Digester_4_and_Digested_Sludge_Storage_Tank_Rehabilitation.pdf

PDF 409 KB Posted

Attached to
Digester 4 and Digested Sludge Storage Tank Rehabilitation
Solicitation number
RFQ for CMAR-26-011
Issued by
Maricopa County, Tucson City, Arizona

About this file

This is a Scope of Work document for the City of Tolleson, Arizona, regarding the rehabilitation of Digester 4 and Digested Sludge Storage Tank at the City's wastewater treatment facility. The City is requesting Statements of Qualifications from qualified Construction Manager at Risk (CMAR) firms to manage and execute the rehabilitation project. The scope encompasses structural repairs, coating restoration, and tank rehabilitation work necessary to restore the digester and storage tank to operational condition. The project involves coordination with City staff, compliance with environmental and safety regulations, and adherence to design specifications provided in the contract documents.

The project requires the selected CMAR firm to demonstrate experience in similar wastewater infrastructure rehabilitation projects, particularly involving digesters and storage tank work. Pricing will be determined through the CMAR procurement process, which typically involves a fee for services separate from actual construction costs. The funding source and total project budget are contingent upon City of Tolleson appropriations and grant funding availability. The contractor must provide comprehensive project management, scheduling, quality assurance, and coordination with all subcontractors and City departments throughout the rehabilitation period.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For more information, please visit our online supplier portal, located at https://procurement.opengov.com/portal/tollesonaz

The City of Tolleson

CONSTRUCTION MANAGER AT RISK

RFQ for CMAR-26-011

DIGESTER 4 AND DIGESTED SLUDGE STORAGE TANK REHABILITATION

RELEASE DATE: November 24, 2026

RESPONSE DEADLINE: January 14, 2027, 3:00 pm

Please refer to the project timeline in this document for all important deadlines.

CONSTRUCTION MANAGER AT RISK RFQ for CMAR-26-011 Title: Digester 4 and Digested Sludge Storage Tank Rehabilitation

Table Of Contents

1. NOTICE

2. INSTRUCTIONS

3. GENERAL DESCRIPTION OF PROJECT

4. PROJECT SCOPE

5. SELECTION PROCESS

6. EVALUATION CRITERIA

7. GENERAL INFORMATION

8. SUBMITTAL REQUIREMENTS

Attachments:

A - CMAR_03.04_Pre-Construction_Services_Contract

B - CMAR_03.05_Construction_Services_Contract_for_CMAR

C - CMAR_03.06_General_Conditions_for_CMAR

D - EPA_Region_9_-_Situation_Specific_Contract_Provisions_and_Sample_Language

E - Appendix_II_to_Part_200__Title_2_(up_to_date_as_of_10-08-2026)

F - Tolleson Digester 4 DSST Rehab 100% Drawings

1. NOTICE

NOTICE AND REQUEST FOR QUALIFICATIONS

FOR

Digester 4 and Digested Sludge Storage Tank Rehabilitation

FOR THE CITY OF TOLLESON

The City of Tolleson requests Statements of Qualifications from qualified Construction Manager at Risk

(CMAR) firms to provide Rehabilitation of Digester 4 and Digested Sludge Storage Tank.

You may download this Request for Qualifications (RFQ) and related form contract from the OpenGov

Procurement Portal. Go to https://procurement.opengov.com/portal/tollesonaz/projects/288297, then click

Digester 4 and Digested Sludge Storage Tank Rehabilitation link to access the RFQ documents.

The Statement of Qualifications (SOQ) must be received electronically via the OpenGov Procurement Portal prior to the submission deadline. All submittals must be fully uploaded no later than 3:00 pm (local time, Phoenix, AZ), Thursday, January 14, 2027.

LATE STATEMENTS OF QUALIFICATIONS WILL NOT BE ACCEPTED.

DIRECT CONTACT WITH SELECTION COMMITTEE MEMBERS OR ANY CITY EMPLOYEE CONCERNING THIS RFQ

AT ANY TIME IS STRICTLY PROHIBITED.

Notice Given By: Crystal Zamora

City Clerk

Tuesday, November 24, 2026

Published in the: Arizona Business Gazette

November 26, 2026

December 3, 2026 https://procurement.opengov.com/portal/tollesonaz/projects/288297

2. INSTRUCTIONS

Interested firms shall submit all required items outlined in the SUBMITTAL REQUIREMENTS section of this

Request for Qualifications through the City's e-Procurement, OpenGov portal no later than 3:00 pm (local time, Phoenix, AZ), Thursday, January 14, 2027.

All inquiries shall be submitted through the OpenGov portal.

3. GENERAL DESCRIPTION OF PROJECT

The City of Tolleson’s Wastewater Treatment Plant located at 9501 W. Pima Road, Tolleson, AZ 85353, is currently rated at 17.5 million gallons per day (mgd) and treats wastewater from residential, industrial and commercial development. This project will undertake rehabilitation of Digester 4 and the Digested Sludge

Storage Tank (DSST) to increase solids stabilization capacity and improve redundancy, per the plans provided in Exhibit F. The project must be completed by June 30, 2028.

One contract may be awarded. One firm may be awarded the contract. There will be a single final list of at least three (3) but not more than five (5) firms.

The work to be performed includes the furnishing of all labor, materials, and equipment for the supply, delivery, fabrication, installation, testing, and other materials and services required for the project. Specific features include, but are not limited to:

1. Digester 4

• Demolish existing Digester 4 gas compressor assembly, heat exchange and associated piping and appearances.

• Clean and coat Digester 4 interior.

• Provide new concrete cover at Digester 4

• Provide new pumped mixing system at Digester 4.

• Provide new sludge circulation pump, heat exchanger, and hot water pumps at Digester 4.

• Provide digester gas sediment trap, PVRV assembly, and other gas handling equipment at Digester 4.

• Provide new digester gas piping for Digester 4 including pipe bridge across access road.

2. DSST

• Demolish existing DSST circulation pump.

• Clean and coat the DSST interior walls.

• Provide new concrete cover at the DSST.

• Provide new pumped mixing system at the DSST.

• Provide new PVRV assembly, sediment trap, and emergency relief hatch at the DSST.

• Provide new digester gas piping for the DSST and connect to the existing digester gas piping system.

3. Waste Gas Burner (Federally Funded)

• Demolish existing candlestick Waste Gas Burner and associated equipment.

• Provide new enclosed waste gas burner and associated equipment including control panel, flame trap, backpressure regulating valve, and drip traps.

4. Electrical

• Replace existing MCC-6.

• Modify existing MCC-6A.

By selecting the CMAR delivery method for this project, the Owner expects the CMAR to collaborate closely with the Owner and Engineer during the pre-construction phase to develop a mutually agreeable guaranteed maximum price (GMP) for delivery of the project. The Owner also expects the CMAR to perform construction phase services for the improvements. Other project-specific objectives include:

• Quality Assurance: Deliver a high-quality project consistent with construction drawings and specifications and built to high standards.

• Cost Certainty: Minimize capital and lifecycle costs. Establish a guaranteed maximum price to control budget and limit financial exposure. Provide regular cost estimate updates with the project team to track cost and compare the cost to the available budget.

• Schedule Optimization: Achieve the schedule completion dates of the Project.

• Risk Management: Achieve an optimal balance of risk allocation between Owner and CMAR while maintaining collaboration.

• Safety Performance: Implement an effective safety program incorporating industry best practices to protect workers, City staff and the community.

• Early Contractor Involvement: Gain constructability input during design to reduce risks and improve efficiency.

• Value Engineering: Drive innovation and identify efficient solutions to reduce lifecycle costs.

• Dispute Avoidance: Reduce disputes through shared goals and open communication.

• Federal Compliance: Complete the Project according to the federal and state funding requirements such as Davis-Bacon, Disadvantaged Business Enterprise, American Iron and Steel, and the Build

America Buy America Act. (Situation Specific Contract Provisions and Sample Language included in

Attachments.)

• Ensure compliance with all applicable EPA - Community Grant funding requirements and 2 CFR Part

200 Uniform Guidance. (Situation Specific Contract Provisions and Sample Language included in

Attachments.)

4. PROJECT SCOPE

4.1. Scope of Work

The City of Tolleson intends to procure a Construction Manager at Risk to construct the improvements described in Section 3. This project will be constructed pursuant to A.R.S. 34-601 et seq. The total program budget for the project is approximately $12,000,000.00, including internal and external costs. The project has a federal funding component through EPA’s Community Grant Program, that is applicable to the Waste Gas

Burner.

The CMAR services will be single-phase qualifications selection for a two-phase CMAR delivery contract.

The first contract, will include the pre-construction services and the preparation and submission of the

Guaranteed Maximum Price (GMP). The selected CMAR will be required to execute a Pre-Construction

Services Contract substantially in the form of Attachment A and, if a GMP acceptable to the City of Tolleson is submitted, a Construction Services Contract substantially in the form of Attachment B, together with the

General Conditions for CMAR in Attachment C.

The selected CMAR will execute a contract with the City of Tolleson to provide pre-construction services of the project as follows:

• CMAR will provide value analysis services, value engineering, and offer cost savings suggestions and best value recommendations.

• CMAR will provide constructability review.

• CMAR will submit a Construction Guaranteed Maximum Price (GMP) to the City of Tolleson.

• The CMAR will act as the City of Tolleson’s fiduciary and have a relationship of trust and confidence between itself and the City of Tolleson. For that reason, the Project will be an “open book” job whereby the city of Tolleson may attend any and all meetings of the CMAR firm relating to the Project and have access to any and all books and records of the CMAR relating to the Project.

After CMAR has submitted a Construction Guaranteed Maximum Price acceptable to the City of Tolleson, CMAR and the City of Tolleson may execute a second contract for complete construction services for the construction of the project. The CMAR will assume the risk of delivering the Project through a guaranteed maximum price contract. The CMAR will be responsible for construction means and methods. The CMAR shall self-perform at least 45% of the total contract price for construction.

5. SELECTION PROCESS

The City reserves the option to conduct interviews with the highest scoring respondents based upon the initial

Statement of Qualifications evaluation.

In the event the City chooses to conduct interviews, the interview evaluation criteria will be provided to the respondents selected for interview.

Selection Committee: A Selection Committee will review the Statements of Qualifications.

Each firm will then be ranked accordingly.

No interviews are planned.

Contract Negotiation: Upon completion of the final rankings, the City of Tolleson will enter into negotiations with the highest ranked firm for a pre-construction phase services contract for the Project. If a contract cannot be successfully negotiated with the highest ranked firm, then negotiations will be terminated with that firm and the City of Tolleson will enter into negotiations with the next highest ranked firm until an agreement is reached or an impasse is declared.

Key Personnel: The Firm shall ensure that Key Personnel identified in its SOQ shall be the Key Personnel assigned to the project. Such Key Personnel shall not be replaced without prior written acceptance of the City of Tolleson. Unauthorized replacements will result in disqualification of the SOQ or breach of the Pre-

Construction Services Contract (Attachment A).

6. EVALUATION CRITERIA

Each SOQ will be evaluated according to the following criteria:

No. Evaluation Criteria Scoring Method Weight (Points)

1. Project Understanding:

Understanding of Project Approach to Performing the Required

Services:

• Describe your firm’s understanding of the City’s need for this project, including project issues and challenges.

• Discuss the major issues your firm has identified on this project and how you intend to address those issues.

• Describe how the team will accommodate existing constraints.

• Identify the work components critical to the project’s success and how these components would be achieved.

• Describe systems used for scheduling, estimating and managing construction. Briefly describe the firm’s experience on quality control, dispute resolution, and safety management,

• Provide a preliminary project schedule that reflects an "ideal" timeline

Points Based 25

(25% of Total) for GMP preparation and construction.

2. Identification of Risks and Value

Add Options

Identification of Risks and Value

Add Options:

• List and prioritize major risk items that are unique to this project. This includes areas that may cause the project to not be completed on time, not finished within budget, or may be a source of dissatisfaction for the

City. Explain how the CMAR will avoid/minimize the risk.

• Describe any innovative approaches or concepts that will allow the project schedule to be expedited.

• Describe the firm's troubleshooting processes when integrating new infrastructure into an existing operational system.

Points Based 25

(25% of Total)

3. Experience and Qualifications of the Firm:

Experience and Qualifications of the Firm:

• Identify at least three comparable municipal projects, in the last 5-years, in which the firm served as either Construction

Manager at Risk, or/

General Contractor.

• For each comparable project identified, provide:

A. Description of project.

B. Role of the firm (specify whether Construction

Manager at Risk, Construction Manager or

General Contractor). If CM at Risk or General

Contractor, identify the percent of work self-performed. Also specify services provided during design phase, (cost of estimating, scheduling, value engineering, etc.)

C. Project’s original contracted construction cost and final construction cost.

D. Team members and role.

E. Construction dates.

F. Project Owner.

Points Based 20

(20% of Total)

G. Reference information (two names with telephone numbers per project).

4. Firm/Team - General Information

Firm/Team - General Information

• Provide a general description of the firm / team that is proposing to provide the construction services described herein.

Explain the legal organization of the proposed firm or team. Provide an organization chart showing key personnel. List the names of the key persons who will be providing the services describing the services each will provide.

• Provide the following information:

(A) List the Arizona professional and contractor licenses held by the firm and/or individuals who will be assigned to this project. Provide the license numbers and expiration dates, if applicable. The contractor need not be licensed, but the person or firm actually performing construction services on behalf of the contractor must be currently, and have been for at least one year immediately prior, a licensed general contractor in the State of

Arizona.

(B) Identify any contract or subcontract held by the firm or officers of the firm, which has been

Points Based 10

(10% of Total) terminated within the last five years. Identify any claims arising from a contract which resulted in a formal claim being filed with a public entity pursuant to A.R.S. 12-

821.01 or has resulted in litigation or arbitration within the last five years. Briefly describe the circumstances and the outcomes.

(C) Provide a statement from an

AM Best, Inc. rating of A or better surety company of the Company’s bonding capacity. Unless otherwise required by the public records law, this information will be confidential and will not be made part of the public record.

5. Experience of Key Personnel:

Experience of key personnel assigned to this project:

• For each key person identified, list at least two comparable projects in which they have played a primary role. If a project selected for a key person is the same as one selected for the firm, provide just the project name and role of the key person. For other projects provide:

A. Description of project.

B. Role of the person.

C. Project’s original contracted construction cost and final construction cost.

D. Construction dates.

E. Project Owner.

F. Reference information (two names with telephone numbers per project).

• Identify the home office location of key staff on this project, their length of time with the firm, and the percent of their work expected to be done locally.

• List any proposed consultants, including key staff names and the

Points Based 15

(15% of Total) experience and qualifications of these individuals.

6. Subcontractor Selection Plan

Subcontractor Selection Plan

Responses shall include the firm’s proposed subcontractor selection plan. The proposed subcontractor selection plan must provide for the selection of subcontractors based on qualifications alone or on a combination of qualifications and price and shall not select subcontractors based on price alone. As a minimum, describe which tasks the firm proposes to perform with its own forces and which major tasks will be executed by subcontractors.

Points Based 5

(5% of Total)

7. GENERAL INFORMATION

7.1. City Rights

The City of Tolleson reserves the right to reject any or all SOQs, to waive any informality or irregularity in any

SOQs received, and to be the sole judge of the merits of the respective SOQs received. No binding contract will exist between the submitter and the City until the City and successful respondent execute a written contract, after approval by the City Council.

This RFQ does not commit the City of Tolleson to award a contract, to defray any costs incurred in the preparation of a response to this request, or to procure or contract for services.

The City of Tolleson reserves the right to extend the date by which the submittals are due.

The City of Tolleson reserves the right to cancel, in part or in its entirety, this RFQ including but not limited to: selection schedule, submittal date, and submittal requirements. If the City of Tolleson cancels or revises the RFQ all potential respondents of record will be notified through the OpenGov application.

All submittals become the property of the City of Tolleson. Except for the name of firms on the final list (if there is a final short list), no information contained in a Statement of Qualifications shall be made public until after award and execution of a contract with a CMAR firm.

The City of Tolleson reserves the right to request additional information and/or clarifications from any or all respondents to this RFQ.

7.2. Instructions

Respondents may not rely on any oral instructions. Any changes to this will be in the form of an addendum.

7.3. Inquiries

Any question related to the Request for Qualifications shall be directed to the OpenGov Procurement Portal.

The submitter shall not contact or ask questions of the department for which the requirement is being procured. Any and all questions shall be submitted in writing. Verbal or telephone inquiries directed to City staff will not be answered. Within two business days following the Final Date for Inquiries listed on the cover page of this RFQ, answers to all questions received will be available on OpenGov. No questions, submitted in any form, will be answered after the Final Date for Inquiries.

7.4. Contact with City Employees

All firms interested in this project (including the firm’s employees, representatives, agents, lobbyists, attorneys, and sub-consultants) will refrain, under penalty of disqualification, from direct or indirect contact for the purpose of influencing the selection or creating bias in the selection process with any person who may play a part in the selection process. This policy is intended to create a level playing field for all potential firms, assure that contract decisions are made in public and to protect the integrity of the selection process.

https://procurement.opengov.com/portal/tollesonaz/projects/288297

7.5. Equal Opportunity

The City is an equal opportunity employer. Minority and women’s business enterprises are encouraged to submit Statements of Qualifications on the Project.

7.6. Protests; Informal and Formal

Any respondent may protest this RFQ issued by the City, the ranking of the respondents and proposed award of a Contract, or the actual award of a Contract. All protests will be considered in accordance with the City of

Tolleson's protest policy and procedures set forth in City Procurement Code § 3-5-300, which is publicly available from the City Clerk's Office, 9055 West Van Buren Street, Tolleson, Arizona 85353.

7.7. No Constitution of Obligation

This RFQ does not obligate the City of Tolleson to any cost incurred in the preparation of and the submission of the SOQ nor to enter into an agreement with any of the submitting firms.

All submittals become property of the City of Tolleson, will not be returned and are subject to Public Records requests pursuant to Arizona law.

7.8. Right to Review and Evaluate Performance

Within forty-five (45) days after every project completion or as the City deems necessary, the City reserves the right to evaluate the Firm's performance, and provide a copy of the evaluation report to the Firm. The Firm shall then have ten (10) days to respond in writing to the evaluation. The evaluation factor under “Past

Performance” in future selections for Firm on City work that the Firm may wish to participate.

7.9. Confidential Information

If a firm/individual believes that a SOQ contains information that should be withheld from the public record, a statement advising the City Representative of this fact shall accompany the submission and the information shall be identified.

The information identified by the firm/individual as confidential shall not be disclosed until the City

Representative makes a written determination.

The City Representative shall review the statement and information and shall determine in writing whether the information shall be withheld.

If the City Representative determines to disclose the information, the City Representative shall inform the firm/individual in writing of such determination.

7.10. American Iron and Steel

Consolidated Appropriations Act, 2014 (Act), includes an “American Iron and Steel” (AIS) requirement that requires the use of iron and steel products that are produced in the U.S. for projects for the construction, alteration, maintenance, or repair of a public water system or treatment works. Waivers may be granted if a grantee can demonstrate a justifiable reason and a waiver request is approved by EPA. Additional details and a description of AIS requirements are available on EPA’s website at:

https://www.epa.gov/system/files/documents/2022-10/AIS%20Overview.pdf

7.11. Brooks Architect-Engineers Act

The Brooks-Architect Engineers Act requires grantees to use qualifications-based selection for contracting with architectural and engineering forms. Instead of selecting the lowest bidder, this process evaluates firms on their demonstrated competence, qualifications, and experience for the specific services needed, followed by a negotiation for a fair and reasonable price. The Brooks Architect-Engineers Act applies to certain Community

Grants projects, namely those that contain Clean Water Act State Revolving Fund activities under the Clean

Water Act. The Brooks Architect-Engineers Act does not apply to those projects that contain Drinking Water

State Revolving Fund activities.

7.12. Build America, Buy America (BABA)

BABA is a provision in the 2021 Infrastructure Investment and Jobs Act that requires the use of American-made iron, steel, manufactured products, and construction materials for all Federally funded infrastructure projects in the U.S. BABA includes a process for agencies to grant waivers if there is a lack of availability of necessary materials or if applying BABA would significantly increase project costs (e.g. by more than 25%).

Grantees and subrecipients must maintain detailed records to demonstrate that they have complied with

BABA. For more information about BABA waivers see Build America, Buy America (BABA) Approved Waivers |

US EPA.

7.13. Davis Bacon and Related Acts

When required by Federal program legislation, all prime construction contracts in excess of $2,000 awarded by non-Federal entities must include a provision for compliance with the Davis-Bacon Act (40 U.S.C. §§ 3141-

3144, and 3146-3148) as supplemented by Department of Labor regulations (29 C.F.R. Part 5, “Labor

Standards Provisions Applicable to Contracts Covering Federally Financed and Assisted Construction”). In accordance with the statute, contractors must be required to pay wages to laborers and mechanics at a rate not less than the prevailing wages specified in a wage determination made by the Secretary of Labor. In addition, contractors must be required to pay wages not less than once a week. The grantee must place a copy of the current prevailing wage determination issued by the Department of Labor in each solicitation. The decision to award a contract or subcontract must be conditioned upon the acceptance of the wage determination. The grantee must report all suspected or reported violations to the EPA. The contracts must also include a provision for compliance with the Copeland “Anti-Kickback” Act (40 U.S.C. § 3145), as supplemented by Department of Labor regulations (29 C.F.R. Part 3, “Contractors and Subcontractors on

Public Building or Public Work Financed in Whole or in Part by Loans or Grants from the United States”). The

Act provides that each contractor or subrecipient must be prohibited from inducing, by any means, any person employed in the construction, completion, or repair of public work, to give up any part of the compensation to which he or she is otherwise entitled. The grantee must report all suspected or reported violations to the

Federal awarding agency.

https://www.epa.gov/system/files/documents/2022-10/AIS%20Overview.pdf

Link(s) to these contract provisions for Davis-Bacon and Related Acts (DBRA) must be included in all contracts to which Davis-Bacon and Related Acts apply, unless a link with identical information, or an attachment with identical information, or the language in these contract provisions is provided verbatim in the contracts, as required by 29 C.F.R. § 5.5.

8. SUBMITTAL REQUIREMENTS

1. Upload your statement of qualifications here.*

Firm/Team - shall submit one consolidated file.

SOQs shall be a maximum of 10 pages, 8 1/2 x 11, minimum 10-point font.

Maximum of (2) 11x17 pages may be included in the 10 page limit.

Cover letter, cover, resumes, table of contents, dividers are not included in page count.

*Response required

2. Resumes*

Include resume for each team member and key individual that will be directly involved with the project (max 2 page). Briefly describe their experience with similar projects, number of years with the firm and their length of experience in their respective industry.

*Response required

3. Firm/Team - Bonding Capacity*

Provide a statement from an AM Best, Inc. rating of A or better surety company of the Company’s bonding capacity. Unless otherwise required by the public records law, this information will be confidential and will not be made part of the public record.

The selected CMAR will be required to furnish a Performance Bond and a Payment Bond, each in an amount equal to the full Contract Price, as required by the General Conditions for CMAR (Attachment C).

*Response required

4. System for Award Management (SAM.gov)*

Please be advised that this project is funded in whole or in part by federal financial assistance. Because federal funds are involved, all contractors, subcontractors, and vendors are legally required to have an active registration in the federal System for Award Management (SAM.gov) and obtain a Unique Entity ID (UEI) before any contracts can be finalized or payments processed.

If already registered: Please include your company’s legal name, registered address, and Unique Entity ID

(UEI) within your SOQ so we can verify your active status.

If NOT registered: Go to SAM.gov to register your entity and obtain a UEI.

Important Notes:

Cost: Registration on SAM.gov is 100% free. Beware of third-party scams charging a fee to register you.

https://sam.gov/

Timeline: Registration can take several weeks to process. Please initiate this process immediately to avoid any project delays or withholding of payments.

☐ Please confirm

*Response required

5. Is the Firm able to meet City of Tolleson insurance requirements?*

Required insurance requirements are identified in the Pre-Construction Services Contract (Attachment A, Section 7.0) and the General Conditions for CMAR (Attachment C).

Within ten (10) days of execution of a contract with the City of Tolleson, the successful Firm shall furnish proof of insurance in the amounts listed in the forms of Contract.

☐ Yes

☐ No

*Response required

6. Arizona State Contractor's Licenses and Classifications*

Upload table of Arizona State Contractor's Licenses and Classifications here.

Prior to award, the selected CMAR must also provide to the City Clerk its Contractor's License classification and number, City of Tolleson Privilege Tax License number, Arizona Privilege Tax License number, and Federal

Tax I.D. number, as required by Section 6.16 of Attachment A.

*Response required

7. Authorization for release of Performance Information and Waiver*

I confirm that I am authorized and hereby consent and authorize all those companies and government entities listed in my Statement of Qualifications and any other government entity for whom this company has performed construction services, to disclose and release to the City of Tolleson, or their representatives, information, records and opinions concerning this company’s construction performance. The purpose of this disclosure is to provide references to the City of Tolleson. I hereby waive any claim it may have against the City of Tolleson or any company or entity providing information to the City of Tolleson by reason of any information being disclosed or opinions provided regarding the actions or performance of this company.

☐ Please confirm

*Response required

8. Non-Discrimination Certification*

By submitting a SOQ, the firm/individual certifies:

It shall not discriminate against any employee or applicant for employment in violation of Federal Executive

Order 11456.

It has not given, offered to give, nor intends to give at any time hereafter, any economic opportunity, future employment, gift, loan, gratuity, special discount, trip favor or service to a City employee, officer or agent in connection with the submitted SOQ. Failure to certify the SOQ, or providing a false statement, shall void the submitted SOQ and any resulting Agreement.

It (including the firm/individual’s employees, representatives, agents, lobbyists, attorneys, and subcontractors) will refrain, under penalty of disqualification, from direct or indirect contact for the purpose of influencing the selection or creating bias in the selection process with any person who may play a part in the selection process, including the Selection Committee, elected officials, the City Manager, Assistant City

Managers, Department Heads, and other staff.

In addition to reviewing and understanding the submittal requirements, it has reviewed the attached CMAR

Pre-Construction Services Contract, CMAR Construction Services Contract, and General Conditions for CMAR, including the Scope of Work and any Exhibits.

☐ Yes

☐ No

*Response required

9. By submitting a SOQ, the firm/individual confirms it will meet the following requirements as applicable:*

(1) American Iron and Steel (AIS);

(2) Build America, Buy America (BABA);

(3) Davis-Bacon prevailing wage and labor standards;

(4) Appendix II to 2 CFR Part 200 contractual provisions including Suspension and Debarment and Anti-

Lobbying; and

(5) National Environmental Policy Act and other federal environmental crosscutters.

Federal requirements, including the provisions in Attachments D and E, will be incorporated into the Pre-

Construction Services Contract, the Construction Services Contract, and all subcontracts.

☐ Please confirm

*Response required

10. Exceptions*

Do you take any exceptions to the terms and conditions of the RFQ?

☐ Yes

☐ No

*Response required

When equals "Yes"

10.1. Exceptions Taken*

If exceptions are taken, please download Form template contract document from Attachments, indicate exceptions using tracked changes, save and upload tracked changes document for consideration.

*The City reserves right to accept or reject exceptions.

*Response required

11. Business Enterprises Designation*

Are you a Small, Minority, Disadvantaged or Women-Owned Business Enterprise?

☐ Yes

☐ No

*Response required

When equals "Yes"

11.1. Business Enterprise Designation *

Select all that apply

☐ Small Business Enterprise (SBE)

☐ Minority Business Enterprise (MBE)

☐ Disadvantaged Business Enterprise (DBE)

☐ Women-Owned Business Enterprise (WBE)

*Response required

12. Cover Letter

Consultant shall upload cover letter.

1. NOTICE
2. INSTRUCTIONS
3. GENERAL DESCRIPTION OF PROJECT
4. PROJECT SCOPE
4.1. Scope of Work
5. SELECTION PROCESS
6. EVALUATION CRITERIA
7. GENERAL INFORMATION
7.1. City Rights
7.2. Instructions
7.3. Inquiries
7.4. Contact with City Employees
7.5. Equal Opportunity
7.6. Protests; Informal and Formal
7.7. No Constitution of Obligation
7.8. Right to Review and Evaluate Performance
7.9. Confidential Information
7.10. American Iron and Steel
7.11. Brooks Architect-Engineers Act
7.12. Build America, Buy America (BABA)
7.13. Davis Bacon and Related Acts
8. SUBMITTAL REQUIREMENTS
1. Upload your statement of qualifications here.*
2. Resumes*
3. Firm/Team - Bonding Capacity*
4. System for Award Management (SAM.gov)*
5. Is the Firm able to meet City of Tolleson insurance requirements?*
6. Arizona State Contractor's Licenses and Classifications*
7. Authorization for release of Performance Information and Waiver*
8. Non-Discrimination Certification*
9. By submitting a SOQ, the firm/individual confirms it will meet the following requirements as applicable:*
10. Exceptions*
10.1. Exceptions Taken*
11. Business Enterprises Designation*
11.1. Business Enterprise Designation *

12. Cover Letter

File details come from the government source that posted it. Updated .