Attachment E - Submittals
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 05_-_KE-AIR_AIR-CW_SPEC_-_Amendment_4.docx | DOCX document | |
| DE-SOL-0010658_000004.pdf | ||
| DE-SOL-0010658_000003.pdf | ||
| Site_Visit_Attendance_Roster.pdf | ||
| DE-SOL-0010658_000002.pdf | ||
| DE-SOL-0010658.pdf | ||
| DE-SOL-0010658_000001.pdf | ||
| 05_-_0512_KE-AIR_AIR-CW_bidding_schedule.pdf | ||
| 21_-_DE-SOL-0010658.pdf | ||
| Foreign_National_Data_Card.pdf | ||
| 12_-_Wage_Determination.pdf | ||
| ke_air_cw_final_project_dwgs_11_14_16.pdf | ||
| 05_-_0512_KE-AIR_AIR-CW_spec_841_50715DC.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Title:
KESWICK-AIRPORT 230-KV TRANSMISSION LINE RECONDUCTORING
PROJECT Award Date:
Contract No.: NTP:
Contractor: Completion Date:
Contractor's Western's Location Date Submittal Item In Date Approved
# # Submittal Item Standards Date Due Submitted Rejected COMMENTS
STANDARD 1
1 Construction Schedule 1.1.4.1. (see Project Specifications)
2 Breakdown of Contract Prices 1.1.6.1. NLT 30-days after
NTP
3 Railways, Highways, and Utility Lines 1.3.5.3. Prior to starting stringing
4 Safety and Health Program 1.4.1.5. NLT 10-days prior to start of construction
5 Copies of Certifications, Test Records & Technical Data 1.4.1.10. Prior to use
6 - Load Performance Tests 1.4.1.10.(1) Prior to use
7 - Crane & Aerial Lift Equipment Annual Inspection Records 1.4.1.10.(2) Prior to use
8 - Brake Performance Test 1.4.1.10.(3) Prior to use
9 - Test Results of Protective Ground Leads 1.4.1.10.(4) Prior to use
10 - Material Safety Data Sheets 1.4.1.10.(5) Prior to use
11 - Manufacturer's Load Rating For Hoists and Grips 1.4.1.10.(6) Prior to use
12 - Certification of Fabricated Lifting and Rigging Devices 1.4.1.10.(7) & 1.4.11 Prior to use
13 - Medical Examiner's Certificate 1.4.1.10.(8) & 1.4.3.3 Prior to use
14 - Data For Excavation Protective System 1.4.1.10.(9) & 1.4.5.5 Prior to use
15 Assurance of Competency in Equipment Operation 1.4.3.4. Prior to use
16 Suspended Work Cart Work Procedure 1.4.12 Prior to use
17 Helicopter Operations and Safety Program 1.4.13 NLT 15-days prior to helicopter operations
18 Protective Ground Lead Test Results & Certification 1.4.14.3. Prior to use
19 Clearance, Hot Line Order & Special Work Permit Requests 1.4.15.3.
NLT 10-working days prior to starting work
20 Stringing Plan 1.4.17.3. Prior to stringing
21 HLO/Clearance Approval or Denial From Other Utilities 1.4.17.4.(3) 1) Prior to stringing
22 Transmission Line Removal Plan 1.4.18 Prior to removal
STANDARD 10
SUBMITTAL TRACKING SHEET
DE-SOL-0010658
Attachment E
Contractor's Western's Location Date Submittal Item In Date Approved
# # Submittal Item Standards Date Due Submitted Rejected COMMENTS
23 Catalog Data Sheets of Accessories & Hardware Used In Conductor & Overhead Ground Wire Installation 10.2.2. NLT 40-days prior to material installation
24 Drawings of Insulator & Overhead Groundwire Assemblies and Details 10.2.2. NLT 40-days prior to material installation
25 Complete Material List 10.2.2. NLT 40-days prior to material installation
26 Conductor Insulator Assembly Test Reports 10.2.3.1. & 10.3.3. ASAP
27 Conductor Test Reports 10.2.3.2. & 10.6.1.2. ASAP
28 Overhead Groundwire Test Reports 10.2.3.3. & 10.6.2.2. ASAP
29 Overhead Groundwire Assemblies Test Reports 10.2.3.4. & 10.4.3. ASAP
30 Ground Resistance Measurements 10.2.3.5. & 10.5.3. ASAP
31 Vibration Damper Data, Drawings, and Test Reports 10.2.3.6. & 10.6.4.3. ASAP
32 Conductor Spacer Damper Test Reports 10.2.3.7. & 10.6.6.2. ASAP
33 Optical Overhead Groundwire Test Reports 10.2.3.8. & 10.6.3.2. ASAP
34 Assembly & Installation Instructions For Conductor Insulator Assemblies 10.3.4 NLT two weeks prior to installation
35 Optical Overhead Groundwire Suspension Clamp Attachment Assemblies 10.4.2.3. Prior to use
STANDARD 13
36 Recycled Materials Quantity Report 13.2.1. & 13.7.2. Prior to Final Invoice submission
37 Products Containing Recovered Materials Report 13.2.2. & 13.8.3. Prior to Final Invoice submission
38 Waste Material Quantity Report 13.2.2. Prior to Final Invoice submission
39 Spill Prevention, Notification and Clean-up Plan 13.2.5. NLT 14-days prior to start of work
40 Prevention of Air Pollution Permits 13.2.9. NLT 14-days prior to start of work
41 Clean Vehicle Policy 13.5 & 13.A.1.e. Prior to start of work
42 Stormwater Pollution Prevention Plan 13.16 NLT 14-days prior to start of work
STANDARD 15
43 As-Built Drawings 15.2.6. Prior to Final Invoice submission
*Submittal required if item is used in the performance of the contract.
"NLT"= No Later Than "NTP"= Notice To Proceed "ASAP"= As Soon As Practicable
DE-SOL-0010658
Attachment E
Sheet1