND SUMMARY SCHEDULE Based on your understanding of the RFP requirements, provide a schedule Gantt chart showing Phase 1 (Preconstruction Phase), Phase 2 (On-site Construction) and Phase 3 (Post Construction) in accordance with mandatory scheduled performance of 365 calendar days.
The schedule should present the requirements to complete the required design and field work. It must include all milestones and durations, to include:
1. All necessary permits, licenses, and certificates
2. Site specific contractor management plans
3. Key Work Breakdown Structure (WBS) activities
4. Long lead procurements (i.e., Portland Cement Concrete (PCC) Mix
Design, etc.)
5. Critical path, starting with award and ending at project closeout.
6. Simultaneous and concurrent activities
7. Construction sequence (phasing is required, temporary fueling required at time of NTP) If there are no long lead procurements, state this on the project schedule.
For scheduling purposes assume the contract award is Thursday, May 23, 2024, with NTP approximately 2 weeks later.
4.2 TECHNICAL EVALUATION
Pricing data will not be part of the technical evaluation. Criteria for the technical evaluation set forth in the solicitation will be sole basis for determining the technical merit of proposals. Factor(s) listed above will be assigned a technical evaluation of “Acceptable” or “Unacceptance”
Adjectival Rating Description Acceptable Proposal meets the requirement of the solicitation Unacceptable Proposal does not meet the requirement of the solicitation
Factor 1: Specialized Experience Experience that does not show the collective work activities on the submitted projects will be deemed unacceptable.
Submissions which do not demonstrate a complete representation of the criteria listed above will be evaluated as Unacceptable.
Factor 2: Proposed Contract Duration and Summary Schedule The Government will evaluate the contractor’s understanding of the requirements of the design and construction as portrayed in your schedule Gantt chart. Requirements to be evaluated include but are not limited to demonstrated complete and logical scheduling of milestones and durations for Phase 1 (Preconstruction Phase), Phase 2 (On-Site Construction) and Phase 3 (Post Construction). Submissions which demonstrate a complete and logical schedule will be evaluated as Acceptable. Submissions that are incomplete, illogical or lack thought out phasing will be evaluated as Unacceptable.
Omission of requested information will be evaluated as Unacceptable.
4.3 VOLUME 2: PRICING SUBMISSION REQUIRMENTS
4.3.1 Factor 3: Price
The pricing proposal shall contain the following information:
a. Section 00 10 00, Solicitation/Contract Form and Pricing Schedule
4.4 PRICE EVALUATION
The price proposal submitted in response to this request will be evaluated using one or more of the proposal analysis techniques identified in FAR 15.404-1(b). Contract award will be made to the proposal found to be the lowest price technically acceptable to the Government in accordance with FAR 52.217-5 Evaluation of Options.
5. EVALUATION FOR AWARD
Lowest Price Technically Acceptable (LPTA) will be the proposal evaluation used for award. Uniformity of the proposal is essential to assure accurate evaluation. Proposal must comply with the instructions in the solicitation.
The lowest priced proposal will be evaluated to determine technically acceptable contractor(s). If the lowest proposed offer is determined to be technically acceptable, the Government reserves the right to not evaluate the technical proposal(s) submitted by the other offeror(s). A proposal that fails to comply with any minimum technical requirements will not be eligible for award regardless that it may offer the lowest price.
Any Factor evaluated as “Unacceptable” in any TAB will render the complete technical portion of the offer as “Unacceptable”. No further evaluation will be made on the Offeror’s proposal, including price.
6. SELECTION AND AWARD WITHOUT EXCHANGES
It is the intent of the Government to make award based upon initial offers.
Proposals are intended to be evaluated, and award made, without exchanges with the offerors, unless exchanges are determined to be necessary.
Section 00 45 00 - Representations and Certifications
52.204-8 Annual Representations and Certifications MAR 2023 52.204-24 Representation Regarding Certain Telecommunications and
Video Surveillance Services or Equipment
NOV 2021
52.209-7 Information Regarding Responsibility Matters OCT 2018 52.209-13 Violation of Arms Control Treaties or Agreements --
Certification
NOV 2021
52.236-28 Preparation of Proposals--Construction OCT 1997 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
SEP 2022
252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation
DEC 2019
252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation
MAY 2021
252.225-7050 Disclosure of Ownership or Control by the Government of a Country that is a State Sponsor of Terrorism
DEC 2022
52.204-17 OWNERSHIP OR CONTROL OF OFFEROR (AUG 2020)
(a) Definitions. As used in this provision--
Commercial and Government Entity (CAGE) code means—
(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity by unique location; or
(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support and Procurement Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Commercial and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as a NATO CAGE (NCAGE) code.
Highest-level owner means the entity that owns or controls an immediate owner of the offeror, or that owns or controls one or more entities that control an immediate owner of the offeror. No entity owns or exercises control of the highest level owner.
Immediate owner means an entity, other than the offeror, that has direct control of the offeror. Indicators of control include, but are not limited to, one or more of the following: Ownership or interlocking management, identity of interests among family members, shared facilities and equipment, and the common use of employees.
(b) The Offeror represents that it [ ___ ] has or [ ___ ] does not have an immediate owner. If the Offeror has more than one immediate owner (such as a joint venture), then the Offeror shall respond to paragraph (c) and if applicable, paragraph (d) of this provision for each participant in the joint venture.
(c) If the Offeror indicates ``has'' in paragraph (b) of this provision, enter the following information:
Immediate owner CAGE code:
Immediate owner legal name: ___
(Do not use a ``doing business as'' name)
Is the immediate owner owned or controlled by another entity?:
[ ___ ] Yes or [ ___ ] No.
(d) If the Offeror indicates ``yes'' in paragraph (c) of this provision, indicating that the immediate owner is owned or controlled by another entity, then enter the following information:
Highest-level owner CAGE code:
Highest-level owner legal name:
(Do not use a ``doing business as'' name)
52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES--REPRESENTATION (OCT
2020)
(a) Definitions. As used in this provision, “covered telecommunications equipment or services” and "reasonable inquiry" have the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.
(c) Representations.
(1) The Offeror represents that it [ ___ ] does, [ ___ ] does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.
(2) After conducting a reasonable inquiry for purposes of this representation, the offeror represents that it [ ___ ] does, [ ___ ] does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.
252.204-7007 ALTERNATE A, ANNUAL REPRESENTATIONS AND CERTIFICATIONS (NOV 2023)
Substitute the following paragraphs (b), (d) and (e) for paragraphs (b) and (d) of the provision at FAR 52.204-8:
(b)(1) If the provision at FAR 52.204-7, System for Award Management, is included in this solicitation, paragraph
(e) of this provision applies.
(2) If the provision at FAR 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (e) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
__ (i) Paragraph (e) applies.
__ (ii) Paragraph (e) does not apply and the Offeror has completed the individual representations and certifications in the solicitation.
(d)(1) The following representations or certifications in the SAM database are applicable to this solicitation as indicated:
(i) 252.204-7016, Covered Defense Telecommunications Equipment or Services--Representation. Applies to all solicitations.
(ii) 252.216-7008, Economic Price Adjustment--Wage Rates or Material Prices Controlled by a Foreign Government. Applies to solicitations for fixed-price supply and service contracts when the contract is to be performed wholly or in part in a foreign country, and a foreign government controls wage rates or material prices and may during contract performance impose a mandatory change in wages or prices of materials.
(iii) 252.225-7042, Authorization to Perform. Applies to all solicitations when performance will be wholly or in part in a foreign country.
(iv) 252.225-7049, Prohibition on Acquisition of Certain Foreign Commercial Satellite Services--Representations.
Applies to solicitations for the acquisition of commercial satellite services.
(v) 252.225-7050, Disclosure of Ownership or Control by the Government of a Country that is a State Sponsor of Terrorism. Applies to all solicitations expected to result in contracts of $150,000 or more.
(vi) 252.229-7012, Tax Exemptions (Italy)--Representation. Applies to solicitations when contract performance will be in Italy.
(vii) 252.229-7013, Tax Exemptions (Spain)--Representation. Applies to solicitations when contract performance will be in Spain.
(viii) 252.247-7022, Representation of Extent of Transportation by Sea. Applies to all solicitations except those for direct purchase of ocean transportation services or those with an anticipated value at or below the simplified acquisition threshold.
(2) The following representations or certifications in SAM are applicable to this solicitation as indicated by the Contracting Officer: [Contracting Officer check as appropriate.]
____ (i) 252.209-7002, Disclosure of Ownership or Control by a Foreign Government.
____ (ii) 252.225-7000, Buy American--Balance of Payments Program Certificate.
____ (iii) 252.225-7020, Trade Agreements Certificate.
____ Use with Alternate I.
____ (iv) 252.225-7031, Secondary Arab Boycott of Israel.
____ (v) 252.225-7035, Buy American--Free Trade Agreements--Balance of Payments Program Certificate.
____ Use with Alternate I.
____ Use with Alternate II.
____ Use with Alternate III.
____ Use with Alternate IV.
____ Use with Alternate V.
____ (vi) 252.226-7002, Representation for Demonstration Project for Contractors Employing Persons with Disabilities.
____ (vii) 252.232-7015, Performance-Based Payments--Representation.
(e) The Offeror has completed the annual representations and certifications electronically via the SAM website at https://www.sam.gov. After reviewing the SAM database information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in FAR 52.204-8(c) and paragraph (d) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer, and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [Offeror to insert changes, identifying change by provision number, title, date____]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
FAR/DFARS provision No.
Title Date Change
Any changes provided by the Offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications located in the SAM database.
Section 00 72 00 - General Conditions
52.202-1 Definitions JUN 2020 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government JUN 2020 52.203-7 Anti-Kickback Procedures JUN 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
JUN 2020
52.203-13 Contractor Code of Business Ethics and Conduct NOV 2021 52.203-13 Contractor Code of Business Ethics and Conduct NOV 2021 52.203-17 Contractor Employee Whistleblower Rights NOV 2023 52.204-2 Alt II Security Requirements (MAR 2021) - Alternate II APR 1984 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber
Content Paper
MAY 2011
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
JUN 2020
52.204-13 System for Award Management Maintenance OCT 2018 52.204-14 Service Contract Reporting Requirements OCT 2016 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.204-21 Basic Safeguarding of Covered Contractor Information Systems
NOV 2021
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment
NOV 2021
52.204-27 Prohibition on a ByteDance Covered Application JUN 2023 52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for Debarment
NOV 2021
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
OCT 2018
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.210-1 Market Research NOV 2021 52.211-13 Time Extensions SEP 2000 52.211-18 Variation in Estimated Quantity APR 1984 52.219-8 Utilization of Small Business Concerns SEP 2023 52.222-1 Notice To The Government Of Labor Disputes FEB 1997 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards - Overtime
Compensation
MAY 2018
52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records JUL 2021 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014
52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.222-35 Equal Opportunity for Veterans JUN 2020 52.222-36 Equal Opportunity for Workers with Disabilities JUN 2020 52.222-37 Employment Reports on Veterans JUN 2020 52.222-40 Notification of Employee Rights Under the National Labor
Relations Act
DEC 2010
52.222-50 Combating Trafficking in Persons NOV 2021 52.222-54 Employment Eligibility Verification MAY 2022 52.222-55 Minimum Wages for Contractor Workers Under Executive
Order 14026
JAN 2022
52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2022 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
SEP 2013
52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-11 Ozone-Depleting Substances and High Global Warming
Potential Hydrofluorocarbons.
JUN 2016
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
AUG 2018
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
JUN 2020
52.223-20 Aerosols JUN 2016 52.223-21 Foams JUN 2016 52.224-3 Privacy Training JAN 2017 52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.227-1 Authorization and Consent JUN 2020 52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
JUN 2020
52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 (Dev) Individual Surety--Pledge of Assets (DEVIATION 2020-
O0016)
FEB 2021
52.228-12 Prospective Subcontractor Requests for Bonds DEC 2022 52.228-15 Performance and Payment Bonds--Construction JUN 2020 52.229-3 Federal, State And Local Taxes FEB 2013 52.229-11 Tax on Certain Foreign Procurements--Notice and
Representation
JUN 2020
52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-17 Interest MAY 2014 52.232-18 Availability Of Funds APR 1984 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
MAR 2023
52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996
52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007 52.244-6 Subcontracts for Commercial Products and Commercial
Services
DEC 2023
52.246-12 Inspection of Construction AUG 1996 52.246-13 Inspection--Dismantling, Demolition, or Removal of
Improvements
AUG 1996
52.246-21 Warranty of Construction MAR 1994 52.248-3 Value Engineering-Construction OCT 2020 52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (Apr 2012) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
JAN 2023
252.203-7002 Requirement to Inform Employees of Whistleblower Rights DEC 2022 252.203-7003 Agency Office of the Inspector General AUG 2019 252.203-7004 Display of Hotline Posters JAN 2023 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Antiterrorism Awareness Training for Contractors JAN 2023 252.204-7012 Safeguarding Covered Defense Information and Cyber
Incident Reporting
JAN 2023
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
JAN 2023
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2023
252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.204-7020 NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.204-7021 Contractor Compliance with the Cybersecurity Maturity
Model Certification Level Requirement
JAN 2023
252.204-7022 Expediting Contract Closeout MAY 2021 252.205-7000 Provision Of Information To Cooperative Agreement Holders JUN 2023
252.209-7004 Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of Terrorism
MAY 2019
252.222-7006 Restrictions on the Use of Mandatory Arbitration Agreements JAN 2023 252.223-7004 Drug Free Work Force SEP 1988 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.223-7008 Prohibition of Hexavalent Chromium JAN 2023 252.225-7048 Export-Controlled Items JUN 2013 252.227-7023 Drawings and Other Data to become Property of Government MAR 1979 252.227-7033 Rights in Shop Drawings APR 1966 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2022 252.244-7000 Subcontracts for Commercial Products or Commercial
Services
NOV 2023
252.247-7023 Transportation of Supplies by Sea JAN 2023
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 365 days after receipt of Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $760.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.219-14 LIMITATIONS ON SUBCONTRACTING (DEVIATION 2021-O0008) (FEB 2023)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Definition. “Similarly situated entity,” as used in this clause, means a first-tier subcontractor, including an independent contractor, that—
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.
(c) Applicability. This clause applies only to—
(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;
(4) Orders expected to exceed the simplified acquisition threshold and that are—
(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);
(5) Orders, regardless of dollar value, that are—
(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and
(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.
(d) Independent contractors. An independent contractor shall be considered a subcontractor.
(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for—
(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding certain other direct costs and certain work performed outside the United States (see paragraph (e)(1)(i)), to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded.