This document contains the specifications for the Gold Star Family Memorial Infrastructure Improvement project in Annapolis, Maryland. The project is being led by the Maryland Department of General Services (DGS) and includes the installation of a new parking lot, lighting, and an ADA-accessible route to the existing memorial. The project has a bid date of March 31, 2023, and the contract will be awarded to a single prime contractor.
The specifications outline the project scope, contract requirements, submittal procedures, quality assurance, temporary facilities and controls, product requirements, and other administrative details. An allowance has been included for unit-cost items. Minority Business Enterprises are encouraged to respond to this solicitation. The successful contractor will be required to provide a 24-month warranty on the completed project.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GOLD STAR FAMILY MEMORIAL
INFRASTRUCTURE IMPROVEMENTS
1919 Harwood Rd
Annapolis, MD 21409
STATE OF MARYLAND and
DEPARTMENT OF GENERAL SERVICES
Ellington E. Churchill, Jr., DGS Secretary
301 W. Preston St., Baltimore, Maryland 21201
BOARD OF PUBLIC WORKS
Larry Hogan, Governor Peter Franchot, Comptroller Nancy K. Kopp, Treasurer
B-450-210-001
PROJECT SPECIFICATIONS
March 31, 2023
Architect Civil Engineer WGM Architecture & Interiors Bay Engineering, Inc.
165 Log Canoe Circle, Suite B1 2661 Riva Road, Building 800 Stevensville, Maryland 21666 Annapolis, Maryland 21401
MEP Engineer Kibart, Inc.
901 Dulaney Valley Road, Suite 301 Towson, MD 21204
MINORITY BUSINESS ENTERPRISES ARE ENCOURAGED
TO RESPOND TO THIS SOLICITATION
GOLD STAR FAMILY MEMORIAL 2 - 1
INFRASTRUCTURE IMPROVEMENTS 95% CD - October 14, 2022
ANNAPOLIS, MD DGS # B-450-210-003
SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 0 – PROCUREMENT AND CONTRACTING REQUIREMENTS Pages
Notice To Bidders - Solicitation Fact Sheet (eMarylandMarketplace attachment) Instructions to Bidders for Construction Projects (March 2007) (eMarylandMarketplace attachment) General Conditions for Construction Contracts (August 2013) (eMarylandMarketplace attachment) Bid Proposal Affidavit (eMarylandMarketplace attachment) Contractors Questionnaire (eMarylandMarketplace attachment) Bid Bond, if applicable (eMarylandMarketplace attachment) Minority Business Enterprise Utilization Procedures (July 2014) (eMarylandMarketplace attachment) MBE Attachment D-1A Forms (eMarylandMarketplace attachment) List of Prevailing Wage Rates, if applicable Addenda, if any (eMarylandMarketplace attachment)
Pre-Bid Conference/Site Visit (Refer to: State Finace and Procurement Article §14- 302(a)(7)(v) and COMAR 21.11.03.09.C.(2)(e))
Seals and Signatures SS-1 to SS-1 List of Drawings 000001-1 to 000001-2
DIVISION 01 - GENERAL REQUIREMENTS Pages
011000 Summary 011000-1 to 011000-3 013300 Submittal Procedures 013300-1 to 013300-6 014000 Quality Requirements 014000-1 to 014000-6 015000 Temporary Facilities and Controls 015000-1 to 015000-10 016000 Product Requirements 016000-1 to 016000-4 017000 Execution Requirements 017000-1 to 017000-7 017700 Closeout Procedures 017700-1 to 017700-4 017823 Operation and Maintenance Data 017823-1 to 017823-6 017839 Project Record Documentation 017839-1 to 017839-3
DIVISION 02 – EXISTING CONDITIONS
024100 Selective Site Demolition 024100-1 to 024100-4
DIVISION 03 – CONCRETE
This Division not used
GOLD STAR FAMILY MEMORIAL 2 - 2
ANNAPOLIS, MD DGS # B-450-210-003
DIVISION 04 - MASONRY
This Division not used
DIVISION 05 – METALS
This Division not used
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
This Division not used
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
This Division not used
DIVISION 08 - OPENINGS
This Division not used
DIVISION 09 – FINISHES
This Division not used
DIVISION 10 – SPECIALTIES
This Division not used
DIVISION 11 – EQUIPMENT
This Division not used
DIVISION 12 - FURNISHINGS
GOLD STAR FAMILY MEMORIAL 2 - 3
ANNAPOLIS, MD DGS # B-450-210-003
DIVISION 13 – SPECIAL CONSTRUCTION
This Division not used
DIVISION 14 – CONVEYING SYSTEMS
This Division not used
DIVISIONS 21 – FIRE SUPPRESSION
This Division not used
DIVISIONS 22 & 23 – PLUMBING & MECHANICAL
This Division not used
DIVISION 26 – ELECTRICAL
260500 Common Work Results for Electrical 260500-1 to 260500-13 260519 Low Voltage Electrical Power Conductors & Cables 260519-1 to 260519-4 260526 Grounding and Bonding for Electrical Systems 260526-1 to 260526-5 260533 Raceways and Boxes for Electrical Systems 260533-1 to 260533-5 260543 Underground Ducts and Raceways for Electrical 260543-1 to 260543-7 262000 Low Voltage Electrical Distribution 262000-1 to 262000-4 265000 Lighting 265000-1 to 265000-8
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
GOLD STAR FAMILY MEMORIAL 2 - 4
ANNAPOLIS, MD DGS # B-450-210-003
DIVISION 31 – EARTHWORK
311000 Site Clearing 311000-1 to 311000-6 312000 Earth Moving 312000-1 to 312000-15
DIVISION 32 – EXTERIOR IMPROVEMENTS
321216 Asphalt Paving 321216-1 to 321216-8 321313 Concrete Paving 321216-1 to 321216-12 321373 Concrete Paving Joint Sealants 321216-1 to 321216-5 321723 Pavement Marking 321216-1 to 321216-3 329200 Turfs and Grasses 329200-1 to 329200-3 329300 Plants 329300-1 to 329300-11
DIVISION 33 – UTILITIES
334000 Storm Drainage Utilities 334000-1 to 334000-6
END OF SPECIFICATIONS TABLE OF CONTENTS
SS - 1 SEALS AND SIGNATURES BID
DOCUMENTS – March 31, 2023
DGS # B-450-210-001
SEALS AND SIGNATURES
Architect – Wheeler Goodman Masek & Associates
“The Contract Documents for the indicated public improvement (DGS # B-450-210-001) were prepared under my supervision and, to the best of my knowledge, information and belief, they comply with the relevant building codes of the State of Maryland.”
Civil Engineer – Bay Engineering, Inc.
"I hereby certify that these documents were prepared or approved by me, and that I am a duly licensed professional engineer under the laws of the State of Maryland, License No. 49194, Expiration Date 06-17-2024."
MEP Engineer – Kibart, Inc.
"I hereby certify that these documents were prepared or approved by me, and that I am a duly licensed professional engineer under the laws of the State of Maryland, License No. 17655, Expiration Date 01-11-2024."
GOLD STAR FAMILY MEMORIAL
ANNAPOLIS, MD
GOLD STAR FAMILY MEMORIAL 000001 - 1 LIST OF DRAWINGS
INFRASTRUCTURE IMPROVEMENTS BID DOCUMENTS – March 31, 2023
CHARLES COUNTY, MD DGS # B-450-210-001
SECTION 000001 – LIST OF DRAWINGS
GENERAL
G100 COVER SHEET
CIVIL
C-1 SITE GENERAL NOTES
C-2 EXISTING CONDITIONS PLAN
C-3 DEMOLITION PLAN
C-4 SITE PLAN
C-5 GRADING PLAN
C-6 SEDIMENT & EROSION CONTROL PLAN - PHASE 1
C-7 SEDIMENT & EROSION CONTROL PLAN - PHASE 2
C-8 SEDIMENT & EROSION CONTROL PLAN - PHASE 3
C-9 SEDIMENT & EROSION CONTROL DA AREA
C-10 EROSION & SEDIMENT CONTROL DETAILS & SPECIFICATIONS
C-11 EROSION & SEDIMENT CONTROL DETAILS & SPECIFICATIONS
C-12 EROSION & SEDIMENT CONTROL DETAILS & SPECIFICATIONS
C-13 EROSION & SEDIMENT CONTROL DETAILS & SPECIFICATIONS
C-14 SITE DETAILS PLAN
C-15 MICRO-BIORETENTION PLAN, DETAILS & SPECIFICATIONS
C-16 MICRO-BIORETENTION DETAILS & SPECIFICATIONS
C-17 REQUIRED WATER QUALITY/IMPERVIOUS AREA MAP
C-18 ESD DRAINAGE AREA MAP
C-19 PRE & POST-DEVELOPMENT DRAINAGE AREA MAP
LANDSCAPE
L-1 TREE PRESERVATION PLAN
L-2 LANDSCAPE PLAN
ELECTRICAL
E-001 COVER SHEET-ELECTRICAL
E-100 ELECTRICAL SITE PLAN - NEW WORK
E-100C ELECTRICAL SITE PLAN – PHOTOMETRICS
E-501 ELECTRICAL DETAILS AND SCHEDULES
END OF SECTION 000001
GOLD STAR FAMILY MEMORIAL 011000 - 1 SUMMARY
ANNAPOLIS, MD DGS # B-450-210-001
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Work under separate contracts.
4. Access to site.
5. Work restrictions.
6. Specification and drawing conventions.
1.3 PROJECT INFORMATION
A. Project Identification: GOLD STAR FAMILY MEMORIAL INFRASTRUCTURE IMPROVEMENTS
1. Project Location: 1919 Harwood Rd, Annapolis, MD 21409
B. Owner: Maryland Department of General Services, 301 W. Preston Street, Room 1405, Baltimore, MD 21201
1. Owner's Representative: Thomas LeQuire, Project Manager
C. Architect: WGM, 165 Log Canoe Circle, Suite B1, Stevensville, MD, 21666, 410-263-6787
1. Contact: Jeremy Kline, AIA, LEED AP BD+C, 410.2631.6787 x123
D. Architect's Consultants: The Architect has retained the following design professionals who have prepared designated portions of the Contract Documents:
1. Civil Engineer: Bay Engineering Inc., 2661 Riva Road, Building 800, Annapolis, Maryland 21401, 410-897-9290
2. MEP Engineer: Kibart, a Bowman Company, 901 Dulaney Valley Road, Suite 301, Towson, MD 21204, 410-494-1111
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following items:
1. The project consists of installation of a new parking lot to serve the Gold Star Family Memorial on the north side of Chase Road. The parking lot will include new lighting, and an ADA accessible route from the parking lot to the existing memorial. An add Alternate will include some select uplighting for the memorial and the introduction of a power pedestal in that area.
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.5 WORK UNDER SEPARATE CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract or other contracts. Coordinate the Work of this Contract with work performed under separate contracts.
GOLD STAR FAMILY MEMORIAL 011000 - 2 SUMMARY
ANNAPOLIS, MD DGS # B-450-210-001
B. Concurrent Work: Owner will award separate contract(s) for the following construction operations at Project site.
Those operations may be conducted simultaneously with work under this Contract.
1.6 ACCESS TO SITE
A. General: Contractor shall have full use of Project site for construction operations during construction period.
1.7 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
2. On-Site Work Hours: Monday through Friday, 7am – 4pm; and with other requirements of authorities having jurisdiction.
3. If artifacts are revealed as a result of construction activity, work must cease and the Department of General
Services shall be notified immediately.
B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Owner not less than 10 days in advance of proposed utility interruptions.
2. Obtain Owner's written permission before proceeding with utility interruptions.
C. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.
D. Controlled Substances: Use of tobacco products and other controlled substances on Project site is not permitted.
1.8 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall,"
"shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 1 General Requirements: Requirements of Sections in Division 1 apply to the Work of all Sections in the
Specifications.
C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the
Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual
Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings.
D. Warranty:
1. The Contractor must warrant the project as a whole for a period of 24 months from the date of
Substantial Completion. This warranty period is the minimum warranty period required for any and all elements of the project, but does not relieve the Contractor of additional and/or longer Warranty measures required by individual specification sections.
PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
GOLD STAR FAMILY MEMORIAL 012100 - 1
ANNAPOLIS, MD
SECTION 012100 ALLOWANCES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements governing allowances.
1. Certain items are specified in the Contract Documents by allowances. Allowances have been established in lieu of additional requirements and to defer selection of actual materials and equipment to a later date when additional information is available for evaluation. If necessary, additional requirements will be issued by Change Order.
B. Types of allowances include the following:
1. Unit-cost allowances.
C. Related Sections include the following:
1. Division 1 Section "Contract Modification Procedures" for procedures for submitting and handling Change Orders for allowances.
2. Division 1 Section "Unit Prices" for procedures for using unit prices.
1.3 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, advise Architect of the date when final selection and purchase of each product or system described by an allowance must be completed to avoid delaying the Work.
B. At Architect's request, obtain proposals for each allowance for use in making final selections. Include recommendations that are relevant to performing the Work.
C. Purchase products and systems selected by Architect from the designated supplier.
1.4 SUBMITTALS
A. Submit proposals for purchase of products or systems included in allowances, in the form specified for Change Orders.
B. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.
C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
ALLOWANCES
BID DOCUMENTS – March 31, 2023
DGS # B-450-210-001
GOLD STAR FAMILY MEMORIAL 012100 - 2
ANNAPOLIS, MD
1.5 COORDINATION
A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.
1.6 UNIT-COST ALLOWANCES
A. Allowance shall include cost to Contractor of specific products and materials under allowance and shall include taxes, freight, and delivery to Project site.
B. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials under allowance shall be included as part of the Contract Sum and not part of the allowance.
C. Allowance Adjustment: The base bid shall include all unit price items in the quantities indicated in the schedule at the end of this section. To adjust allowance amounts, prepare a Change Order proposal based on the difference between the indicated allowance quantity and the verified quantity of work performed for each unit price item, multiplied by the submitted unit price.
1. If verified quantity is less than the scheduled quantity allowance, Change Order proposal shall be a credit back to the project.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 ALLOWANCE UTILISATION
A. The overall dollar amount for each allowance item included in each scope of work will be required to be shown on the prime Schedule of Values under the headers: "Unit Rate Allowance #...". Use of allowances shall be tracked in the field via signed tickets; allowances may not be used without prior written approval, and compensation will not be provided without signed tickets.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF UNIT PRICE ALLOWANCES
A. See “Unit Price Schedule” in “Unit Price” section.
END OF SECTION 012100
ALLOWANCES
GOLD STAR FAMILY MEMORIAL 013300 - 1
ANNAPOLIS, MD
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
B. Related Requirements:
1. Division 1 Section "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data.
2. Division 1 Section "Operation and Maintenance Data" for submitting operation and maintenance manuals.
3. Division 1 Section "Demonstration and Training" for submitting video recordings of demonstration of equipment and training of Owner's personnel.
1.3 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require Architect's responsive action.
Action submittals are those submittals indicated in individual Specification Sections as "action submittals."
B. Informational Submittals: Written and graphic information and physical samples that do not require Architect's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."
C. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.
1.4 ACTION SUBMITTALS
A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Architect and additional time for handling and reviewing submittals required by those corrections.
1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule.
2. Submit concurrently with the first complete submittal of Contractor's construction schedule.
3. Format: Arrange the following information in a tabular format:
a. Scheduled date for first submittal.
b. Specification Section number and title.
c. Submittal category: Action; informational.
d. Name of subcontractor.
e. Description of the Work covered.
f. Scheduled date for Architect's final release or approval.
g. Scheduled date of fabrication.
h. Scheduled dates for purchasing.
i. Scheduled dates for installation.
j. Activity or event number.
1.5 SUBMITTAL ADMINISTRATIVE REQUIREMENTS
SUBMITTAL PROCEDURES
GOLD STAR FAMILY MEMORIAL 013300 - 2
ANNAPOLIS, MD
A. Architect's Digital Data Files: Electronic digital data files of the Contract Drawings will not be provided by Architect for Contractor's use in preparing submittals.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.
3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.
4. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Architect's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Architect will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow 15 days for review of each resubmittal.
4. Sequential Review: Where sequential review of submittals by Architect's consultants, Owner, or other parties is indicated, allow 24 days for initial review of each submittal.
5. Concurrent Consultant Review: Where the Contract Documents indicate that submittals may be transmitted simultaneously to Architect and to Architect's consultants, allow 18 days for review of each submittal.
Submittal will be returned to Architect before being returned to Contractor.
D. Paper Submittals: Place a permanent label or title block on each submittal item for identification.
E. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
F. Options: Identify options requiring selection by Architect.
G. Deviations and Additional Information: On an attached separate sheet, prepared on Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by Architect on previous submittals, and deviations from requirements in the Contract Documents, including minor variations and limitations. Include same identification information as related submittal.
H. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are marked with approval notation from Architect's action stamp.
I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
J. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Architect's action stamp.
PART 2 - PRODUCTS
SUBMITTAL PROCEDURES
GOLD STAR FAMILY MEMORIAL 013300 - 3
ANNAPOLIS, MD
2.1 SUBMITTAL PROCEDURES
A. General Submittal Procedure Requirements: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.
1. Submit electronic submittals via email as PDF electronic files.
(Typical distribution procedure.)
a. Architect will return annotated file. Annotate and retain one copy of file as an electronic Project record document file.
2. Submit electronic submittals via email as PDF electronic files and paper submittals as follows:
(Distribution procedure for submittals larger than 11 x 17, when printed.)
3. Action Submittals: Submit five paper copies of each submittal unless otherwise indicated. Architect will return two copies.
4. Informational Submittals: Submit three paper copies of each submittal unless otherwise indicated. Architect will not return copies.
5. Certificates and Certifications Submittals: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
4. For equipment, include the following in addition to the above, as applicable:
a. Wiring diagrams showing factory-installed wiring.
b. Printed performance curves.
c. Operational range diagrams.
d. Clearances required to other construction, if not indicated on accompanying Shop Drawings.
5. Submit Product Data before or concurrent with Samples.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement.
f. Relationship and attachment to adjoining construction clearly indicated.
g. Seal and signature of professional engineer if specified.
D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
SUBMITTAL PROCEDURES
GOLD STAR FAMILY MEMORIAL 013300 - 4
ANNAPOLIS, MD
2. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Number and title of applicable Specification Section.
e. Specification paragraph number and generic name of each item.
3. For projects where electronic submittals are required, provide corresponding electronic submittal of Sample transmittal, digital image file illustrating Sample characteristics, and identification information for record.
4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
a. Samples that may be incorporated into the Work are indicated in individual Specification Sections.
Such Samples must be in an undamaged condition at time of use.
b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.
5. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
a. Number of Samples: Submit three full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Architect will return one submittal with options selected.
6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components;
small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
a. Number of Samples: Submit three sets of Samples. Architect will retain two Sample sets; remainder will be returned.
1) Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated.
2) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations.
E. Coordination Drawing Submittals: Comply with requirements specified in Division 1 Section "Project Management and Coordination."
F. Application for Payment and Schedule of Values: Comply with requirements specified in Division 1 Section "Payment Procedures."
G. Test and Inspection Reports and Schedule of Tests and Inspections Submittals: Comply with requirements specified in Division 1 Section "Quality Requirements."
H. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified in Division 1 Section "Closeout Procedures."
I. Maintenance Data: Comply with requirements specified in Division 1 Section "Operation and Maintenance Data."
J. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person.
Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified.
K. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.
SUBMITTAL PROCEDURES
GOLD STAR FAMILY MEMORIAL 013300 - 5
ANNAPOLIS, MD
L. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
M. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.
N. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
O. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
P. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
Q. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
R. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:
1. Name of evaluation organization.
2. Date of evaluation.
3. Time period when report is in effect.
4. Product and manufacturers' names.
5. Description of product.
6. Test procedures and results.
7. Limitations of use.
S. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
T. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
U. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
V. Design Data: Prepare and submit written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.
2.2 DELEGATED-DESIGN SERVICES
A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.
1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Architect.
SUBMITTAL PROCEDURES
GOLD STAR FAMILY MEMORIAL 013300 - 6
ANNAPOLIS, MD
B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally signed PDF electronic file and three paper copies of certificate, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.
1. Indicate that products and systems comply with performance and design criteria in the Contract Documents.
Include list of codes, loads, and other factors used in performing these services.
PART 3 - EXECUTION
3.1 CONTRACTOR'S REVIEW
A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Architect.
B. Project Closeout and Maintenance Material Submittals: See requirements in Division 1 Section "Closeout Procedures."
C. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
3.2 ARCHITECT'S ACTION
A. Action Submittals: Architect will review each submittal, make marks to indicate corrections or revisions required, and return it. Architect will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action.
B. Informational Submittals: Architect will review each submittal and will not return it, or will return it if it does not comply with requirements. Architect will forward each submittal to appropriate party.
C. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Architect.
D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.
E. Submittals not required by the Contract Documents may be returned by the Architect without action.
END OF SECTION 013300
SUBMITTAL PROCEDURES
GOLD STAR FAMILY MEMORIAL 014000 - 1
ANNAPOLIS, MD
SECTION 014000 - QUALITY REQUIREMENTS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for quality assurance and quality control.
B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.
1. Specific quality-assurance and -control requirements for individual construction activities are specified in the
Sections that specify those activities. Requirements in those Sections may also cover production of standard products.
2. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -control procedures that facilitate compliance with the Contract Document requirements.
3. Requirements for Contractor to provide quality-assurance and -control services required by Architect, Owner, or authorities having jurisdiction are not limited by provisions of this Section.
C. Related Requirements:
1. Divisions 2 through 31 Sections for specific test and inspection requirements.
1.3 DEFINITIONS
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.
B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements.
Services do not include contract enforcement activities performed by Architect.
C. Preconstruction Testing: Tests and inspections performed specifically for Project before products and materials are incorporated into the Work, to verify performance or compliance with specified criteria.
D. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with specified requirements.
E. Source Quality-Control Testing: Tests and inspections that are performed at the source, e.g., plant, mill, factory, or shop.
F. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.
G. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.
H. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.
QUALITY REQUIREMENT
GOLD STAR FAMILY MEMORIAL 014000 - 2
ANNAPOLIS, MD
1. Use of trade-specific terminology in referring to a trade or entity does not require that certain construction activities be performed by accredited or unionized individuals, or that requirements specified apply exclusively to specific trade(s).
I. Experienced: When used with an entity or individual, "experienced" means having successfully completed a minimum of five previous projects similar in nature, size, and extent to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.
1.4 CONFLICTING REQUIREMENTS
A. Referenced Standards: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement.
Refer conflicting requirements that are different, but apparently equal, to Architect for a decision before proceeding.
B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding.
1.5 INFORMATIONAL SUBMITTALS
A. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
1.6 REPORTS AND DOCUMENTS
A. Test and Inspection Reports: Prepare and submit certified written reports specified in other Sections. Include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples and tests or inspections.
5. Names of individuals making tests and inspections.
6. Description of the Work and test and inspection method.
7. Identification of product and Specification Section.
8. Complete test or inspection data.
9. Test and inspection results and an interpretation of test results.
10. Record of temperature and weather conditions at time of sample taking and testing and inspecting.
11. Comments or professional opinion on whether tested or inspected Work complies with the Contract
Document requirements.
12. Name and signature of laboratory inspector.
13. Recommendations on retesting and reinspecting.
B. Manufacturer's Technical Representative's Field Reports: Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections. Include the following:
1. Name, address, and telephone number of technical representative making report.
2. Statement on condition of substrates and their acceptability for installation of product.
3. Statement that products at Project site comply with requirements.
4. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.
5. Results of operational and other tests and a statement of whether observed performance complies with requirements.
6. Statement whether conditions, products, and installation will affect warranty.
7. Other required items indicated in individual Specification Sections.
QUALITY REQUIREMENT
GOLD STAR FAMILY MEMORIAL 014000 - 3
ANNAPOLIS, MD
C. Factory-Authorized Service Representative's Reports: Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections. Include the following:
1. Name, address, and telephone number of factory-authorized service representative making report.
2. Statement that equipment complies with requirements.
3. Results of operational and other tests and a statement of whether observed performance complies with requirements.
4. Statement whether conditions, products, and installation will affect warranty.
5. Other required items indicated in individual Specification Sections.
1.7 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.
B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
D. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar in material, design, and extent to those indicated for this Project.
F. Specialists: Certain Specification Sections require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.
1. Requirements of authorities having jurisdiction shall supersede requirements for specialists.
G. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 329; and with additional qualifications specified in individual Sections; and, where required by authorities having jurisdiction, that is acceptable to authorities.
1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7.
2. NVLAP: A testing agency accredited according to NIST's National Voluntary Laboratory Accreditation
Program.
H. Manufacturer's Technical Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
I. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
J. Preconstruction Testing: Where testing agency is indicated to perform preconstruction testing for compliance with specified requirements for performance and test methods, comply with the following:
1. Contractor responsibilities include the following:
a. Provide test specimens representative of proposed products and construction.
QUALITY REQUIREMENT
GOLD STAR FAMILY MEMORIAL 014000 - 4
ANNAPOLIS, MD
b. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying the Work.
c. Provide sizes and configurations of test assemblies, mockups, and laboratory mockups to adequately demonstrate capability of products to comply with performance requirements.
d. When testing is complete, remove test specimens, assemblies, and mockups; do not reuse products on Project.
2. Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and similar quality-assurance service to Architect, with copy to Contractor. Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
1.8 QUALITY CONTROL
A. Contractor Responsibilities: All tests, inspections, and other quality control services specified by DGS or any other authorities having jurisdiction are Contractor’s responsibility. Cost for all services shall be included in the Contract price. Perform additional quality-control activities required to verify that the Work complies with requirements, whether specified or not.
1. Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.
2. Where services are indicated as Contractor's responsibility, engage a qualified testing agency to perform these quality-control services.
3. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed.
4. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service.
5. Testing and inspecting requested by Contractor and not required by the Contract Documents are Contractor's responsibility.
6. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.
B. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified in Division 1 Section "Submittal Procedures."
C. Manufacturer's Technical Services: Where indicated, engage a manufacturer's technical representative to observe and inspect the Work. Manufacturer's technical representative's services include participation in preinstallation conferences, examination of substrates and conditions, verification of materials, observation of Installer activities, inspection of completed portions of the Work, and submittal of written reports.
D. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents.
E. Testing Agency Responsibilities: Cooperate with Architect and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.
1. Notify Architect and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.
2. Determine the location from which test samples will be taken and in which in-situ tests are conducted.
3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from…