Amendment_00004_Spec_Page_49.docx

DOCX document 19 KB Posted

Attached to
Longtin Substation, Stage 02 construction project Federal contract opportunity
Solicitation number
DE-SOL-0005448
Issued by
Department of Energy Western Area Power Administration

About this file

Amend. 000004 Spec Page 49

View the file

Other files for this federal contract opportunity

Other files attached to Longtin Substation, Stage 02 construction project, newest first.
File Type Posted
Amendment_00004_Spec_Page_12.docx DOCX document
SF-30_Amend._000004.pdf PDF
Amendment_00004_Spec_Page_47_.docx DOCX document
Amendment_000004_Spec_Pages_1-9_Table_of_Contents.pdf PDF
Amendment_00004_Spec_Page_23_.docx DOCX document
Amendment_00004_Spec_Page_14.docx DOCX document
Amendment_000004_spec_page_50.docx DOCX document
Amendment_00004_Spec_Page_22.docx DOCX document
Amendment_00004_Spec_Page_18.docx DOCX document
Amendment_00003_Spec_Page_10_.docx DOCX document
ATTCH_E_-_WD_AZ27-_Building.pdf PDF
Amendment_00003_Spec_Page_12_.docx DOCX document
Amendment_000003_spec_page_104.docx DOCX document
Amendment_00003_Spec_Page_14.docx DOCX document
Amendment_00003_Spec_Page_47_.docx DOCX document
ATTCH_D_-_WD_AZ14-_Heavy.pdf PDF
Amendment_00003_Spec_Page_23_.docx DOCX document
LNG02_Amendment_000003_List_6-28-13_Drawing_List.pdf PDF
ATTCH_A-_Bid_Schedule-_Amendment_00003.pdf PDF
Amendment_000003_spec_page_50.docx DOCX document
Amendment_00003_Spec_Page_18.docx DOCX document
Amendment_00003_Spec_Page_22_.docx DOCX document
Terms_and_Cond._Page_30-6.28.2013.pdf PDF
SF-30-_Amend._000003.pdf PDF
Drawings-Amendment_000002.pdf PDF
List_of_Drawings-Amendment_000002.pdf PDF
ATTCH_B-_SPECS_Amendment_000002.pdf PDF
ATTCH_A-_Bid_Schedule-_Amendment_000002.pdf PDF
Site_Visit_Attendees.pdf PDF
For_Information_Only_Davis_Transformer_Dwgs-Amend._000002.pdf PDF
SF30-Amend._000002.pdf PDF
SF30-Amend._000001.pdf PDF
ATTCH_E_-_WD_AZ27-_Building.pdf PDF
ATTCH_A-_Bid_Schedule-4.19.13.pdf PDF
ATTCH_D_-_WD_AZ14-_Heavy.pdf PDF
ATTCH_C-_DRAWINGS_5.7.2013.pdf PDF
ATTCH_B-_SPECS_5.7.13.pdf PDF
Solicitation.pdf PDF
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 000004

CONDUCTOR CHARACTERISTICS
DAVIS DAM-PARKER DAM No. 1

230-kV

Weight (LBS/FT)
0.896
Ultimate strength, as computed for the strength of the individual strands, not less than (LBS)
31,100
Aluminum strands Number
26
Composite strands Number
7

Stringing, splicing, sagging, and clipping in three spans of existing 1/2-inch-diameter, galvanized, high-strength steel, 7-strand overhead ground wire as described; and furnishing and installing material to complete the overhead ground wire installation, except for material furnished and installed as part of tension assemblies for overhead ground wires and accessories.

Performing all work to re-install any vibration dampers for 795 kcmil, ACCR, “Drake/3M” conductors and 1/2-inch diameter, galvanized, high-strength steel, 7-strand overhead ground wires in the two (2) spans at structures 13/1 to 13/2 and 13/3 to13/4. If only one (1) damper is currently in the span, one (1) damper should be located at the existing damper distance from the existing suspension structures. If two (2) dampers are currently located one (1) at each end of the span, then locate one (1) damper at the new structure and one (1) at the existing structure, at the existing damper distance. If two (2) dampers are currently in the same span, both at the same structure, locate both dampers at the existing damper distance from the suspension structures.

Bidding Schedule items “Furnishing and installing optical overhead ground wire assemblies” include furnishing material and performing work and tests to furnish and install optical overhead ground wire assemblies complete with suspension clamp or bolted dead end, suitable for 0.465-inch diameter, 48 fiber optical overhead ground wire, shown on drawing 41 1031. An estimate of material quantities for each type of structures is shown on drawing DAD-PAD 1 1005.

Optical overhead ground wire assemblies shall comply with the characteristics of Table 10-3.

TABLE 10-3 – OPTICAL OVERHEAD GROUND WIRE ASSEMBLY CHARACTERISTICS

OPTICAL OVERHEAD GROUND WIRE ASSEMBLY CHARACTERISTICS
OPGW-SA SUSPENSION
OPGW-SL SUSPENSION
OPGW-TH SUSPENSION
OPGW-TLV TENSION
OPGW-TV TENSION
Minimum Ultimate Strength (LBS)
15,000
15,000
20,000
20,000
20,000

Bidding Schedule item “Furnishing and installing one (1) 0.465-inch diameter, 48 fiber optical overhead ground wire” includes furnishing and stringing, sagging, and clipping in the optical overhead ground wire and furnishing and installing material to complete the optical overhead ground wire installations, except for material furnished and installed as a part of suspension and tension assemblies for optical overhead ground wires and accessories.

The OPGW shall be installed from the Take-Off Structure at Longtin Substation (Station 765+61.4) to the Take-Off Structure at Topock Substation (Station 1149+71). The OPGW shall be installed on the steel take-off structures, steel lattice towers, and steel H-frame structures west OGW attachment