This is a Design-Build (DB) Statement of Work (SOW) for the National Park Service Office Renovations at Building 50 in the Denver Federal Center, located in Lakewood, Colorado. The project involves comprehensive office renovation of a 146,187-gross square foot facility, with the primary goal of consolidating three National Park Service directorates into a single location. Key project priorities include creating a curatorial space, adding a mother's room, implementing gender-neutral restrooms, upgrading kitchenettes, repairing walls, installing new flooring, and adding window treatments. The renovation aims to provide clarity of place, improve accessibility, and demonstrate sustainability, with a design-build approach that emphasizes collaborative design and operational excellence throughout the project lifecycle.

The project will be executed as a Firm-Fixed-Price (FFP) Design-Build contract through the U.S. General Services Administration (GSA) Public Buildings Service, Rocky Mountain Region 8. The renovation will transform the existing building to accommodate the Intermountain Region (IMR), Denver Service Center (DSC), and Washington Area Support Office (WASO), creating distinctive "neighborhoods" with shared spaces and intuitive circulation. The design-build process will involve multiple phases including concept design, design development, construction documents, construction, and closeout, with extensive stakeholder engagement, design reviews, and compliance with GSA's interim core building standards. The project is set to be completed within 465 days after the Notice to Proceed, with an estimated construction cost between $5,000,000 and $10,000,000.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DB Statement of Work FY25 v.01 National Park Service/ DFC Building 50

U.S. General Services Administration Rocky Mountain Region 8

Design & Construction Division

Section I.H of the Agreement

STATEMENT OF WORK, SPECIFICATIONS,

DRAWINGS, EXHIBITS, AND OTHER

ATTACHMENTS

National Park Service – DFC Building 50 Office Renovations

DESIGN BUILD TEAM | DESIGN BUILD (DB) PROJECT DELIVERY

U.S. GENERAL SERVICES ADMINISTRATION (GSA) PUBLIC BUILDINGS SERVICE (PBS)

PROJECT IDENTIFICATION:

PROJECT NAME National Park Service – DFC Building 50 Office Renovations

SOLICITATION NUMBER

REGION GSA Rocky Mountain Region 8

DIVISION GSA OFFICE OF DESIGN & CONSTRUCTION

BUILDING NAME Denver Federal Center / Building 50

BUILDING ADDRESS CO0527AA

W. 6th Ave. & Kipling Street Lakewood, CO 80225

CONTRACTING OFFICER Joseph Dorsey

PROJECT MANAGER Patrick Insley

LAST REVISION April 1, 2025

Table of Contents

I. SUMMARY

II. THE PROJECT

A. PROJECT DESCRIPTION

1. BUILDING BACKGROUNDS AND PREVIOUS STUDIES AND PROJECTS

2. PROPOSED ACTION

3. TENANT AGENCIES

4. ADDITIONAL STAKEHOLDERS

5. CONTINUOUS OPERATIONS AND PHASING

6. SUPPLEMENTAL PROJECT INFORMATION

7. PROJECT WORK ITEMS

8. CONTRACT TYPE

B. PROJECT GOALS & OBJECTIVES

1. GOALS

2. OBJECTIVES

C. PROJECT DELIVERY APPROACH

D. DESIGN BUILD (DB) CONTRACTOR TEAM

1. STAFFING

2. KEY PERSONNEL

3. OTHER PERSONNEL

4. EXPERTISE

5. DB CONTRACTOR TEAM SUBSTITUTION

6. DB CONTRACTOR'S DOCUMENT MANAGER (CDM)

E. PROJECT DURATION AND SCHEDULE MILESTONES

F. PROJECT STAGES, PHASES AND WORK SEQUENCE

1. PRE-AWARD OFFEROR PROPOSAL PREPARATION STAGE

2. DB CONTRACT AWARD

3. PROCUREMENT PHASE OWNER COMMENTS

4. DESIGN STAGE

5. CONSTRUCTION STAGE

6. CLOSEOUT AND TURNOVER STAGE

7. FINANCIAL CLOSEOUT STAGE

G. PROJECT DELIVERY TEAM ROLES AND RESPONSIBILITIES

1. OWNER'S QUALITY ASSURANCE DESIGN REVIEWERS

2. OWNER'S OPERATIONS AND MAINTENANCE STAFF (OMS)

3. COMMISSIONING PROVIDER (CXP)

4. CONSTRUCTION MANAGER AS ADVISOR (CMa) ROLE AND RESPONSIBILITIES

5. GSA REGIONAL FIRE PROTECTION AND LIFE SAFETY ENGINEER

6. GSA REGIONAL ENVIRONMENTAL COORDINATOR

7. GSA'S BUILDING TECHNOLOGY SERVICES DIVISION

8. OTHER DESCRIPTIONS

9. OCCUPANT AGENCIES ROLES AND RESPONSIBILITIES

10. VENDORS AND INSTALLERS BY OTHER CONTRACTS

III. GENERAL REQUIREMENTS

A. OWNER'S PROJECT REQUIREMENTS (OPR)

1. TECHNICAL PERFORMANCE STANDARDS AND CRITERIA

2. SPACE REQUIREMENTS & SPATIAL DATA MANAGEMENT (SDM)

3. INTERIM CORE BUILDING STANDARDS

4. DELIVERABLES MATRIX

5. FUNCTIONAL REQUIREMENTS: PLANNING & DESIGN

6. COMMISSIONING PLAN - PRELIMINARY

7. BASIS OF DESIGN (BOD)

B. PERFORMANCE REQUIREMENTS

1. BUILDING DESIGN STANDARDS (BDS)

2. FIRE PROTECTION & LIFE SAFETY

3. ACCESSIBILITY

4. PHYSICAL SECURITY

C. PROJECT DELIVERY REQUIREMENTS

1. SPATIAL DATA MANAGEMENT (SDM)

2. INTERIM CORE BUILDING STANDARD CERTIFICATION

3. PERMITS AND FEES

4. BUILDING DESIGN STANDARDS (BDS)

5. DELIVERABLES MATRIX

6. COMPLIANCE MATRIX

7. OPERATIONAL EXCELLENCE PROGRAM

8. DESIGN REVIEW - PROCESS AND PROCEDURES

9. CONSTRUCTION SUBMITTAL & RFI PROCESSING

D. PROJECT MANAGEMENT

1. RECORD KEEPING

2. COMMUNICATIONS PLAN

3. QUALITY ASSURANCE AND QUALITY CONTROL PLAN

4. PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)

5. POST-AWARD CONCEPT DESIGN UPDATE

E. RISK MANAGEMENT

1. RISK MANAGEMENT WORKSHOPS

2. RISK REGISTER

F. COST AND SCHEDULE MANAGEMENT

1. COST MANAGEMENT

2. SCHEDULE MANAGEMENT

G. CHANGE MANAGEMENT

H. SHOP DRAWINGS REVIEW

IV. SCOPE OF SERVICES

A. GENERAL

B. SITE-BUILDING INVESTIGATIONS

1. SURVEYS AND GEOTECHNICAL REPORTS

2. UTILITY COORDINATION

C. DESIGN STAGE SERVICES

1. DESIGN PHASE

2. EXISTING DOCUMENTATION

3. PHASING REQUIREMENTS

4. REVIEW SUBMISSIONS

5. TECHNOLOGY REQUIREMENTS

6. DISCLOSURE

7. DEVIATIONS

D. POST-AWARD CONCEPT DESIGN PHASE

1. PROCUREMENT PHASE OWNER COMMENTS

2. INTERIM CORE BUILDINGS STANDARD WAIVER REQUEST

3. PRE-NTP SUBMITTAL REVIEW AND ACCEPTANCE

4. NOTICE TO PROCEED

5. PRE-CONSTRUCTION MEETING

6. OPERATIONAL EXCELLENCE (OE) REQUIREMENTS

7. DESIGN PHASE SEQUENCE / INCREMENTAL DESIGN PACKAGES & FAST

TRACK CONSTRUCTION

8. PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)

9. ADDITIONAL STUDIES

10. BIM COORDINATION

11. INTEGRATED DESIGN REVIEW WORKSHOP (IDR)

12. SELECTIVE DEMOLITION

13. SITE ANALYSIS REPORT

14. DESIGN REVIEWS - PROCESS AND PROCEDURES

15. DESIGN SUBMISSION DELIVERABLES

16. SAFEGUARDING ASSETS STATEMENT

17. NATIONAL ENVIRONMENTAL POLICY ACT (NEPA)

18. RISK ANALYSIS REVIEW

19. COMMISSIONING

20. PROJECT READINESS CHECKLIST

21. INTERIM CORE BUILDINGS STANDARD CONCURRENCE & COMPLIANCE

MATRIX

22. GSA CONCURRENCE

23. PRESENTATION OF THE FINAL CONCEPT DESIGN

24. COMMISSIONER'S BRIEFING PRESENTATION

25. FINAL CONCEPT APPROVAL

E. DESIGN DEVELOPMENT (DD) PHASE

1. MEETINGS, REVIEW PROCEDURES, AND DELIVERABLES

2. DESIGN REFINEMENT

3. SPACE PLANNING

4. CONSTRUCTION WORK SEQUENCING AND COORDINATION PLAN

5. MOCK-UP'S AND TESTING

6. ADDITIONAL DATA, SERVICES, OR TESTING

7. SYSTEMS SELECTIONS ANALYSIS MEETINGS

8. DESIGN QUALITY REVIEW

9. COMMISSIONING

10. FIRE PROTECTION CERTIFICATION

11. PHYSICAL SECURITY REVIEW MEETING

12. NEPA COORDINATION

13. DESIGN REVIEW

14. GSA CONCURRENCE

15. PRESENTATION OF THE DD

16. DESIGN DEVELOPMENT APPROVAL

F. CONSTRUCTION DOCUMENTS (CD) PHASE

1. MEETINGS, REVIEW PROCEDURES, AND DELIVERABLES

2. CONSTRUCTION DOCUMENTS COORDINATION

3. GSA CONCURRENCE

4. PRESENTATION OF THE CONSTRUCTION DOCUMENT SUBMISSIONS

5. CO APPROVAL

G. CONSTRUCTION SERVICES STAGE

1. SPECIAL EMPHASIS RESPONSIBILITIES

2. CONSTRUCTION START COORDINATION

3. CONSTRUCTION ADMINISTRATION

4. CONSTRUCTION PROGRESS PHOTOS, WEB-CAM AND VIRTUAL INSPECTIONS

5. SITE SECURITY

6. CONSTRUCTION PHASE RECORD KEEPING AND REPORTING

7. CONSTRUCTION SAFETY PROGRAM

8. PROJECT PROGRESS MEETINGS

9. CONSTRUCTION SCHEDULES

10. GSA SUBMITTAL PROCESSING

11. INSPECTION AND TESTING

12. REQUESTS FOR INFORMATION

13. AS-BUILT DRAWINGS & SPECIFICATIONS

14. DB CONTRACTOR PAYMENT REQUEST

15. LESSONS LEARNED / BEST PRACTICES WORKSHOP

16. CONSTRUCTION PHASE COMMISSIONING

17. LESSONS LEARNED/BEST PRACTICES DEBRIEF

H. CLOSEOUT & TURNOVER STAGE

1. PUNCH LIST

2. ACCEPTANCE

3. SUBSTANTIAL COMPLETION

4. OPERATIONS & MAINTENANCE MANUAL(S)

5. WARRANTIES & CERTIFICATES

6. FINAL RECORD DOCUMENTS, AS-BUILT DRAWINGS, AS-BUILT MODELS &

SPECIFICATIONS

7. BUILDING PRESERVATION PLAN (BPP)

8. BUILDING DESIGN STANDARD (BDS)

9. CAD LIBRARY COORDINATION

10. BUILDING INFORMATION MODELS AND BIM DELIVERABLES

11. MATERIAL SAMPLES, ATTIC STOCK, & SPARE PARTS

12. PREPARATION FOR OCCUPANCY

13. FINAL PROFESSIONAL PHOTOGRAPHY & FINAL DESIGN PRESENTATION

RENDERINGS

14. PROJECT AWARDS & CERTIFICATIONS

15. PROJECT DEDICATION CEREMONY

16. MEASUREMENT & VERIFICATION IMPLEMENTATION

17. 1-YEAR PROPERTY MANAGEMENT RETRAINING

I. OCCUPANCY STAGE

1. PROJECT DOCUMENTS

2. CAD ASSIGNMENT DRAWINGS

3. FURNITURE, FIXTURES, & EQUIPMENT (FFE) MOVE-IN PHASE

4. OCCUPANT AGENCY TECHNOLOGIES

5. OPERATIONS & MAINTENANCE SERVICES

E. CONTRACT FINANCIAL CLOSEOUT

1. CONTRACT CLOSE-OUT

2. PROJECT FINANCIAL CLOSE-OUT

V. ADMINISTRATIVE PROCEDURES

A. DESIGN PHASE PROGRESS REVIEWS AND PAYMENTS

B. CONSTRUCTION PROGRESS REVIEWS, REPORTS, PAYMENTS & DELAYS

C. CONTRACT FINANCIAL CLOSEOUT

D. TRAVEL, REPRODUCTION, AND DELIVERY

F. SECURITY CLEARANCE AND MANAGEMENT

G. DOCUMENT SECURITY

VI. APPENDIX OWNER'S PROJECT REQUIREMENTS (OPR)

I.SUMMARY

The purpose of this document is to provide an overview of the Project and DB Contractor requirements as a part of the Design-Build (DB-101) Agreement. This Statement of Work is one part of Section I.H of the Agreement that includes Specifications, Drawings, Exhibits, and Other Attachments. For conflicts or ambiguities within or among the contract documents the DB Contractor must refer to the DB-101 Agreement.

II.THE PROJECT

The Statement of Work (SOW) specifies the processes and procedures the DB Contractor shall employ when executing the planned work. The SOW is designed to describe not only what is to be done, but also how it is to be done. The SOW does not redefine contractual terms and conditions.

The purpose of this document is to provide an overview of the Project and DB Contractor requirements as a part of the Design-Build (DB) contract. This document combined with the documentation contained in the Appendix, and hyperlinks provided constitutes the scope of work (SOW). For conflicts or ambiguities within or among the contract documents the DB Contractor shall refer to the Agreement.

A. Project Description

The U.S. General Services Administration (GSA) intends to renovate office and office related space in existing GSA Building 50 at the Denver Federal Center (DFC) campus. Most recently, the Bureau of Land Management occupied Building 50; during this tenancy, Building 50 was primarily used as an office function. At the conclusion of the renovation project, three departments of the National Park Service will use Building 50 as their office and workstation space. The 146,187-gross square feet includes space for office, office related space, conference rooms, workstations, restrooms, and basement storage. Upon termination and consolidation of current leases in the Denver metropolitan area, the National Park Service (NPS) will temporarily occupy the northwest corner of the Building 50 (approximately 25,250-square feet), leaving the balance of available area open to for the office renovation project.

The U.S. General Services Administration (GSA) intends to award a Firm-Fixed-Price (FFP) DB Contract for the NPS DFC Building 50 Office Renovations pursuant to the Federal Acquisition Regulation (FAR) Design-Build Selection Procedures and incorporating Design - Construction - Operational Excellence policies and procedures, and other requirements as described within this Statement of Work.

1. BUILDING BACKGROUNDS AND PREVIOUS STUDIES AND PROJECTS

Building 50 was originally designed and constructed in 1941 as a tooling, grinding, and hardening shop facility which contributed to the World War II munitions fabrication effort and campus located in Denver, Colorado. The original building is a single story, T-shaped floor plan and was constructed with cast-in-place concrete frame and multi-wythe masonry enclosure. A two-story expansion was added in 1974, consisting of a below-grade basement level and main level to align with the original Building 50 first floor finished floor elevation. The 1974 addition is constructed with pre-cast concrete columns and girders which support pre-cast concrete double-t floor planks. The 1974 era exterior enclosure consists of patterned pre-cast concrete wall panels in the Brutalist architectural style.

2. PROPOSED ACTION

3. TENANT AGENCIES

4. ADDITIONAL STAKEHOLDERS

5. CONTINUOUS OPERATIONS and PHASING

a. It is anticipated that the NPS will vacate the construction area, and no phasing will be necessary during construction.

6. SUPPLEMENTAL PROJECT INFORMATION

This project requires specialized technical specifications, material and equipment procurement, installation; reporting, and measurement. Successful project delivery will depend on active DB Contractor collaboration with the CMa / CxP, GSA and other subject matter experts.

7. PROJECT WORK ITEMS

General Description

The U.S. General Services Administration (GSA) intends to renovate office and office related space in existing GSA Building 50 at the Denver Federal Center (DFC) campus. Most recently, the Bureau of Land Management occupied Building 50; during this tenancy, Building 50 was primarily used as an office function. At the conclusion of the renovation project, three departments of the National Park Service will use Building 50 as their office and workstation space. The 146,187-gross square feet includes space for office, office related space, conference rooms, workstations, restrooms, and basement storage. Upon termination and consolidation of current leases in the Denver metropolitan area, the National Park Service (NPS) will temporarily occupy the northwest corner of the Building 50 (approximately 25,250-square feet), leaving the balance of available area open to for the office renovation project.

Additional project priorities:

a. Curatorial space, considering required space need, loading, temperature, security, emergency, lighting, and humidity.

b. Mother's room with wet sink.

c. Showers/Gender Neutral Restrooms.

d. Power added to floor in large conference/training room.

e. Interior door access for secured rooms such as IT and equipment storage will need a

Gallagher card readers (server and controller already present).

f. Replace/Upgrade all Kitchenettes, add filtered water stations, microwaves and refrigerators.

g. Add segregation for break areas and space plan the shared spaces.

h. Repair walls and paint or apply custom wallpaper.

i. New flooring.

j. Window treatments where needed.

8. CONTRACT TYPE

As noted in the Agreement, this SOW is for a Firm Fixed Price (FFP) Contract.

B. Project Goals & Objectives

1. GOALS

a. Provide the NPS a permanent government facility footprint as quickly as possible.

b. Increase accessibility and equity that support the GSA/NPS Strategic Plan.

c. Maintain full office operations and storage facility functions.

d. Deliver excellent design.

e. Deliver flexible, efficient, scalable facilities to meet tenant mission requirements.

2. OBJECTIVES

a. Create a Curatorial space; considering the required space need, loading, temperature, security, emergency, lighting, and humidity.

b. Add a Mother's room with wet sink.

c. Add Showers/Gender Neutral Restrooms.

d. Add power added to floor in large conference/training room.

e. Add interior door access for secured rooms such as IT and equipment storage will need a Gallagher card readers (server and controller already present).

f. Replace/Upgrade all Kitchenettes, add filtered water stations, microwaves and refrigerators.

g. Add segregation for break areas and space plan the shared spaces.

h. Repair walls and paint or apply custom wallpaper/wall treatment.

i. Install new flooring as needed.

j. Window treatments where needed.

C. Project Delivery Approach

This project must utilize the Design Build (DB) delivery method, DB contract procured by competitive negotiation using a two-phase design-build selection procedure (FAR Subpart 36.3). The DB scope of work includes all labor, materials, systems and equipment required to provide architectural and engineering design, construction, and other related services necessary to design and to construct the NPS Building 50 Office Renovation. Related services include, but are not limited to, building demolition, site planning, geotechnical investigation, historic preservation, environmental mitigations, testing and inspection during construction, and coordination with the CMa - commissioning agent and its representatives.

This project must be accomplished using a collaborative DB delivery method, an enhanced version of Integrated Project delivery. A successful project outcome will depend on the trust and collaboration between the project stakeholders; GSA, National Parks Service, consultants, DB Contractor, and city neighbors. All required work is included in a single design and construction effort. After award of the DB contract, the DB Contractor must continue the development of the approved concept design and prepare construction documentation following the 2024 P-100 design review and submission process and as described herein (GSAM 552.236-72 and the FAR clause 52.236-21 ). The DB Contractor must serve as the A/E of record and construct the project.

GSA envisions a highly collaborative design-build delivery approach for this project, with the outcome that the DB Contractor must work closely with the GSA and NPS and other tenant representatives to deliver a final project that meets the needs and expectations as defined within the supporting documents.

This Contract is a firm fixed price Design-Build contract that includes a final design concept submission, Design Development design phase, Construction Document design phase, and all construction work. GSA may have a separate contract with a Construction Manager as agent (CMa) for this project. As part of the CMa’s contract, GSA must retain a Commissioning Provider (CxP) to assist with the development of the contract commissioning performance requirements. The DB Contractor must perform commissioning-related tasks in accordance with the GSA Commissioning Guide.

During the development from initial concept to final concept the Design-Build team must work closely with the GSA, NPS and all other involved parties to ensure that all the goals are addressed.

D. Design Build (DB) Contractor Team

1. STAFFING

The DB Contractor must provide experts in disciplines listed in the Facilities Standards for the Public Buildings Service ( 2024 P-100), and as otherwise required in this section, with credentials as indicated, as they apply to this project. The DB Contractor must provide sufficient staff of project managers, architects, Interior designers, workplace specialists, design engineers, field engineers, superintendents, inspection and testing engineers, scheduling specialists, cost engineers, traffic modeling engineer, clerical and accounting personnel, etc. to perform the required work.

2. KEY PERSONNEL

Interior Designer

Acoustic Designer/Engineer

Workplace Change Management Specialist

3. OTHER PERSONNEL

In addition to the key team members identified within this document, the DB Contractor must provide administrative, clerical, and technical personnel as necessary to perform the services required under this contract.

4. EXPERTISE

At a minimum, the DB Contractor’s team members should include of the following experts to provide expertise (a single individual may be assigned more than ONE of the responsibilities / expertise listed below) as and when needed for efficient and effective operations:

Within 10 after the Notice to Proceed (NTP) the DB Contractor must edit the Communications Plan, and complete the team entries.

a. Project Executive

b. Senior Project Manager

c. Assistant Project Manager

d. Pre-Construction (a.k.a design-phase Manager) Project Manager

The design-phase manager ensures that both design and build functions conform to the contract and meet the financial requirements of the team budgets. Responsible for coordinating and integrating the design process.

e. Lead Architectural Designer

f. Interior Architect | Interior Designer

g. Workplace Change Management Specialist

h. Engineering Designers - All Disciplines including civil - structural, geotechnical, hydrology and hydraulics, mechanical, electrical

i. Fire Protection Engineer: Defined in 2024 P-100 § 7.1.3.1

j. Physical Security and Access Control Consultant/Coordinator

k. Security Consultant

l. Lighting Design Consultant

m. Acoustic Consultant

n. Lead Environmental Coordinator

o. Quality Control Superintendent

p. Construction Superintendent

q. Construction Supervisor

r. Cost Engineer

s. Construction Scheduler

t. Safety Officer

u. O&M Quality Control coordinator

v. Information Technology (IT) Consultant/Coordinator

w. Document Manager (CDM)

5. DB CONTRACTOR TEAM SUBSTITUTION

During the performance of the services required under this contract, the DB Contractor must obtain GSA written consent from the Contracting Officer before making any substitution for subDB Contractors and outside associates or consultants specifically identified and agreed to in the request for qualifications, proposal, contract, and any contract modifications.

6. DB CONTRACTOR’S DOCUMENT MANAGER (CDM)

The CDM must provide a single point of contact to manage documents and coordinate submissions.

The DB Contractor must coordinate with GSA’s BIM POC within15 after the NTP to confirm the BIM Execution Plan (BEP) and COBie Information Delivery Plan, including naming conventions, format, structure, and training requirements.

The CDM must:

a. Control of all project documentation, including PMIS requirements

b. Control of as-builts and project files

c. Execute real time updating of as-builts with change orders, bulletins, RFIs.

d. Provide] submissions of as-builts identifying all changes to date for Quality Control reviews.

e. Coordination with PBS CAD Standards, GSA National BIM, CDX & COBie Standard other Electronic Data

f. Coordination with Operations and Maintenance

E. Project Duration and Schedule Milestones

A copy of the full project schedule can be found in the OPR, Project Schedule.

Milestone Schedule Trigger Event

Contract Agreement - Firm Fixed Price Award DB contract award

DB Contractor Notice to Proceed (NTP) NTP provided by CO after review and acceptance of Safety and

Health plan, etc.

Clarification and Integration of Procurement Phase Comments

PROCUREMENT PHASE OWNER COMMENTS

Conduct prior to Kick-off mtg

Project Kick-off meeting 7 days after NTP

Commissioners Presentation Virtual – Around 30 days after

NTP

65% Design Issuance 90 days after NTP

65% Design Review and Comments 30 days after 65% Design Issuance

95% Design Issuance 45 days after 65% Design Review

95% Design Review 30 Days after 95% Design Issuance

100% Design Issuance 30 Days after 95% Design Review

Acceptance of CD | Construction Start At 100% Design Issuance

Construction Substantially Complete 8 Months after Construction Start

(465 Days after NTP)

F. Project Stages, Phases and Work Sequence

This Statement of Work is organized to identify the scope of services that are to be performed in a sequential manner however the DB Contractor may propose a schedule of design and construction activities that overlap a.k.a. Fast-track delivery strategy of beginning construction before the design is completed. The DB Contractor must refer to GSA 01 31 10 PROSPECTUS CPM SCHEDULE SPECS.

1. PRE-AWARD OFFEROR PROPOSAL PREPARATION STAGE

2. DB CONTRACT AWARD

3. PROCUREMENT PHASE OWNER COMMENTS

4. DESIGN STAGE

a. Post-award Concept Phase

b. Design Development Phase

c. Construction Documents Phase

5. CONSTRUCTION STAGE

6. CLOSEOUT AND TURNOVER STAGE

7. FINANCIAL CLOSEOUT STAGE

G. Project Delivery Team Roles and Responsibilities

In the performance of the contract requirements, the DB Contractor must work in concert with other parties on the Project Delivery Team. The Project Delivery Team must include other contractors, CMa & CxP, GSA personnel, occupant agency representatives including occupant agencies and other stakeholders. GSA must develop, periodically update, and maintain throughout the course of the project, a listing of the Project Delivery Team membership and respective roles and responsibilities. The other GSA-contracted major parties involved or to be involved in the Project Delivery Team, and their respective overall roles and responsibilities, are as follows:

1. OWNER’S QUALITY ASSURANCE DESIGN REVIEWERS

GSA’s responsibility to meet complex requirements of the Legislative and Executive Branch of the federal government necessitate maintaining a staff of professionals (subject matter experts (SME) experienced in quality assurance reviews of DB Contractor submissions. SMEs participate in both formal and informal design reviews to verify that standards and objectives are met. Design reviews provide GSA with the opportunity to consider and document how design decisions will affect building functionality and assure that the occupant agencies are presented with design solutions that satisfy the OPR. Comments from every design review must be addressed satisfactorily before beginning the design of the subsequent design phase.

2. OWNER’S OPERATIONS AND MAINTENANCE STAFF (OMS)

The Owner’s OMS will actively participate in developing the “Systems Acceptance Criteria” and “Functional Test Procedures” and the DB Contractor provided training. OMS will participate in design reviews, system selection, functional performance testing, and the commissioning process.

3. COMMISSIONING PROVIDER (CXP)

The CxP Scope of Services is the responsibility of the Cma. The only systems anticipated to need commissioning are the mechanical systems associated with priorities a, d, and e discussed in section II.A.7

a. For this contract the CxP is a subconsultant to the CMa. Therefore, the CMa is the Commissioning Provider.

b. The CxP is responsible for developing the commissioning requirements for incorporation into the DB contract performance specification.

c. The CxP must develop the Cx plan, testing requirements and performance specifications, and propose/coordinate failure criteria.

d. The CxP manages and leads the Cx meetings.

e. CxP services must consist of work as necessary to verify and document compliance with the GSA performance objectives throughout the design, construction, start-up, and the initial period of operation.

f. The CxP advises GSA on issues involving the commissioning process, emphasizing the long-term performance and maintainability of the systems included in the commissioning scope of work.

g. The CxP must advise GSA of deficiencies involving the design, construction, testing, adjusting and balancing, or other deficiencies that would compromise the ability of the facility to meet the needs of GSA.

h. The CxP is authorized to recommend to GSA the acceptance, modification, or rejection of all materials, procedures, schedules, tests, reports, or other required commissioning submittals.

i. The CxP is not authorized to change the DB Contractor’s Contract Documents, schedules, costs, or scope of work.

4. CONSTRUCTION MANAGER AS ADVISOR (CMa) ROLE AND RESPONSIBILITIES

The GSA hires a professional construction manager to be its advisor. During design the CMa assists with design management. The CMa performs constructability reviews of design development and construction documents. The CMa provides quality assurance services to monitor the DB Contractor’s Quality Assurance Quality Control (QAQC) Plan (refer to GSA 014000 QUALITY ASSURANCE & CONTROL REQUIREMENTS GUIDANCE ), during the design and construction periods.

The CMa serves as the CxP directly or indirectly by subcontracting CxP services. To reduce confusion during project coordination and collaboration activities on the project, the DB Contractor must review the CMa and CxP DB SOW template FY24 DRAFT v. Key CMa responsibilities are to:

a. Assists GSA to ensure the DB meets the contract requirements.

b. Serve as facilitator and coordinator of all parties’ collaboration required project activities to assist GSA with ensuring this project’s execution proceeds per plan.

c. After DB contract award, perform and coordinate Concept Design, Design Development, and Construction Documents reviews and comments’ resolution.

d. Participate in the commissioning process, coordinating with GSA and the CxP to develop the project’s commissioning goals, and supporting inspections and testing practices that ensure the project will meet the project’s Commissioning Plan’s objectives.

e. Produce 3rd party cost estimates, review change order requests, and provide other construction management services to assist GSA fulfill its fiduciary responsibilities.

6.

7. GSA REGIONAL FIRE PROTECTION AND LIFE SAFETY ENGINEER - Authority Having Jurisdiction

(AHJ)

The GSA regional fire protection engineer will participate in each phase of the project from concept through design, construction, final acceptance, and occupancy to ensure that fire protection and life safety requirements are incorporated into the project. The GSA regional fire protection engineer will review design plans, specifications, and related information; review DB Contractors’ submittals for compliance with contract documents; witness acceptance testing and commissioning of fire protection and life safety systems; and upon successful completion of commissioning and acceptance of tested systems, will issue certificates of occupancy (or temporary certificates of occupancy) before occupancy.

The GSA regional fire protection engineer is the authority having jurisdiction (AHJ) for technical requirements in this chapter, including all fire protection and life safety code interpretations and code enforcement requirements. As the AHJ, the GSA regional fire protection engineer has the right to revise the specific requirements as defined in the Interim CORE Building Standards based on a technical evaluation and analysis and the project’s specific needs.

8. GSA REGIONAL ENVIRONMENTAL COORDINATOR

Coordinate the review of design submittals for compliance with the mitigation measures identified in the NEPA report prepared by others, as well as compliance with environmental regulations and standards related to:

a) Stormwater Management (EISA 438 and Local Requirements))

b) Fuel Storage Tanks (Fuel Oil/Diesel)

c) Hazardous Materials

d) Firing Range Design

e) General environmental compliance

f) Indoor air quality during construction

g) Compliance with NEPA mitigation measures related to:

1) Clean Air Act and Clean Water Act Permitting (floodplains and wetlands)

2) Threatened and Endangered and Sensitive Species (plants and wildlife)

9. GSA’S BUILDING TECHNOLOGY SERVICES DIVISION

GSA business unit responsible for facility technology requirements including Cyber, IT Network, Monitoring, Controls, and Smart Building, refer to Technology Requirements.

10. OTHER DESCRIPTIONS

Refer to the project Communications Plan, for ROLES & RESPONSIBILITIES.

11. OCCUPANT AGENCIES ROLES AND RESPONSIBILITIES

The NPS is the customer to GSA. Their role is to provide GSA with their requirements and internally communicate construction schedules to the organizations within the facility.

12. VENDORS AND INSTALLERS BY OTHER CONTRACTS

To support governmental requirements of this project that are not included in this DB contract, the Government will issue additional contracts to vendors and installers to complete the work to meet these requirements. GSA will assist with collaborative coordination between the DB Contractor and other vendors and installers. For example, the work could include scopes such as furniture installation. Refer to GSA 011000 SUMMARY § 1.3 WORK BY OTHER contractors.

a. The DB Contractor must provide site/project access for the other vendors and installers, including loading dock access, dumpster, and staging areas, and coordinate this DB contract's work to not impede the execution of the scope required by the other contracts.

b. The DB Contractor must maintain contact with GSA to set up a process to monitor and report upon the status of these contracts that must be represented within the DB Contractor’s master schedules submitted to GSA. To support the other vendor and installer DB Contractors’ work, the DB Contractor must provide background drawings in .dwg format as required when requested.

END of SECTION

GENERAL REQUIREMENTS

Requirements in this section shall apply to all project stages described in the Scope of Services section.

Some of the requirements noted in this section may be subject to exercise of contract option(s).

As a general matter, the Interim Core Building Standards represents baseline performance requirements for the project. In addition, other policies, and procedures provide detailed procedures and requirements that the DB Contractor must follow. Refer to the OPR for a listing of the Standards and Design Criteria Documents.

As a general matter, the Solicitation and Agreement, Interim CORE Building Standards, Project Specific Exclusions or Qualifications, Owner’s Project Requirements (OPR), and standards incorporated by reference represent the overarching documents that govern the DB Contractors performance in executing the SOW. The Interim CORE Building Standards, specifies performance standard minimums for the Building 50 National Parks Service Office Remodel. The DB Contractor is encouraged to exceed the minimum requirements and offer “betterments” to the Government while accomplishing the programmatic, performance and functional goals for the project.

All efforts, material and work performed under this contract must comply with applicable federal codes based on the requirements of the current edition of recognized and accepted building standards, codes, and regulations, including, but not limited to documents referenced in the document list Technical Performance Criteria. The applicable version of each document must be the version current at the time of award of this contractunless otherwise noted. Any conflicts or ambiguities within or among the referenced standards and criteria documents, or any deviations from requirements contained in the documents, must be reported to GSA’s Contracting Officer in writing, for determination as to applicability.

Among the documents listed in Exhibits and other Attachments, include design documents that were prepared by other design professionals and GSA. These documents are provided for reference only: the Design-Builder’s design professionals (Architects and Engineers) must be responsible for the complete design of the project, including all drawings and specifications. Other documents describe design requirements to which the work produced by this contract must conform.

The DB Contractor must ensure that NO A/E Copyright claims are included within the project documents.

A. Owner’s Project Requirements (OPR)

In General the OPR describes:

Whole building concepts diagram location of the shared spaces in relation to Inter-Mountain Region (IMR), Denver Service Center (DSC), and Washington Area Support Office (WASO) neighborhoods.

Each neighborhood should have easy access to the shared spaces. Three main design goals have been communicated as highly desirable by the National Park Service user groups located in Building 50:

- The office renovation design must provide clarity of place for each organization and must achieve intuitive circulation to shared and support spaces with wayfinding implementations that are easy to follow.

- The office renovation design must be inclusive and make achieving accessibility goals a high priority.

- Sustainability is an inherent purpose for NPS, and distinctively integrating in the NPS mission. Office renovations must embrace and demonstrate a clear commitment to sustainability.

It should be noted that Building 50 will host a plethora of individuals whose primary responsibility is with the design and construction of NPS owned facilities; the Design Build contractor should consider workplace change management as a project betterment to their proposed design services.

The National Parks Services is collocating from several different buildings to a single building (Building 50) at the Federal Center. The new space will need to accommodate three groups:

Intermountain Region (IMR), Denver Service Center (DSC), and Washington Area Support Office (WASO). These three directorates also have common shared spaces. IMR is comprised of 8 directorates, DSC is 7 directorates, and WASO is 16. Each directorate is divided into neighborhoods with shared spaces mixed within each group: overflow workstations, breakrooms, collaboration spaces, and team meeting areas. Each of the neighborhoods also has easy access to the building shared facilities, such as: conference rooms, restrooms, libraries, copy areas and storage.

The design Intent of the “Neighborhoods” is to make each neighborhood visually different from one another in order to enhance the functionality of intuitive wayfinding and the identity of place. For example, wall colors, large-scale environmental graphics, and room name nomenclature could be used to provide unique character and identity to each neighborhood. The design intent is for each “Neighborhood” to have a theme and/or color scheme, to set it apart from the other 3 “Neighborhoods.”

Included in the Neighborhood’s shared spaces are:

Closed Meeting spaces

- Team Rooms (Large, Medium, and Small)

- Quiet Rooms/Phone Rooms

Open Collaborations Areas (Large, Medium, and Small)

Kitchenette and Break rooms

Print rooms, Open print areas, and Printer/fax stations

Wellness/Lactation Areas

These neighborhood spaces are common/shared spaces located within each Neighborhood.

1. TECHNICAL PERFORMANCE STANDARDS AND CRITERIA

The Design Stage services and Construction Stage work under this Statement of Work must comply with Technical Performance Standards and Criteria.

The Office Renovation project is primarily comprised of new tenant finishes and fit-out for NPS in Building 50, at the Denver Federal Center. The NPS is consolidating three main directorate spaces from several building leases into a single location, Denver Federal Center Building 50. Based on NPS mission statement, a high priority is placed on reuse, repurpose, and recycle as much of the existing Building 50 interior walls and space as is programmatically possible.

No utility work or infrastructure-related core and shell scope of work is anticipated for the interior renovation project; any utility work, including utility locations requires surveying for incorporation into the utility geodatabase per SOP 32.

Refer to OPR report for technical outlines per discipline.

a. Design Criteria, Codes, and Standards

At a minimum, the following codes and standards apply to this project. Please note, the Designer will use the latest editions of the code and standards at the time of contract award.

ACI 318, Building Code Requirements for Structural Concrete

ACI 360R, Guide to Design of Slabs-on-Ground

AISC 360, Specification for Structural Steel Buildings

Architectural Barriers Act (ABA)

Architectural Barriers Act Accessibility Standard (ABAAS)

Applicable National Fire Protection Association (NFPA) Standards

Applicable Occupational Safety and Health Administration (OSHA) Standards

Applicable American National Standards Institute (ANSI) Publications

ASCE 7, Minimum Design Loads and Associated Criteria for Buildings and Other Structures

ASHRAE 55, Thermal Environmental Conditions for Human Occupancy

ASHRAE 62.1, Ventilation and Acceptable Indoor Air Quality

ASHRAE 90.1, Energy Standard for Sites and Buildings Except Low-Rise Residential Buildings

ASHRAE 135, BACnet™--A Data Communication Protocol for Building Automation and Control Networks

ASHRAE 140, Standard Method of Test for the Evaluation of Building Energy Analysis Computer Programs

ASHRAE Guideline 12, Managing the Risk of Legionellosis Associated with Building Water Systems

ASHRAE Guideline 36, High-Performance Sequences of Operation for HVAC Systems

ASHRAE Handbooks

ASHRAE Planning Framework for Protecting Commercial Building Occupants from Smoke During Wildfire Events

Building Technologies Technical Reference Guide (BTTRG)

Buy American Act

Facilities and Equipment.; Society of American Archivists (n.d.);

https://www2.archivists.org/node/14805

Federal Energy Management Program (FEMP)

GSA Data Normalization for Building Automation Systems v2.5

GSA P120 Public Buildings Service Cost and Schedule Management Policy Requirements, (November 2022)

General Service Administration, Denver Federal Center, Standard Operating Procedure

(SOP) 33

Illuminating Engineering Society, The Lighting Handbook – Tenth Edition

International Building Code (IBC)

International Existing Building Code (IEBC)

International Energy Conservation Code (IECC)

International Green Construction Code (IgCC)

International Mechanical Code (IMC)

International Plumbing Code (IPC)

The Museum Handbook Part I: Museum Collections. National Park Service. (2023, January 1); https://www.nps.gov/museum/publications/mhi/mhi.pdf

NARA 1571, Archival Storage Standards;

https://www.archives.gov/files/preservation/1571-archival-storage-standards-full-version.pdf

NFPA 70, National Electric Code

NFPA 101, Life Safety Code (LSC)

National Park Service – Space Request Calculator (dated January 30, 2023)

Sheet Metal and Air Conditioning Contractors’ National Association (SMACNA) Standards

Significant New Alternatives Policy (SNAP) Program (by EPA)

TIA 569, Telecommunications Pathways and Spaces

The Masonry Society (TMS) 402/602, Building Code for Masonry Structures

UL 924, Emergency Lighting

The designated Authority Having Jurisdiction (AHJ) for this project is GSA.

2. SPACE REQUIREMENTS & SPATIAL DATA MANAGEMENT (SDM)

From the function, finishes, adjacencies, equipment, security, circulation, servicing, parking, public space, technology, systems, etc.

The Contractor must Include the GSA approved space requirements in a NBSAP compliant SDM Prospectus Project Area Summary.]. The SDM Prospectus Project Area Summary will include the original Housing Plan and the SDM iteration of the Housing Plan which will include all categories of space. The SDM iteration of the Housing Plan must become the Baseline Spatial Area Design Outline. PBS P-100, PROJECT SPECIFIC EXCLUSIONS

3. Interim CORE Building Standards

The Interim CORE Building Standards are attached to the OPR and make up the baseline requirements for all GSA Design and Construction Efforts.

4. DELIVERABLES MATRIX

5. FUNCTIONAL REQUIREMENTS: PLANNING & DESIGN

Whole building concepts diagram location of the shared spaces in relation to Inter-Mountain Region (IMR), Denver Service Center (DSC), and Washington Area Support Office (WASO) neighborhoods.

Each neighborhood should have easy access to the shared spaces. Three main design goals have been communicated as highly desirable by the National Park Service user groups located in Building 50:

- The office renovation design must provide clarity of place for each organization and must achieve intuitive circulation to shared and support spaces with wayfinding implementations that are easy to follow.

- The office renovation design must be inclusive and make achieving accessibility goals a high priority.

- Sustainability is an inherent purpose for NPS, and distinctively integrating in the NPS mission. Office renovations must embrace and demonstrate a clear commitment to sustainability.

It should be noted that Building 50 will host a plethora of individuals whose primary responsibility is with the design and construction of NPS owned facilities; the Design Build contractor should consider workplace change management as a project betterment to their proposed design services.

The concepts developed as part of this OPR are a quadrant option, a spine option, and a split option.

There are pros and cons to each conceptual option.

6. COMMISSIONING PLAN - PRELIMINARY

[Editor: The CxP must provide the preliminary Commissioning plan in the OPR. The Preliminary plan will provide the basis for the Cx process, quality assurance process, standards and expectations.]

7. BASIS OF DESIGN (BoD)

The DB Contractor must update and submit a BoD Report with each formal design review and must at a minimum the following:

1. Description of the principles, assumptions, rationale, criteria, and considerations used for calculations and decisions required during design.

2. The technical approach planned for the project is incorporated into the project technical specifications.

3. The code analysis, catalog cuts and manufacturers information used to set the minimum levels of quality performance set by the design.

4. The OE Analysis.

5. must respond to each applicable system as described in the Interim CORE Building Standards

B. Performance Requirements

In General

The Government will use the OPR and Performance Requirements to determine whether the DB Contractor’s work complies with the contract requirements. The DB Contractor must provide all services in accordance with the version of the Technical Performance Standards and Criteria and References issued at the time of contract award.

For conflicts or ambiguities within or among the contract documents the DB Contractor must refer to the Agreement.

If a requirement contained in the Reference Materials exceeds, and/or conflicts with that required by the Interim CORE Building Standards, the DB Contractor must comply with the most stringent requirement unless otherwise directed by the Contracting Officer. The DB Contractor may exceed requirements contained in the Reference Materials to accomplish programmatic and functional goals for the project, including but not limited to energy performance, sustainability, or industry best practices.

1. BUILDING DESIGN STANDARDS (BDS)

In order to ensure all buildings under GSA’s jurisdiction and control maintain design integrity and efficient building operations, to preserve the original design, and to ensure consistency in all future alterations, GSA PBS has established the project specific Building Design Standard.

The BDS must document the overall space planning strategies for buildings in an effort to maintain the original architectural intent and value for each property.

The DB Contractor must identify key elements in their design and develop an outline BDS document for those identified elements that is based on the Adobe In Design template provided by GSA. The BDS must be based on the post-award final concept design. The document must include guidelines for analysis of the significant exterior design characteristics of the building. The document may have standard items, such as finishes and fixtures, and must be organized in common categories so that they can be easily referenced. The manual may also include sketches, graphics and diagrams.

These established design guidelines must provide a design reference to “future” building alterations.

The DB Contractor must provide at the CD/IFC submission, a submittal that must contain updated information from the finish, hardware, lighting, and signage schedule. This information must include:

wall, floor, ceiling and specialty finishes, as well as hardware, plumbing fixtures, and lighting fixture specifications as designed and constructed. The BDS document must guide the selection of finishes, hardware, lighting and signage in all alterations to the building, preserving the original design intent as established by the DB Contractor.

2. FIRE PROTECTION & LIFE SAFETY

Fire protection and life safety design requirements must comply with Interim CORE Building Standards and additional requirements as identified in the OPR, Fire and Life Safety.

In cases where the National Fire Protection Association (NFPA) is silent on an issue, and the International Building Code (IBC) addresses the issue, the IBC requirement must apply.

The DB Contractor’s registered fire protection engineer must be a full participant in the Project Delivery Team throughout the Design and Construction Stages of the project, and must design the fire alarm, fire pump, and fire sprinkler systems and for any smoke control systems that may be necessitated by the DB Contractor's design.

3. ACCESSIBILITY

The Architectural Barriers Act Accessibility Standard (ABAAS) is mandatory for all GSA projects. The DB Contractor is responsible for identifying local accessibility requirements. If local requirements have been established, the most stringent requirements must prevail between local requirements and the ABAAS. Refer Interim CORE Building Standards

a. This project must be designed to afford full accessibility by disabled persons without having to add separate or special facilities except where specific exclusions from this requirement are provided in applicable standards and criteria documents.

b. The DB Contractor must refer to the P-100 2024v and the Pre-Alteration Assessment (and/or) Requirements, i.e. accessibility assessment for submission requirements.

c. The DB Contractor shall become familiar with and follow the Guidance as set forth in the GSA DEIA Strategic Plan with respect to advancing accessibility and prioritizing access to underserved communities.

4. PHYSICAL SECURITY

The DB Contractor shall not need to install physical security measures. Card readers shall be installed as discussed in the OPR.

C. Project Delivery Requirements

GSA has specific requirements when delivering its projects. The DB Contractor must perform the services and activities to complete the following project delivery requirements:

1. SPATIAL DATA MANAGEMENT (SDM)

At each design phase submission the DB Contractor must incorporate the processes and procedures for space assignments, measurements, and tabulations as identified in the SDM Requirements, refer to the Standards and Design Criteria Documents.

a. Provide an IFC BIM and 2D CAD plans, one for each level of the facility, with assignment data and space boundaries that comply with the National Business Space Assignment Policy. Refer to GSA’s National BIM, CDX & COBie Standard for additional technical requirements to complete SDM drawings.

b. Design for the NPS Building 50 project should not to deviate from the OPR for the priorities identified in section II.A.7 without prior written approval from the Contracting Officer.

c. Coordinate with the regional SDM Manager to develop the SDM Reports and CAD Assignment Plans.

d. The DB Contractor must use the GSA Pricing Desk Guide, 5th Edition to implement GSA concepts (such as Shell and Core Construction and Tenant Improvements) and the GSA National Business Space Assignment Policy, (NBSAP) 2021 edition which explains building measurement and space assignment. [Editor: SDM examples may be found @ SDM Space Reconciliation Report Examples]

e. A Space Program Reconciliation Report (SPRR) is required at each of the design submittal stages. The DB Contractor must create a SPRR that illustrate the difference between the:

1) Space Requirements and the actual building design

2) The SPRR must include a narrative explaining all differences and variances.

3) The SPRR must ensure that the programmatic areas are fully defined, that circulation factors are properly applied, allowances are included for support areas and options accounted for in the design program. It should include tabulations of the usable, rentable, and gross square foot areas of the project in compliance with the NBSAP.

2. Interim CORE Building Standard Certification

At each stage of design process, the DB Contractor must certify that the design complies with all of the contract requirements, including the OPR, Interim CORE Building Standards, and any local regulatory agencies and review boards.

The DB Contractor must provide a narrative, in bullet form, which specifically identifies how proposed design features will support performance expectations of the project. Any deviations must be explicitly identified and submitted for approval by GSA.

3. PERMITS AND FEES

The DB Contractor is not anticipated to need any permits or pay any associated fees for this project.

4. BUILDING DESIGN STANDARDS (BDS)

There is no specific BDS for this project.

5. DELIVERABLES MATRIX

The Deliverables Matrix has this project’s detailed list of design review deliverables and…