Amendment_00003_Spec_Page_14.docx

DOCX document 19 KB Posted

Attached to
Longtin Substation, Stage 02 construction project Federal contract opportunity
Solicitation number
DE-SOL-0005448
Issued by
Department of Energy Western Area Power Administration

About this file

AMEND. 000003- SPEC PAGE 14

View the file

Other files for this federal contract opportunity

Other files attached to Longtin Substation, Stage 02 construction project, newest first.
File Type Posted
Amendment_00004_Spec_Page_12.docx DOCX document
SF-30_Amend._000004.pdf PDF
Amendment_00004_Spec_Page_47_.docx DOCX document
Amendment_000004_Spec_Pages_1-9_Table_of_Contents.pdf PDF
Amendment_00004_Spec_Page_23_.docx DOCX document
Amendment_00004_Spec_Page_14.docx DOCX document
Amendment_000004_spec_page_50.docx DOCX document
Amendment_00004_Spec_Page_22.docx DOCX document
Amendment_00004_Spec_Page_49.docx DOCX document
Amendment_00004_Spec_Page_18.docx DOCX document
Amendment_00003_Spec_Page_10_.docx DOCX document
ATTCH_E_-_WD_AZ27-_Building.pdf PDF
Amendment_00003_Spec_Page_12_.docx DOCX document
Amendment_000003_spec_page_104.docx DOCX document
Amendment_00003_Spec_Page_47_.docx DOCX document
ATTCH_D_-_WD_AZ14-_Heavy.pdf PDF
Amendment_00003_Spec_Page_23_.docx DOCX document
LNG02_Amendment_000003_List_6-28-13_Drawing_List.pdf PDF
ATTCH_A-_Bid_Schedule-_Amendment_00003.pdf PDF
Amendment_000003_spec_page_50.docx DOCX document
Amendment_00003_Spec_Page_18.docx DOCX document
Amendment_00003_Spec_Page_22_.docx DOCX document
Terms_and_Cond._Page_30-6.28.2013.pdf PDF
SF-30-_Amend._000003.pdf PDF
Drawings-Amendment_000002.pdf PDF
List_of_Drawings-Amendment_000002.pdf PDF
ATTCH_B-_SPECS_Amendment_000002.pdf PDF
ATTCH_A-_Bid_Schedule-_Amendment_000002.pdf PDF
Site_Visit_Attendees.pdf PDF
For_Information_Only_Davis_Transformer_Dwgs-Amend._000002.pdf PDF
SF30-Amend._000002.pdf PDF
SF30-Amend._000001.pdf PDF
ATTCH_E_-_WD_AZ27-_Building.pdf PDF
ATTCH_A-_Bid_Schedule-4.19.13.pdf PDF
ATTCH_D_-_WD_AZ14-_Heavy.pdf PDF
ATTCH_C-_DRAWINGS_5.7.2013.pdf PDF
ATTCH_B-_SPECS_5.7.13.pdf PDF
Solicitation.pdf PDF
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 000003

7. Eight (8) single-phase coupling capacitor voltage transformer, 69-kV with support
700 ea
NST 10-4-13

NLT 10-25-13

$8,000 ea

8. Twelve (12) single-phase current transformer, 230-kV with support
1,200 ea
NST 10-4-13

NLT 10-25-13

$19,000 ea

9. One (1) single-phase power voltage transformer, 69-kV with support
2,500
NST 10-4-13

NLT 10-25-13

$50,000

10. Five (5) Vertical switchboard sections (CHA3 through CHA7)

1,000 ea
NST 10-24-13

NLT 11-14-13

$55,000 ea

11. Three (3) control panels for SWTC
1,000 ea
NST 10-24-13

NLT 11-14-13

$55,000 ea

12. One (1) 125 VDC station battery system (58 cells and rack)

150 cell
NST 11-5-13

NLT 11-19-13

$38,500

13. Two (2) station battery chargers – BHC1 and BHC2
500 ea
NST 11-5-13

NLT 11-19-13

$20,000 ea

NST – No sooner than.

NLT – No later than.

POINTS OF DELIVERY: Material furnished by Western will be delivered to Longtin Substation. The Contractor is responsible for moving Western-furnished material from temporary storage locations to final destinations.

1. PROTECTION OF MATERIAL: Provide climate controlled (minimum of 70 degrees Fahrenheit for 24-hours a day) indoor storage for items 10 through 13 above. Provide protection against the elements after being removed from indoor storage and before installation. Approximately 200square-feet of indoor storage will be required.

B. RIGHTS-OF-WAY:

1. GENERAL: Orient construction methods and equipment to utilize Government-furnished rightsof-way or obtain additional temporary access without additional cost to Western.

2. ACCESS EASEMENTS: Western has acquired access easements from existing public roads to the transmission line and some off right-of-way access along the transmission line. This off right-of-way access route is to provide access to the transmission line structure sites not accessible by traveling the transmission line.

3. WORK ON THE RIGHT-OF-WAY:

a. General: Perform work on the rights-of-way necessary for access to or along the transmission line. Only that excavation, dozing, or blading that is absolutely necessary will be allowed. Excavation, dozing, and blading for ease of travel may only be performed after field review and approval by the COR. Unauthorized excavation, dozing, or blading shall immediately be repaired or Western will have the damage repaired and backcharge the Contractor for all costs involved.

Ease of Travel and Crane Landings: Excavation, dozing, or blading done for ease of travel on any easement or for crane landings shall be restored to the original contour of the land and shall be compacted to a dry density not less than the natural in-place dry