About this file
This is a General Conditions document for a Construction Manager at Risk (CMAR) engagement by the City of Tolleson, Arizona, for the Digester 4 and Digested Sludge Storage Tank Rehabilitation project. The document establishes the contractual framework and standard terms governing the relationship between the City, the CMAR firm, and other project participants. The General Conditions outline the responsibilities, obligations, and procedures that will apply throughout the project delivery process, including provisions for project management, coordination, quality assurance, safety requirements, and dispute resolution mechanisms.
The General Conditions document addresses key operational aspects of the CMAR delivery method, including the roles and authorities of the CMAR firm in pre-construction and construction phases, insurance and bonding requirements, change order procedures, payment terms, schedule management, and compliance with applicable laws and regulations. The document establishes protocols for site management, communication protocols among project stakeholders, handling of construction documents, and procedures for addressing construction defects or performance issues. Additionally, the conditions specify indemnification obligations, limitations of liability, and mechanisms for resolving disputes between parties, ensuring clear expectations and reducing potential conflicts during project execution.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF TOLLESON
CONSTRUCTION GENERAL CONDITIONS FOR
CONSTRUCTION MANAGER AT RISK (CM@R)
For
Project Name: ______________________________ Project No:
Contract No:
Date:
TABLE OF CONTENTS
PAGE
1PART I
GENERAL CONDITIONS - PM/CM AND A/E
2PART II
GENERAL CONDITIONS – DEFINITIONS
3PART III
GENERAL CONDITIONS - INSURANCE AND BONDS, INDEMNIFICATION, NOTICE TO PROCEED
33.1
CM@R’S INSURANCE
63.2
REQUIREMENT OF CONTRACT BONDS
73.3
INDEMNIFICATION
83.4
SAFETY WARRANTY
3.5
NOTICE TO PROCEED
10PART IV
GENERAL CONDITIONS - COMMENCEMENT, PROSECUTION AND PROGRESS
104.1
COMMENCEMENT
114.2
SUBCONTRACTORS
114.3
CM@R’S REPRESENTATIVE AND EMERGENCIES
124.4
CONTRACT DOCUMENTS
124.5
ERRORS AND OMISSIONS
134.6
QUALIFICATIONS FOR EMPLOYMENT
144.7
CHARACTER OF WORKERS
144.8
MAINTENANCE OF TRAFFIC
154.9
CLEANUP AND DUST CONTROL
164.10
SANITATION
164.11
WATER
164.12
CONSTRUCTION STAKING
174.13
BLUE STAKE
174.14
UTILITIES SHOWN ON THE PLANS
174.15
UTILITIES NOT SHOWN ON THE PLANS
184.16
DRIVEWAYS AND WALKS
184.17
TREES AND SHRUBBERY
184.18
IRRIGATION DITCHES AND STRUCTURES
194.19
ROADS AND FENCES
194.20
PROTECTION OF WORK AND CLEANING UP
194.21
METHODS AND EQUIPMENT
204.22
SUSPENSION OF WORK
204.23
DELAYS AND EXTENSION OF TIME
214.24
TOLLESON'S RIGHT TO CARRY OUT THE WORK
214.25
TERMINATION FOR BREACH OF CONTRACT
22PART V GENERAL CONDITIONS - CONTROL OF WORK
225.1
TIME OF WORK
TABLE OF CONTENTS
PAGE
275.2
A/E TO INTERPRET CONTRACT DOCUMENTS
285.3
FORMAL PROTEST
285.4
PLANS
295.5
CONFORMITY WITH PLANS AND ALLOWABLE DEVIATIONS
295.6
COORDINATION AND INTERPRETATION OF PLANS AND SPECIFICATIONS
295.7
ORDER OF WORK
295.8
COOPERATION BETWEEN CM@R AND OTHER CONTRACTORS
5.9
TESTING AND INSPECTION
315.10
LINES AND GRADES
315.11
USE OF SITE
315.12
SEPARATE CONTRACTS TO TOLLESON
5.13
TESTS
5.14
COOPERATION BETWEEN CM@R AND HOMEOWNER’S ASSOCIATION
33PART VI
GENERAL CONDITIONS - CHANGES IN THE WORK
336.1
CHANGES IN THE WORK
336.2
PRICING OF CHANGES
346.3
COST PLUS ADJUSTMENT
356.4
EFFECT ON SURETIES
36PART VII
GENERAL CONDITIONS - MATERIALS AND WORKMANSHIP
367.1
GENERAL
367.2
SUBSTITUTION OF MATERIAL OR EQUIPMENT
367.3
SHOP DRAWINGS, PRODUCT DATA AND SAMPLES
387.4
MATERIALS FURNISHED BY TOLLESON
387.5
STORAGE OF MATERIALS
387.6
REJECTED MATERIALS AND WORK
387.7
GUARANTEE OF WORK – WARRANTY
7.8
NO EXERCISE OF AUTHORITY BY A/E AND PM/CM
41PART VIII
GENERAL CONIDITIONS - LEGAL RELATIONS AND RESPONSIBILITY
418.1
LAWS TO BE OBSERVED
418.2
HOURS OF LABOR
418.3
ALIEN LABOR
418.4
LABOR DISCRIMINATION
418.5
PERMITS AND LICENSES
428.6
PATENTED DEVICES, MATERIALS, AND PROCESSES
428.7
SURVEY LAND MONUMENTS
428.8
PROTECTION OF PERSON AND PROPERTY
438.9
CONSTRUCTION SAFETY PROGRAM AND REGULATIONS
438.10
PROTECTION OF ANTIQUITIES
438.11
CONTINGENCIES
TABLE OF CONTENTS
PAGE
438.12
NON-RESPONSIBILITY OF TOLLESON
438.13
PROPERTY RIGHTS IN MATERIAL
448.14
PROTECTION OF FINISHED OR PARTIALLY FINISHED WORK
448.15
ADMINISTRATIVE CLAIMS
45PART IX
GENERAL CONDITIONS - COMPLETION OF WORK, LIQUIDATED DAMAGES AND FINAL ACCEPTANCE
459.1
FAILURE TO COMPLETE WORK WITHIN TIME FOR COMPLETION AND LIQUIDATED DAMAGES
469.2
COMPLETION/LIQUIDATED DAMAGES
9.3
SPECIAL DAMAGES
469.4
FINAL CLEANING UP
479.5
RECORD DRAWINGS
479.6
COMPLETION AND INSPECTION
489.7
FINAL ACCEPTANCE
49PART X - GENERAL CONDITIONS - PAYMENTS TO CM@R
4910.1
GENERAL
4910.2
PARTIAL PAYMENT
10.3
PAYMENT OF ITEMS IN SCHEDULE OF VALUES
10.4
PAYMENT FOR "EXTRA WORK" AND FOR "CHANGES IN THE WORK”
10.5
ASSIGNMENT OF PAYMENTS
5010.6
FINAL PAYMENT AND CONTRACT CLOSEOUT
1PERFORMANCE BOND
H-
1LABOR AND MATERIALS BOND
I-
1NOTICE TO PROCEED
J-
CHANGE ORDER FORM
K-1
CONTRACTOR'S AFFIDAVITS REGARDING SETTLEMENT OF CLAIMS
L-1
1AUTHORIZED SIGNATURE FORM
M-
1SUPPLEMENTARY CONDITIONS
SC-
1TECHNICAL SPECIFICATIONS
TS-
PART I
GENERAL CONDITIONS
PROJECT MANAGER/CONSTRUCTION MANAGER, ARCHITECT/ENGINEER TC "1.17
CONSTRUCTION MANAGER AND ENGINEER" \f C \l "2" 1.1 This Project will be coordinated by a Project Manager/Construction Manager (PM/CM), who will report the progress of the Work and compliance with the Contract Documents to TOLLESON’S Representative. Generally, PM/CM will (1) oversee the progress of the Work, (2) receive submittals, requests for information and other information from CM@R, (3) transmit submittals and other information as appropriate to Architect/Engineer (A/E), (4) make recommendations to TOLLESON regarding Change Orders and request for extensions of time, (5) make recommendations to TOLLESON regarding requests for payment, (6) maintain Project records, (7) determine Substantial and Final Completion of the Project, and (8) accomplish other tasks related to the coordination of the Work.
1.2 Generally, A/E will review and approve shop drawings, make interpretations of the Contract Documents and make determinations regarding substitution of Methods and Materials. Other duties are set forth in the Contract Documents. Drawings and Specifications and copies thereof furnished by A/E are and shall remain the property of TOLLESON. They are to be used only with respect to this Project and are not to be used on any other Project.
1.3 PM/CM will be retained by TOLLESON during the construction and until final payment to the CM@R is made. PM/CM will report to, advise, and consult with TOLLESON’S Representative. All instructions to CM@R shall be forwarded through PM/CM. PM/CM will have the authority to act on behalf of TOLLESON only to the extent provided in the Contract Documents. CM@R shall not be relieved from CM@R's obligations to perform the Work in accordance with the Contract Documents either by the activities or duties of PM/CM in its administration of the Contract, or by inspections, tests or approvals required. In the case of termination of the Contract of PM/CM, TOLLESON shall appoint a PM/CM against whom CM@R makes no reasonable objection and whose status under the Contract Documents shall be that of the former PM/CM.
PART II
DEFINITIONS TC "PART II – GENERAL CONDITIONS - DEFINITIONS" \f C \l "1" 2.1 The definitions set forth in the Pre-Construction Services Contract shall apply to these General Conditions.
PART III
INSURANCE AND BONDS TC "PART III - GENERAL CONDITIONS - AWARD AND EXECUTION OF CONTRACT" \f C \l "1" , INDEMNIFICATION, NOTICE TO PROCEED 3.1
CM@R’S INSURANCE
TC "3.3
CONTRACTOR'S INSURANCE" \f C \l "2" 3.1.1 General: CM@R agrees to comply with all TOLLESON ordinances and state and federal laws and regulations. Without limiting any obligations or liabilities of CM@R, CM@R shall purchase and maintain, at its own expense, hereinafter stipulated minimum insurance with insurance companies duly licensed by the State of Arizona with an AM Best, Inc. rating of A or above with policies and forms satisfactory to TOLLESON. Failure to maintain insurance as specified may result in termination of this Contract at TOLLESON’S option.
3.1.2 No Representation of Coverage Adequacy: By requiring insurance herein, TOLLESON does not represent that coverage and limits will be adequate to protect CM@R. TOLLESON reserves the right to review any and all of the insurance policies and/or endorsements cited in this Contract but has no obligation to do so. Failure to demand such evidence of full compliance with the insurance requirements set forth in the Contract Documents or failure to identify any insurance deficiency shall not relieve CM@R from, nor be construed or deemed a waiver of, its obligation to maintain the required insurance at all times during the performance of the Contract.
3.1.3 Additional Insured: All insurance coverage and self-insured retention or deductible portions, except Workers Compensation Insurance, shall name, to the fullest extent permitted by law for claims arising out of the performance of the Contract, TOLLESON, TOLLESON’S Representative, PM/CM, A/E, their agents, representatives, officers, directors, officials and employees as Additional Insured as specified under the respective coverage sections of these Contract Documents.
3.1.4 Coverage Term: All insurance required herein shall be maintained in full force and effect until all Work or services required to be performed under the terms of subject Contract is satisfactorily performed, completed and formally accepted by TOLLESON, unless specified otherwise in these Contract Documents.
3.1.5 Primary Insurance: CM@R’S insurance shall be primary insurance as respects performance of subject Contract and in the protection of TOLLESON as an Additional Insured.
3.1.6 Occurrence Basis: All insurance coverage shall be on an occurrence basis and not a claims made basis.
3.1.7 Waiver: All policies, including Workers’ Compensation insurance, shall contain a waiver of rights of recovery (subrogation) against TOLLESON, its agents, representatives, officers, directors, officials and employees for any claims arising out of the Work. CM@R shall arrange to have such subrogation waivers incorporated into each policy via formal written endorsement thereto.
3.1.8 Policy Deductibles and or Self-Insured Retentions: The policies set forth in these requirements may provide coverage which contains deductibles or self-insured retention amounts. Such deductibles or self-insured retention shall not be applicable with respect to the policy limits provided to TOLLESON. CM@R shall be solely responsible for any such deductible or self-insured retention amount. TOLLESON, at its option, may require CM@R to secure payment or such deductible or self-insured retention by a surety bond or irrevocable and unconditional Letter of Credit.
3.1.9 Use of Subcontractors: If any Work under the Contract Documents is subcontracted in any way, CM@R shall execute a written agreement with Subcontractor containing the same Indemnification Clause and Insurance Requirements set forth herein protecting TOLLESON and CM@R. CM@R shall be responsible for executing the agreement with Subcontractor and obtaining Certificates of Insurance verifying the insurance requirements.
3.1.10 Evidence of Insurance: Prior to commencing any Work under the Contract Documents, CM@R shall furnish TOLLESON with Certificate(s) of Insurance, or formal endorsements as required by the Contract Documents, issued by CM@R’S insurer(s) as evidence that policies are placed with acceptable insurers as specified herein and provide the required coverage, conditions, and limits of coverage specified in the Contract Documents and that such coverage and provisions are in full force and effect. If a Certificate of Insurance is submitted as evidence of coverage, TOLLESON shall reasonably rely upon the Certificate of Insurance as evidence of coverage but such acceptance and reliance shall not waive or alter in any way the insurance requirements or obligations of this Contract. Such certificates shall identify the Project. If any of the above cited policies expire during the life of the Contract, it shall be CM@R’S responsibility to forward renewal Certificates within ten (10) days after the renewal date containing all of the insurance provisions. Certificates shall specifically cite the following provisions:
3.1.10.1 TOLLESON, PM/CM, A/E, their agents, representatives, officers, directors, officials and employees are Additional as follows:
A.
Commercial General Liability – Under ISO Form CG 20 10 11 85 or equivalent.
B.
Auto Liability – Under ISO Form CA 20 48 or equivalent.
C.
Excess Liability – Follow Form to underlying insurance as required.
3.1.10.2 CM@R’S insurance shall be primary insurance as respects performance of Contract.
3.1.10.3 All policies, including Workers Compensation, waive rights of recovery (subrogation) against TOLLESON, its agents, representatives, officers, directors, officials, and employees for any claims arising out of Work performed by CM@R under the Contract Documents.
3.1.10.4 Certificate shall cite 30-day advance notice cancellation provision.
3.1.10.5 Project descriptive information including:
A.
Project Name B.
Project Number C.
Contract Number 3.1.11
REQUIRED COVERAGE
3.1.11.1 Commercial General Liability: CM@R shall maintain “occurrence” form Commercial General Liability insurance with an unimpaired limit of not less than $5,000,000 for each occurrence, $5,000,000 Products and Completed Operations Annual Aggregate, and a $5,000,000 General Aggregate Limit on a per project basis endorsed by means of ISO Endorsement CC-2503 1185 or equivalent. The policy shall cover liability arising from premises, operations, independent CM@R’s, products-completed operations, personal injury and advertising injury. Coverage under the policy will be at least as broad as Insurance Services Offices, Inc. policy form CG 00 010 93 or equivalent thereof, including but not limited to, separation of insured’s clause. To the fullest extent allowed by law, for claims arising out of the performance of this Contract, TOLLESON, PM/CM, A/E, their agents, representatives, officers, directors, officials and employees shall be cited as an Additional Insured under Insurance Service Offices, Inc. Commercial General Liability Additional Insured Endorsement form CG 20 10 11 85, or equivalent, which shall read “Who is an Insured (Section II) is amended to include as an insured the person or organization shown in TOLLESON, but only with respect to liability arising out of “your work” for that insured by or for you.” CM@R, its successors and or assigns, is required to maintain Commercial General Liability insurance as specified hereunder for a minimum period of three (3) years following completion and acceptance of subject Work. CM@R shall submit Certificate of Insurance evidencing such Commercial General Liability insurance during said three-year period containing all of the insurance requirements set forth herein including naming TOLLESON, PM/CM, A/E, their agents, representatives, officers, directors, officials and employees as Additional Insured as required. If any excess insurance is utilized to fulfill the requirements of this paragraph, such excess insurance shall be “follow form” equal or broader in coverage scope than underlying insurance.
3.1.11.2 Vehicle Liability: CM@R shall maintain Business Automobile Liability insurance with a limit of $3,000,000 each occurrence on CM@R’S owned, hired, and non-owned vehicles assigned to or used in the performance of the Work. Coverage will be at least as broad as Insurance Services Office, Inc. coverage code “1” “any auto” policy form CA 00 01 12 93 or equivalent thereof. If any hazardous material, as defined by any local, state or federal authority, is the subject, or transported, in the performance of the Work, an MCS 90 endorsement is required providing $5,000,000 per occurrence limits of liability for bodily injury and property damage. To the fullest extent allowed by law, for claims arising out of the performance of this Contract, TOLLESON, PM/CM, A/E, their agents, representatives, officers, directors, officials, and employees shall be cited as an Additional Insured under the Insurance Service Officers, Inc. Business Auto policy Designated Insured Endorsement form CA 20 48 or equivalent. If any excess insurance is utilized to fulfill the requirements of this paragraph, such excess insurance shall be “follow form” equal or broader in coverage scope than underlying insurance.
3.1.11.3 Worker’s Compensation Insurance: CM@R shall maintain Worker Compensation Insurance to cover obligations imposed by federal and state statutes having jurisdiction of CM@R’S employees engaged in the performance of the Work and shall also maintain Employers Liability Insurance of not less than $1,000,000 for each accident, $1,000,000 disease for each employee and $1,000,000 disease policy limit.
3.1.11.4 Builder’s “All Risk”: CM@R shall maintain Builder’s “All Risk” Insurance in an amount not less than one hundred percent (100%) of the Contract price. Such policy shall include coverage for fire, lightening, vandalism, malicious mischief, riot, civil commotion, smoke, sprinkler leakage, water damage, windstorm, hail, earthquake, landslide, flood and collapse or loss due to the results of faulty workmanship during the Contract Time and until Final Acceptance of the Work by TOLLESON. On pipeline and similar Projects where fire hazard is negligible or nonexistent, TOLLESON may waive the requirement for fire insurance and/or accept an installation waiver.
3.1.11.5 Railroad Protection Liability: If the Work involves a railroad right-of-way (as described in the Special Conditions) Railroad Protective Liability Insurance coverage is required in the amounts set forth in the Special Conditions.
3.2
REQUIREMENT OF CONTRACT BONDS TC "3.4
REQUIREMENT OF CONTRACT BONDS" \f C \l "2" 3.2.1 Concurrently with the execution of the Contract, CM@R shall furnish TOLLESON the following bonds, which shall become binding upon the Award of the Contract to CM@R:
3.2.1.1 A Performance Bond in an amount equal to the full Contract Price conditioned upon the faithful performance of the Contract in accordance with Plans, Specifications and Conditions thereof. Such bond shall be solely for the protection of TOLLESON. The Performance Bond shall remain in force the greater of (a) two years after Final Completion of the Work, or (b) until the expiration of all warranties and guarantees as required by the Contract.
3.2.1.2 A Payment BOND in an amount equal to the full Contract Price solely for the protection of the claimants supplying labor or Materials to CM@R or his Subcontractors in the prosecution of the Work provided for in such Contract. The Payment Bond shall remain in effect for at least one year after Final Completion of the Work.
3.2.1.3 Each such bond shall include a provision allowing the prevailing party in a suit on such bond to recover as a part of this judgment such reasonable attorney's fees as may be fixed by a judge of the court.
3.2.1.4 Each such bond shall be executed by a surety company or companies holding a certificate of authority to transact surety business in the State of Arizona issued by the Director of the Department of Insurance pursuant to Title 20, Chapter 2, Article 1 of the Arizona Revised Statutes and any amendments thereto. The bonds shall be made payable and acceptable to TOLLESON. The bonds shall be written or countersigned by an authorized representative of the surety who is either a resident of the State of Arizona or whose principal office is maintained in this State and the bonds shall have attached thereto a certified copy of the Power of Attorney of the signing official.
3.2.1.5 Subcontractor Bonds: All Subcontractors whose total Contract value exceeds $50,000.00 shall provide Payment and Performance Bonds which meet the same requirements as Bonds required for CM@R.
3.3
INDEMNIFICATION TC "3.5
INDEMNIFICATION OF THE CITY AGAINST LIABILITY" \f C \l "2" 3.3.1 To the fullest extent permitted by laws and regulations, CM@R shall indemnify, appear, defend and hold harmless TOLLESON, PM/CM, A/E (“Indemnitees”) and their respective consultants and the officers, Councilmembers, directors, employees, agents and other consultants of each and any of them from and against all liabilities, damages, losses and costs, including reasonable attorney fees and court costs, but only to the extent caused by the negligence, recklessness or intentional wrongful conduct of CM@R or other persons employed or used by CM@R in the performance of this Contract. It is the intent that Indemnities shall, in all instances, be indemnified against all liability losses and damages of any nature whatsoever, for or on account of any injuries to or death of persons or damages to or destruction of property belonging to any person arising out of or in any way connected with the performance of the Work, regardless of whether or not caused in part by any act of a person or entity indemnified hereunder. This provision shall survive termination or cancellation of the Contract Documents. The fact that not every claim, cost, loss, or damage incurred may not be covered by CM@R does not diminish the indemnification obligation contained in this Section.
3.3.2 If any claim, action or proceeding is brought against Indemnitees by reason of any event that is the subject of this Contract and or described herein, upon demand made by Indemnitees, CM@R, at its sole cost and expense, shall pay, resist or defend such claim or action on behalf of Indemnitees by an attorney of CM@R, or if covered by insurance CM@R’S insurer, all of which must be approved by Indemnitees, which approval shall not be unreasonably withheld or delayed. Indemnitees shall cooperate with all reasonable efforts in the handling and defense of such claim. Included in the foregoing, Indemnitees may engage its own attorney to defend or assist in its defense. Any settlement of claims shall fully release and discharge the indemnified parties from any further liability for those claims. The release and discharge shall be in writing and shall be subject to approval by Indemnitees, which approval shall not be unreasonably withheld or delayed. If CM@R neglects or refuses to defend Indemnitees as provided by this Contract, any recovery or judgment against Indemnitees for a claim covered under this Contract shall conclusively establish CM@R’s liability to Indemnitees in connection with such recovery or judgment, and if TOLLESON desires to settle such dispute, Indemnitees shall be entitled to settle such dispute in good faith and CM@R shall be liable for the amount of such settlements and all expenses connected to the defense, including reasonable attorney fees, and other investigative and claims adjusting expenses.
3.4
SAFETY WARRANTY TC "3.6
SAFETY WARRANTY" \f C \l "2" 3.4.1 TOLLESON shall not be responsible for safety on the project site, including but not limited to, providing or assuring a safe place for the performance of the construction, methods of construction employed by the CM@R, subcontractors, suppliers or other entities or their partners, officers, agents, employees, or occupancy by any person.
3.4.2 CM@R shall provide and maintain in a neat, sanitary condition such accommodations for the use of his employees as may be necessary to comply with the requirements and regulations of the Arizona State Department of Health or as specified by the Maricopa County Health Department, Sanitary Code. CM@R shall provide all safeguards, safety devices and protective equipment and take any other needed actions, on his own responsibility or as PM/CM may determine, reasonably necessary to protect the life and the health of employees on the job, the safety of the public and to protect property in connection with the performance of the Work. Precaution shall be exercised by CM@R at all times for the protection of persons (including employees and TOLLESON representatives) and property. CM@R shall comply with the provisions of all applicable laws, pertaining to such protection including all Federal and State occupational safety and health acts, and standards and regulations promulgated thereunder.
3.4.3 CM@R warrants that CM@R is aware of and understands the hazards presented to persons, property and the environment relating to and arising out of the Work. In the event CM@R or any of CM@R’S Subcontractors are working or operating in an unsafe manner, CM@R shall immediately take full and appropriate steps to assure the safety of those working in the job site. CM@R acknowledges TOLLESON’S right under this Contract to stop work if TOLLESON determines the Work is not proceeding in a safe manner and may result in injury to persons or property. TOLLESON, PM/CM and A/E shall not be liable for the costs incurred by CM@R if the Work is stopped for safety reasons. PM/CM, with TOLLESON approval, shall issue a stop work order until the violation ceases. PM/CM shall immediately notify CM@R in writing of the reasons Work was stopped.
3.5
NOTICE TO PROCEED TC "3.7
NOTICE TO PROCEED" \f C \l "2"
CM@R or Subcontractors shall not start Work on any part of the Project until Notice to Proceed has been issued by TOLLESON. The Notice to Proceed will be sent to CM@R by certified mail or delivered to him in person. The date for the official start of the Contract will be set forth in the Notice to Proceed. The Notice to Proceed shall not be issued until the Contract has been executed and all insurance, bonds and other required documents have been submitted to TOLLESON.
PART IV
GENERAL CONDITIONS
COMMENCEMENT, PROSECUTION AND PROGRESS TC "PART IV - GENERAL CONDITIONS - COMMENCEMENT, PROSECUTION AND PROGRESS" \f C \l "1" 4.1
COMMENCEMENT TC "4.1
COMMENCEMENT" \f C \l "2" 4.1.1 Within ten (10) working days after the Notice Of Award, a pre-construction conference will be held to establish a working understanding among the parties as to the Work and to discuss the schedules referred to in Section 5.1, procedures for handling submittals, processing Applications for Payment, and maintaining required records.
4.1.1.1 The conference shall be attended by: CM@R and his superintendent, Principal Subcontractors, Representatives of principal suppliers and manufacturers as appropriate, PM/CM, A/E, Representatives of TOLLESON, Others as requested by CM@R, PM/CM, TOLLESON, or A/E.
4.1.1.2 The purpose of the conference is to designate responsible personnel and establish a working relationship. Matters requiring coordination will be discussed and procedures for handling such matters established. The agenda will include but not be limited to:
a. Discussion of Construction Management Plan (Developed during Preconstruction Phase services) b.
Discussion of Quality Control Plan c.
Discussion of CM@R's Initial Construction Schedule (See Section 5.1) d.
Transmittal, review, and distribution of CM@R's submittals e.
Processing applications for payment f.
Maintaining record documents g.
Critical work sequencing h.
A/E’s Instruction Bulletins and Change Orders i.
Use of premises, office and storage areas, security, housekeeping and TOLLESON’S needs j.
Major equipment deliveries and priorities k.
CM@R's Safety Program
4.1.1.3 PM/CM will preside at the conference and will develop the agenda and arrange for keeping the minutes and distributing the minutes to all persons in attendance.
4.1.2 CM@R shall commence Work on or before the tenth (10th) working day after the date set forth in the Notice to Proceed, and shall complete all Work under the Contract within the Contract Time. The Notice to Proceed will be issued no later than thirty (30) calendar days after the Notice of Award unless otherwise agreed upon in writing, or as may be specified in the Special Conditions.
4.2
SUBCONTRACTORS TC "4.2
SUBCONTRACTORS" \f C \l "2" 4.2.1 Subcontracts shall be in accordance with, and CM@R shall be bound by, the following provisions:
4.2.1.1 All subcontracts shall be subject to review and acceptance by TOLLESON.
4.2.1.2 All subcontracts shall be in writing and shall provide that all Work to be performed thereunder shall be performed in accordance with the terms of the Contract.
4.2.1.3 All Subcontractors whose total Project value exceeds $50,000.00 shall provide Payment and Performance Bonds that meet the same requirements as bonds required for CM@R.
4.2.1.4 True copies of any and all subcontracts shall be furnished to TOLLESON.
4.2.1.5 The subcontracting of any part of the Work will in no way relieve CM@R of his responsibility or liability or obligation under the Contract.
4.2.1.6 All subcontracts and purchase orders for equipment shall state guaranteed delivery dates, at such times as determined by CM@R that will allow CM@R to complete the Project within the Contract Time.
4.2.2 If TOLLESON or PM/CM has reasonable objection to any proposed Subcontractor, CM@R shall submit a substitute to whom TOLLESON and PM/CM have no reasonable objection, and the Contract Price shall be increased or decreased by the difference in cost occasioned by such substitution and an appropriate Change Order shall be issued.
4.2.3 CM@R shall make no substitution for any Subcontractor, person or entity previously selected if TOLLESON or PM/CM make reasonable objection to such substitution.
4.3
CM@R’S REPRESENTATIVE AND EMERGENCIES TC "4.3
CONTRACTOR'S REPRESENTATIVE AND EMERGENCIES" \f C \l "2" 4.3.1 CM@R shall at all times be present at the Work, in person or represented by a competent superintendent who shall supervise and direct the Work and shall be authorized by CM@R to receive and fulfill instructions from PM/CM.
4.3.2 CM@R shall supervise and direct the Work. CM@R shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction. CM@R shall employ and maintain on the SITE a qualified supervisor or superintendent who shall be designated in writing by CM@R as CM@R’S representative at the site. The supervisor or superintendent shall have full authority to act on behalf of CM@R and all communications given to the supervisor shall be as binding as if given to CM@R. The supervisor or superintendent shall be present on the SITE at all times as required to perform adequate supervision and coordination of the Work.
4.3.3 Emergencies that may arise during the progress of the Work may require special effort or require extra shifts of men to continue the Work beyond normal working hours. CM@R shall be prepared in case of such emergencies from whatever cause, to do all necessary Work promptly.
4.4
CONTRACT DOCUMENTS TC "4.4
CONTRACT DOCUMENTS" \f C \l "2" 4.4.1 CM@R shall keep at the Site a copy of the Contract Documents and shall give PM/CM access thereto at all times.
4.4.2 The documents that make up the Contract Documents are intended to be complete and complementary, and to prescribe a complete Work which CM@R shall perform in a manner acceptable to PM/CM and in full compliance with the terms of the Contract. CM@R shall provide TOLLESON with a complete and operable Work, even though the Plans and Specifications may not specifically call out all items or items of work required of CM@R to complete his task. If any omissions are made of information necessary to carry out the full intent and meaning of the Contract Documents, CM@R shall immediately notify PM/CM, who shall immediately notify A/E. A/E will make the necessary corrections for furnishing of detailed instructions. In case of discrepancies, the more stringent requirement shall govern.
4.4.3 Any drawings or Plans listed anywhere in the Contract Documents or Addenda thereto shall be regarded as a part thereof and of the Contract. Anything mentioned in the Specifications and not indicated on the Plans or not mentioned in these Specifications and indicated on the Plans shall be of the same force and effect as if indicated or mentioned in both.
4.4.4 CM@R shall perform the Work in accordance with the lines, grades, cross sections, and dimensions indicated on the Plans and detailed drawings.
4.4.5 Unless otherwise specified, CM@R shall furnish all materials, labor, tools, equipment, water, light, power, transportation, superintendence, temporary construction of every nature, and incidentals, including, but not limited to, dust and traffic control measures, and to perform all Work involved in executing the Contract in a satisfactory and workmanlike manner within the Contract Time.
4.4.6 Anything in the Contract Documents notwithstanding, CM@R accepts the responsibility of constructing a watertight, weather-tight, and totally functional Project.
4.5
ERRORS AND OMISSIONS TC "4.5
ERRORS AND OMISSIONS" \f C \l "2"
The Plans are presumed to be correct, but CM@R shall be required to check carefully all dimensions before beginning the Work. If any errors or omissions are discovered, PM/CM shall be so notified in writing. PM/CM shall immediately notify A/E who will then make such corrections and interpretations as may be deemed necessary for fulfilling the intent of the Plans and Specifications and shall issue appropriate A/E’s Instruction Bulletins. Any such adjustments made by CM@R without prior review and acceptance shall be at CM@R’s own risk. The settlement of any complication or disputed expenses arising from such adjustment shall be made by CM@R at his own expense.
4.6
QUALIFICATIONS FOR EMPLOYMENT TC "4.6
QUALIFICATIONS FOR EMPLOYMENT" \f C \l "2" 4.6.1 No person under the age of sixteen (16) years for normal occupations, no person under the age of eighteen (18) years in hazardous occupations and no person currently serving a sentence in a penal or correctional institution shall be employed to perform any Work under this Contract.
4.6.2 Immigration Law Compliance Warranty:
4.6.2.1 As required by A.R.S. § 41-4401, Contractor hereby warrants its compliance with all federal immigration laws and regulations that relate to its employees and A.R.S. § 23-214(A). Contractor further warrants that after hiring an employee, Contractor verifies the employment eligibility of the employee through the E-Verify program.
4.6.2.2 If Contractor uses any subcontractors in performance of the Work, subcontractors shall warrant their compliance with all federal immigration laws and regulations that relate to its employees and A.R.S. § 23-214(A), and subcontractors shall further warrant that after hiring an employee, such subcontractor verifies the employment eligibility of the employee through the E-Verify program.
4.6.2.3 A breach of this warranty shall be deemed a material breach of the Contract that is subject to penalties up to and including termination of the Contract. Contractor is subject to a penalty of $100 per day for the first violation, $500 per day for the second violation, and $1,000 per day for the third violation. TOLLESON at its option may terminate the Contract after the third violation. Contractor shall not be deemed in material breach of this Contract if the Contractor and/or subcontractors establish compliance with the employment verification provisions of Sections 274A and 274B of the federal Immigration and Nationality Act and the E-Verify requirements contained in A.R.S. § 23-214(A).
4.6.2.4 TOLLESON retains the legal right to inspect the papers of any Contractor or subcontractor employee who works on the Contract to ensure that the Contractor or subcontractor is complying with the warranty. Any inspection will be conducted after reasonable notice and at reasonable times.
4.6.2.5 If state law is amended, the parties may modify this paragraph consistent with state law.
4.6.3 Equal Treatment of Workers: CM@R shall keep fully informed of all federal and state laws, county and local ordinances, regulations, codes and all orders and decrees of bodies or tribunals having any jurisdiction or authority, which in any way affect the conduct of the WORK. CM@R shall at all times observe and comply with all such laws, ordinances, regulations, codes, orders and decrees; this includes, but is not limited to laws and regulations ensuring equal treatment for all employees and against unfair employment practices, including the Occupational Safety and Health Administration (“OSHA”) and the Fair Labor Standards Act (“FLSA”). CM@R shall protect and indemnify TOLLESON and its representatives against any claim or liability arising form or based on the violation of such, whether by CM@R or its employees.
4.7
CHARACTER OF WORKERS TC "4.7
CHARACTER OF WORKERS" \f C \l "2" 4.7.1 CM@R shall have in place and enforce a drug-free workplace policy which complies with the requirements of the Drug-Free Workplace Act.
4.7.2 CM@R shall at all times employ sufficient labor and equipment for prosecuting the several classes of Work to full completion in the manner and time required by the Contract Documents.
4.7.3 All workmen shall be competent and have sufficient skill, knowledge and experience in their class of work and in the operation of equipment required to perform all Work properly and satisfactorily.
4.7.4 CM@R shall at all times enforce strict discipline and good order among its workmen and shall not permit the use of alcohol or controlled substances (without a medical authorization) at the site.
4.7.5 Any person employed by CM@R or any Subcontractor who, in the opinion of PM/CM does not perform his work in a proper and skillful manner or is intemperate or disorderly shall, at the written request of PM/CM be removed from the Work by CM@R or Subcontractor employing such persons, and shall not be employed again in any portion of the Work without the approval of PM/CM. CM@R or Subcontractor shall hold TOLLESON harmless from damages or claims for compensation that may occur in the enforcement of this section.
4.7.6 Should CM@R or Subcontractor fail to remove such person as required above or fail to furnish suitable and sufficient personnel for the proper prosecution of the Work, TOLLESON may suspend the Work by written notice until such orders are complied with.
4.8
MAINTENANCE OF TRAFFIC TC "4.8
MAINTENANCE OF TRAFFIC" \f C \l "2" 4.8.1 CM@R’S operations shall be in accordance with the Manual on Uniform Traffic Control Devices, Latest Edition. These operations shall cause no unnecessary inconvenience to the public and public access rights shall be considered at all times. Unless otherwise authorized in the Specifications or on a temporary basis by PM/CM, traffic shall be permitted to pass through the Work area. CM@R shall coordinate with the various agencies to include governmental, commercial and public, so that adequate services are maintained.
4.8.2 CM@R shall become familiar with and follow TOLLESON’S procedures when submitting traffic control plans for approval.
4.8.3 Safe and adequate pedestrian and vehicular access shall be provided and maintained to fire hydrants, commercial and industrial establishments, churches, schools, parking lots, motels, hospitals, fire stations, police stations, residential properties and establishments of a similar nature.
4.8.4 Grading operations, roadway excavation and fill construction shall be conducted and maintained in such a manner as to provide a reasonably satisfactory and safe surface for vehicular and pedestrian traffic. When rough grading is completed, the roadbed shall be brought to and maintained in a reasonably smooth condition, satisfactory and safe for vehicular traffic at the posted speed limit. Pedestrian walkways shall be provided and maintained in a like manner. CM@R shall accomplish any additional grading operations and/or repairs, including barricade replacement or repairs during working and non-working periods which, in the opinion of PM/CM, are required.
4.8.5 CM@R shall provide an asphalt paved surface for any temporary bypass that is in place longer than ten (10) CALENDAR days.
4.8.6 In the event of abnormal weather conditions, such as windstorms and rainstorms, CM@R shall immediately inspect his Work area and take all necessary actions to insure that public access and safety are maintained.
4.8.7 CM@R shall provide PM/CM with the emergency phone number of his representative.
4.8.8 CM@R representative shall be available for contact twenty-four (24) hours per day, seven (7) days per week.
4.9
CLEANUP AND DUST CONTROL TC "4.9
CLEANUP AND DUST CONTROL" \f C \l "2" 4.9.1 Throughout all phases of construction, including suspension of Work, and until final acceptance of the Project, CM@R shall keep the Work area clean and free from rubbish, excess material and debris generated by construction activities.
4.9.2 CM@R shall take whatever steps, procedures or means required to prevent any dust nuisance due to his construction operations. The dust control measures shall be maintained at all times to the satisfaction of PM/CM and in accordance with the requirements of the Maricopa County Bureau of Air Control Rules and Regulations.
4.9.3 Failure of CM@R to comply with PM/CM's written cleanup orders may result in an order to suspend Work until the condition is corrected. No additional compensation or time will be allowed as a result of such suspension and PM/CM has the authority to take such other measures as may be necessary to remedy the situation.
4.10
SANITATION TC "4.10
SANITATION" \f C \l "2" 4.10.1 CM@R shall provide suitable and adequate sanitary conveniences for the use of all persons employed on the Project. All sanitary conveniences shall conform to the regulations of the public authority having jurisdiction over such matters. At the completion of the Project, all such sanitary conveniences shall be removed, and the premises left in a sanitary condition.
4.10.2 CM@R shall cooperate with and follow directions of the Arizona Department of Public Health Services and the Maricopa County Health Department with respect to sanitation facilities. State and County Public Health Service representatives shall have access to the Work wherever it is in preparation or progress, and CM@R shall provide proper facilities for such access and inspection.
4.11
WATER TC "4.11
WATER" \f C \l "2" 4.11.1 CM@R and each Subcontractor shall supply adequate pure cool drinking water with individual drinking cups for the use of employees on this construction. The quality of drinking water shall meet all applicable federal, state and local standards for drinking water.
4.11.2 It shall be the responsibility of CM@R to provide and maintain, at his own expense, an adequate supply of water for his use for construction and to install and maintain necessary supply connections and piping for same. Before final acceptance of the completed Project, all temporary connections and piping installed by CM@R shall be removed.
4.11.3 CM@R shall apply for a fire hydrant meter and pay for all construction water used at the current rates charged by TOLLESON, if CM@R desires to obtain water from the distribution system at any point. If a fire hydrant is taken out of service by the CM@R, the CM@R shall notify TOLLESON’S Water Services Department and mark the hydrant as being ‘Out of Service’ as required by TOLLESON. Verify with TOLLESON’S Water Services Department for special requirements on the use of fire hydrant water.
4.12
CONSTRUCTION STAKING TC "4.12
CONSTRUCTION STAKING" \f C \l "2" 4.12.1 Construction staking will be made by CM@R in accordance with the technical requirements of Section 105.8 of the MAG Specifications unless otherwise provided in the Special Conditions. CM@R shall provide and pay for all facility layout staking, including elevations and all other Project staking.
4.12.2 Replacement of construction stakes that have been knocked out due to CM@R’S Work or lack of Work, weather conditions, traffic, vandalism or utility CM@R’S will be done at CM@R’S expense.
4.13
BLUE STAKE TC "4.13
BLUE STAKE" \f C \l "2"
CM@R is required to notify Blue Stake (263-1100) prior to the excavation of any material in accordance with A.R.S. § 40-360.22. CM@R shall directly contact TOLLESON for marking of electrical for traffic signals, sprinkler and irrigation facilities.
4.14
UTILITIES SHOWN ON THE PLANS TC "4.14
UTILITIES SHOWN ON THE PLANS" \f C \l "2" 4.14.1 Regardless of what utilities are shown on the Plans, it shall be CM@R’S responsibility to verify these locations and any additional lines which may exist through consulting with TOLLESON, utility companies and/or "Blue Stake."
4.14.2 Existing utilities are indicated on Project Plans in accordance with the best information available. CM@R shall notify all owners of utilities when his Work is in progress. If a utility is damaged, the CM@R shall make such arrangements as are necessary to make emergency repairs, in a manner satisfactory to TOLLESON.
4.14.3 If a utility is shown on the Project Plans and cannot be located by the CM@R, any Work in conflict with the utility shall be delayed until the location of the utility is confirmed by TOLLESON. Costs associated with such delay will be borne by the CM@R.
4.14.4 No extra compensation will be made for the repair of any individual or house service utility or utility lines damaged by CM@R’S labor forces or equipment, nor for any damage incurred through neglect or failure to provide protective barriers, lights and other devices or means required to protect such existing utilities.
4.14.5 CM@R shall expose all sanitary and storm sewers, water, gas, electric, telephone utility lines, and other underground structures that might interfere with the Work, in order to permit survey location prior to construction.
4.14.6 CM@R shall assume full responsibility for damages to any underground facility/utility properly shown on the Plans or properly located by the Utility Owner, as a result of failing to obtain information as to its location, failing to excavate in a careful and prudent manner (as defined in MAG Spec’s), or failing to take measures for protection of the facilities/utilities. The CM@R is liable to the Owner of the Underground Facility/Utility for the total cost of the repair.
4.15
UTILITIES NOT SHOWN ON THE PLANS TC "4.15
UTILITIES NOT SHOWN ON THE PLANS" \f C \l "2" 4.15.1 If utility lines are encountered which are not shown on the Plans, and not located, or incorrectly located by the Utility Owner, other than individual or house service utility lines, and these lines are damaged or work is required to clear same, then MAG Spec Section 109.8 and A.R.S. § 40-360 shall apply.
4.15.2 The work necessary for the raising, lowering, or relocating of any such utility shall be at the Utility Owner’s expense. The necessary Work may be done by the Utility Owner or by CM@R, or as a collaborative effort, at the option of the Utility Owner. All Work shall be in accordance with the standards of TOLLESON and the Utility Owner.
4.15.3 In most cases, individual or house service utility lines are not shown on the Plans. It shall be CM@R’S responsibility to locate and protect these individual or house services. If, due to CM@R’S operations, any of these lines are damaged, he shall repair or replace these lines in a manner satisfactory to the owner of the utility at no extra cost to TOLLESON. In addition, the cost of location, protection, and working around these individual or house service utility lines shall be included in CM@R’S cost for the Work under this Contract.
4.16
DRIVEWAYS AND WALKS TC "4.16
DRIVEWAYS AND WALKS" \f C \l "2" 4.16.1 Inconvenience caused by digging across driveways and sidewalks shall be kept to a minimum by restoring the serviceability of the drive or sidewalk as soon as possible. Before blocking driveways, CM@R shall notify the property owner. CM@R shall replace or repair any damage done to driveways and walks to not less than the condition existing prior to CM@R’S Work. If it is necessary to leave an excavation open across driveways or sidewalks, CM@R shall provide temporary relief in the form of steel plates over the excavation.
4.16.2 Temporary paving replacement in front of business establishments shall be placed immediately following backfill and shall remain in place until the condition of the backfill is suitable for permanent pavement replacement.
4.16.3 Direct access shall be provided at all times to fire stations, fire hydrants, hospitals, police stations, and at all other agencies or services where emergencies may require immediate access to same.
4.17
TREES AND SHRUBBERY TC "4.17
TREES AND SHRUBBERY" \f C \l "2" 4.17.1 All trees and shrubbery within the right-of-way or easements shall be protected by CM@R insofar as practicable. No trees or shrubbery shall be removed without the prior approval of TOLLESON.
4.17.2 In the event shrubbery or trees must be trimmed or removed, CM@R shall notify the property owner to do so within a reasonable time prior to construction. All shrubbery or trees not removed by the property owner shall be trimmed or removed by CM@R and hauled from the job at CM@R’S expense.
4.17.3 All trees, shrubs, hedges, brush, etc., designated on the Plans, or by PM/CM for removal, shall be completely removed and disposed of as indicated on the Plans or specified.
4.18
IRRIGATION DITCHES AND STRUCTURES TC "4.18
IRRIGATION DITCHES AND STRUCTURES" \f C \l "2"
CM@R shall contact the owners of any ditches, irrigation lines, and appurtenances which interfere with the Work and shall make arrangements for dry-up or scheduling of water deliveries. CM@R shall be liable for any damage due to irrigation facilities damaged by his operations and shall repair such damaged facilities to an "equal or better than" original condition.
4.19
ROADS AND FENCES TC "4.19
ROADS AND FENCES" \f C \l "2" 4.19.1 Streets and roads subjected to interference by the prosecution of this Work shall be kept open in compliance with Section 4.8 and shall be maintained by CM@R until the Work is completed.
4.19.2 All fences located in easements, when damaged or temporarily removed, shall be restored to a condition equal to or better than the original condition. Such fences shall be restored at CM@R’S expense.
4.20
PROTECTION OF WORK AND CLEANING UP TC "4.20
PROTECTION OF WORK AND CLEANING UP" \f C \l "2" 4.20.1 CM@R shall be responsible for the protection of all Work until its completion and final acceptance, and he shall at his own expense, replace damaged or lost material, or repair damaged parts of the Work, and CM@R and his Sureties shall be liable.
4.20.2 CM@R shall remove from the vicinity of the completed Work all plant, surplus material or equipment belonging to him or used under his direction during construction. All surplus excavated material, concrete, plaster and debris of all kinds shall be removed from TOLLESON’S premises, streets or portions of building or property at or adjacent to the site of the Work excepting that select material which may be required for refilling or grading the surface. Salvage material shall be stored at areas designated by PM/CM. Where an area is indicated to be "cleared", all the weeds, vegetation, shrubs and trees shall be removed unless they are specifically noted not to be removed.
4.20.3 In the event of abnormal weather conditions, such as windstorms and rainstorms, CM@R shall immediately inspect his Work area and take all necessary actions to insure that the project Site is protected and maintained.
4.21
METHODS AND EQUIPMENT TC "4.21
METHODS AND EQUIPMENT" \f C \l "2" 4.21.1 The methods and equipment adopted by CM@R shall be such as will secure a satisfactory quality of Work and will enable CM@R to complete the Work in the time agreed upon. The selection and use of these methods and equipment is the responsibility of CM@R.
4.21.2 When the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .