CMAR_03.04_Pre-Construction_Services_Contract.doc

DOC document 177 KB Posted

Attached to
Digester 4 and Digested Sludge Storage Tank Rehabilitation
Solicitation number
RFQ for CMAR-26-011
Issued by
Maricopa County, Tucson City, Arizona

About this file

Pre-Construction Services Contract Summary

This document is a Pre-Construction Services Contract for Construction Manager at Risk (CM@R) established by the City of Tolleson, Arizona, for the Digester 4 and Digested Sludge Storage Tank Rehabilitation project. The contract outlines the CM@R's responsibilities during the design phase, including providing professional pre-construction services such as constructability and bid-ability reviews, cost estimating, scheduling, value engineering analysis, and procurement planning. Key deliverables include a Construction Management Plan, Project Schedule using Critical Path Method, cost estimates updated throughout design phases (schematic design, design development, and construction documents at 30%, 60%, 95%, and 100% completion), Design Document Reviews, Guaranteed Maximum Price (GMP) proposals, and competitive bidding for subcontractors. The CM@R must participate in weekly project management meetings, conduct value engineering evaluations, prepare a Cost Estimate Development Log, develop a Subcontractor Selection Plan with minimum three qualified bidders per trade, and maintain an open-book accounting arrangement allowing TOLLESON to audit all project-related records and attend CM@R meetings. The contract specifies that the CM@R must have adequate staffing with key personnel subject to TOLLESON approval, and maintains a fiduciary relationship with the City.

The contract compensation is structured on a time-and-material basis with a not-to-exceed amount for Basic Services and Additional Services (such as potholing and surveying) paid according to an hourly rate schedule with direct labor costs, indirect costs capped at 115% of direct labor, and fixed fees capped at 10% of combined direct and indirect costs. The Total Project Cost comprises the GMP (sum of Cost of the Work and Indirect Costs), Preconstruction Services, and any prior phase GMPs. The CM@R accepts full responsibility for work accuracy and completeness at no additional cost and must immediately notify TOLLESON if estimated costs exceed the project budget. For horizontal construction projects, the CM@R must self-perform at least 45% of construction work. The contract requires the CM@R to maintain professional liability insurance, comply with all federal and state laws including E-Verify employment verification requirements, obtain necessary contractor licenses and privilege tax licenses, and provide indemnification to TOLLESON. The contract is governed by Arizona law with jurisdiction in Maricopa County Superior Court, and TOLLESON retains the right to terminate the contract without cause or abandon portions of the project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-CONSTRUCTION SERVICES CONTRACT

FOR CONSTRUCTION MANAGER AT RISK (CM@R) PROJECT

Project Name:

Project No.:

Contract No.:

Date:

TABLE OF CONTENTS

PAGE

1.0

TERMS AND DEFINITIONS

2.0

PRE-CONSTRUCTION SCOPE OF SERVICES

3.0

PERIOD OF SERVICES

4.0

CONTRACT AMOUNT AND PAYMENTS

5.0

CITY OF TOLLESON’S RESPONSIBILITIES

6.0

CONTRACT CONDITIONS

7.0

INSURANCE

SIGNATURE PAGE

EXHIBITS

A Hourly Rate Schedule Form

B Guaranteed Maximum Price (GMP) Proposal

C Total Project Cost

D Project Description

E Cost Estimate Development Log

PRE-CONSTRUCTION SERVICES CONTRACT

FOR CONSTRUCTION MANAGER AT RISK (CM@R) PROJECT

THIS CONTRACT, made and entered into this _____ day of _________________, 20__, by and between the City of Tolleson, an Arizona municipal corporation, “TOLLESON” and _________________________ the “CONSTRUCTION MANAGER AT RISK” or “CM@R”. TOLLESON and CM@R, in consideration of the mutual covenants set forth, agree as follows:

1.0

TERMS AND DEFINITIONS

1.1 Addenda: Written or graphic instruments issued prior to the submittal of the GMP Proposal(s), which clarify, correct or change the GMP Proposal(s) requirements.

1.2 Alternate Systems Evaluations: Alternatives for design, means, and methods or other scope considerations that are evaluated using value engineering principles and have the potential to reduce construction costs while still delivering a quality and functional Project. These alternatives shall be tracked using a Cost Estimate Development Log (Paragraph 1.12).

1.3 Change Order: A document signed by CM@R and TOLLESON that authorizes an addition, deletion, or revision in the scope of services or Deliverables, or an adjustment in the Contract Amount or the period of services, issued on or after the Effective Date of this Agreement.

1.4 Contract: This written document signed by TOLLESON and CM@R covering the pre-construction phase of the Project and including the Contract Documents to this Agreement.

1.5 Construction Documents: A set of Drawings and Specifications, as defined, upon which cost estimates and GMP Proposal(s) are to be based.

1.6 Construction Fee: The CM@R’s profit.

1.7 Allowances Costs: Those items included in the GMP as allowances (See Exhibits B and C).

1.8 Contract Documents: This Agreement, CM@R final approved GMP Proposal (including documentation accompanying the GMP Proposal and any post GMP Proposal documentation submitted prior to the final approval of the GMP Proposal), the Notice to Proceed for pre-construction services, the General Conditions for Construction Phase, the Specifications and the Drawings produced by the Engineer, all Written Amendments and Change Orders to this Contract, the geotechnical report, and any other documents so designated in this Agreement.

1.9 Contract Amount: The approved not-to-exceed GMP as identified in paragraph 4.1.

1.10 Contract Time(s): The number of Working Days or the dates related to the construction phase that as stated in Construction Documents applies to achievement of Substantial Completion and/or completion of the construction Work so that it is ready for final payment.

1.11 Cost Estimate: The labor, materials, and equipment costs developed by the CM@R, and updated during each of the design phases, to support the “Cost of the Work” values used to develop the Guaranteed Maximum Price (GMP) for the Cost Model described in Exhibit B.

1.12 Cost Estimate Development Log: This document shall be developed by the CM@R during the design phases of the project and lists design modifications in a tabular form that, if accepted, will result in additive and deductive changes to the Cost Estimate (See Exhibit E). The initial list includes design modifications for consideration that the CM@R, from past experience with similar projects, presents for consideration by the Team.

1.13 Cost of the Work: The sum of all allowable direct costs during construction that would be, or actually were necessarily incurred by the CM@R, directly or through Sub-consultants, Subcontractors, and/or Suppliers in properly furnishing and performing the Work required by the Contract Documents. (See Exhibits B and C)

1.14 Cost Model: The cost model is identified in Exhibit B and on Cost Model Form 04.04. The cost model provides a formula for developing the Total Project Cost. The Total Project Cost is the sum of the Cost of the Work (Direct Costs), Indirect Cost, and Preconstruction Services.

1.15 Day: Calendar Day unless otherwise specified.

1.16 Deliverables: The work products prepared by the CM@R in performing the scope of work described in this Contract. Some of the major deliverables to be prepared and provided by the CM@R during the pre-construction phase include but are not limited to: Construction Management Plan, Cost Model, Project Schedule, Schedule of Values, alternative system evaluations, procurement strategies and plans, cost estimates, construction market surveys, cash flow projections, GMP Proposals, Subcontractor procurement plan, Statement of Proposed MBE/WBE Utilization, Subcontractor agreements, Sub-Bid packages, Supplier agreements, and others as indicated in this Contract or required by the Project Team.

1.17 Drawings: The one hundred percent construction submittal, which visually represent the scope, extent and character of the Work to be furnished and performed by CM@R during the construction phase. Drawings have been prepared or approved by the Engineer, approved by TOLLESON and are referred to and are included in the Contract Documents. The term includes Drawings that have reached a sufficient stage of completion and released by the Engineer solely for the purpose of review and/or use in performing constructability or bid-ability reviews and in preparing cost estimates (e.g., conceptual design Drawings, preliminary design Drawings, detailed design Drawings at 30%, 60%, 95% or 100%), but “not for construction”. Shop drawings are not Drawings as so defined.

1.18 Engineer: The person, firm or corporation named as such in this Contract who has the rights, duties, responsibilities, and limits of authority as set forth therein (A/E).

1.19 Final Completion: Final Completion is defined as the date when, in the opinion of TOLLESON and the PM/CM, all substantial completion inspection punch-list items have been addressed and the work is complete in accordance with the contract documents.

1.20 Force Majeure: Force Majeure means fire, unavoidable casualty, flood (assuming CM@R has taken reasonable precautions), earthquake, epidemic, civil disturbance, war, freight embargo, riot, sabotage (by persons other than the CM@R and Subcontractors), or any other similar act or condition, in each case only to the extent the event in question is beyond the control of and without the fault or negligence of the CM@R. A labor shortage or material shortage is not Force Majeure.

1.21 General Conditions Costs: Includes those costs identified in Exhibit C.

1.22 Guaranteed Maximum Price (GMP) Proposal: The maximum compensation payable to the CM@R in performance of the work for the project as specified in the contract documents or subsequently adjusted by modification through a GMP Change Order. The GMP Proposal(s) are to be delivered pursuant to Article 2 of this Contract and are described in Exhibits B and C.

1.23 Horizontal Construction: Means highways, roads, streets, bridges, canals, floodways, earthen dams, and landfills (A.R.S. § 34-101.16).

1.24 Laws and Regulations; Laws or Regulations: Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities and courts having jurisdiction.

1.25 Notice of Award: The written notice by TOLLESON to the CM@R stating that upon compliance by the CM@R with the condition’s precedent enumerated therein, within the time specified, TOLLESON will sign and deliver this Contract.

1.26 Notice to Proceed: A written notice given by TOLLESON to CM@R fixing the date on which the CM@R will start to perform CM@R’s obligations under this Contract.

1.27 Progress Payment Application: The form that is accepted by TOLLESON and used by CM@R is requesting progress payments or final payment and which will include such supporting documentation as is required by the Contract Documents and/or TOLLESON.

1.28 Project: The total design and construction of which the pre-construction services and construction phase Work to be provided may be the whole, or a part.

1.29 Project Team: Pre-construction services team consisting of TOLLESON, PM/CM, A/E, CM@R, and other stakeholders responsible for making decisions regarding the Project.

1.30 Record Drawings: Drawings (plans) prepared after construction is complete that represent the work accomplished under the contract.

1.31 Samples: Physical examples of materials, equipment, or workmanship representative of a part of the construction phase Work and which establish the standards by which the portion of the construction phase Work will be evaluated.

1.32 Shop Drawings: All Drawings, diagrams, illustrations, schedules and other data or information specifically prepared or assembled by or for the CM@R and submitted by the CM@R to illustrate some portion of the Work.

1.33 Specifications: The part(s) of the Contract Documents for the construction phase consisting of written technical descriptions of materials, equipment, construction systems, standards and workmanship as applied to the Work and certain administrative details applicable thereto.

1.34 Subcontractor: An individual, firm or corporation having a direct contract with the CM@R or any other individual, firm or corporation having a contract with the aforesaid contractors at any tier, who undertakes to perform a part of the pre-construction services or construction phase Work at the site for which the CM@R is responsible for. Subcontractors will be selected through the Sub-Bid process described in paragraph 2.7 of this Contract.

1.35 Substantial Completion: The construction phase Work (or a specified part thereof) has progressed to the point where, in the opinion of the PM/CM, as evidenced by a Certificate of Substantial Completion, such construction phase Work is sufficiently complete in accordance with the Contract Documents for the construction phase, so that the Work (or specified part) can be utilized for the purposes for which it is intended; without any outstanding concurrent Work at the site, except as may be required to complete or correct Punch List items. If no such certificate is issued, Substantial Completion takes place when the construction phase Work is complete and ready for final payment as evidenced by the PM/CM’s written recommendation of final payment. The terms “substantially complete” and “substantially completed” as applied to all or part of the construction phase Work refers to Substantial Completion thereof.

1.36 Supplier: A manufacturer, fabricator, supplier, distributor, materialman or vender having a direct contract with CM@R or any Subcontractor.

1.37 Total Float: Number of Working Days by which the pre-construction services or construction phase Work or any part of the same may be delayed without extending a pertinent schedule milestone in the Project Schedule.

1.38 Work: The entire completed construction or the various separately identifiable parts thereof, required to be furnished during the construction phase. Work includes and is the result of performing or furnishing labor and furnishing and incorporating materials, resources and equipment into the construction, and performing or furnishing services and documents as required by the Contract Documents for the construction phase.

1.39 Working Days: Every day on the calendar exclusive of Saturdays, Sundays and holidays observed by TOLLESON.

1.40 Written Amendment: A written modification to the Contract Documents, signed by TOLLESON and the CM@R on or after the Effective Date of this Contract and normally dealing with the non-engineering or non-technical aspects of the Contract Documents.

2.0

PRE-CONSTRUCTION SCOPE OF SERVICES

For the fee set forth in Section 4, CM@R to furnish professional pre-construction services during the design of the Project described in Appendix D. The CM@R accepts a relationship of trust and confidence between itself and TOLLESON and undertakes to act as TOLLESON’s fiduciary in all matters related to the Project. The CM@R acknowledges that they have the expertise to complete the Work identified in this Contract and agrees to furnish its best skills and best judgment to cooperate with TOLLESON and provide support to the Engineer during the design of the Project, and in all ways to further the interests of TOLLESON and the Project. The CM@R shall furnish cost effective recommendations to maintain project budgets, efficient constructability reviews, business administration, field supervision and shall use its best efforts to see to it that the work of the Project is done in the best and most expeditious, economical manner consistent with the interests of TOLLESON, and in strict conformity with the Contract Documents, including all reasonable implications therein. Because of the CM@R’s fiduciary duties to TOLLESON, the Project will be an “open book” job whereby TOLLESON may attend any and all meetings of the CM@R firm relating to the Project, and TOLLESON or its designated auditors or accountants shall have access to any and all records of the CM@R or maintained by the CM@R relating to the Project.

2.1

GENERAL

2.1.1 A/E and PM/CM: TOLLESON has contracted separately with an Engineer to provide engineering duties for the Project. TOLLESON has either designated a TOLLESON staff member to act as TOLLESON’s PM/CM or has contracted separately with a person, firm or corporation to act as TOLLESON’s PM/CM. The PM/CM has no design responsibilities of any nature. None of the activities of the PM/CM supplant or conflict with the design, budget, or any other services and responsibilities furnished by CM@R or subconsultants. All instructions by TOLLESON relating to this Contract will be issued or made through the PM/CM. All communications and submittals of CM@R to TOLLESON shall be issued or made through the PM/CM unless TOLLESON or the PM/CM shall otherwise direct. The PM/CM shall not reasonably withhold approval for the CM@R to communicate directly with TOLLESON or the A/E. The PM/CM shall have the authority to establish procedures, consistent with this Contract, to be followed by the CM@R and to call periodic conferences to be attended by the CM@R and the CM@R’s subconsultants, throughout the term of this Contract.

2.1.2 Program Evaluation: As a participating member of the Project Team, the CM@R will provide to TOLLESON, within 20 Working Days of the Notice to Proceed, a written evaluation of the Project Program and Project Budget, each in terms of the other, with recommendations as to the appropriateness of each.

2.1.3 Project Management/Team/Progress Meetings: These meetings will present general project progress, address design options that arise during the design process, and receive input and direction from TOLLESON engineering and operational staff. Project management meetings shall be conducted weekly or as required. Team meetings shall be conducted throughout the design portion of the project, to complement the project schedule and design review meetings. The CM@R will participate in each meeting, report on the project construction schedule and cost estimate, and provide pertinent input when required.

2.1.4 The CM@R will provide pre-construction services, described herein, in a proactive manner and consistent with the intent of the most current Drawings and Specifications. The CM@R will promptly notify TOLLESON in writing whenever the CM@R determines that any Drawings or Specifications are inappropriate for the Project and or cause changes in the scope of Work requiring an adjustment in the Project Schedule, GMP and/or in the Contract Time for the Work, to the extent such are established.

2.1.5 The CM@R, when requested by TOLLESON or at its own initiative, if sanctioned by TOLLESON, will attend, make presentations and participate as may be appropriate in public agency and/or community meetings, germane to the Project. The CM@R will assist the A/E and PM/CM in the preparation of drawings, schedule diagrams, budget charts and other materials describing the Project, when their use is required or apropos in any such public agency meetings. This contract will require _____ (__) such public meetings.

2.2

CONSTRUCTION MANAGEMENT PLAN (CMP)

2.2.1 Prior to the start of construction the CM@R will prepare, and submit to TOLLESON, a Construction Management Plan (CMP), which will detail but not necessarily be limited to the CM@R’s determinations concerning: (1) Project milestone dates and the Project Schedule, including the broad sequencing of the design and construction of the Project, (2) investigations, if any, to be undertaken to ascertain subsurface conditions and physical conditions of existing surface and subsurface facilities and underground utilities, (3) alternate strategies for fast-tracking and/or phasing the construction, (4) separate bidding documents/packages and strategies for the early procurement of long-lead equipment and/or materials, (5) the number of separate sub-agreements to be awarded to Subcontractors and Suppliers for the Project construction, (6) permitting strategy, (7) safety and training programs, (8) construction quality control, (9) the Cost Model and basis of the model, (10) a matrix summarizing each Project Team member’s responsibilities and roles and (11) construction security.

2.2.2 The CM@R will add detail to its previous version of the CMP to keep it current throughout the pre-construction services phase, so that the CMP is ready for implementation at the start of the construction phase. The update/revisions will take into account (a) revisions in Drawings and Specifications; (b) the CM@R’s examination of the results of any additional investigatory reports of subsurface conditions, drawings of physical conditions of existing surface and subsurface facilities and documents depicting underground utilities placement and physical condition, whether obtained by TOLLESON, PM/CM, A/E or the CM@R, (c) unresolved permitting issues, and significant issues, if any, pertaining to the acquisition of land and right of way, (d) the fast-tracking if any of the construction, or other chosen construction delivery methods, (e) the requisite number of separate bidding documents to be advertised, (f) the status of the procurement of long-lead time equipment and/or materials and (g) funding issues identified by TOLLESON.

2.2.3 The CM@R will prepare a written report on the market conditions that may affect the budget or the schedule and provide the report to the PM/CM.

2.2.4 Cost Estimate Development Log: This document shall be developed by the CM@R at the beginning of the project and will initially include additive and deductive cost item suggestions that the CM@R has found from past experience on similar projects to be appropriate for consideration by the project team. The CM@R shall update this log on a regular basis during the design process and all additive/deductive items shall be approved by the PM/CM with input from the A/E.

2.3

PROJECT SCHEDULE

2.3.1 The fundamental purpose of the “Project Schedule” is to identify, coordinate and record the tasks and activities to be performed by all the Project Team members and then for the Project Team to utilize that Deliverable as a basis for managing and monitoring all members’ compliance with the schedule requirements of the Project. Each Project Team member is responsible for its compliance with the Project Schedule requirements. The CM@R will develop a project schedule and will assist the PM/CM in updating and maintaining the Project Schedule on behalf of and to be used by the Project Team based on input from other Project Team members. The Project Schedule will be consistent with the most recent revised/updated CMP. The Project Schedule will use the Critical Path Method (CPM) technique, unless required otherwise, in writing by TOLLESON. The CM@R will use Primavera compatible scheduling software to assist the PM/CM to establish, update, and maintain the Project Schedule. The Project Schedule will be presented in graphical and tabular reports as agreed upon by the Project Team. The Project Schedule will include all tasks and deliverables required by each member of the Project Team to identify long lead items such as Right of Way transactions, Utility Relocation Activity, Permitting Requirements, Railroad coordination, etc. If Project phasing as described below is required, the Project Schedule will indicate milestone dates for the phases once determined. The Project Schedule’s activities will directly correlate with the Schedule of Values specified in paragraph 2.5. The Construction Schedule developed during the preconstruction phase shall be resource loaded for manpower and cash flow during the construction phase of the project.

2.3.2 The CM@R will include and integrate in the Project Schedule the services and activities required of the PM/CM, A/E and CM@R, including all pre-construction and construction phase activities. The Project Schedule will detail activities to the extent required to show: (a) the coordination between conceptual design, preliminary design, and development of the Construction Documents (detailed design), (b) separate long-lead procurements, (c) permitting issues, (d) land and right-of-way acquisition, if any, (e) bid packaging strategy and awards to Subcontractors and Suppliers, (f) major stages of construction, (g) start-up, and (h) occupancy of the completed Work by TOLLESON. The Project Schedule will include by example and not limitation, proposed activity sequences and durations for design, procurement, construction and testing activities, milestone dates for actions and decisions by the Project Team, preparation and processing of shop drawings and samples, delivery of materials or equipment requiring long-lead time procurement, milestone dates for various construction phases, total float for all activities, relationships between the activities, TOLLESON’s occupancy requirements showing portions of the Project having occupancy priority, and proposed dates for Substantial Completion and when the Work would be ready for final acceptance.

2.3.3 The Project Schedule will be updated and maintained by the PM/CM with assistance from the Project Team throughout the pre-construction services phase such that it will not require major changes at the start of the construction phase to incorporate CM@R’s plan for the performance of the construction phase Work. The PM/CM will provide updates and/or revisions to the Project Schedule for use by the Project Team, whenever required, but not less often than monthly. The PM/CM will include with such submittals a narrative describing its analysis of the progress achieved to-date vs. that planned, any concerns regarding delays or potential delays, and any recommendations regarding mitigating actions. The Project Schedule update will be submitted to the PM/CM by the 3rd Friday of each month to be reviewed and submitted to TOLLESON’s Representative.

2.3.4 Project Phasing: If phased construction is deemed appropriate and TOLLESON approves, the CM@R will review the design and make recommendations regarding the phased issuance of Construction Documents to facilitate phased construction of the Work, with the objective of reducing the Project Schedule and/or Cost of the Work. The CM@R will take into consideration such factors as natural and practical lines of work severability, sequencing effectiveness, access and availability constraints, total time for completion, construction market conditions, labor and materials availability, and other factors pertinent to saving time and cost.

2.3.5 Long-Lead Time Item Procurement: The CM@R will provide the PM/CM with a written list of long-lead items, if any, that must be procured during the pre-construction phase to meet the Project Schedule requirements and recommend a schedule for their procurement.

2.3.5.1 TOLLESON may procure such long-lead items on terms and conditions acceptable to the CM@R to the extent TOLLESON determines that it is their own best interest to do so under purchase orders executed by TOLLESON. Upon TOLLESON’s acceptance of any CM@R GMP Proposals, which includes such long-lead time items, the applicable purchase orders will be assigned by TOLLESON to the CM@R, who will accept responsibility for such items as if they were initially procured by the CM@R. The CM@R will be entitled to receive the construction fee associated with the pre-purchased equipment value as compensation for accepting this responsibility.

2.3.5.2 If TOLLESON concludes alternately, that it is in its own best interest to have the CM@R procure such long-lead time items, TOLLESON may, at its sole discretion, direct the CM@R to solicit bids, and upon approval by TOLLESON of the terms and conditions of their purchase, TOLLESON will authorize in writing the CM@R to issue purchase orders for those items. Only upon approval of GMP Proposals, or upon a separate executed procurement agreement, will TOLLESON authorize the CM@R to actually expend Project funds for such long-lead items.

2.3.5.3 If TOLLESON chooses not to procure long-lead time items prior to acceptance of a GMP Proposal, the CM@R will list the items and a delivery schedule in the Sub-Bid Documents. The CM@R will notify the potential Suppliers, Subcontractors, and fabricators of the required delivery schedule so that it will be taken into consideration, if necessary, in their bid.

2.4

DESIGN DOCUMENT REVIEWS

2.4.1 The CM@R will evaluate periodically the availability of labor, materials/equipment, building systems, cost-sensitive aspects of the design; and other factors that may impact GMP Proposals and/or the Project Schedule and provide this information in a written report to the PM/CM.

2.4.2 The CM@R will identify, in writing and in conjunction with the Project Team, those additional surface and subsurface investigations that are required to provide the necessary information for the CM@R to construct the Project. After completion of pre-construction services, the CM@R may provide additional investigations to improve the adequacy and completeness of the site condition information and data made available with the Construction Documents. The CM@R will be responsible for the time and cost required to obtain such additional investigations, except as otherwise provided by specific Additional Services.

2.4.3 The CM@R will meet with the Project Team as required to review designs during their development. The CM@R will thoroughly familiarize itself with the evolving documents through schematic design (30%), design development (60%), construction documents (95%), and final documents (100%). The CM@R will proactively advise the Project Team and make recommendations on factors related to construction costs, and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and labor and material availability. The CM@R will also advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as concerns that exist with respect to coordination of the Drawings and Specifications. The CM@R will recommend cost effective alternatives.

2.4.4 The CM@R will conduct constructability and bid-ability reviews of the Drawings and Specifications at the 30%, 60%, and 95% document submittals. The reviews will attempt to identify all discrepancies and inconsistencies in the Construction Documents especially those related to clarity, consistency, and coordination of Work of Subcontractors and Suppliers.

2.4.4.1 Constructability Reviews: The CM@R will evaluate whether (a) the Drawings and Specifications are configured to enable efficient construction, (b) design elements are standardized, (c) construction efficiency is properly considered in the Drawings and Specifications, (d) module/preassembly design are prepared to facilitate fabrication, transport and installation, (e) the design promotes accessibility of personnel, material and equipment and facilitates construction under adverse weather conditions, (f) sequences of Work required by or inferable from the Drawings and Specifications are practicable, and (g) the design has taken into consideration, efficiency issues concerning; access and entrance to the site, lay-down and storage of materials, staging of site facilities, construction parking, and other similar pertinent issues.

2.4.4.2 Bid-ability Reviews: The CM@R will check cross-references and complementary Drawings and sections within the Specifications, and in general evaluate whether (a) the Drawings and Specifications are sufficiently clear and detailed to minimize ambiguity and to reduce scope interpretation discrepancies, (b) named materials and equipment are commercially available and are performing well or otherwise, in similar installations, (c) the design provides as-built data, (d) Specifications include alternatives in the event a requirement cannot be met in the field, (e) and the Project is likely to be subject to differing site conditions considering the data on subsurface conditions, physical conditions of existing surface and subsurface facilities and physical conditions of underground utilities made available by the design or resulting from conditions inherent to work similar to the Work.

2.4.4.3 The results of the reviews will be provided to TOLLESON, in formal, written reports clearly identifying all discovered discrepancies and inconsistencies in the Drawings and Specifications with notations and recommendations made on the Drawings, Specifications and other documents. If requested by TOLLESON, the CM@R will meet with the PM/CM and A/E to discuss any findings and review reports.

2.4.4.4 The CM@R’S reviews will be from a contractor’s perspective, and though it will serve to reduce the number of Requests for Information (RFIs) and changes during the construction phase, responsibility for the Drawings and Specifications will remain with the Engineer and not the CM@R.

2.4.5 Notification of Variance of Deficiency: It is the CM@R’s responsibility to assist the A/E in ascertaining that the Construction Documents are in accordance with applicable laws, statutes, ordinances, building codes, rules and regulations as they relate to the performance of the Work. If the CM@R recognizes that portions of the Construction Documents as they relate to the performance of the Work are at variance with applicable laws, statutes, ordinances, building codes, rules and regulations it will promptly notify the A/E, PM/CM and TOLLESON in writing, describing the apparent variance or deficiency.

2.4.6 Alternate Systems Evaluations: The Project Team, at all regularly scheduled Design Review Meetings will routinely identify and evaluate, using value engineering principles, any alternate systems, approaches, design changes that have the potential to reduce Project costs while still delivering a quality and functional product. If the Project Team agrees, the CM@R in cooperation with the PM/CM and A/E will perform a cost-benefit analysis of the alternatives and submit such in writing to the Project Team. The Project Team will decide which alternatives will be incorporated into the Project. The Engineer will have full responsibility for the incorporation of the alternatives into the Drawings and Specifications. The CM@R will include the cost of the alternatives into the Cost Model and any GMP Proposals.

2.5

COST MODEL, COST ESTIMATES AND SCHEDULE OF VALUES

2.5.1 As soon as practical during the schematic design phase, the CM@R will review all available information regarding the design and scope of the Project and, based upon that review, will develop a schematic design Cost Estimate that will serve as input to the Cost Model identified in Exhibit B. The Cost Estimate will be continually updated and kept current as the design phases progress until a final GMP for the entire Project is established. The Cost Estimate will be the best representation by the CM@R of what the complete functional Project’s construction costs will be. The CM@R will communicate to the Project Team, any assumptions made in preparing the Cost Estimate. The Cost Model will include (a) the Cost of the Work (Cost Estimate, allowances and contingencies), (b) Indirect Costs, and (c) Preconstruction Services. The sum of (a) and (b) defines the GMP and the sum of (a) through (c) gives the Total Project Cost.

2.5.2 During the design phases the CM@R shall maintain a Cost Estimate Development Log (see Exhibit E) in which he tracks the additive and/or deductive changes to the Cost Estimate based on the CM@R’s review of design documents made available at the specified design phase. The PM/CM, A/E and CM@R will reconcile any disagreements on the estimate to arrive at an agreed upon Cost Estimate for the construction costs based on the scope of the Project through that specified design phase. The design phases applicable to this paragraph are: schematic design completion, design development completion, construction documents completion, and final completion at 30%, 60%, 95% and 100%. If the Project Team requires additional updates of the Cost Estimate beyond that specified in this paragraph, the CM@R will provide the requested information in a timely manner.

2.5.3 If at any point the Cost Estimate submitted to TOLLESON exceeds previously accepted estimates agreed to by the Project Team or other key aspects of the Cost Model or TOLLESON’s Project Budget, the CM@R will make appropriate recommendations to the PM/CM and A/E on means/methods, materials, and/or other design elements that it believes will reduce the estimated construction costs, (without altering the project’s basic program) such that it is equal to or less than the established Project Team’s target and/or the Project Budget. These changes to the Cost Estimate shall be identified in the Cost Estimate Development Log.

2.5.4 Before the first Application for Payment, the CM@R shall submit to TOLLESON, and the parties shall agree upon, a schedule of values, setting forth the various portions of the Work, and the portions of the GMP allocated to each portion. This schedule of values shall be used as a basis for payment.

2.5.5 The CM@R will prepare a monthly cash flow projection for the Project. This projection shall be updated on a monthly basis to reflect payments to the CM@R for completed work.

2.6

GUARANTEED MAXIMUM PRICE (GMP) PROPOSALS

2.6.1 TOLLESON’s construction budget for this Project is ___________________. During the formulation of the project and execution of the design the CM@R shall maintain cost controls to deliver the Project GMP within the project budget. If at any time during the design of the Project it appears that the cost of construction may exceed the project construction budget the CM@R shall immediately notify TOLLESON. If the GMP provided by the CM@R at any phase exceeds the project budget, the CM@R shall recommend approaches to bring the project within budget.

2.6.2 The Indirect Cost percentages associated with General Conditions, Bond allowance, Sales Taxes, Insurance allowance, and Contractor’s Fee; of the Guaranteed Maximum Price (GMP) Cost Model given in Exhibit B shall be negotiated prior to the execution of the Contract and shall be used in subsequent GMP Proposal development. These percentages are to be applied to the “Cost of the Work” estimates for both additive and deductive change orders.

2.6.3 At the stage of design as approved by TOLLESON and PM/CM, the CM@R shall, if requested by TOLLESON, propose a GMP, which shall be the sum of the estimated Cost of the Work and the Indirect Costs as defined in the “Guaranteed Maximum Price (GMP) Cost Model” given in Exhibit B.

2.6.4 The preconstruction services shall be negotiated separately and shall include all costs, including indirect costs and fee, associated with that phase of the work.

2.6.5 The Total Project Cost is the sum of the GMP Proposal, Preconstruction Services, and prior phase GMPs as defined in the Guaranteed Maximum Price Cost Model given in Exhibit B.

2.6.6 The CM@R shall include with the GMP Proposal a written statement of its basis, which shall include:

2.6.6.1 A list of the Design Materials and Construction Documents, including all addenda, which were used in preparation of the GMP Proposal.

2.6.6.2 A list of allowances and a statement of their basis.

2.6.6.3 A list of the assumptions and clarifications made by the CM@R in the preparation of the GMP Proposal to supplement the information contained in the Design Materials and Construction Documents.

2.6.6.4 The date of Substantial Completion upon which the GMP Proposal is based and the Schedule of Work upon which the date of Substantial Completion is based.

2.6.6.5 A schedule of applicable alternate prices.

2.6.6.6 A schedule of applicable unit prices.

2.6.6.7 A statement of Additional Services included, if any.

2.6.6.8 The time limit for acceptance of the GMP Proposal.

2.6.6.9 A list of the proposed personnel or positions that the CM@R intends to station at the jobsite to manage the work.

2.6.7 The CM@R shall meet with TOLLESON and the PM/CM to review the GMP Proposal. In the event that TOLLESON and PM/CM discover any inconsistencies or inaccuracies in the information presented, TOLLESON and PM/CM shall promptly give written notice to the CM@R, who shall make appropriate adjustments to the GMP Proposal, its basis or both.

2.6.8 Prior to TOLLESON’S acceptance of the Contractor’s GMP Proposal, the CM@R shall not incur any cost to be reimbursed as part of the Cost of the Work, except as provided in this Agreement or as TOLLESON and PM/CM may specifically authorize in writing.

2.6.9 The CM@R, in preparing any GMP Proposal, will obtain from the A/E three sets of signed, sealed, and dated Construction Documents (including all addenda). The CM@R will prepare its GMP in accordance with TOLLESON’s “Request for GMP Proposal” requirements based on the most current completed Construction Documents at that time. The CM@R will mark the face of each document of each set upon which its proposed GMP is based. The CM@R will send one set of those documents to the PM/CM, keep one set and return the third set to the A/E.

2.6.10 An updated/revised Project Schedule will be included with any GMP Proposal(s) that reflects the scope of Work shown in the current set of design documents upon which the GMP Proposal(s) is based. Any such Project Schedule updates/revisions will continue to comply with the requirements of paragraph 2.3.

2.6.11 In the event the CM@R elects, in its sole discretion, to maintain a Contractor Contingency within the GMP, the Contractor Contingency must be acceptable to TOLLESON. In addition, the terms and conditions regarding use of the contingency during the construction phase will be established by TOLLESON and reflected in the contract for that phase of the Project. The use of the Contractor Contingency will be based on these mutually agreeable terms and conditions and written approval from the Owner shall be a prerequisite to the CM@R’s use of the Contractor Contingency. CM@R will establish and maintain a Contractor Contingency Log and shall review the status of the Contractor Contingency with the PM/CM at each weekly meeting.

2.6.12 GMP Proposal(s) Review and Approval 2.6.12.1 The CM@R will meet with the PM/CM and A/E to review any GMP Proposal(s) and the written statement of its basis. In the event the PM/CM or A/E discovers inconsistencies or inaccuracies in the information presented, the CM@R will make adjustments as necessary to the GMP Proposal, its basis or both.

2.6.12.2 Upon receipt of any GMP Proposal from the CM@R, TOLLESON may submit the same documents that were used by CM@R in developing his GMP to an independent third party or to the A/E for review and verification. The third party or A/E will develop an independent estimate of the Cost of the Work and review the Project Schedule for the associated scope of the GMP Proposals.

2.6.12.3 If the CM@R’S GMP Proposal is greater than the independent third party or A/E’s estimate, TOLLESON may require the CM@R to reconfirm its GMP Proposal. The CM@R will accept the independent third parties or A/E’s estimate for the Cost of the Work as part of his GMP or present a report within seven days of a written request to TOLLESON identifying, explaining, and substantiating the differences. The CM@R may be requested or at its own discretion submit a revised GMP Proposal for consideration by TOLLESON. At that time TOLLESON may do one of the following:

A.

Accept the CM@R’S original or revised GMP Proposal, if within TOLLESON’s budget, without comment.

B.

Accept the CM@R’S original or revised GMP Proposal that exceeds TOLLESON’s budget and indicate in writing to the CM@R that the Project Budget has been increased to fund the differences.

C.

Reject the CM@R’S original or revised GMP Proposal because it exceeds either or both TOLLESON’s budget and the independent third party’s or A/E’s estimate, in which event, TOLLESON may terminate this Contract and/or elect to not enter into a separate contract with the CM@R for the construction phase associated with the scope of Work reflected in the GMP Proposal.

2.6.12.4 If during the review and negotiation of GMP Proposals design changes are required, TOLLESON will authorize and cause the A/E to revise the Construction Documents to the extent necessary to reflect the agreed-upon assumptions and clarifications contained in the final approved GMP Proposal. Such revised Construction Documents will be furnished to the CM@R. The CM@R will promptly notify the A/E and PM/CM if any such revised Construction Documents are inconsistent with the agreed-upon assumptions and clarifications.

2.7

COMPETITIVE BIDDING AND SUB-BIDS

2.7.1 The CM@R will develop a written Subcontractor Selection Plan for approval by TOLLESON that includes the names of a minimum of three qualified Subcontractors for each trade in the Project and solicit bids for the various Work categories. If there are not three qualified Subcontractors available for a specific trade, the CM@R will request approval by the PM/CM to submit less than three names. No change in the approved Subcontractors will be allowed without prior written approval by TOLLESON.

2.7.2 If prior to receipt of Sub-Bids or prior to award of Subcontractors or Suppliers, TOLLESON objects to any nominated Subcontractor or Supplier or to any self-performed Work for good reason, the CM@R will nominate a substitute Subcontractor or Supplier, preferably if such option is still available, from those who submitted Sub-Bids for the Work affected. Once such substitute Subcontractors and Suppliers are consented to by TOLLESON, the CM@R proposed GMP for the Work or portion thereof will be correspondingly adjusted to reflect any higher or lower costs from any such substitution.

2.7.3 The CM@R will distribute Drawings and Specifications and conduct a pre-bid conference with prospective Subcontractors.

2.7.4 If the Work is defined as Horizontal Construction the CM@R shall self-perform at least 45% of the construction Work.

2.7.5 The CM@R, at the required time, will close the bidding and collect all Sub-Bids received within the prescribed deadline for receipt of Sub-Bids. Promptly, after the closing of Sub-bids, the CM@R will (in the presence of the PM/CM) open and read all properly and timely submitted Sub-Bids. The CM@R will submit a completed Sub-Bid tabulation form to the PM/CM within a reasonable time after the closing of the Sub-Bid opening proceedings.

2.7.6 The CM@R, upon opening of Sub-Bids will evaluate them including, but not limited to, the evaluation of lower tier Subcontractors, Subcontractor qualification submittals and prospective Suppliers selected by each apparent low Sub-Bidder. The CM@R will resolve any Sub-Bid withdrawal, protest or disqualification in connection with the award at no increase in the Cost of the Work.

2.7.7 If the CM@R elects to utilize a subcontractor whose bid was not lowest the CM@R shall request written approval from TOLLESON for use of the subcontractor and shall state the reason(s) for not using the lowest bidder.

2.7.8 Within fifteen (15) Days after Sub-Bid opening, the CM@R will deliver to the PM/CM a written Notice of Intent to Award, itemizing the Subcontractors and Suppliers selected by the CM@R. The Notice of Intent to Award will detail (a) for each Sub-agreement the amount of the Sub-Bid and the corresponding Subcontractor or Supplier, (b) the sum of Sub-Bids received for all intended Sub-agreements, (c) trade work that the CM@R intends to self-perform, if any.

2.7.9 Early selection of subcontractors or suppliers based on qualifications and/or price will be performed in accordance with applicable State procurement laws. If the CM@R believes early selection of subcontractors is in the best interest of the Project the MC@R will notify the PM/CM in writing outlining which subcontractors and/or suppliers should be considered on this basis. This procedure shall be in accordance with the Subcontractor Selection Plan. The PM/CM will review this request and respond in writing within fourteen (14) days.

3.0

PERIOD OF SERVICES

3.1 The pre-construction services described in Section 2 will be performed by CM@R in accordance with the most current update/revised Project Schedule. Failure on the part of the CM@R to adhere to the Project Schedule requirements for activities for which it is responsible will be sufficient grounds for termination of this Contract by TOLLESON.

3.2 If the date of performance of any obligation or the last day of any time period provided for herein should fall on a Saturday, Sunday, or holiday for TOLLESON, then said obligation will be due and owing, and said time period will expire, on the first day thereafter which is not a Saturday, Sunday or legal TOLLESON holiday. Except as may otherwise be set forth herein, any performance provided for herein will be timely made if completed no later than 5:00 p.m. on the day of performance.

4.0

CONTRACT AMOUNT AND PAYMENTS

4.1

CONTRACT AMOUNT

Based on the Preconstruction Services fee proposal submitted by the CM@R and accepted by TOLLESON (which by reference is made a part of this Contract); TOLLESON will pay the CM@R on a Time and Material basis as follows:

4.1.1 For the Basic Service described in Section 2, and performed to the satisfaction of TOLLESON, the not-to-exceed amount: ___________ dollars and no cents ($_______).

4.1.2 For the Additional Services described in paragraph 4.3, and performed to the satisfaction of TOLLESON, the not-to-exceed amount: ___________ dollars and no cents ($_______).

4.2

PAYMENTS

4.2.1 Requests for monthly payments by the CM@R for pre-construction services will be submitted to PM/CM and will be accompanied by a progress report, detailed invoices, and receipts. Any request for payment will include, as a minimum, a narrative description of the tasks accomplished during the billing period, a listing of any Deliverables submitted, and copies of any Subconsultants’ requests for payment, an updated cash flow report, plus similar narrative and listings of Deliverables associated with their Work. Services will be paid in accordance with the work effort expended on that service during the preceding month.

4.2.2 The Contract fees for CM@R and Subconsultants will be based upon the hourly rate schedule included as Exhibit A attached.

4.2.3 The CM@R will pay all sums due Subconsultants for services and reimbursable expenses within fourteen (14) calendar days after the CM@R has received payment for those services from TOLLESON.

4.2.4 The CM@R agrees that no charges or claims for costs or damages of any type will be made by it for any delays or hindrances such as utility companies and outside agencies which are beyond the reasonable control of TOLLESON during the progress of any portion of the services specified in this Agreement. Such delays or hindrances, if any, will be solely compensated for by an extension of time (noncompensable) for such reasonable period as may be mutually agreed between the parties. It is understood and agreed, however, that permitting the CM@R to proceed to complete any services, in whole or in part after the date to which the time of completion may have been extended, will in no way act as a waiver on the part of TOLLESON of any of its legal rights herein.

4.2.5 No compensation to the CM@R will be allowed contrary to Title 34 of the Arizona Revised Statutes.

4.2.6 If any service(s) executed by the CM@R is abandoned or suspended in whole or in part, for a period of more than 180 days through no fault of the CM@R, the CM@R is to be paid for the services performed prior to the abandonment or suspension.

4.3

ADDITIONAL SERVICES

The following Additional Services may be required for the successful completion of this Project. Mark-ups are not authorized and only the items specifically identified below will be reimbursed as authorized herein:

A.

Potholing

B.

Surveying

C.

Other

[Modify Additional Services as required] 5.0

CITY OF TOLLESON’S RESPONSIBILITIES

5.1 TOLLESON, at no cost to the CM@R, will furnish the following information:

5.1.1 One copy of data TOLLESON determines pertinent to the Work. However, the CM@R will be responsible for searching the records and requesting information it deems reasonably required for the Project.

5.1.2 Available data and information pertaining to relevant policies, standards, criteria, studies, etc.

5.1.3 TOLLESON’s representative who will serve as PM/CM during the term of this Contract is ______________________. PM/CM has the authority to administer this Contract and will monitor CM@R’s compliance with all terms and conditions stated herein.