Attch D Submittal Log
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_2.pdf | ||
| Amendment_3.pdf | ||
| Attch_A_-_Amendment_3_Bidding_Schedule_.pdf | ||
| Attch_B_-__Amendment_3_Specifications_.pdf | ||
| Attch_C-_Amendment_3_Drawings.pdf | ||
| Amendment_2.pdf | ||
| Amendment_00001.pdf | ||
| 21e_Attch_C_Amendment_1_Drawings.pdf | ||
| 21e_Attch_C_Drawings_Table_of_Contents_Rev_7_8_15.pdf | ||
| 21c_Attch_B__Specifications_-_REV_7_9_15.pdf | ||
| Pre-Bid_Site_visit_attendees.pdf | ||
| 21d_Attch_A_-_Bidding_Schedule_Rev_7_8_15.pdf | ||
| 21h_Attch_F_-_Foreign_National_Data_Card.pdf | ||
| 21g_Attch_E_Wage_Determination_NV150022_1_23_2015.pdf | ||
| 21e__Attch_C_-_Drawings.pdf | ||
| 21d_Attch_A_-_Bidding_Schedule.pdf | ||
| 21c_Attch_B_-_Specifications.pdf | ||
| 21i_Attch_G_o442_21_(2).pdf | ||
| Solicitation_DE-SOL-0008469.pdf | ||
| Amendment_2.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Title: Mead Substation Stage 15 Award Date:
Contract No.: NTP:
Contractor: Completion Date:
Location Date Submittal Item In Date Date Sent to Date
# # Submittal Item Standards Due Submitted CSO Approved COMMENTS
STANDARD 1
1 Construction Schedule 1.1.4.1. (see project spec)
2 Survey Plan 1.1.5.2.(1) Prior to survey work
3 Breakdown of Contract Prices 1.1.6.1. NLT 30 days after NTP
4 Electrical Equipment & Steel Purchase Orders 1.2.3.1.
NLT 10 working days after PO award
5 Cable Location Plan w/Print of Locations 1.3.4.2 & 1.4.5.2 Prior to starting excavation
6 Acknowledgement When Stringing Over Energized Lines 1.3.5.3. Prior to starting stringing
7 Safety and Health Program 1.4.1.5.
NLT 10 days prior to start of construction
8 Copies of Certifications, Test Records & Technical Data 1.4.1.10. Prior to use
9 - Load Performance Tests 1.4.1.10.(1) Prior to use
10 - Crane & Aerial Lift Equipment Annual Inspection Records 1.4.1.10.(2) Prior to use
11 - Brake Performance Test 1.4.1.10.(3) Prior to use
12 - Test Results of Protective Ground Leads 1.4.1.10.(4) Prior to use
13 - Material Safety Data Sheets 1.4.1.10.(5) Prior to use
14 - Manufacturer's Load Rating For Hoists and Grips 1.4.1.10.(6) Prior to use
15 - Certification of Fabricated Lifting and Rigging Devices 1.4.1.10.(7) & 1.4.11 Prior to use
16 - Medical Examiner's Certificate 1.4.1.10.(8) & 1.4.3.3 Prior to use
17 - Data For Excavation Protective System 1.4.1.10.(9) & 1.4.5.5 Prior to use
18 Assurance of Competency in Equipment Operation 1.4.3.4. Prior to use
19 Respiratory Protection Program 1.4.4.8 Prior to work requiring resp.
protection
20 Structure Erection Plan 1.4.8.1. Prior to structure erection
21 Protective Ground Lead Test Results & Certification 1.4.14.3. Prior to use
22 Clearance, Hot Line Order & Special Work Permit Requests 1.4.15.3.
NLT 10 working days prior to starting work
23 Stringing Plan 1.4.17.3. Prior to stringing
24 HLO/Clearance Approval or Denial From Other Utilities 1.4.17.4.(3) 1) Prior to stringing
STANDARD 2
SUBMITTAL TRACKING SHEET
Location Date Submittal Item In Date Date Sent to Date
# # Submittal Item Standards Due Submitted CSO Approved COMMENTS
25 Earth Material Testing Laboratory 2.1.1.2.(1) & 2.7.1.2.(1) 20 days prior to compacting
26 Earth Material Compaction Test Reports 2.1.1.2.(2)& 2.7.1. Immed. after test complete
27 Gravel Surfacing Material Gradation 2.1.1.4 Prior to placing
28 Gravel Surfacing Density & Compaction Test Results 2.1.1.4 NLT 7 days after test complete
29 Herbicide Applicator's References 2.1.1.5.(1) & 2.11.3.2.
NLT 30 calendar days prior to application
30 Herbicide Applicator's Certification/License 2.1.1.5.(2) NLT 30 calendar days prior to application
31 Herbicide Application Plan 2.1.1.5.(3) NLT 30 calendar days prior to application
32 Herbicide Application Final Report 2.1.1.5.(4) NLT 7 days after application
33 Batch Certification 2.1.1.7.(6) NLT 20 days prior to paving
34 Earth Backfill Material 2.3.1.3. & 2.8.1.2.(1) Prior to refill
STANDARD 3
35 Concrete Testing Laboratory 3.1.1.2.(1) & 3.1.1.3.
NLT 20 days prior to concrete placement
36 Concrete Mix Design 3.1.1.2.(2) & 3.1.1.5. NLT 10 days prior to use
37 Fly Ash For Concrete 3.1.1.2.(5) & 3.1.1.4. NLT 20 days prior to use
38 Admixtures and Curing Compound 3.1.1.2.(6) & 3.1.1.4. NLT 10 days prior to use
39 Batch Certificates 3.1.1.2.(7) Provide at delivery
40 Test Reports 3.1.1.2.(8) Immed. upon completing
41 Void Forming Material 3.1.1.2.(9) & 3.1.1.4. &
3.1.4.2. Prior to use
42 Nonshrink Grout 3.1.1.2.(10) Prior to use
43 Drawings & Data For Electrical Equip. Foundation Design 3.2.1.2. Prior to installation
44 Approval Drawings For Precast Cable Trench 3.2.1.3. Prior to precasting
45 Approval Drawings For Precast Concrete Pull Boxes 3.2.1.4. Prior to precasting
46 Final Drawings For Precast Cable Trench & Pull Boxes 3.2.1.5. Prior to material shipment
STANDARD 4
47 Approval Drawings For Steel Structures & Steel Modifications 4.1.1.2. Prior to fabrication
48 Approval Drawings & Data For Oil Storage Tanks 4.1.1.3. Prior to fabrication
49 Final Drawings For Steel Structures & Oil Storage Tanks 4.1.1.4. Prior to material shipment
# # Submittal Item Standards Due Submitted CSO Approved COMMENTS
50 Weld Procedures 4.1.1.5.(1) & 4.1.7.4. Prior to fabrication
51 Partial Penetration Weld - Test & Evaluation Procedure 4.1.1.5.(2) & 4.1.7.4. Prior to fabrication
52 Nondestructive & Metallographic Test Reports 4.1.1.5.(3) & 4.1.7.4. NLT 20 days after test
53 Connection Bolts 4.1.1.6. Prior to fabrication
54 Mill Test Reports 4.1.1.7. Prior to fabrication
55 Dulling Surface Treatment For Galvanizing 4.1.1.8. Prior to use
56 Tower Test Procedures 4.1.1.9.(1) Prior to testing
57 Calibration of Load Testing Devices 4.1.1.9.(2) NLT 5 days prior to testing
58 Tower Test Report 4.1.1.9.(3) NLT 4 weeks after testing
59 Certified Mill Test Reports 4.1.5.3. Prior to shipping material
60 Magnetic Particle and Dye Penetrant Weld Test (if required by COR) 4.1.7.5. Upon test completion
61 Master List of Bundles - Steel Structure & Tower Material 4.1.13 Upon completion of material bundling
STANDARD 9
62 Contractor On-site Test Personnel 9.1.2.2.(2) Prior to working on-site
63 Electrical Test Reports & Documents 9.1.2.2.(3) NLT 7 days after testing
64 Continuity & Megohmmeter Testing Personnel 9.1.2.2.(7) Prior to testing
65 Infrared Inspection Tape 9.1.2.2.(15) NLT 48 hours after testing
66 Equipment Installation Drawings Including Seismic Qualification Report Table 9-1 & 9.1.3.2. NLT 60 days after NTP
67 Equipment Informational Drawings & Data Table 9-1 & 9.1.3.3. NLT 60 days after NTP
68 Equipment Final Drawings Table 9-1 & 9.1.3.4.(1) NLT 21 days prior to equip.
installation
69 Equipment Parts Identification Lists & Bills of Materials Table 9-1 & 9.1.3.4.(2) NLT 21 days prior to equip.
installation
70 Manufacturer's Operation & Maintenance Instructions Table 9-1 & 9.1.3.4.(3) NLT 21 days prior to equip.
installation
71 Equipment & Oil Test Reports Table 9-1 & 9.1.3.5. Prior to shipping equipment
72 Equipment Insulating Liquid PCB Certification Table 9-1 & 9.1.3.6. Prior to delivery of oil or equip.
73 Insulated Conductor Data Table 9-1 & 9.1.3.7. NLT 60 days after NTP
74 Revised Wiring Diagrams Table 9-1 & 9.1.3.9.
NLT 60 days after receipt of drawings
# # Submittal Item Standards Due Submitted CSO Approved COMMENTS
75 Contractor's As-Built Equipment Drawings Table 9-1 & 9.1.3.10.(1) NLT 60 days after equip.
checkout
76 As-built Western Drawings Table 9-1 & 9.1.3.10.(2) NLT 60 days after equip.
checkout
77 Test Reports For Ground Tests 9.2.1.3.
NLT 15 days after completion of testing
STANDARD 12
78 Manufacturer's Data 12.1.1.2.
STANDARD 13
79 Recycled Materials Quantity Report 13.2.1. & 13.7.2.
80 Products Containing Recovered Materials Report 13.2.2. & 13.8.3.
81 Spill Prevention Notification & Cleanup Plan 13.2.5. & 13.11.2.
82 Tanker Oil Spill Prevention & Response Plan 13.2.6. & 13.11.3.
83 Pesticide Use Plan 13.2.7 & 13.12.3.
84 Asbestos Licenses or Certificates 13.2.10. & 13.15.
85 Water Pollution Permits 13.2.12. & 13.17.2.
86 PCB Test Reports 13.2.13 & 13.18.2
87 Oil & Oil-Filled Electrical Equipment Receipt 13.2.14. & 13.18.5.
88 Cleanup Work Management Plan 13.2.16. & 13.19.2.
89 Post Cleanup Report 13.2.17. & 13.19.7.
STANDARD 15
90 As-Built Drawings 15.2.6.
*Submittal required if item is used in the performance of the contract.
"T"= Submit transmittal sheet only.
"NLT"= No Later Than "NTP"= Notice To Proceed "ASAP"= As Soon As Practicable